In The Receivership Of: Applied Restoration, Inc. ( 2023 )


Menu:
  •        IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    In the Matter of the Receivership of:
    No. 84320-6-I
    APPLIED RESTORATION, INC.
    DIVISION ONE
    ANDERSEN CONSTRUCTION                            PUBLISHED OPINION
    COMPANY,
    Appellant,
    v.
    REVITALIZATION PARTNERS, LLC,
    Respondent.
    HAZELRIGG, A.C.J. — Andersen Construction Company appeals two
    separate orders for turnover issued by a court commissioner in favor of receiver
    Revitalization Partners, LLC, and challenges the superior court’s denial of its
    motion for revision. Andersen also argues the commissioner erred when they
    disallowed its claims against Applied Restoration, Inc. and entered final judgment
    in favor of the receiver. Because the record establishes that Andersen repeatedly
    refused to comply with the court orders pursuant to the receivership statute and
    because Andersen fails to demonstrate any error arising from the decisions of
    either the commissioner or judge in this matter, we affirm.
    No. 84320-6-I/2
    FACTS
    In May 2019, Applied Restoration, Inc. (ARI) and Andersen Construction
    Company entered into an agreement (subcontract) for ARI to perform work on the
    construction of the Quil Ceda Creek Casino (project), owned by the Tulalip Tribes
    of Washington (owner). ARI served as a subcontractor for Andersen, the general
    contractor on the project. In accordance with the agreement, ARI employed nine
    to ten laborers per day who worked directly on the project and also subcontracted
    with third parties (sub-tier subs) who provided further labor and materials for ARI’s
    work on the project. Through March 2020, Andersen paid ARI for the work that it
    had performed pursuant to the billing process and terms set out in the subcontract
    and prime contract. 1 On March 31, due to ongoing financial difficulties, ARI
    assigned all of its assets to Revitalization Partners, LLC and, on April 2, the trial
    court entered an order appointing Revitalization as the general receiver of ARI’s
    property and assets. At the time of the assignment, ARI had not paid all sub-tier
    subs for their work on the project, in violation of the subcontract. On April 6,
    Revitalization contacted Andersen, explained that ARI had been placed into
    receivership and identified itself as the receiver. 2 Revitalization assured Andersen
    that it would continue to operate ARI and fulfill its obligations on the project as
    previously agreed.
    1 The subcontract expressly incorporated various terms and provisions set out in the prime
    contract between Andersen and the owner.
    2 “Receivership” simply means “the case in which the receiver is appointed.”            RCW
    7.60.005(11). A “general receivership” is “a receivership in which a general receiver is appointed”
    and a “custodial receivership” is “a receivership in which a custodial receiver is appointed.” Id.
    -2-
    No. 84320-6-I/3
    Thereafter, Andersen stopped paying ARI and did not pay Revitalization for
    the work performed post-assignment. Revitalization demanded assurance from
    Andersen that it would pay ARI for the work, but Andersen refused absent certain
    conditions: “If the Receiver cannot guarantee that it will pay all pre-receivership
    claims related to this Project, then Andersen cannot issue April’s payment, the
    Receiver must reject the subcontract agreement and Andersen will find another
    subcontractor.” According to Andersen, Revitalization was not entitled to payment
    from Andersen because the “unequivocal language of the Subcontract between
    Andersen and ARI . . . control[led] the terms of payment to ARI and/or the
    Receiver.” Revitalization had paid sub-tier subs $42,467.25 for post-assignment
    work and ARI extended over $200,000.00 on work and materials for the project
    during that time.
    Between May and July 2020, Revitalization filed three motions against
    Andersen for turnover of the subcontract funds pursuant to RCW 7.60.005(9) and
    .070. On May 15, Revitalization filed its first motion, seeking $157,342.97, but that
    motion was denied as the project owner had not yet paid Andersen, accordingly it
    had neither possession or control of the funds.        The statute requires either
    possession or control of funds as a prerequisite to turnover. RCW 7.60.070.
    Roughly two weeks later, the owner issued payment to Andersen for work ARI had
    completed in April 2020.       Revitalization then requested confirmation from
    Andersen that it would pay ARI for post-assignment work but, on June 3, Andersen
    again refused to do so unless Revitalization guaranteed that it would pay all pre-
    assignment claims related to the project.
