Day Island Yacht Harbor, V General Construction Co ( 2014 )


Menu:
  •                                                                                                      FILED
    COURT OF APPEALS
    DIVISION II
    20!   AUG 12 PM ! 2: 136
    IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    DIVISION II
    GENERAL CONSTRUCTION CO.,                                                       No. 44402 -0 -II
    Appellant,
    v.
    DAY ISLAND YACHT HARBOR, INC.,                                        UNPUBLISHED OPINION
    Respondent.
    HUNT, P. J. —    General Construction      Company       appeals a $   1. 25 million jury verdict based
    on its finding that General Construction breached its construction contract with Day Island Yacht
    Harbor, Inc.      General Construction     argues    that ( 1)   the trial court erred as a matter of law in
    admitting Brian McGuire' s testimony         about   the value of his    marina, (   2) the jury verdict lacked
    substantial supporting evidence, and ( 3) the trial court erred in denying General Construction' s
    motion for new trial for these foregoing two reasons and also because ( a) the verdict did not " do
    substantial justice" and ( b) the trial court improperly ruled that General Construction waived its
    right to challenge McGuire' s opinion testimony about the diminution in value of his marina. Br.
    of   Appellant   at   37. We   affirm.
    No. 44402 - -II
    0
    FACTS
    I. MARINE CONSTRUCTION CONTRACT
    Day Island Yacht Harbor, Inc. is a Washington corporation, which Brian McGuire
    acquired     in 1970.        Beginning in 1988, Day Island contracted with General Construction, a
    construction company specializing in marine- related construction work, whenever Day Island
    needed piling replaced or other marine construction work.
    On May 20, 2008, Day Island and General Construction entered into a construction
    agreement for dredging and piling work at Day Island Yacht Harbor, for an agreed price in
    excess     of $   800,000.     The agreement provided that General Construction would furnish the
    necessary     personnel,      equipment,      and       facilities for the    project   and   that its duties included ( 1)
    mobilizing      and   demobilizing     cranes, anchors,        buckers,     and material    barges; (     2) demolishing float
    piles; (   3) moving the floats       and    boathouses to temporary               anchorage; (   4)   dredging ( " all   work to
    clamshell     dredge into     small    barges "); (      5) driving new piles; and ( 6) installing long wood piles
    between existing        wood piles.      Clerk'     s   Papers ( CP)   at    12.    General Construction also agreed to
    dredge the     marina    down to   a   depth   of minus        ten feet with a one -foot      allowance.       The agreement
    stipulated    that the project would commence                  July 16,     2008.     The agreed price was in excess of
    800,000.
    General Construction began dredging in July 2008, but it encountered difficulties and
    could not     dredge to the    required minus            10 -foot depth. General Construction told McGuire that it
    was experiencing resistance " in hardpan" and was unable to dredge the north and south ends of
    the   marina.     Verbatim Report       of   Proceedings ( VRP)        at    281.    McGuire paid General Construction
    615, 000 for its work to date.
    2
    No. 44402 -0 -II
    Concerned that General Construction had not completed its work in some areas, McGuire
    hired Wilson & Associates to survey the                   area.   The survey revealed that General Construction
    had   not   properly dredged the       area:    For example, under three boathouses in the north end, there
    was    still material    that   needed    dredging.        The south end of the moorage basin was not fully
    dredged.       And the boathouses on the eastern end appeared to have shifted eastward. The survey
    also revealed that although General Construction was supposed to have dredged 12, 800 cubic
    yards of material, it had dredged only about 7, 000 cubic yards.
    Finishing   the   project required     taking     the      marina     apart and "   starting   over ";   it involved
    such work as re- wiring, removing material underwater, pumping sediment onto the shore,
    removing and replacing pilings at the north and south ends of the marina, re- wiring the facility,
    and   potentially obtaining        a   new     permit.     VRP        at   319.    McGuire' s attempt to have General
    Construction finish the          dredging       failed.     So McGuire contacted other marine construction
    companies       and   sought price     estimates     for    finishing       the   dredging:     McGuire contacted Frank
    Immel at Global Divers about the cost of removing underwater material and pumping sediment
    on    shore.    McGuire       contacted   Thompson Pile               Driving     about   removing the      pilings.    And he
    contacted Sound Rock and Bulkhead about dredging the material that General Construction had
    failed to dredge and refused to complete.
