State Of Washington V. American Tobacco Co. ( 2024 )


Menu:
  •        IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    STATE OF WASHINGTON,
    No. 85360-1-I
    Respondent,
    DIVISION ONE
    v.
    UNPUBLISHED OPINION
    AMERICAN TOBACCO CO.,
    Defendant,
    COMMONWEALTH BRANDS INC.;
    COMPANIA INDUSTRIAL de
    TABACOS MONTE PAZ, SA;
    DAUGHTERS & RYAN, INC.;
    FARMERS TOBACCO CO.; HOUSE
    OF PRINCE A/S; ITG BRANDS, LLC,
    JAPAN TOBACCO INTERNATIONAL
    USA, INC.; KING MAKER
    MARKETING INC.; KRETEK
    INTERNATIONAL; LIGGETT GROUP
    LLC; P.T. DJARUM; PETER
    STOKKEBYE TOBAKSFABRIK A/S;
    PHILIP MORRIS USA, INC.; R.J.
    REYNOLDS TOBACCO COMPANY;
    REEMTSMA CIGARETTENFABRIKEN
    GMBH; SANTA FE NATURAL
    TOBACCO COMPANY;
    SCANDINAVIAN TOBACCO GROUP
    LANE LIMITED; SHERMAN’S 1400
    BROADWAY NYC, LLC; TOP
    TOBACCO, LP; VON EICKEN
    GROUP; and WIND RIVER TOBACCO
    CO. LLC,
    Appellants.
    No. 85360-1-I/2
    MANN, J. — In the 1990s, several states, including Washington, sued major
    cigarette manufacturers, seeking to protect the public health and gain compensation for
    costs incurred from treating smoking-related illnesses. The participating manufacturers
    (PMs) and the states settled their dispute in the late 1990s and entered into a Master
    Settlement Agreement (MSA), which requires the PMs to make annual cash payments
    to the states in perpetuity.
    In 2022, the PMs moved in King County Superior Court to vacate a reallocation
    order issued by the 2004 arbitration panel (2004 Panel). The trial court concluded that
    none of the applicable statutory grounds for vacating the order exist and denied the
    motion. The PMs appeal the trial court’s decision. We affirm.
    I
    In 1998, 46 states, the District of Columbia, and 5 United States territories
    (collectively, the Settling States or States) settled a lawsuit against 4 major cigarette
    manufacturers resulting in the MSA. State v. Am. Tobacco Co., 28 Wn. App. 2d 452,
    459, 
    537 P.3d 303
     (2023) (Tobacco I). 1 The MSA is a landmark public health
    agreement. State v. R.J. Reynolds Tobacco Co., 
    151 Wn. App. 775
    , 778, 
    211 P.3d 448
    (2009).
    Over 50 tobacco manufacturers, the PMs, have agreed to be bound by the terms
    of the MSA. Tobacco I, 28 Wn. App. 2d at 459. Manufacturers that have not joined the
    MSA are known as “Non-Participating Manufacturers” (NPMs).
    1 This court issued an unpublished opinion on a different dispute arising out of the MSA on the
    same day: State v. American Tobacco Co., No. 84691-4-I (Wash. Ct. App. Oct. 16, 2023) (unpublished),
    https://www.courts.wa.gov/opinions/pdf/846914.pdf. Accordingly, this opinion refers to the published
    opinion as Tobacco I. More detailed background facts can be found in Tobacco I.
    -2-
    No. 85360-1-I/3
    The MSA requires the PMs make annual cash payments to the States in
    perpetuity to offset increased costs to the States’ healthcare systems caused by
    smoking. Tobacco I, 28 Wn. App. 2d at 459. The annual payments are subject to
    possible adjustments, including the adjustment at issue: the NPM Adjustment. The
    NPM Adjustment applies when the PMs experience a market share loss to the NPMs in
    a given year. MSA § IX(d)(1); Tobacco I, 28 Wn. App. 2d at 460.
    The NPM Adjustment applies “to the Allocated Payments of all Settling States.”
