Alexandria Real Equities Inc. John J. Cox, Dean A. Takko, V. University Of Wa ( 2023 )


Menu:
  •                                                                                              Filed
    Washington State
    Court of Appeals
    Division Two
    December 5, 2023
    IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    DIVISION II
    ALEXANDRIA REAL ESTATE EQUITIES,                                  No. 57985-5-II
    INC., a Washington State Taxpayer, JOHN
    JOSEPH COX, a Washington State Taxpayer,
    and DEAN A. TAKKO, a Washington State
    Taxpayer,
    PUBLISHED OPINION
    Appellants,
    v.
    UNIVERSITY OF WASHINGTON, a Public
    Institution of Higher Education and Agency of
    the State of Washington.
    Respondent.
    PRICE, J. — This case arises from a selection process used by the University of Washington
    (UW) to retain a real estate developer for a new building on its campus. The development plan
    involved a variation of a leaseback arrangement. UW proposed to enter an 80-year ground lease
    with a developer for the property. The developer, in turn, would demolish an existing building
    and construct the new one, incurring all of the costs. The developer would own the building for
    the 80-year duration of the ground lease, but UW would agree in advance to lease back a portion
    of the building space from the developer. At the end of the ground lease, the building’s ownership
    would return to UW.
    Alexandria Real Equities, Inc. (ARE) was one of the two finalists to negotiate for the
    development contract, but UW ultimately selected ARE’s competitor.
    No. 57985-5-II
    Litigation resulted. At the superior court, ARE and two individual taxpayers asserted three
    claims against the university—(1) UW lacked authority to enter into this particular type of
    agreement, (2) UW failed to use a required competitive bidding procedure to select a developer,
    and (3) UW’s selection process was arbitrary and capricious because it did not follow the selection
    process described in a request for developers’ proposals. The superior court granted UW summary
    judgment on the first and second claims, and the third claim proceeded to a bench trial. Following
    the trial, the superior court dismissed ARE’s third claim for lack of standing and because it
    concluded UW’s selection process was not arbitrary and capricious. ARE appeals.
    We affirm the superior court’s summary judgment order because UW had authority to enter
    into the contracts with ARE’s competitor and UW was not required to strictly adhere to a specific
    competitive bidding process. We also affirm the dismissal of ARE’s third claim because ARE
    lacked standing for the claim.
    FACTS
    I. BACKGROUND
    A. UW’S DEVELOPMENT PLANS
    UW is a state university with a campus in Seattle and is governed by a “Board of Regents.”
    In 2019, UW began its process to redevelop its West Campus (a 70-acre portion of its Seattle
    campus) to create an “innovation district.” Clerk’s Papers (CP) at 1458. UW wanted the new
    West Campus to serve as a central location for students and faculty in multiple fields to partner
    with businesses, government, nonprofit organizations, and the Seattle community to solve critical
    problems. UW created a 30-year plan to redevelop West Campus, with 19 locations identified for
    reconstruction.
    2
    No. 57985-5-II
    The first site selected for reconstruction was site W27. The site is a 1.5-acre property, and
    its redevelopment is focused on clean energy science and technologies. The new building will
    “house UW faculty, students, classrooms[,] and research facilities, along with public and private
    sector tenants with compatible research and technologies.” CP at 96. UW intends for the building
    to “[f]acilitate[] multidisciplinary academic and professional exploration,” “[p]rovide[] students
    with immersive and experiential learning environments,” and “enhance[] strong connections
    between UW faculty, staff[,] and students with external partners to expand the impact of UW
    research, teaching/learning[,] and public service activities.” CP at 98. The construction of the
    new building will utilize a “ground lease development structure” that UW had previously used for
    other projects outside of West Campus. CP at 161.
    Under the ground lease development structure, UW executes a long-term, 80-year ground
    lease to the developer. The developer then demolishes the existing building and designs, finances,
    and constructs the new building. The developer owns the building for the term of the ground lease,
    bearing full responsibility for project risks and costs. Throughout the duration of the ground lease,
    UW agrees to lease approximately 30,000 square feet (about 9 percent) of the new building at a
    fixed rate. UW also has the option to lease an additional 70,000 square feet, which would bring
    its total usage of the building to about 30 percent. The remainder of the building is leased to non-
    UW tenants, but with certain restrictions—the tenants must be “private and public tenants that
    have activities, research[,] and/or products focused on sustainable solutions and [that] are
    complementary with the UW’s education and research mission.” CP at 107. At the end of the
    80-year duration, the developer returns ownership of the building to UW.