    II. PROCEDURE
    On May 19, 2011, Day Island sued General Construction for breach of contract, alleging
    that ( 1) General Construction had breached its duty to perform dredging and marina operations in
    accordance with their written agreement; and ( 2) as a result of this breach, Day Island was
    entitled     to specific   performance       or   damages.            General Construction responded with a set of
    3
    No. 44402 - -II
    0
    interrogatories asking Day Island to list specific damages, which it did. There was a jury trial in
    October 2012.
    A. Trial Testimony
    1.       Day Island' s witnesses
    Jeffrey   Layton,    a coastal civil engineer with              Layton &    Sell, had worked as an engineer
    with   General Construction       since   1977.         In 2002, McGuire had contacted Layton to help with
    permitting for the     Day    Island   project.       Layton testified that the main dispute between McGuire
    and General Construction involved the south area of Day Island and the diagonal boathouses.
    The plan was for General Construction ( 1) to dig out a small area around the south end to allow
    material   to flow down the     channel    into      the marina    before   dredging       underneath   the boathouse, ( 2)
    to   remove   the boathouses in the basin and to store them offshore, and ( 3)                          then to return the
    boathouses to their original positions. But General Construction did not move all the boathouses.
    McGuire testified about the agreement into which Day Island had entered with General
    Construction. He stated that General Construction had failed to dredge 200 to 250 cubic yards at
    the   north end of    the marina and 250 cubic yards at the south end.                      McGuire had first noticed a
    problem before General Construction left the site in September 2008; and he had complained to
    Tom Jirava,        General Construction'         s    employee      in    charge    of   site   operations,   that General
    Construction had        not   completed     dredging        the    south    and    north    ends.   In September 2008,
    McGuire contacted General Construction, asking it to complete the promised dredging; General
    Construction       refused.   Nor did General Construction assist McGuire to fix the problems its
    incomplete    dredging    had   caused.     Instead, General Construction told McGuire to contact Frank
    4
    No. 44402 -0 -II
    Immel     and    to hire   a    diver to "   suck      the mud up and put it up on [ the] property," which would
    have cost over $500,000. VRP at 308.
    McGuire had been             unable       to   find    another   contractor to "     fix" General Construction' s
    failure to dredge the north and south ends of the marina and its failure to move the boathouses,
    without       first taking the     marina apart and           starting   over.   VRP   at   318.    The cost of rebuilding the
    marina,       including    rewiring, would be            at   least $    1 9 million, the amount McGuire had already
    spent on       the   project.   When McGuire' s counsel asked if he had an opinion about how much the
    value of the marina had dropped as a result of General Construction' s failure to dredge properly,
    General Construction              objected on grounds of           lack    of   foundation   and expertise.     The trial court
    overruled       the objection, stating that McGuire could answer and that the weight " goes to the
    jury."
    Marty Jackson testified that Day Island had hired him and his former partner John
    Patterson to work with General Construction to replace the boathouses back into the basin and to
    secure    them in place with pilings.                  General Construction had to "               get certain piling in place"
    before Jackson and General Construction could bring in the first row of boathouses; General
    Construction would then install pilings outside the boathouses to secure them before the next row
    of   boathouses        could    be brought in       and secured.         Jackson saw General Construction dredge and
    pile drive using two barges, which Jackson believed were rather large for working in Day
    Island'   s   small    basin, "   sort of   like   a   bull in   a china   shop."    General Construction' s large barges'
    appeared to have a hard time maneuvering around the docks and pilings inside the basin because
    clearance was minimal.
    No. 44402 - -I1
    0
    2. General Construction' s Witness
    Ken Preston, an estimator and superintendent at General Construction, testified that
    removing all the material that General Construction had failed to remove would cost about
    95, 000.   Preston had arrived at this figure by calculating the total number of yards of material
    that still needed to be removed ( 500) divided by the yards that could be removed per day ( 30),
    which would take about 2 weeks at a cost of $5200 a day as quoted by Immel at Global Diving.