    MSA § IX(d)(2)(A) (emphasis added). But a state can avoid a reduction in its annual
    payment if it demonstrates that it “had a Qualifying Statute . . . in full force and effect
    during the entire calendar year immediately preceding the year in which the payment in
    question is due, and diligently enforced the provisions of such statute during such entire
    calendar year.” MSA § IX(d)(2)(B)(i).
    If a state does not adopt or does not diligently enforce a Qualifying Statute, 2 its
    Allocated Payment is subject to reduction:
    The aggregate amount of the NPM Adjustments that would have applied
    to the Allocated Payments of those Settling States that are not subject to
    an NPM Adjustment pursuant to subsection (2)(B) shall be reallocated
    among all other Settling States pro rata in proportion to their respective
    Allocable Shares . . . and such other Settling States’ Allocated Payments
    shall be further reduced accordingly.
    MSA § IX(d)(2)(C).
    During arbitration over the 2003 NPM Adjustment, the PMs reached a partial
    settlement, the “Term Sheet Settlement,” with some states, these states are known as
    the “Resolved States.” Because of this, a panel of three retired federal judges (2003
    2 Washington’s qualifying statute was enacted in 1999, codified as chapter 70.157 RCW.
    -3-
    No. 85360-1-I/4
    Panel) considered how to treat the Resolved States in the NPM Adjustment. The 2003
    Panel determined that the Independent Auditor should treat the Resolved States as
    diligent and not subject to the 2003 NPM Adjustment, but reduced the Adjustment by a
    percentage equal to the aggregate Allocable Shares of the Resolved States. 3 Pursuant
    to this pro rata judgment reduction, the Resolved States’ shares of the Adjustment, as
    reduced, would be reallocated among the non-diligent states. Each of the states found
    non-diligent moved to vacate that ruling in their respective state courts and prevailed. 4
    Eight states joined the 2004 NPM Adjustment Arbitration; by that time, the
    number of Resolved States had risen to thirty-seven. In the case management order for
    the arbitration, the Arbitrating States agreed they would have the burden to prove their
    diligence. The “overarching question” for the 2004 Panels to consider was whether the
    Arbitrating States “diligently enforced” their Qualifying Statutes in 2004.
    In a 2017 interim order, the Panel “deem[ed] it appropriate to establish a
    procedure” for the reallocation of the 2004 NPM Adjustment (2017 Reallocation Order).
    The Panel decided it would presume that the Resolved States were non-diligent for
    2004. The Panel also created a new procedure through which the PMs would be
    allowed to contest and rebut that presumption as to any or all Resolved States.
    Maryland, one of the Arbitrating States, sought reconsideration of that order, which was
    3 Each PM makes a single nationwide payment into an escrow account in the overall amount
    calculated and determined by the Independent Auditor. Since 1998, PricewaterhouseCoopers LLP has
    been the Independent Auditor. The Independent Auditor then allocates the nationwide payments among
    the States according to each State’s Allocable Share.
    4 Two of the six states settled their disputes and became Resolved States. The cases from the
    four remaining states, Pennsylvania, Missouri, Maryland, and New Mexico, are discussed later in this
    opinion.
    -4-
    No. 85360-1-I/5
    stayed until after state-specific diligence determinations could be made. Six states were
    found diligent. Washington and Missouri, however, were found non-diligent. 5
    Following briefing from the parties and oral argument, the Panel granted the
    Arbitrating States’ motion to vacate the 2017 Reallocation Order (2022 Reallocation
    Order). The Panel explained:
    The Members of the 2004 NPM Adjustment Panels conclude that in
    attempting in our May 2017 Reallocation Order to craft a reasonable
    alternative procedure to address the treatment of Resolved States with
    regard to calculating reallocation, we endeavored to make more efficient a
    process for which we lacked authority in the first place. As held by each of
    the MSA Courts to consider the issue, the fact that the MSA is silent on
    the treatment of States that negotiate a settlement for purposes of
    calculating reallocation of the NPM Adjustment does not create an
    ambiguity in the MSA which allows the Panels to impose a procedure they
    think reasonable.