    3
    No. 57985-5-II
    To begin the construction process, UW hired Jones Lang LaSalle Americas, Inc. (JLL), a
    firm that helps public entities with development solutions, to provide real estate services for the
    site W27 development. JLL created a general procedure for the site W27 development, involving
    a two-step process for selecting a developer. First, a “Request for Qualifications” (RFQ) would
    solicit potential developers. Second, the responding developers with the best overall proposals
    would be invited to participate further with a “Request for Proposals” (RFP).
    In January 2020, UW posted the RFQ for development of site W27, including the details
    about the proposed ground lease development structure.            UW received responses from
    11 developers. UW selected four of the developers to participate in the next-step RFP process,
    two of which were ARE and Wexford Science & Technology, LLC (Wexford).
    The RFP provided to the selected developers described UW’s intent to negotiate the ground
    lease development structure. The RFP stated that UW “may elect to work directly with [the]
    Developer on other similar projects in the future without further competitive requests for
    proposals.” CP at 109. Additionally, the RFP explained that the developers’ proposals would be
    evaluated and scored by UW’s evaluators, called the “Slating Committee,” “based on the criteria
    identified in [the] RFP.” CP at 126.
    UW received proposals from three developers, including ARE and Wexford.                 The
    developers were able to submit questions to UW as part of the negotiation process; one developer
    asked UW to “describe any associated scoring, ranking, or numerical weights assigned to the
    criteria.” Ex. 66, at 3. In response, UW issued an addendum to the RFP, stating it would evaluate
    the proposals for specified criteria in the RFP, but would not at that time indicate weight or
    importance of the items.     UW’s Slating Committee reviewed the proposals and conducted
    4
    No. 57985-5-II
    interviews but did not use actual scorecards for the different developers. Ultimately, UW selected
    Wexford as the developer for site W27.
    B. UW/WEXFORD LEASES
    UW began negotiating the leases for the development with Wexford. Wexford won the
    bid to be the developer, leading UW to execute the contracts with Wexford’s related entity, LS
    W27 JV, LLC (LS W27)1. The parties signed an initial agreement to lease in March 2022. The
    subsequent ground and building leases were signed in May 2022.
    The ground lease required Wexford to design, finance, construct, and maintain the facility.
    The companion building lease then required Wexford to lease 100,000 square feet of building
    space back to UW. The ground lease self-executes upon “closing,” which is dependent on certain
    conditions precedent. The only relevant condition precedent is the absence of litigation that would
    prevent UW or Wexford from performing under the leases. The building lease self-executes when
    the building is substantially completed.
    C. ARE’S SUBSEQUENT ACTIONS
    When ARE learned Wexford had been selected as the site W27 developer, its lawyer wrote
    to UW’s President questioning the “methodology and objectivity of the RFP process.” CP at 153.
    The letter requested that UW reconsider and select ARE instead. UW declined.
    ARE and its Senior Vice President, John Cox, then sent letters to the Washington State
    Attorney General asserting that the RFP selection process was illegal and requesting the attorney
    1
    Wexford had a five percent equity interest in LS W27.
    5
    No. 57985-5-II
    general “enjoin the execution/performance of the illegal [c]ontracts.” CP at 769. The attorney
    general declined to respond.
    II. ARE’S COMPLAINTS AND UW’S MOTION FOR SUMMARY JUDGMENT
    In June 2021, ARE, together with two individual taxpayers, Cox (in his individual capacity)
    and former state legislator Dean Takko, filed a lawsuit against UW, asserting two claims.2 ARE’s
    first claim (Claim 1) contended UW lacked authority to enter into the leases for site W27. ARE’s
    second claim (Claim 2) alleged UW failed to use competitive bidding procedures required under
    public works law.
    UW moved for summary judgment on both of ARE’s claims in August 2021. UW asserted
    it had general authority to enter into the leases through several different statutes, including RCWs
    28B.20.130, 28B.140.010, and 28B.10.300. UW also argued the building’s construction was not
    a public work because UW was not incurring construction costs and, therefore, the statutory
    competitive bidding process did not apply.