    The    cost of " mob[   ilizing]   and   demob[ ilizing]"     would    be   about $   15, 000. 1   VRP at 567.
    Instructions2
    B.   Jury
    The trial     court   instructed the    jury    to determine ( 1)     whether General Construction had
    breached its     contract with     Day    Island; ( 2)   whether Day Island had sustained damages as a result
    of    General Construction'        s   breach;   and (   3)   the amount of damages, if any, Day Island had
    sustained.      On the specific issue of determining damages, the jury instructions stated that if the
    jury found Day Island proved that it had incurred actual damages and if the jury determined the
    amount of such actual           damages, then the jury        should award actual         damages to    Day    Island.   Jury
    instruction 10 also specified that in calculating damages, the jury should determine the " sum of
    money that will put the plaintiff [Day Island] in as good a position as it would have been in if
    both    plaintiff and   defendant had      performed all of         their promises    under   the contract."   CP at 168.
    1 Mobilization is the preliminary process and cost of starting a dredging project before the actual
    dredging takes place: It includes towing the equipment to the site and preparing the equipment
    and barges. Demobilization involves offloading and removing this equipment from the site after
    the work is completed.
    2
    General Construction did not challenge the jury instructions below. Nor does it challenge them
    on appeal.
    6
    No. 44402 -0 -II
    C. Closing Arguments
    Day Island argued to the jury that ( 1) to repair the marina, Global Diving would charge
    about $ 500, 000 and General Construction would charge about $ 200, 000 to pull the pilings; and
    2) the property value had dropped to about 60 to 80 percent of the amount paid for the dredging
    operation, $     1. 14   million and $      1. 52   million,   respectively.     Day Island also told the jury that the
    measure of damages was to " put Mr. McGuire back in as good a position as he would be if he
    hadn' t   met   these guys,"       and   that "[   McGuire] spent a million - ine figuring this marina was going
    n
    to be   turnkey    to    pass on   to his next      generation.    Instead, he has      a mess.    I would like to have him
    see the million -
    nine         back   and start all over."       VRP at 896.
    General Construction             argued     that to     show   damages,       Day   Island had to "      prove by a
    preponderance           of evidence      the breach of contract and that             they     were   damaged," but "[       t]hey
    didn' t really     produce    any damage            evidence,"    and   Day   Island'   s   damages did     not amount      to " a
    million five" because, based on Preston' s testimony, the cost to move the boathouses and to
    remove the remaining material out was only $95, 000. VRP at 879.
    D. Verdict; Judgment
    The jury entered a special verdict finding that ( 1) General Construction had breached its
    contract      with     Day   island to furnish the necessary                  personnel,     equipment,      and facilities to
    accomplish       the    dredging    and associated       float   and marina repair at        Day   Island Yacht Harbor; ( 2)
    as a result of General Construction' s breach of contract, Day Island had sustained damages; and
    3) the   amount of       these damages       was $    1, 250,000. The trial court entered judgment on November
    2, 2012, awarding          Day     Island $ 1, 250, 000 in damages, plus costs and disbursements set forth in
    its   costs   bills. The trial     court   denied    Day   Island'   s request   for attorney fees    or   litigation   expenses.
    No. 44402 -0 -II
    E. Motion for New Trial
    General Construction           moved      for   a new trial and/ or remittur on grounds                    that ( 1)   Day
    Island did not provide sufficient evidence to support the jury' s verdict, and a new trial was
    warranted under      CR 59( a)( 7); (     2) McGuire' s testimony was inadmissible and the trial court' s
    admission of     his testimony    constituted an error of             law   under   CR 59( a)( 8); and ( 3) the verdict did
    3
    not "   do   substantial   justice,"    which      warranted      a   new     trial under CR          59( a)( 9).   CP    at    211.
    General Construction argued that McGuire' s failure to present evidence of the value of Day
    Island before the     alleged    damage       warranted         a new trial.        The trial court noted that although
    General Construction had objected to the specific question about McGuire' s opinion on how
    much the drop in value of the marina was, General Construction did not further object, file a
    motion to strike, or challenge any subsequent testimony.