    The MSA unambiguously sets forth the procedure by which a State may
    seek relief from the NPM Adjustment by showing its diligence in enforcing
    its Qualifying Statute. MSA Sec. IX(d)(2). The MSA says nothing about
    Resolved States, nor does it provide for allowing the PMs to assert a
    diligence claim on behalf of a Resolved State, or to contest and rebut a
    presumption that a Resolved State is non-diligent to exclude them from
    the NPM Adjustment.
    The Panel concluded that the Resolved States “must be deemed to be subject to the
    2004 NPM Adjustment for purposes of calculating reallocation.” Further, the procedure
    allowing the “PMs to contest and rebut a presumption of non-diligence on behalf of
    Resolved States as set forth in the May 2017 Reallocation Order constituted an
    unauthorized amendment of the MSA.”
    The PMs moved to vacate the 2022 Reallocation Order. The trial court denied
    the PMs’ motion to vacate concluding that no applicable statutory grounds for vacating
    5 New Mexico was also found non-diligent but a court later vacated that determination.
    -5-
    No. 85360-1-I/6
    the order exist. The trial court specifically ruled that “[t]he Panel did not fail to consider
    material evidence because it interpreted the contract not to allow anyone other than a
    state to prove a diligence claim.” And, “[t]he Panel did not exceed its authority because
    the Panel had the authority to interpret the MSA and it did so.”
    The PMs appeal.
    II
    A
    The parties disagree whether the Federal Arbitration Act (FAA), 
    9 U.S.C. § 10
    , or
    the Washington uniform arbitration act (WUAA), chapter 7.04A RCW, applies here. The
    PMs concede, however, that any differences between Washington law and federal law
    are immaterial. 6 We agree.
    First, under the FAA, vacatur is permitted only “where the arbitrators were guilty
    of misconduct . . . in refusing to hear evidence pertinent and material to the controversy”
    or “where the arbitrators exceeded their powers.” 
    9 U.S.C. § 10
    (a)(3), (4). Similarly,
    under the WUAA, the court shall vacate an award if an arbitrator “refused to consider
    evidence material to the controversy” or “exceeded the arbitrator’s powers.” RCW
    7.04A.230(1)(c), (d).
    This court recently reiterated the limits of our review of an arbitration decision:
    Under Washington law, “[c]ourts will review an arbitration decision only in
    certain limited circumstances, such as when an arbitrator has exceeded
    [their] legal authority.” Int’l Union of Operating Eng’rs v. Port of Seattle,
    
    176 Wn.2d 712
    , 720, 
    295 P.3d 736
     (2013). “To do otherwise would call
    6 The MSA provides, “[t]he arbitration shall be governed by the United States Federal Arbitration
    Act.” MSA § XI(c). However, the MSA also contains choice of law provisions, the MSA “shall be
    governed by the laws of the relevant Settling State, without regard to the conflict of law rules of such
    Settling State.” MSA § XVIII(n). In addition, MSA §§ II(p) and VII(a) provide it is “the respective court in
    each Settling State” that has “exclusive jurisdiction” over disputes arising out of the MSA.
    -6-
    No. 85360-1-I/7
    into question the finality of arbitration decisions and undermine alternative
    dispute resolution.” Int’l Union of Operating Eng’rs, 
    176 Wn.2d at 720
    .
    Our review of an arbitrator’s award is “limited to the same standard
    applicable in the court which confirmed, vacated, modified, or corrected
    that award.” Salewski v. Pilchuck Veterinary Hosp., Inc., 
    189 Wn. App. 898
    , 903, 
    359 P.3d 884
     (2015). We review only whether one of the
    statutory grounds to vacate an award exists. Salewski, 
    189 Wn. App. at 903-04
    . The party challenging the award bears the burden of showing
    such grounds exist. Cummings v. Budget Tank Removal & Env’t Servs.,
    LLC, 
    163 Wn. App. 379
    , 388, 
    260 P.3d 220
     (2011).
    Tobacco I, 28 Wn. App. 2d at 478.
    Because the applicable provisions of the FAA and WUAA are so similar, we do
    not reach the issue of which law applies.
    B
    The PMs assert that they are entitled to vacatur of the arbitration award because
    the Panel exceeded its authority in issuing the 2022 Reallocation Order. We disagree.