    -3-
    No. 84320-6-I/4
    On June 4, Revitalization told Anderson that ARI’s employees would not be
    working on the project that day due to “Andersen’s unwillingness to commit to
    paying [ARI] for the work being done, as well as the completed work.” That same
    day, Andersen forwarded a letter to Revitalization from the owner to demand return
    of its $113,480.89 payment to Andersen for the work on the project in April. On
    June 5, Revitalization demanded Andersen turn over the subcontract funds for the
    May billing and provided notice of another action for turnover, but Andersen
    refused and, further, remitted the April funds to the owner.
    On June 11, Revitalization filed a second motion for turnover for the April
    billing. On July 7, after reviewing the motion, accompanying declarations, and
    exhibits, the superior court commissioner granted the motion and ordered
    Andersen to pay the subcontract funds to Revitalization for both April and May
    2020. The order required Andersen to pay Revitalization for labor, materials, and
    vendor costs directly related to the project and to place the balance of the amount
    set out in each month’s billing into the court registry. Further, the court ordered
    Andersen to follow the same payment pattern for the month of June, due on
    August 20. Andersen then filed a motion for reconsideration of the order, but the
    commissioner rejected Andersen’s arguments and denied reconsideration.
    Subsequently, Andersen filed a motion for revision of the commissioner’s denial of
    reconsideration by a superior court judge. The court denied the motion for revision.
    On July 29, as Andersen had not complied with the commissioner’s
    previous turnover order regarding payment for the month of May, Revitalization
    filed a third motion for turnover. Though Andersen had placed most of the funds
    -4-
    No. 84320-6-I/5
    for the May billing into the court registry pending outcome of the motion, the
    previous order required Anderson pay those funds directly to Revitalization. On
    November 3, the commissioner granted the third motion for turnover, in part, and
    ordered the funds for the May billing to be released to Revitalization. 3
    On February 26, 2021, Andersen filed an amended proof of claim wherein
    it asserted an unsecured debt of $941,444.45 against ARI and Revitalization based
    on the following: “(i) alleged incomplete work by ARI ($664,146), (ii) cost to repair
    north exterior ($45,339), (iii) amounts to be retained for subcontractor payments
    ($18,139.82), (iv) amounts paid by Andersen to subcontractors Salmon Bay and
    PCI [(Performance Contracting, Inc.)] ($302,098.92), and (v) insurance costs
    ($13,096.40).” Andersen additionally sought $76,483.24 as reimbursement for its
    direct payment to PCI.         Though the foregoing amounts total $1,119,303.38,
    Andersen still owed $177,858.93 to Revitalization for work completed post-
    assignment and sought to offset that amount by reducing the claim to $941,444.45.
    On April 21, 2021, Revitalization filed a motion to authorize rejection of the
    executory contract with Andersen pursuant to RCW 7.60.130.                        The motion
    expressly requested that the court authorize Revitalization’s rejection of the
    subcontract between ARI and Andersen. On May 14, the commissioner granted
    the motion and authorized Revitalization to reject the subcontract. 4
    3 Andersen filed a motion for discretionary review of the July 7 and November 3 orders
    granting turnover, which this court denied. Ruling Den. Rev., Andersen Constr. Co., v.
    Revitalization Partners, LLC, No. 82096-6-I (Wash. Ct. App. May 7, 2021).
    4 In briefing, Revitalization asserts that Andersen did not seek rejection damages under
    RCW 7.60.130(2) within the statutorily proscribed timeframe, thus waiving any such recovery on
    that basis. Andersen has not responded to that contention.
    -5-
    No. 84320-6-I/6
    On February 3, 2022, Revitalization filed an objection to Andersen’s claim
    and sought leave of the court to disallow a portion of the unsecured claim. A
    hearing on the motion was conducted on March 16, at the conclusion of which the
    court entered an order disallowing Andersen’s claims. Specifically, the order
    disallowed $1,006,023.09 of Andersen’s claim, allowed $113,340.29 as an
    unsecured claim, and prohibited the $177,858.93 offset sought by Andersen.
    Andersen was ordered to pay Revitalization that amount due under the subcontract
    directly. However, despite repeated requests from Revitalization, Andersen did
    not make the payment and Revitalization filed a motion seeking a contempt finding
    for Andersen’s failure to remit payment. Though the court did not hold Andersen
    in contempt, it entered an order providing that the remedy for further
    noncompliance would be to “reduce the obligation to a judgment.”
    On June 10, 2022, Revitalization filed a motion to enter final judgment
    against Andersen. The motion was heard on June 27 and, despite filing a written
    objection to the judgment, Andersen failed to appear for the hearing.        The
    commissioner entered judgment in favor of Revitalization in the amount of
    $177,858.93.