    The trial court also noted that ( 1) after the trial court overruled General Construction' s
    objection,    McGuire had testified        about       his   opinion of     the   drop   in his   marina' s value; ( 2)   General
    Construction had waived its objection to this testimony; and ( 3) the jury had heard the evidence,
    rendered a verdict, and used the information presented at trial to reach their verdict. For these
    reasons, the trial court denied General Construction' s motion for new trial and/ or remittur.
    4
    General Construction          appeals.
    3 General Construction also argued below that a new trial was warranted under CR 59( a)( 6) and
    CR 59( a)( 5).    But these grounds are not before us on appeal.
    4
    General Construction does          not raise   the   remittur     issue   on appeal.
    No. 44402 -0 -II
    ANALYSIS
    I. ADMISSION OF MCGUIRE' S TESTIMONY
    General Construction first argues that the trial court erred in admitting McGuire' s
    testimony   on   damages.       More specifically, General Construction contends that ( 1) McGuire was
    not qualified to opine about the Day Island marina' s diminution in property value as a result of
    its ( General     Construction'       s)    breach    of   contract,   and (   2)    McGuire' s testimony was both
    incompetent      and prejudicial           because   Day   Island failed to    lay   a proper   foundation for it. This
    argument fails.
    A. Standard of Review
    We review for abuse of discretion a trial court' s ruling on the admissibility of opinion
    evidence.   State      v.   Demery,    
    144 Wn.2d 753
    , 758, 
    30 P.3d 1278
     ( 2001).                It is well settled that an
    owner is qualified to testify about the value of his property; no further " expert[ isej" is required.
    See McCurdy       v.    Union Pac. R.R., 
    68 Wn.2d 457
    , 468 - 69, 
    413 P. 2d 617
     ( 1966); Wicklund v.
    Allraum, 
    122 Wn. 546
    , 547 -48, 
    211 P. 760
     ( 1922);                   State v. Hammond, 
    6 Wn. App. 459
    , 462, 
    493 P.2d 1249
     ( 1972).
    A property owner is presumed to be sufficiently acquainted with its value and the value
    of surrounding lands to give an intelligent estimate of the value of his property. State v. Wilson,
    
    6 Wn. App. 443
    , 451, 
    493 P.2d 1252
     ( 1972).                         An owner' s knowledge about the value of his
    property may come from many sources, including inquiries, comparisons, purchases, and sales.
    Wicklund, 
    122 Wn. at 547
    . The source of the property owner' s knowledge may affect the weight
    of   his testimony but        not   its admissibility.       Wicklund, 
    122 Wn. at 547
    ; McInnis &    Co. v. W.
    9
    No. 44402 -0 -II
    Tractor Equip. Co., 
    67 Wn.2d 965
    , 968, 970, 
    410 P.2d 908
     ( 1966).
    B. Admissibility
    It is   undisputed    that    McGuire       was    the   owner of     Day   Island Yacht Harbor, Inc.       General
    Construction challenges the proposition that a real property owner can testify about its value,
    based     on    Wicklund' s   and    McPhee'       s   focus   on personal       property,    not real   property.   But General
    Construction ignores that Washington courts have extended this long -established personal
    property       value rule   to   real     property.     See State ex rel. Bremerton Bridge Co. v. Superior Court
    for   Kitsap Cnty.,       
    194 Wn. 196
    , 198 -99, 
    77 P. 2d 800
     ( 1938).                          Furthermore, a key case that
    General Construction             cites,   State   v.   Wilson, 
    6 Wn. App. 443
    , 
    493 P. 2d 1253
     ( 1972), stands for
    the very proposition that it contests here, namely that " the owner of real property has a right to
    testify   as   to the value of his property."             Wilson, 6 Wn.          App.   at   451.   We hold that the trial court
    did not abuse its discretion in allowing McGuire to testify about the value of his property.