    Tobacco I recently discussed the narrow circumstances for vacatur on this
    ground:
    In considering a motion to vacate on this ground, we examine whether
    there is an error of law “‘on the face of the award’” that goes to the
    arbitrator’s decision. Salewski, 
    189 Wn. App. at 904
     (quoting Federated
    Servs. Ins. Co. v. Pers. Representative of [Est.] of Norberg, 
    101 Wn. App. 119
    , 123, 
    4 P.3d 844
     (2000)). But “the facial legal error standard is a very
    narrow ground for vacating an arbitral award.” Broom v. Morgan Stanley
    DW Inc., 
    169 Wn.2d 231
    , 239, 
    236 P.3d 182
     (2010). “Limiting judicial
    review to the face of the award is a shorthand description for the policy
    that courts should accord substantial finality to arbitrator decisions.” Est.
    of Norberg, 
    101 Wn. App. at 123
    . “‘The error should be recognizable from
    the language of the award, as, for instance, where the arbitrator identifies
    a portion of the award as punitive damages in a jurisdiction that does not
    allow punitive damages.’” Salewski, 
    189 Wn. App. at 904
     (quoting
    Cummings,
    163 Wn. App. at 389
    ). The example provided in Salewski was
    indeed more than an ordinary legal error, but one contrary to the long
    established public policy of Washington that “recovery of punitive
    damages is contrary to the public policy of the State and will not be
    allowed unless expressly authorized by statute.” Kennewick Educ. Ass’n
    -7-
    No. 85360-1-I/8
    v. Kennewick Sch. Dist. No. 17, 
    35 Wn. App. 280
    , 282, 
    666 P.2d 928
    (1983) (citing Spokane Truck & Dray Co. v. Hoefer, 
    2 Wash. 45
    , 
    25 P. 1072
     (1891)). Barring a statutory basis for vacating an arbitration award,
    the general rule is that “[a]rbitrators, when acting under the broad authority
    granted them by both the agreement of the parties and the statutes,
    become the judges of both the law and the facts.” N. State Constr. Co. v.
    Banchero, 
    63 Wn.2d 245
    , 249, 
    386 P.2d 625
     (1963).
    28 Wn. App. 2d at 478-79.
    Under the FAA, in determining whether arbitrators “exceeded [their] powers,” a
    court must examine whether the award draws its “essence from the contract.” Oxford
    Health Plans LLC v. Sutter, 
    569 U.S. 564
    , 569, 
    133 S. Ct. 2064
    , 
    186 L. Ed. 2d 113
    (2013). That is, a court must determine whether the award can be “rationally derived”
    from the agreement between the parties. Ario v. Underwriting Members of Syndicate 53
    at Lloyds for 1998 Year of Account, 
    618 F.3d 277
    , 295 (3d Cir. 2010). “Because the
    parties ‘bargained for the arbitrator’s construction of their agreement,’ an arbitral
    decision ‘even arguably construing or applying the contract’ must stand regardless of a
    court’s view of its (de)merits.” Oxford Health, 
    569 U.S. at 569
     (quoting E. Associated
    Coal. Corp. v. Mine Workers, 
    531 U.S. 57
    , 62, 
    121 S. Ct. 462
    , 
    148 L. Ed. 2d 354
    (2000)). To show the Panel exceeded its powers, the PMs must prove the Panel
    “act[ed] outside the scope of [its] contractually delegated authority” by issuing an award
    reflecting the Panel’s “own notions of economic justice” rather than “drawing its essence
    from the contract.” Oxford Health, 
    569 U.S. at 569
    .
    The MSA’s arbitration clause submits any dispute or claim “arising out of or
    relating to calculations performed by, or any determinations made by, the Independent
    Auditor,” including the NPM Adjustment, to binding arbitration. MSA § XI(c). The
    -8-
    No. 85360-1-I/9
    parties do not dispute that the Panel had the authority to interpret the applicable
    provisions in the MSA.
    The PMs contend that prior court decisions, based on the 2003 NPM Adjustment,
    support their position that the 2022 Reallocation Order exceeds the bounds of the MSA.