    While UW’s summary judgment motion was pending, ARE filed an amended complaint
    adding a third claim (Claim 3). ARE’s Claim 3 asserted that UW’s developer selection process
    was arbitrary and capricious.
    The superior court granted UW’s summary judgment motion and dismissed Claims 1 and
    2.3 Claim 3 remained.
    2
    Although ARE, Cox, and Takko were plaintiffs as to all claims, we refer to the plaintiffs
    collectively as ARE for brevity.
    3
    ARE filed a supplemental declaration on January 4, 2022, with additional evidence it wanted the
    superior court to consider for summary judgment. The supplemental declaration included exhibits
    with information about postconstruction costs UW will incur while renting building space from
    6
    No. 57985-5-II
    III. BENCH TRIAL
    ARE and UW proceeded to a bench trial on Claim 3.4 After hearing testimony from
    numerous witnesses and considering over 100 exhibits, the superior court rejected ARE’s
    Claim 3. The superior court determined that ARE lacked standing to pursue Claim 3 and further
    determined UW was not arbitrary and capricious in its selection of Wexford.
    The superior court entered lengthy findings of fact. In ruling for UW, the superior court
    determined that ARE lacked standing as a disappointed bidder and as a taxpayer. Findings of fact
    relevant to those decisions included the following:
    34. UW and Wexford have executed the contracts (the Amended and Restated
    Agreement to Lease, the Ground Lease, and the Building Lease, collectively the
    Leases) that were procured and negotiated in connection with the Site W27
    development.
    ....
    36. The Leases are self-executing and require UW and Wexford to “close” on the
    transaction subject to certain Conditions Precedent. The Ground Lease commences
    upon “Closing” and the Office Lease commences upon substantial completion of
    the Site W27 Facility.
    37. The only relevant “Condition Precedent” provides that UW and Wexford’s
    obligations are conditioned on there being no litigation that would affect UW’s or
    Wexford’s ability to perform.
    ....
    39. [ARE] presented evidence at trial as to the costs incurred in responding to the
    W27 RFP and anticipated profits that it believes it would have earned had it been
    selected as the W27 developer.
    Wexford. UW objected to consideration of the evidence because it was not timely filed in
    accordance with CR 56. The superior court agreed and did not consider the declaration.
    4
    Only ARE, the company, participated in the bench trial because the superior court had previously
    dismissed Cox and Takko from Claim 3 based on standing.
    7
    No. 57985-5-II
    CP at 1469-70.
    Conclusions of law relevant to the superior court’s standing decisions included the
    following:
    1. The Court concludes that [ARE] lacks standing to pursue its claim in this matter,
    both as a disappointed bidder and as a taxpayer, as follows:
    2. The Court concludes that [ARE] lacks standing as a disappointed bidder to
    pursue its claims. Under Washington law, a bidder loses standing to pursue claims
    concerning the procurement of a public project once the contracts at issue have been
    executed. Dick Enterprises, Inc. v. Metro. King County, 
    83 Wn. App. 566
    , 572,
    
    922 P.2d 184
     (1996). A disappointed bidder’s sole remedy under Washington law
    is to sue to enjoin execution of the contract at issue in the procurement.
    ....
    4. The Court concludes that the Leases bind UW and Wexford to the terms of the
    proposed W27 development, subject only to a litigation contingency that allows
    Wexford to terminate the Amended and Restated Agreement to Lease.
    5. Any remaining or future agreements or contracts between UW and Wexford
    associated with Site W27 development flow from the agreement that has already
    been signed. [ARE] lacks disappointed bidder standing to challenge such contracts
    to the extent they flow from any agreements related to Site W27 in existence at the
    time of trial.
    ....
    7. The Court concludes that [ARE] lacks standing as a Washington State taxpayer
    to pursue its claims because it has failed to establish that it has incurred any “special
    injury” beyond that suffered by any other Washington taxpayer.
    8. The evidence of injury or damages presented by [ARE] included costs incurred
    in responding to the RFP and selection process and the alleged loss of its anticipated
    profits. These alleged losses or damages are only associated with [ARE] not being
    selected as the developer for the W27 project.
    CP at 1470-72. Thus, Claim 3 was dismissed.