    General Construction also argues that the trial court improperly admitted McGuire' s
    testimony under Wilson, in which we ruled that an owner' s testimony about the fair market value
    of his real property becomes incompetent when it is based on irrelevant factors and ignores
    relevant       factors. This     argument also         fails because Wilson is distinguishable. In Wilson, we held
    that ( 1)      evidence of the cost of reproducing or replacing a building is admissible when the
    structures are well adapted                to the land    on which        they    stand; (   2) such reproduction cost is not
    admissible when the sole factor for determining fair market value is based on structures located
    on " another comparable-parcel of                 realty ";    and ( 3) because the owner' s valuation testimony was
    10
    No. 44402 -0 -II
    based solely on the cost of rebuilding structures on a different, but comparable, plot of land, the
    trial   court   did   not abuse     its discretion in excluding           such   testimony. Wilson, 6 Wn. App. at 450-
    51.
    Here, however, McGuire testified about the cost to reconstruct the same buildings at the
    same place on          the   same   land   at   his   Day Island     marina.      Thus,   our   holding   in Wilson —that the
    cost    of    reconstruction        on   the    same    plot    of   land is     admissible —supports       the    trial   court' s
    admission of          McGuire' s testimony here.               Through McGuire' s testimony and related exhibits,
    Day Island provided estimates of reconstruction costs on its own marina, not on a comparable
    plot of land.5
    We further note that Wilson involved appellate review of the trial court' s exclusion of the
    property owner Wilson' s valuation; here, in contrast, the issue is whether the trial court erred in
    admitting property           owner    McGuire'        s valuation    testimony. As we explained in the Standard of
    Review        section    of this    analysis,     we give deference to the trial court' s evidentiary rulings,
    reversing only where in making such rulings, the trial court abused its discretion. We hold that
    the trial court did not abuse its discretion in admitting the testimony of McGuire, who as Day
    Island' s owner, was qualified as a matter of law to testify about the value of his property, both
    before and after General Construction' s breach of contract, to prove damages.
    5
    Day Island also provided ample other valuation evidence, including testimony from numerous
    witnesses,       correspondence            between       the   parties,    and    price    estimates      from    other    marine
    construction companies.   In contrast, the record in Wilson comprised a short record containing
    only Dr. Wilson' s testimony. Wilson, 6 Wn. App. at 444 -45.
    11
    No. 44402 -0 -II
    II. SUBSTANTIAL EVIDENCE SUPPORTS JURY VERDICT
    General. Construction next argues that substantial evidence does not support the jury' s
    1. 25   million      damages    verdict.    General Construction asserts that under the diminution in value
    theory, Day Island failed to provide the fair market value of the marina before and after General
    Construction' s breach of contract. We disagree.
    A. Standard of Review
    Courts       are reluctant   to interfere with a        jury' s   fair damages      award.     Washington State
    Physicians Ins. Exch. &            Ass' n   v.   Fisons   Corp.,      
    122 Wn.2d 299
    , 329, 
    858 P.2d 1054
     ( 1993).
    Thus, we view the evidence in the light most favorable to the jury' s verdict. State v. Curtiss, 
    161 Wn. App. 673
    , 693, 
    250 P. 3d 496
     ( 2011).               And there is a strong presumption that a jury' s
    damages award is correct. RCW 4.76.030, Green v. McAllister, 
    103 Wn. App. 452
    , 461, 
    14 P.3d 795
     ( 2000).
    Nevertheless, an appellate court may overturn a jury' s damages award that is " outside the
    range     of substantial evidence           in the   record."     Bingaman     v.   Grays Harbor         Cmty. Hosp., 
    103 Wn.2d 831
    , 835, 
    699 P. 2d 1230
     ( 1985).                     Substantial evidence is the quantum of evidence
    sufficient      to   persuade a rational,     fair -
    minded       person   that the   premise   is true.   Sunnyside Valley
    Irrigation Dist.        v.   Dickie, 
    149 Wn.2d 873
    , 879, 
    73 P. 3d 369
     ( 2003). "``                Evidence of damage is
    sufficient if it affords a reasonable basis for estimating loss and does not subject the trier of fact
    to   mere speculation or conjecture. "'              Clayton v. Wilson, 
    168 Wn.2d 57
    , 72, 
    227 P. 3d 278
     ( 2010)
    quoting State v. Mark, 
    36 Wn. App. 428
    , 434, 
    675 P.2d 1250
     ( 1984)).