    Four courts considered the 2003 Panel’s Award: Maryland, Pennsylvania, Missouri, and
    New Mexico. State v. Philip Morris, Inc., 
    225 Md. App. 214
    , 
    123 A.3d 660
     (Ct. Spec.
    App. 2015) (Maryland); Commonwealth v. Philip Morris USA, Inc., 
    114 A.3d 37
     (Pa.
    Commw. Ct. 2015) (Pennsylvania); State ex rel. Greitens v. Am. Tobacco Co., 
    509 S.W.3d 726
    , 729 (Mo. 2017) (Missouri); Ord. Denying Pl.’s Mot. to Vacate Final Arb.
    Award & Granting Pl.’s Mot. to Vacate Partial Arb. Award, New Mexico ex rel. King v.
    Philip Morris, USA, No. D-101-cv-1997-01235 (Santa Fe 1st Judicial Dist. Ct. N.M. Sept.
    27, 2016) (New Mexico I).
    The 2003 Panel determined that the Independent Auditor should treat the
    Resolved States as diligent and not subject to the 2003 NPM Adjustment, but reduced
    the Adjustment by a percentage equal to the aggregate Allocable Shares of the
    Resolved States. All four courts concluded that the applicable MSA provisions
    unambiguously establish the conditions under which a State’s NPM Adjustment
    allocation would shift—if the State diligently enforced its qualifying statute. Maryland,
    
    225 Md. App. at 245-46
    ; Pennsylvania, 114 A.3d at 62; Missouri, 509 S.W.3d at 738;
    New Mexico I, ord. at 7. All four courts also concluded the 2003 Panel exceeded its
    power because the adopted procedure, the pro rata reduction to the reallocation,
    constituted an amendment of the MSA without consent of all parties affected by it.
    -9-
    No. 85360-1-I/
    10 Maryland, 225
     Md. App. at 247; Pennsylvania, 114 A.3d at 62; Missouri, 509 S.W.3d at
    738-39; New Mexico I, ord. at 7. 7
    The PMs assert that the 2003 cases are indistinguishable from the case here
    because the 2004 Panel also exceeded its powers by treating the Resolved States as
    not diligent without a factual determination.
    But the question before this court is limited to “whether the arbitrator (even
    arguably) interpreted the parties’ contract, not whether [the arbitrator] got its meaning
    right or wrong.” Oxford Health, 
    569 U.S. at 564
    . Or whether there is an error of law on
    the face of the award. Salewski, 
    189 Wn. App. at 904
    . Both tests “are intended to be
    narrow means of vacating an arbitration award.” Tobacco I, 28 Wn. App. 2d at 480.
    Here, the Panel did not exceed its power under either test. The Panel
    determined that the Resolved States “have not elected to invoke the option of
    challenging the application of the NPM Adjustment for 2004 by demonstrating that they
    diligently enforced the provisions of their Qualifying Statute under MSA Sec. IX(d)(2)(A)
    and (B).” Further, “the Resolved States must be deemed to be subject to the 2004 NPM
    Adjustment for purposes of calculating reallocation in accord with MSA Sec. IX(d)(1).”
    Unlike the 2003 Panel, the 2004 Panel interpreted the MSA and determined that
    it unambiguously set forth the procedure by which a State may seek relief from the NPM
    adjustment. The 2004 Panel used the plain language of the MSA to make its
    7 The MSA can only be amended by agreement of all parties affected by the amendment and
    “[t]he terms of any such amendment shall not be enforceable in any Settling State that is not a signatory
    to such amendment.” MSA § XVIII(j).
    -10-
    No. 85360-1-I/11
    determination. And because the 2004 Panel had the authority to interpret the MSA,
    they did not exceed their powers.
    The PMs also repeatedly assert that “the Panel fundamentally erred in holding
    that it ‘lacked authority’ to address the diligence of Resolved States.” But the actual
    holding of the Panel was:
    [I]n attempting in our May 2017 Reallocation Order to craft a reasonable
    alternative procedure to address the treatment of Resolved States with
    regard to calculating reallocation, we endeavored to make more efficient a
    process for which we lacked authority in the first place. . . . the fact that
    the MSA is silent on the treatment of States that negotiate a settlement for
    purposes of calculating reallocation of the NPM Adjustment does not
    create an ambiguity in the MSA which allows the Panels to impose a
    procedure they think reasonable.