    8
    No. 57985-5-II
    ARE appeals the summary judgment order dismissing Claims 1 and 2 and the conclusions
    of law dismissing Claim 3.5
    ANALYSIS
    I. CLAIMS 1 AND 2 WERE PROPERLY DISMISSED ON SUMMARY JUDGMENT
    ARE challenges the superior court’s dismissal of Claims 1 and 2 at summary judgment.
    For Claim 1, ARE argues UW did not have statutory authority to enter into a transaction under the
    ground lease development structure. For Claim 2, ARE asserts, even if UW had authority to enter
    into the transaction, UW failed to comply with the statutory bidding procedures required for
    selecting a developer. We affirm the superior court on both claims.
    A. SUMMARY JUDGMENT STANDARD OF REVIEW
    We review a superior court’s grant of summary judgment de novo. Crisostomo Vargas v.
    Inland Wash., LLC, 
    194 Wn.2d 720
    , 728, 
    452 P.3d 1205
     (2019). Summary judgment may be
    granted if there is no genuine issue of material fact and the moving party is entitled to judgment
    as a matter of law. CR 56(c); Meyers v. Ferndale Sch. Dist., 
    197 Wn.2d 281
    , 287, 
    481 P.3d 1084
    (2021). A genuine issue of material fact exists if reasonable minds could disagree on the
    conclusion of a factual issue controlling the outcome of the litigation. Sartin v. Estate of McPike,
    15 Wn. App. 2d 163, 172, 
    475 P.3d 522
     (2020), review denied, 
    196 Wn.2d 1046
     (2021). When
    determining whether to grant summary judgment, we view all facts and inferences in the light most
    favorable to the nonmoving party. 
    Id.
    5
    As noted above, the superior court had previously dismissed Cox and Takko for Claim 3 based
    on standing. Because that order has not been appealed, only ARE, the company, remains an
    appellant for Claim 3.
    9
    No. 57985-5-II
    B. CLAIM 1—UW HAD AUTHORITY TO ENTER TRANSACTION
    ARE argues UW had no authority to enter into transactions arising from a ground lease
    development structure. UW responds by claiming statutory authority from three individual
    statutes—RCW 28B.20.130, RCW 28B.10.300, and RCW 28B.140.010. We determine that
    RCW 28B.20.130 grants UW the authority to enter into the transaction with Wexford.
    The legislature has granted broad authority to UW for managing its own property. Indeed,
    chapter 28B.20 RCW applies exclusively to UW and grants the UW Board of Regents expansive
    powers under statute. See RCW 28B.20.020. Relevant here, RCW 28B.20.130 provides the Board
    of Regents with “[g]eneral powers and duties,” including the grant of “full control of the university
    and its property of various kinds, except as otherwise provided by law.” RCW 28B.20.130(1).
    ARE appears to agree that RCW 28B.20.130 grants broad power to UW. But ARE focuses
    on the statute’s language, “except as otherwise provided by law,” and contends the language has
    been interpreted to limit UW’s “full control” when there is an applicable statute. See Univ. of
    Wash. v. City of Seattle, 
    188 Wn.2d 823
    , 832-33, 
    399 P.3d 519
     (2017); RCW 28B.20.130.
    For this case, ARE argues there is such a statute—RCW 28B.10.300—that limits UW’s
    authority to engage in this project. RCW 28B.10.300 generally applies to all state universities in
    Washington, not just UW, and authorizes them to enter ground lease transactions for eight specific
    building types. The statute permits boards of regents for various state universities to enter into
    contracts for:
    10
    No. 57985-5-II
    [T]he construction, installation, equipping, repairing, renovating and betterment of
    buildings and facilities for the following:
    (a) Dormitories
    (b) Hospitals
    (c) Infirmaries
    (d) Dining halls
    (e) Student activities
    (f) Services of every kind for students, including, but not limited to, housing,
    employment, registration, financial aid, counseling, testing and offices of the dean
    of students
    (g) Vehicular parking
    (h) Student, faculty and employee housing and boarding[.]
    RCW 28B.10.300(1). Such contracts include leases. RCW 28B.10.300(3).
    ARE contends the site W27 building does not fall into any of these eight building types.
    And because this project falls outside of the eight building types specifically permitted by
    RCW 28B.10.300, ARE argues this statute operates to limit UW’s very general authority under
    RCW 28B.20.130. In other words, the limitation of distinct building types in RCW 28B.10.300
    constitutes the “except as otherwise provided by law” limitation in RCW 28B.20.130.