    12
    No. 44402 -0 -II
    B. Breach of Contract Construction Damages
    For   determining       construction       damages,    our State Supreme Court has adopted the
    Restatement ( Second)      of   Contracts § 348, at 119 -20, which provides, in pertinent part:
    1) If a breach delays the use of property and the loss in value to the injured party
    is not proved with reasonable certainty, he may recover damages based on the
    rental value of the property or on interest on the value of the property.
    2) If a breach results in defective or unfinished construction and the loss in value
    to the injured party is not proved with sufficient certainty, he may recover
    damages based on
    a) the diminution in the market price of the property caused by the breach, or
    b) the reasonable cost of completing performance or of remedying the defects if
    that cost is not clearly disproportionate to the probable loss in value to him.
    Eastlake Construction      v.   Hess, 
    102 Wn.2d 30
    , 47 -48, 
    686 P. 2d 465
     ( 1984) (       emphasis added).
    In cases involving breach of contract based on unfinished construction, the plaintiff can
    prove   damages based      on   the cost to have the work completed          by   another contractor.   Eastlake,
    
    102 Wn.2d at 47
    . If, however, performance was defective instead of unfinished, the plaintiff can
    recover damages based on the cost to remedy the defects. Eastlake, 
    102 Wn.2d at 48
    . If the cost
    to remedy the defects includes the cost of undoing the defective work and if this remedial cost is
    clearly excessive, damages should reflect the difference between the property' s fair market price
    with and without the defects. Eastlake, 
    102 Wn.2d at 48
    .
    General Construction argues that Eastlake 's diminution in value theory required the jury
    to ascertain damages based on the difference between the property' s fair market values
    immediately    before    and    immediately    after   the damage.      Colella v. King County, 
    72 Wn.2d 386
    ,
    393, 
    433 P. 2d 154
     ( 1967);         Harkoff   v.    Whatcom    Cnty.,   
    40 Wn.2d 147
    , 
    241 P.2d 932
     ( 1952).
    13
    No. 44402 -0 -II
    More      specifically,      General       Construction        contends     McGuire'         s    testimony —that Day Island
    Marina' s property         value    declined     by   about    50 to 70   percent of         the $ 1. 9 million total cost of the
    project6     —
    construction                      was speculative and insufficient to meet Day Island' s burden of proof and
    did   not support     the jury' s $ 1. 25 million damages verdict. We disagree.
    Under Eastlake, the diminution in value theory is not the sole method for calculating
    damages;      rather,      the   parties   can    also   base damages           on   the " reasonable cost of completing
    performance      or of      remedying the defects" for defective                  or unfinished construction.               Eastlake,
    
    102 Wn.2d at 47
    . Furthermore, the instructions here did not direct the jury to use the diminution
    in value theory; instead, the instructions directed the jury to determine the sum of money that
    would put Day Island in as good a position as it would have been if both Day Island and General
    Construction had           performed       all   their promises       under     the contract.             Moreover, neither party
    6
    The   original $   615, 000 contract between General Construction and Day Island was part of the
    total " project costs."          See 3 VRP at 658.
    7
    See, e. g., Jury Instruction 10, derived from WPIC 303.01, which provided, in pertinent part:
    In order to recover actual damages, the plaintiff has the burden of proving
    that the defendant breached a contract with it, and that plaintiff incurred actual
    economic damages as a result of the defendant' s breach, and the amount of those
    damages.
    If your verdict is for plaintiff on plaintiff' s breach of contract claim and if
    you find that plaintiff has proved that it incurred actual damages and the amount
    of those actual damages, then you shall award actual damages to the plaintiff.
    Actual damages are those losses that were reasonably foreseeable, at the
    time the contract was made, as a probable result of a breach.       A loss may be
    foreseeable as a probable result of a breach because it follows from the breach
    either (   a)    in the ordinary           course    of    events,    or (   b)       as   a   result   of   special
    circumstances, beyond the ordinary course of events, that the party in breach had
    reason to know.