    Andersen timely appealed.
    ANALYSIS
    I.    Procedural Posture and Standard of Review
    Andersen first assigns error to the commissioner’s orders that granted the
    receiver’s second and third motions for turnover. According to Andersen, under
    RCW 7.60.070, the orders of turnover for April and May billings were erroneous
    -6-
    No. 84320-6-I/7
    because Andersen did not have possession or control over those funds when the
    turnover was demanded. However, because of the manner by which Andersen
    has pursued review in this case, neither the commissioner’s July 7 order on the
    second motion for turnover concerning the April billings nor the July 17 denial of
    Andersen’s motion for reconsideration of that order are directly before this court.
    On July 7, 2020, the commissioner granted Revitalization’s second motion
    for turnover in part and, on July 17, 2020, denied Andersen’s motion for
    reconsideration of that order. Andersen then filed a motion for revision of the
    commissioner’s July 17 order, but the superior court judge denied that motion.
    Because Andersen challenges the superior court’s denial of revision in its notice
    of appeal to this court, the commissioner’s two previous orders upon which that
    denial of revision was based are outside the scope of our review. “Once the
    superior court makes a decision on revision, the appeal is from that decision.”
    Faciszewski v. Brown, 
    187 Wn.2d 308
    , 313 n.2, 
    386 P.3d 711
     (2016). Accordingly,
    “this court reviews the superior court’s ruling, not the commissioner’s.” Maldonado
    v. Maldonado, 
    197 Wn. App. 779
    , 789, 
    391 P.3d 546
     (2017). The superior court’s
    denial of a motion for revision “constitutes an adoption of the commissioner’s
    decision, and the court is not required to enter separate findings and conclusions.”
    
    Id.
     We review the denial of a motion for revision for an abuse of discretion, which
    exists when the court’s decision is “exercised on untenable grounds or for
    untenable reasons, or if its decision was reached applying the wrong legal
    standard.” River House Dev., Inc. v. Integrus Architecture, P.S., 
    167 Wn. App. 221
    , 231, 
    272 P.3d 289
     (2012); Maldonado, 197 Wn. App. at 789.
    -7-
    No. 84320-6-I/8
    Receiverships are an equitable remedy and trial courts are “accorded great
    flexibility in fashioning relief under [their] equitable powers.” Bero v. Name Intel.,
    Inc., 
    195 Wn. App. 170
    , 179, 
    381 P.3d 71
     (2016); Friend v. Friend, 
    92 Wn. App. 799
    , 803, 
    964 P.2d 1219
     (1998). In matters of equity, trial courts have inherent
    authority beyond that expressly granted by the legislature. See Allen v. Am. Land
    Rsch., 
    95 Wn.2d 841
    , 852, 
    631 P.2d 930
     (1981) (“The superior court’s inherent
    authority to enforce orders and fashion judgments is not dependent on the
    statutory grant.”).   Thus, “[w]e review the authority of a trial court to fashion
    equitable remedies under the abuse of discretion standard.” In re Foreclosure of
    Liens, 
    123 Wn.2d 197
    , 204, 
    867 P.2d 605
     (1994).
    Chapter 7.60 RCW also provides trial courts with broad discretion over
    receiverships. Bero, 195 Wn. App. at 175. For example, courts have discretion to
    appoint and terminate receivers and to “manage the duration of the extraordinary
    remedy.” Mony Life Ins. Co. v. Cissne Fam., LLC, 
    135 Wn. App. 948
    , 952, 
    148 P.3d 1065
     (2006); Bero, 195 Wn. App. at 178. Once the trial court appoints a
    receiver, that person becomes an agent of the court and retains “broad powers to
    manage the receivership property, liquidate assets, and satisfy creditors.” Bero,
    195 Wn. App. at 175.
    With these equitable and statutory powers in mind, we review the trial
    court’s rulings regarding the receivership that order turnover, disallow claims, and
    enter judgment, for an abuse of discretion. Again, an abuse occurs when a
    decision is “‘manifestly unreasonable, or exercised on untenable grounds, or for
    untenable reasons.’” Mony Life Ins., 135 Wn. App. at 952-53 (internal quotation
    -8-
    No. 84320-6-I/9
    marks omitted) (quoting T.S. v. Boy Scouts of Am., 
    157 Wn.2d 416
    , 423, 
    138 P.3d 1053
     (2006)).        The trial court’s findings of fact are reviewed for substantial
    evidence, which exists when there is “a sufficient quantum of evidence in the
    record to persuade a reasonable person that the declared premise is true.”