    UW disputes this argument.         UW acknowledges the limitation from the “except as
    otherwise provided by law” clause, but argues that RCW 28B.10.300 is not the type of statute that
    limits its authority under RCW 28B.20.130. According to UW, RCW 28B.10.300 grants power
    to public universities to enter into agreements, not limits their power to enter into them. One statute
    granting authority to all Washington universities cannot operate to limit UW’s broader grant of
    11
    No. 57985-5-II
    authority in a separate statute. UW essentially argues two positive grants of authority cannot limit
    one another.
    UW’s position is persuasive. RCW 28B.10.300 provides state universities the authority to
    enter into certain transactions, but it does not, on its face, prohibit universities from entering into
    any transactions. Moreover, there is no language in the statute indicating that the eight building
    types are the entire universe of permitted building types for which universities may contract; the
    statute, for example, does not state that universities are only authorized to contract for the
    enumerated building types. Without some language in RCW 28B.10.300 more overtly enacting a
    limitation on the authority of the universities, rather than merely acting as a grant of authority, the
    statute cannot be reasonably seen as functioning as an “except as otherwise provided by law”
    limitation of the broad authority given to UW from RCW 28B.20.130. Simply put, both statutes
    grant UW authority to manage its property holdings. See Hood Canal Sand & Gravel, LLC v.
    Goldmark, 
    195 Wn. App. 284
    , 300, 
    381 P.3d 95
     (2016) (determining chapters that individually
    granted DNR “expansive authority to grant easements” and “certain narrow authority . . . to grant
    easements” did not conflict). Thus, RCW 28B.10.300 does not limit UW’s broad authority to enter
    into property lease agreements.
    UW’s ability to control its property under RCW 28B.20.130, while not limitless, is broad.
    ARE fails to cite any law that prevents this broad grant of authority from permitting the
    12
    No. 57985-5-II
    development structure chosen for site W27.6           Thus, the superior court properly dismissed
    Claim 1. We affirm the superior court.7
    C. CLAIM 2—COMPETITIVE BIDDING REQUIREMENTS DO NOT APPLY
    ARE’s Claim 2 is related to competitive bidding laws. ARE argues that assuming UW has
    the authority to enter into the development structure, UW failed to follow competitive bidding
    procedures required by law. ARE asserts that because UW will incur costs associated with the
    new site W27 building, it is a public work that requires competitive bidding. ARE contends that
    because the bidding for the development did not comply with these laws, UW’s transactions with
    Wexford are ultra vires and void. We disagree.
    Generally, public policy favors competitive bidding laws in Washington. See Manson
    Constr. & Eng’g Co. v. State, 
    24 Wn. App. 185
    , 190, 
    600 P.2d 643
     (1979), review denied, 
    93 Wn.2d 1004
     (1980). Thus, even if a construction contract is within an agency’s general authority,
    noncompliance with statutorily mandated procedures is ultra vires and renders the contract void.
    Failor’s Pharmacy v. Dep’t of Soc. & Health Servs., 
    125 Wn.2d 488
    , 499, 
    886 P.2d 147
     (1994);
    see also Bankston v. Pierce County, 
    174 Wn. App. 932
    , 939, 
    301 P.3d 495
     (2013) (“When a public
    6
    ARE contends that such a broad reading of RCW 28B.20.130 would make RCW 28B.10.300
    superfluous. But considering the breadth of the grant of authority in RCW 28B.20.130, coupled
    with very general language of the exception—“except as otherwise provided by law”—we are
    persuaded that the legislature has the prerogative to provide clear authorization for the specific
    projects listed in RCW 28B.10.300 without eviscerating the broad authority of RCW 28B.20.130.
    7
    UW also asserts that RCW 28B.10.300 and RCW 28B.140.010 each independently grant it power
    to enter into the transaction with Wexford. Because UW has authority under RCW 28B.20.130,
    we do not consider the breadth of any additional authority provided to UW by these other statutes.
    13
    No. 57985-5-II
    body makes a contract in violation of competitive bidding laws, the contract is illegal and imposes
    no obligation on the public body.”).