    In calculating the plaintiff' s actual damages, you should determine the
    sum of money that will put the plaintiff in as good a position as it would have
    14
    No. 44402 -0 -II
    8
    articulated     the diminution in           value    theory during closing             argument.         Accordingly, General
    Construction' s assertion that Day Island was required to prove damages under the diminution in
    value theory fails.
    We turn instead to the              substantial    evidence       that supported the         jury' s $   1. 25 million
    damages       verdict.         McGuire testified that ( 1) "        fix[ ing] the      marina"   involved re- wiring, which
    alone would cost about a quarter million                   dollars; ( 2) he had     spent $   1. 9 million fixing the marina;
    3) there     was no other          way to " fix" the     marina without       taking it    apart and     starting   over; ( 4)   the
    value of the marina probably dropped by about 60 to 80 percent as a result of General
    Construction'        s   breach; ( 5)   part of "   fixing"   the   marina    involved     hiring   a   diver to " suck the mud
    up" that General Construction had failed to dredge at the north and south ends of the marina and
    pump this mud on to shore, which cost about $ 500, 000, VRP at 308, 319; and ( 6) he ( McGuire)
    had already paid General Construction $ 615, 000 for its work, most of which had to be removed
    been in if both plaintiff and defendant had performed all of their promises under
    the contract.
    The burden of proving damages rests with the plaintiff and it is for you to
    determine, based upon the evidence, whether any particular element has been
    proved by a preponderance of the evidence. You must be governed by your own
    judgment, by the evidence in the case, and by these instructions, rather than by
    speculation, guess, or conjecture.
    CP     at   168, (   emphasis        added).     General Construction         WPI 303. 01 correctly
    concedes      that "
    instructed that plaintiff could recover all ``reasonably foreseeable' and `` actual economic damages
    suffered] as a result of        breach.'"    Br. of Appellant at 36.
    8
    General Construction argued that Day Island ( 1) had to prove by a preponderance of evidence
    contract and the damages it suffered as a result, and ( 2) " didn' t really produce any
    the breach of
    damage evidence." VRP at 879. Day Island referenced McGuire' s testimony about the drop in
    the property' s value to show the extent of damages: "                           We can' t tell you what it would cost
    because there            are   too darn   many   problems      involved.       It is   a mess.      So we gave you our best
    opinion as      to what this has done to            our   property   value.   60   to 80   percent of what      he   spent."   VRP
    at 894.
    15
    No. 44402 -0 -II
    and redone at additional cost to Day Island because General Construction refused to repair the
    damage it had      caused.      Frank Immel' s emailed price quote for a dive operation to remove the
    mud    included: $ 3, 120 for an initial investigative dive to assess the project better, an estimated
    84, 000 for " mob[ ilization]           and   demob[ ilization],"       and $   7, 960   per   day for   repair costs.     CP at
    313.   We hold that there was substantial evidence presented at trial to support the jury' s verdict
    of $1. 25 million.
    III. MOTION FOR NEW TRIAL
    Finally, General Construction argues that the trial court abused its discretion in denying
    its ( General Construction'         s)    motion       for   a   new   trial because (     1)   the trial court erroneously
    admitted   McGuire'     s   testimony, ( 2) the trial court improperly ruled that General Construction had
    waived   its   objections to    McGuire' s        testimony, ( 3) substantial evidence did not support the jury' s
    verdict, and (   4) the      verdict "   does    not   do    substantial   justice."      Br.   of   Appellant   at   37.   Again,
    General Construction' s argument fails.
    A. Standard of Review
    It is well settled that granting or denying a motion for a new trial is directed to the
    considerable sound          discretion    of   the trial court.    Coats   v.   Lee & Eastes, Inc., 
    51 Wn.2d 542
    , 552,
    
    320 P.2d 292
     ( 1958).         And we will not intervene with the trial court' s new trial decision absent a
    manifest abuse of       that discretion.          Coats, 
    51 Wn.2d at 552
    .   A trial court abuses its discretion
    when it fails to grant a new trial or amend a judgment where the damage award is contrary to the
    evidence.      Locke   v.   City   of Seattle, 
    162 Wn.2d 474
    , 486, 
    172 P. 3d 705
     ( 2007).                        The test for an
    abuse of discretion is whether no reasonable judge would have reached the same conclusion. In
    16
    No. 44402 -0 -II
    re   Marriage of Landry, 
    103 Wn. 2d 807
    , 809 -10, 
    699 P. 2d 214
     ( 1985). We find no such abuse of
    discretion here.