    Wenatchee Sportsmen Ass’n v. Chelan County, 
    141 Wn.2d 169
    , 176, 
    4 P.3d 123
    (2000).
    II.     Turnover Orders
    A “[r]eceiver” is a “person appointed by the court as the court’s agent, and
    subject to the court’s direction, to take possession of, manage, or dispose of
    property of a person.” RCW 7.60.005(10). Pursuant to RCW 7.60.070, “Upon
    demand by a receiver . . . any person shall turn over any property over which the
    receiver has been appointed that is within the possession or control of that person
    unless otherwise ordered by the court for good cause shown.” Property is defined
    in this chapter as “all right, title, and interests, both legal and equitable, and
    including any community property interest, in or with respect to any property of a
    person with respect to which a receiver is appointed, regardless of the manner by
    which the property has been or is acquired.” RCW 7.60.005(9). 5 Further, once a
    trial court enters an order appointing a receiver, an automatic stay that is applicable
    to all persons arises of “[a]ny act to obtain possession of estate property from the
    5 Andersen argues in its brief that the trial court erred in entering both orders for turnover
    because “Andersen did not have property belonging to ARI” as defined by the subcontract. Its
    argument largely relies on the contention that the terms of the subcontract supersede the provisions
    of the receivership statute, such as RCW 7.60.070 and .110(c). However, as set out in detail herein,
    Andersen offers no authority in support of this position which is clearly at odds with both the court’s
    equitable powers and general public policy considerations.
    -9-
    No. 84320-6-I/10
    receiver, or to interfere with, or exercise control over, estate property.” RCW
    7.60.110(1)(c).
    A. April Billing
    The April billing funds were addressed in the order granting the second
    motion for turnover, the order denying reconsideration of that turnover order, and
    the superior court’s order denying revision of the order denying reconsideration.
    Though we elect to address the arguments of the parties regarding this assignment
    of error and go to the original ruling by the commissioner, we note that Andersen
    offers no argument as to how the judge’s order denying revision was an abuse of
    discretion.
    When it granted the second motion for turnover, the trial court found that
    Andersen was withholding the April billing, which amounted to $113,481.00, and
    that Andersen’s claim for an offset of $272,236.83 against that billing was not
    appropriate. Andersen was ordered to pay $113,481.00 of the subcontract funds
    as follows: $84,164.54 to Revitalization for costs directly related to the project and
    $29,313.46 to be placed in the court registry for the balance of the April billing.
    Those payments were due on July 15, 2020.
    First, Andersen’s argument that it did not have any property belonging to
    Revitalization for the April billing under the terms of the subcontract is irrelevant.
    Andersen offers no authority for its bald assertion that the terms of the subcontract
    control over those of the receivership statute. Again, under RCW 7.60.006(9),
    property belonging to the receiver includes “all right, title, and interests, both legal
    and equitable, and including any community property interest, in or with respect to
    - 10 -
    No. 84320-6-I/11
    any property of a person with respect to which a receiver is appointed, regardless
    of the manner by which the property has been or is acquired.” Because there is
    no dispute that the work addressed in the April billing was performed,
    Revitalization, as the receiver, had a right to payment for that work; the funds
    belonged to Revitalization.
    Second, Andersen cites to United States v. Aubrey, in support of its
    argument that the April funds were Tribal property and Andersen never had control
    of them.   
    800 F.3d 1115
     (9th Cir. 2015).        Andersen’s reliance on Aubrey is
    misplaced. In that case, the United States was prosecuting a contractor who had
    contracted directly with a Tribal organization and the dispute concerned federal
    funds that had been transferred to the Tribal organization. The case is materially
    distinguishable on those facts alone.
    Here, the court’s finding that Andersen was in possession or control of the
    property is supported by substantial evidence. As the commissioner explained
    after reviewing the correspondence from both the owner and Andersen, it was
    clear “that Andersen was paid by the [owner] and Andersen took affirmative action
    to cause the [owner] to cancel payment.” This was confirmed by the content and
    timing of e-mails between the parties, Andersen’s own declaration, and the letter
    from the owner that Andersen forwarded to Revitalization.
    Once the owner issued payment to Andersen for work ARI had completed
    in April, Revitalization requested confirmation from Andersen that it would pay for
    the post-assignment work. However, on June 3, Andersen refused to do so without
    express agreement that Revitalization would pay all pre-assignment claims from
    - 11 -
    No. 84320-6-I/12
    the sub-tier subs. On June 4, in response to this refusal, Revitalization told
    Anderson that its employees would not be working on the project that day.