    State universities are required to comply with competitive bidding procedures under certain
    circumstances. See Former RCW 28B.10.350 (2009); A-Line Equip. Co. v. Lower Columbia Coll.,
    
    49 Wn. App. 217
    , 219, 
    741 P.2d 1057
     (1987). Former RCW 28B.10.350 requires competitive
    bidding when a state university will incur over $90,000 of costs for construction:
    (1) When the cost to . . . any regional or state university of any building,
    construction, renovation, remodeling, or demolition, other than maintenance or
    repairs, will equal or exceed the sum of ninety thousand dollars, . . . complete plans
    and specifications for the work shall be prepared, the work shall be put out for
    public bid, and the contract shall be awarded to the responsible bidder who submits
    the lowest responsive bid.
    (Emphasis added.) But if the construction is not being done at the cost of the university, then the
    construction is not for a public work and the statute would not apply. See Former RCW
    28B.10.350(4) (“Where the estimated cost . . . is less than ninety thousand dollars . . . the
    publication requirements of RCW 39.04.020 [(requiring public bidding for public works)] do not
    apply.”).
    ARE argues that former RCW 28B.10.350 applies here because the cost of the construction
    is actually being paid in part by UW. As noted above, the development structure requires the
    developer to fully fund the demolition and construction costs of the building in exchange for UW’s
    promise in advance to commit to a long-term lease of space. ARE contends UW’s promised rent
    payments mean the construction is actually being done at the “cost” of UW.8 Essentially, ARE
    8
    In support of this argument, ARE cites to its supplemental declaration, which the superior court
    declined to consider below because it was not filed in accordance with CR 56. ARE argues we
    should consider the declaration evidence because it is “appropriately part of the record for this
    14
    No. 57985-5-II
    argues that the millions of promised dollars that will be spent in rent are so closely tied to
    demolition and construction at site W27 that they must be considered payment for the cost of
    construction. If so, then former RCW 28B.10.350 applies and competitive bidding was required.
    ARE supports its argument with this court’s decision in Supporters of the Center, Inc. v.
    Moore, 
    119 Wn. App. 352
    , 
    80 P.3d 618
     (2003). In Supporters, a nonprofit community group was
    running out of money and struggling to complete a civic performing arts center when the project
    received an infusion of funds from both a state agency and the city. Id. at 354-56. The city offered
    its funding through an advance of rent payments—rent that the city initially expected to pay later,
    only after construction was completed. Id. at 360. In the context of a prevailing wage dispute,
    this court held that this public funding, including the advance of city rent payments, made the
    performing arts center a public work, constructed “ ‘at the cost’ ” of public entities. Id. at 360
    (quoting RCW 39.04.010). ARE contends that Supporters stands for the proposition that UW’s
    promised rent payments should be deemed payment for costs for construction.
    ARE also argues the legislature has identified rent as a cost in relation to real property
    acquisition, citing RCW 28B.10.300(5). That provision states that boards of regents for state
    universities are authorized to:
    Contract to pay as rental or otherwise the cost of the acquisition of such lands and
    of the construction and installation of such buildings and facilities on the
    amortization plan[.]
    RCW 28B.10.300(5) (emphasis added).
    appeal and . . . it was presented to (and called to the attention of) the [superior] court.” Appellants’
    Opening Br. at 20 n.8. The declaration appears to merely include additional postconstruction rent
    figures and anticipated maintenance costs. Because the supplemental declaration, even if it is
    considered, does not change our analysis, we decline to further address this issue.
    15
    No. 57985-5-II
    ARE’s position is unpersuasive. First, Supporters does not have application here. The
    circumstances are not similar; UW is not making any advanced rent payments to actually fund the
    building’s demolition or construction. The developer for site W27 will pay the demolition and
    construction costs in their entirety.
    Second, RCW 28B.10.300(5) is similarly inapplicable. This provision narrowly pertains
    to the acquisition of buildings and facilities on an amortization plan. ARE fails to explain how
    this apparent application can be broadly construed to equate lease payments to costs of
    construction in the general sense—especially when the statute does not have any relation to
    competitive bidding laws.