    We have already held that the trial court did not abuse its discretion in admitting
    McGuire'        s   testimony       and    that substantial evidence supports the             jury' s     verdict.   Thus, there
    remain two " new" arguments to address in the new trial context: whether the trial court properly
    ruled that General Construction waived its objection to McGuire' s testimony and whether the
    jury' s   verdict      did " substantial justice." Br. of Appellant at 37. We address each in turn.
    B. Waiver
    General Construction argues that in considering its motion for a new trial, the trial court
    erroneously ruled that. (1) it (General Construction) had waived its right to challenge McGuire' s
    testimony about the value of his marina; and ( 2) because the jury already heard the challenged
    evidence, General Construction should have mounted an additional objection, a motion to strike
    or    a   CR 50       motion    for    a   directed    verdict.    Because General Construction provides no legal
    authority to         support    its   assertions,     contrary to RAP 10. 3(      a)(   6), we do not further consider this
    argument. Moreover, as we note above, we have already held that the trial court did not abuse its
    discretion in admitting McGuire' s testimony.
    C. Jury' s Verdict
    General Construction argues that the trial court erred in not granting a new trial because
    the   jury' s       verdict   did   not    do "   substantial   justice."   Br. of Appellant        at   37.    As we have also
    previously explained, appellate courts are generally reluctant to interfere with a jury' s damage
    award      because the determination                 of   damages is     within   the    province    of   the   jury. Palmer v.
    Jensen, 
    132 Wn.2d 193
    , 197, 
    937 P.2d 597
     ( 1997). We examine the record to determine whether
    17
    No. 44402 -0 -
    II
    the   jury' s   award   is contrary to the     evidence.       Palmer, 
    132 Wn.2d at 197
    .    Where the jury could
    believe or disbelieve the evidence and weigh all of it and remain within the range of the evidence
    in returning the challenged verdict, then it cannot be found as a matter of law that the verdict was
    unmistakably excessive or inadequate to show that the jury was motivated by passion or
    prejudice       based   on   the amount.   James v. Robeck, 
    79 Wn.2d 864
    , 870 -
    71, 
    490 P. 2d 878
     ( 1971).
    If the verdict falls within a range of proven damages, it should not be set aside as excessive.
    James, 
    79 Wn.2d at
    870 -
    71.
    CR 59( a)( 9) provides that a motion for new trial may be granted if "substantial justice has
    not   been done."        But courts rarely grant a new trial for lack of substantial justice under CR
    59( a)( 9) because       of   the   other grounds   afforded under this rule.           Lian v. Stalick, 
    106 Wn. App. 811
    , 825, 
    25 P.3d 467
     ( 2001).                Moreover, contrary to RAP 10. 3(                a)(   6), General Construction
    provides no authority or citation to the record in support of its argument that " substantial justice
    has    not   been done "; instead, it      states, "[   S]   ee prior argument,"      without referring to any specific
    prior    argument.        Therefore,     we   do   not    further       consider   General Construction'        s"   substantial
    justice" argument. Br. of Appellant at 37.
    In light of the substantial supporting evidence that we have already set forth in an earlier
    section of this analysis, we          hold that the      jury' s   award    of $   1. 25 million to Day Island was not
    unmistakably []         excessive" so as to warrant a new trial.             James, 
    79 Wn.2d at
    870 -
    71. We
    further hold that the trial court did not abuse its discretion in denying General Construction' s
    motion for a new trial.
    18
    No. 44402 -0 -II
    We affirm.
    A majority of the panel having determined that this opinion will not be printed in the
    Washington Appellate Reports, but will be filed for public record in accordance with RCW
    2.06.040, it is so ordered.
    We concur:
    W(
    Melnick, J.
    J
    19