    Andersen responded by accusing Revitalization of breaching the subcontract and,
    later that same day, forwarded a letter to Revitalization from the owner that
    demanded return of the April billing funds from Andersen. The commissioner
    expressly found the timing of the e-mails and the word choice in the owner’s letter
    stating, “[i]t has come to the [owner’s] attention . . .,” established that Andersen
    had possession of the April funds, even if temporarily, and withheld them. On June
    5, Revitalization demanded Andersen turn over the funds, but Andersen refused
    and instead returned them to the owner.
    Pursuant to RCW 7.60.070, Andersen was required to “turn over any
    property over which the receiver ha[d] been appointed that [was] within [its]
    possession or control.” Because substantial evidence supports the trial court’s
    finding that “Andersen had possession of the funds owed to ARI” and “withheld
    those funds,” this finding was proper. Moreover, as Revitalization correctly asserts
    in briefing, “If a party could simply avoid the consequences of a receivership by
    transferring estate property, the statute would be useless in effectuating its goals—
    achieving equity for all creditors.”
    Accordingly, the commissioner’s order on turnover as to the April billing was
    not an abuse of discretion and, therefore, the superior court did not abuse its
    discretion in denying Andersen’s motion for revision of the commissioner’s order
    denying reconsideration of the order for turnover.
    - 12 -
    No. 84320-6-I/13
    B. May Billing
    Regarding the order granting the third motion for turnover, Andersen again
    argues that the terms of the subcontract are controlling and asserts that it never
    had possession or control of the May billing funds. Neither argument holds merit;
    the former lacks any supporting authority and the latter is refuted by the fact the
    Andersen placed $81,179.70 into the court registry for the May billing, at least a
    rebuttable demonstration of control over the funds. 6 The commissioner’s order
    granting the second motion for turnover set out the specific procedure Andersen
    was to follow for the funds relating to the April and May billings. When Andersen
    failed to comply with the court’s requirements as to the May billing, the
    commissioner granted the third motion for turnover, which ordered the release of
    funds that Andersen had placed into the court registry for that billing.
    Andersen further argues that both turnover orders were erroneous “due to
    a bona fide dispute over the funds.”                We disagree.         Under RCW 7.60.070,
    Andersen was required to turn over the property to Revitalization “unless there
    exist[ed] a bona fide dispute with respect to the existence or nature of the receiver’s
    interest in the property, in which case turnover shall be sought by means of an
    action under RCW 7.60.160.” Andersen cites to the commissioner’s order granting
    the receiver’s second motion for turnover and argues that, because “portions of
    the funds related to the April Billing were to be placed in the court registry,” RCW
    6 While Andersen asserts that these funds did not constitute the May billing because
    Andersen paid them out of pocket without first being paid by the owner, that alone does not
    establish an abuse of discretion on the part of the trial court. Rather, this order was a clear example
    of the trial court exercising its equitable powers and, considering Andersen’s continued refusal to
    abide by the court’s previous orders under the receivership statute, the trial court’s order was not
    beyond its authority. See Friend, 
    92 Wn. App. at 803-04
    .
    - 13 -
    No. 84320-6-I/14
    7.60.160 should have governed the action. However, Andersen fails to understand
    that the funds that it was ordered to pay directly to the receiver, $84,164.54 for
    demonstrable costs for labor, materials, and vendor costs related to the project,
    were not disputed. As there was no bona fide dispute, there was no abuse of the
    discretion by the commissioner or the superior court on revision.
    Andersen next contends that the turnover orders were erroneous because
    they conflicted with the court’s previous orders in the “Foushee matter.” That
    matter, which involved ARI and a different owner, is distinguishable and
    immaterial. While Andersen argues that the facts are “nearly identical,” it ignores
    the key distinction that Foushee had neither control nor possession of the funds
    the receiver demanded but, as established here, Andersen did. More critically,
    despite Andersen’s argument to the contrary, a different ruling based on distinct
    facts in a tangentially related matter involving the same receivership does not
    trigger application of the law of the case doctrine. “Except in the case of jury
    instructions, the law of the case doctrine requires a prior appellate court decision
    in the same case.” In re Est. of Jones, 
    170 Wn. App. 594
    , 605, 
    287 P.3d 610
    (2012). Because the commissioner’s orders in the Foushee matter constitute
    neither jury instructions nor the decision of an appellate court, the rule of the case
    doctrine is inapplicable here.