    The MSA unambiguously sets forth the procedure by which a State may
    seek relief from the NPM Adjustment by showing its diligence in enforcing
    its Qualifying Statute. MSA Sec. IX(d)(2).
    (Emphasis added.) Thus, the Panel determined, consistent with its interpretation of the
    MSA, that it lacked authority to create an alternative procedure. This aligns with the
    decisions from Missouri, Maryland, Pennsylvania, and New Mexico where it was
    determined the 2003 Panel exceeded its powers by creating a new procedure and this
    constituted an unauthorized amendment of the MSA.
    Finally, the PMs assert the 2022 Reallocation Order impermissibly adds terms to
    the MSA, essentially that the Panel inserted a “irrebuttable presumption of non-diligence
    as to Resolved States that cannot be found anywhere in the MSA.”
    Again, the question before this court is “whether the arbitrator (even arguably)
    interpreted the parties’ contract, not whether [the arbitrator] got its meaning right or
    wrong.” Oxford Health, 
    569 U.S. at 569
    . The Panel interpreted MSA §§ IX(d)(2)(A) and
    -11-
    No. 85360-1-I/12
    (B) and determined that the Resolved States, because they did not elect to challenge
    application of the NPM Adjustment by demonstrating diligent enforcement, must be
    deemed subject to the NPM Adjustment for purposes of calculating reallocation.
    While the PMs strenuously oppose the Panel’s interpretation of the MSA, the
    Panel had the authority to interpret the MSA, interpreted the MSA, and determined how
    to reallocate the 2004 NPM Adjustment. We conclude that the trial court did not err in
    declining to vacate the award because it correctly concluded that the Panel did not
    exceed its authority.
    C
    The PMs assert that they are entitled to vacatur of the 2022 Reallocation Order
    because the Panel refused to hear pertinent and material evidence. We disagree.
    The scope of review under this provision is also narrow. Under the FAA, vacatur
    is appropriate only when “the arbitrators were guilty of misconduct . . . in refusing to
    hear evidence pertinent and material to the controversy.” 
    9 U.S.C. § 10
    (a)(3). “To
    vacate an award on this ground, the ‘misconduct must amount to a denial of
    fundamental fairness of the arbitration proceeding.’” Fellus v. Sterne, Agee & Leach,
    Inc., 
    783 F. Supp. 2d 612
    , 618 (S.D.N.Y. 2011) (quoting AT&T Corp. v. Tyco
    Telecomms. (U.S.) Inc., 
    255 F. Supp. 2d 294
    , 303 (S.D.N.Y. 2003)).
    The Panel explained:
    [T]he States that entered the Term Sheet Settlement with the PMs elected
    not to arbitrate a dispute concerning their diligence before the Panels.
    The Term Sheet Settlement resolved the disputes between the PMs and
    those Resolved States relating not only to the 2004 NPM Adjustment, but
    for the extended period 2003 through 2011. The Term Sheet Settlement
    entered by the Resolved States contained no discussion of Reallocation,
    no admission of liability, or agreement between the Parties concerning
    -12-
    No. 85360-1-I/13
    whether the Resolved States were diligent or non-diligent in the
    enforcement of their Qualifying Statutes. Moreover, since entering the
    Term Sheet Settlement, no Resolved State has sought to prove their
    diligence before this or any tribunal. . . .
    The Resolved States have not elected to invoke the option of challenging
    the application of the NPM Adjustment for 2004 by demonstrating that
    they diligently enforced the provisions of their Qualifying Statute under
    MSA Sec. IX(d)(2)(A) and (B). As a result, the Resolved States must be
    deemed to be subject to the 2004 NPM Adjustment for purposes of
    calculating reallocation in accord with MSA Sex. IX(d)(1).
    Contrary to the PMs assertion, the Panel did not decide to exclude pertinent and
    material evidence. The Panel determined that the MSA does not provide “for allowing
    the PMs to assert a diligence claim on behalf of a Resolved State” and the proposed
    procedure in the interim order in which the PMs would present evidence on the
    Resolved States diligence in a Phase 2 would constitute an unauthorized amendment of
    the MSA. Thus, this evidence was irrelevant. 8
    Last, the PMs assert that they were denied due process when the Panel
    departed from the 2017 Reallocation Order. “In the arbitration context, due process is
    satisfied so long as the arbitrator provided a fundamentally fair hearing, one that meets
    the minimal requirements of fairness—adequate notice, a hearing on the evidence and
    an impartial decision by the arbitrator.” Bhd. of Locomotive Eng’rs & Trainmen Gen.
    Comm. of Adjustment v. Union Pac. R.R. Co., 
    522 F.3d 746
    , 751 (7th Cir. 2008)
    8 The PMs also challenged the 2022 Reallocation Order on the same grounds in New Mexico.
    New Mexico II held that “the Panel properly exercised its authority to decide based on its interpretation of
    the unambiguous language of the MSA that the PMs did not have the right to present evidence regarding
    or otherwise put at issue in the arbitration, the diligence of the Resolved States.” Ord. Denying Defs.’
    Mot. to Vacate 2004 MSA Arbitration Panel’s July 19, 2022 Reallocation Ord., State ex rel. Torrez v.
    Philip Morris, USA, Inc., No. D-101-cv-1997-01235, at 7 (Santa Fe County 1st Jud. Dist. Ct., N.M. Aug.
    30, 2023) (New Mexico II).
    -13-
    No. 85360-1-I/14
    (quoting Int’l Bhd. Elec. Workers v. CSX Transp. Inc., 
    446 F.3d 714
    , 720 (7th Cir.
    2006)), aff’d, 
    558 U.S. 67
    , 
    130 S. Ct. 584
    , 
    175 L. Ed. 2d 428
     (2009).
    The PMs argue that the Panel’s reversal of the 2017 Reallocation Order
    prejudiced their rights. In support, the PMs cite International Union, United Mine
    Workers of America v. Marrowbone Development Co., 
    232 F.3d 383
     (4th Cir. 2000). In
    Marrowbone, a collective bargaining agreement expressly required the arbitrator to
    “conduct a hearing in order to hear testimony, receive evidence and consider
    arguments” if there was a factual dispute involved in the grievance. 
    232 F.3d at 389
    .
    Despite this clear language, and the parties affirmatively acknowledging the existence
    of factual disputes, the arbitrator never convened the hearing. Marrowbone, 
    232 F.3d at 389
    . On appeal, the Fourth Circuit held that this exceeded the arbitrator’s authority and
    denied the union a full and fair hearing. Marrowbone, 
    232 F.3d at 389
    .
    Unlike in Marrowbone, here, the PMs were not denied due process. The Panel
    entered the 2017 Reallocation Order on May 25, 2017. Following Maryland’s objection
    to the order, the Panel stayed consideration of the objection until the state-specific
    hearings were held and all diligence determinations were made. This decision was
    entered on September 10, 2018. Notably, the PMs agreed to defer consideration of this
    issue.
    Following the state-specific determinations, the Panel then issued a briefing
    schedule “to comprehensively address all post-Interim Award issues the Parties wished
    to raise.” Idaho, Maryland, New Mexico, Washington, and Wisconsin jointly moved to
    vacate the 2017 Reallocation Order. Oral arguments were conducted before all judges
    -14-
    No. 85360-1-I/15
    of the assigned 2004 NPM Adjustment Panels and they all participated in drafting the
    2022 Reallocation Order.
    The PMs were on notice in 2018 that this issue had been stayed. Following the
    state-specific determinations, the PMs had notice and were able to provide briefing and
    argument on these issues. Thus, the PMs had notice and an opportunity to be heard.
    Bhd. of Locomotive Eng’rs, 
    522 F.3d at 751
    .
    We conclude that the trial court did not err in declining to vacate the award
    because it correctly concluded that the Panel did not fail to consider material evidence.
    We affirm.
    WE CONCUR:
    -15-
    

Document Info

Docket Number: 85360-1

Filed Date: 8/19/2024

Precedential Status: Non-Precedential

Modified Date: 8/19/2024