    III.   Rejection of Andersen’s Claims
    Andersen avers the trial court erred in rejecting its claims and ordering it to
    pay the subcontract balance to the receiver. Specifically, Andersen challenges the
    - 14 -
    No. 84320-6-I/15
    rejection of claims for the “retention balance ($18,139.81),”7 costs it asserted were
    required to repair ARI’s “defective work ($45,339.00),” and costs of completing
    ARI’s “abandoned work ($664,146.00).”
    The receivership statute is instructive and controlling 8 here; according to
    the relevant provisions, Andersen had 30 days following Revitalization’s rejection
    of the subcontract to file a claim for damages on that basis. A general receiver
    may “reject any executory contract or unexpired lease of the person over whose
    property the receiver is appointed upon order of the court following notice to the
    other party to the contract or lease upon notice and a hearing.” RCW 7.60.130(1).
    Such a rejection “shall be treated as a breach of the contract or lease occurring
    immediately prior to the receiver’s appointment” and any claim of a party to the
    contract or lease, based on the receiver’s rejection of it, “shall be served upon the
    receiver in the manner provided for by RCW 7.60.210 within thirty days following
    the rejection.” RCW 7.60.130(2). Because Andersen failed to file a claim for
    damages within the 30 days after the court permitted Revitalization to reject the
    subcontract, those claims were properly barred.
    7 In construction contracts, “retainage” refers to the percentage that the owner or general
    contractor may withhold from each progress payment to the contractor or subcontractor until final
    completion of the project. Steven Walt & Emily L. Sherwin, Contribution Arguments in Commercial
    Law, 42 EMORY L.J. 897, 907-08 (1993).
    Andersen explicitly asserts that it is entitled to the “reimbursement” of $18,138.81 for the
    retention of three sub-tier subs that Revitalization had not paid, however, it fails to provide any
    statutory basis that would entitle it to such a “reimbursement.”
    8 The majority of Andersen’s argument, once again, focuses on the terms of the subcontract
    rather than those found in the receivership statute and argues, without authority, that the former is
    controlling. The commissioner correctly disagreed.
    - 15 -
    No. 84320-6-I/16
    Andersen next challenges the commissioner’s order disallowing claims for
    completion damages9 based on its determination that Andersen anticipatorily
    breached the subcontract. According to Andersen, it did not anticipatorily breach
    the subcontract and ARI breached the subcontract first by abandoning the work.
    An anticipatory breach is a “‘positive statement or action by the promisor
    indicating distinctly and unequivocally that [they] either will not or cannot
    substantially perform any of [their] contractual obligations.’” Olsen Media v. Energy
    Scis., Inc., 
    32 Wn. App. 579
    , 585, 
    648 P.2d 493
     (1982) (quoting Lovric v. Dunatov,
    
    18 Wn. App. 274
    , 282, 
    567 P.2d 678
     (1977)). “A party’s intent not to perform may
    not be implied from doubtful and indefinite statements that performance may or
    may not take place.” Wallace Real Est. Inv., Inc. v. Groves, 
    124 Wn.2d 881
    , 898,
    
    881 P.2d 1010
     (1994). However, when a party makes repeated conditional threats
    to withhold payment due under a contract, such conduct may qualify as repudiation
    of the contract and an anticipatory breach that justifies the other party walking
    away. See CKP, Inc. v. GRS Constr. Co., 
    63 Wn. App. 601
    , 620, 
    821 P.2d 63
    (1991).
    Here, Andersen expressly, directly, and repeatedly told Revitalization that it
    would not provide further payments unless Revitalization guaranteed it would pay
    the “outstanding amounts owed” to the sub-tier subs under the terms of the
    subcontract. Although Revitalization explained to Andersen that it was prohibited
    9 Completion damages are those “incurred to complete the contract following the owner’s
    just termination of the contract for default or the contractor’s wrongful repudiation of the contract or
    wrongful abandonment of the project.” 6 PHILIP L. BRUNER & PATRICK J. O'CONNOR, JR., BRUNER &
    O'CONNOR ON CONSTRUCTION LAW § 19:78 (2023). Typically, they are measured by “the reasonable
    cost to complete the contract in conformance with its terms, less unpaid contract funds.” Id.
    - 16 -
    No. 84320-6-I/17
    from doing so by the plain language of the receivership statute, Andersen would
    not yield and reiterated its refusal to pay the funds unless Revitalization satisfied
    its condition. In an e-mail to Revitalization, Andersen explicitly stated that “[i]f the
    Receiver cannot guarantee that it will pay all pre-receivership claims related to this
    Project, then Andersen cannot issue April’s payment, the Receiver must reject the
    subcontract agreement and Andersen will find another subcontractor.” According
    to Andersen, Revitalization was not entitled to payment from Andersen as the
    “unequivocal language of the Subcontract between Andersen and ARI . . .
    control[led] the terms of payment to ARI and/or the Receiver.” 10
    Based on its continuous threats and, as the commissioner noted, the fact
    that “[t]hroughout this matter Andersen has been obstructive to the receivership
    process,” we conclude that substantial evidence supports the commissioner’s
    implicit finding that Andersen anticipatorily breached the subcontract before the
    court granted Revitalization permission to reject it.                        Because Andersen
    anticipatorily breached the subcontract and was thus not entitled to completion
    damages, the trial court did not err in disallowing this portion of its claim.
    Andersen further contends that the trial court erred by ordering payment of
    the “subcontract balance,” i.e., the $177,858.93 that Andersen sought as an
    10 As Andersen had posted a payment bond on the project, it faced liability under the
    subcontract in the event that Revitalization failed to pay its sub-tier subs in full. In order to avoid
    its own liability under the terms of the subcontract, Andersen chose to pay the sub-tier subs
    pursuant to the subcontract and in violation of the receivership statute.
    It is unclear whether compliance with the requirements of the receivership statute would
    constitute a defense to any claims against Andersen for breach of the payment terms set out in the
    contract with the project owner, and the parties have made no such argument. In other words,
    while Andersen insists that it had no choice but to withhold payment to Revitalization, Andersen
    may have made a strategic choice to prioritize the subcontract above the receivership statute.
    - 17 -
    No. 84320-6-I/18
    offset. 11 Strangely, Andersen asserts there is “no evidence in the record” that the
    subcontract balance was owed to Revitalization.                   However, at the contempt
    hearing on Andersen’s failure to comply with its payment obligations, Andersen
    confirmed that it sought to “offset” the $177,858.93 from the amount it owed to
    Revitalization because it had already paid the subcontractor PCI in full. The trial
    court rejected Andersen’s attempted offset and explained that the payment to the
    subcontractor PCI was wrongful. The court concluded that Andersen was only
    entitled to an offset in an amount equal to a pro-rata share. In the order disallowing
    Andersen’s claims, the court reiterated that “Andersen paid the subcontractor
    (wrongfully) PCI in full. PCI should only have pro-rata share as other unsecured
    creditors will. Andersen is entitled to PCI’s pro-rata share once that pro-rata share
    is determined.”      Accordingly, the trial court prohibited “the offset sought by
    Andersen in its [c]laim in the amount of $177,858.93” and required Andersen to
    pay that amount directly to Revitalization.
    Under RCW 7.60.210, the submission of all claims in general receiverships
    “arising prior to the receiver’s appointment, must be served in accordance with this
    chapter, and any claim not so filed is barred from participating in any distribution
    to creditors in any general receivership.” RCW 7.60.230 provides the priorities for
    distribution of payment to creditors for the allowed claims in a general receivership.
    Pursuant to the statutory priorities, creditors with general unsecured claims are
    paid on a pro-rata basis after all other claims have been distributed.                         RCW
    11 Again, Andersen relies on its position that it did not anticipatorily breach the subcontract
    and insists that Revitalization abandoned the project. As we have explained, this argument is
    belied by the record.
    - 18 -
    No. 84320-6-I/19
    7.60.230(1)(h). Because Andersen’s claim is unsecured and does not fall within
    any exception to the priority scheme, Andersen shall receive distribution for that
    claim on a pro-rata basis along with any other unsecured creditors. Andersen
    chose to pay its subcontractors for claims that arose before ARI was placed into
    receivership and sought reimbursement of those payments in full as an offset. Its
    arguments on appeal are as unpersuasive as they were in the trial court; Andersen
    cannot circumvent the receivership statute and, though it paid its subcontractors
    in full, it is only entitled to a pro-rata distribution of its claim.
    Andersen’s final challenge to the award of the subcontract balance to
    Revitalization is the assertion that it is barred by the law of the case doctrine
    because it conflicts with the commissioner’s turnover order.             As already
    established, that doctrine has no bearing in this context.
    III.   Entry of Judgment against Andersen
    When Andersen failed to comply with the court’s order on the turnover
    motions, Revitalization moved for a finding of contempt. While the court declined
    to find that Andersen was in contempt, it expressly noted that a remedy for
    Andersen’s continued failure to comply could be entry of judgment. After payment
    had still not been made, Revitalization moved for entry of judgment, to which
    Andersen objected in writing.           However, despite filing formal opposition to
    Revitalization’s action, Andersen failed to appear for the hearing on the motion and
    the trial court entered judgment in favor of Revitalization.
    Andersen argues that the trial court erred in entering judgment against it for
    the same reasons it asserts that the court erred with regard to the order disallowing
    - 19 -
    No. 84320-6-I/20
    its claims.   These arguments have been addressed herein and need not be
    repeated. Andersen further avers that the court erred by refusing the request in
    its written opposition to “enter express findings of fact linking the judgment amount
    to documents in the record.” Revitalization contends that the trial court did not err
    as to the form of the judgment because the trial court had already addressed the
    issues, did not require additional proceedings, and made oral findings of fact.
    As it did in its written objection to the entry of judgment, Andersen cites
    Pacific Marine Insurance Co. v. Department of Revenue, 
    181 Wn. App. 730
    , 737,
    
    329 P.3d 101
     (2014) in its opening brief and claims the case stands for the
    proposition Andersen characterized, in both its pleading in the trial court and
    appellate briefing, as an “[a]ppellate court cannot affirm a superior court’s entry of
    judgment if the grounds are not supported by the court record.” No such rule
    statement lives in that opinion. In Pacific Marine, the court simply provided the
    common rule that an appellate court “may affirm the superior court’s summary
    judgment decision on any ground supported by the record.” 
    Id.
    Beyond the mischaracterization of the language in Pacific Marine, Andersen
    cites no authority for its assertion that the trial court was required to provide explicit
    written findings of fact. This court need not consider arguments for which a party
    has not cited authority. Norcon Builders, LLC v. GMP Homes VG, LLC, 
    161 Wn. App. 474
    , 486, 
    254 P.3d 835
     (2011). Moreover, the trial court made oral findings.
    The commissioner found that awarding Andersen what it sought would have
    provided Andersen an amount close to its pre-filing, rather than post-filing, claim.
    The trial court clearly stated, “That’s not appropriate.”          Andersen does not
    - 20 -
    No. 84320-6-I/21
    challenge the court’s oral findings. Unchallenged findings are treated as verities
    on appeal. Tapper v. Emp’t Sec. Dep’t, 
    122 Wn.2d 397
    , 407, 
    858 P.2d 494
     (1993).
    Absent any authority to the contrary, the trial court did not err by not entering written
    findings of fact in this case.
    IV.    Attorney Fees
    Andersen requests attorney fees, costs, and expenses incurred herein
    pursuant to article 11.5 of the subcontract which provides that the prevailing party
    shall be entitled to such an award. Because Andersen has not prevailed, we reject
    its request for fees and costs.
    Revitalization also seeks an award of attorney fees pursuant to RCW
    7.60.080 and RAP 18.9(a). Under RAP 18.9(a), this court may order a party who
    files a frivolous appeal “‘to pay terms or compensatory damages to any other party
    who has been harmed by the delay or the failure to comply or to pay sanctions to
    the court.’” Kinney v. Cook, 
    150 Wn. App. 187
    , 195, 
    208 P.3d 1
     (2009) (quoting
    RAP 18.9(a)). Such sanctions include “‘an award of attorney fees and costs to the
    opposing party.’” 
    Id.
     (quoting Yurtis v. Phipps, 
    143 Wn. App. 680
    , 696, 
    181 P.3d 849
     (2008)). “[A]n appeal is frivolous if there are no debatable issues upon which
    reasonable minds might differ, and it is so totally devoid of merit that there was no
    reasonable possibility of reversal.” Streater v. White, 
    26 Wn. App. 430
    , 435, 
    613 P.2d 187
     (1980). While we reject Andersen’s arguments, they were not frivolous.
    Accordingly, we decline to award fees as a sanction.
    Revitalization further asserts Andersen’s repeated opposition to the
    cooperation required under RCW 7.60.080 resulted in frivolous litigation and
    - 21 -
    No. 84320-6-I/22
    excessive legal fees. However, the plain language of the statute is devoid of any
    mention of attorney fees and we similarly decline to award them on that proffered
    basis.
    Affirmed.
    WE CONCUR:
    - 22 -
    

Document Info

Docket Number: 84320-6

Filed Date: 12/4/2023

Precedential Status: Precedential

Modified Date: 12/4/2023