    Although UW has committed to spending public funds in leasing space at the new building,
    the funds will be paid as rent only after all construction is completed; the building lease self-
    executes when the building is substantially complete. UW will not incur any risk for the building
    or costs for the stated construction activities—all those costs are incurred by the developer, as is
    the nature of the ground lease development structure. Because UW will not incur any costs for, or
    closely associated with, “building, construction, renovation, remodeling, or demolition,” former
    RCW 28B.10.350(1) and its competitive bidding requirements do not apply.
    In short, ARE’s Claim 2 fails; UW was not required to use competitive bidding procedures
    under former RCW 28B.10.350. We affirm the superior court’s dismissal of this claim.
    II. CLAIM 3—SUPERIOR COURT DID NOT ERR WHEN IT RULED FOR UW
    ARE’s Claim 3 alleged that assuming UW had the authority to enter the development
    structure and assuming competitive bidding laws did not apply, UW’s developer selection process
    16
    No. 57985-5-II
    was arbitrary and capricious. After an extensive bench trial, the superior court determined that
    ARE did not have standing to pursue this claim.9
    ARE argues the superior court erred and it had standing both as a disappointed bidder and
    a taxpayer.10 We hold that ARE did not have standing for Claim 3.
    A. LEGAL PRINCIPLES
    On appeal, we review the superior court’s findings of fact after a bench trial for substantial
    evidence. Harrison Mem’l Hosp. v. Gagnon, 
    110 Wn. App. 475
    , 485, 
    40 P.3d 1221
    , review denied,
    
    147 Wn.2d 1011
     (2002). Unchallenged findings of fact are verities on appeal. Harris v. Urell,
    
    133 Wn. App. 130
    , 137, 
    135 P.3d 530
     (2006), review denied, 
    160 Wn.2d 1012
     (2007).
    We review conclusions of law de novo to determine if they are supported by the findings
    of fact. Scott’s Excavating Vancouver, LLC v. Winlock Props., LLC, 
    176 Wn. App. 335
    , 342,
    
    308 P.3d 791
     (2013), review denied, 
    179 Wn.2d 1011
     (2014).
    B. ARE DID NOT ESTABLISH STANDING AS A DISAPPOINTED BIDDER
    ARE first argues it has standing for Claim 3 as a disappointed bidder. We disagree.
    A disappointed bidder may pursue injunctive relief before contract formation based on
    disappointed bidder standing. BBG Grp., LLC v. City of Monroe, 
    96 Wn. App. 517
    , 519-20,
    
    982 P.2d 1176
     (1999). However, a disappointed bidder loses standing once the contracts at issue
    9
    The superior court also determined, substantively, that UW’s developer selection process was
    not arbitrary and capricious. But because the superior court’s decision on standing, if not error,
    would be dispositive, we limit our discussion to that aspect of the superior court’s decision.
    10
    ARE challenges the superior court’s conclusions of law, but notably does not assign error to any
    of the superior court’s findings of fact.
    17
    No. 57985-5-II
    have been executed. Dick Enterprises, 
    83 Wn. App. at 571
    . Contract formation is the “bright-line
    cutoff point.” Id. at 571.
    ARE has two main arguments about its disappointed bidder standing. ARE first asserts
    that it did not lose its disappointed bidder status because of the post-award switch in the identity
    of the developer. ARE points out that UW has not actually executed contracts for the site W27
    development with Wexford, but with a different corporate entity, LS W27, in which Wexford has
    a five percent equity interest. Thus, ARE argues the contracts resulting from the RFP have not
    been executed and it retains disappointed bidder standing.
    Second, ARE argues that it maintains disappointed bidder standing because the
    “Agreement to Lease” (Ex. 157) requires additional documents be completed before the overall
    transaction can close. ARE does not explain what documents still need to be completed but argues
    that those documents and a monetary deposit must be placed in escrow prior to closing.
    ARE’s first argument about the identities of the contracting parties fails. The superior
    court’s findings of fact clearly found no relevance to the differences in the corporate forms of
    Wexford and LS W27. The superior court’s findings of fact stated that Wexford remained the
    party that was entering the agreements with UW. CP at 1469 (“UW and Wexford have executed
    the contracts (the Amended and Restated Agreement to Lease, the Ground Lease, and the Building
    Lease, collectively the Leases) that were procured and negotiated in connection with the Site W27
    development.”). Because ARE has not assigned error to any of the superior court’s findings of
    fact, they are verities on appeal. Harris, 133 Wn. App. at 136. Because we apply these
    unchallenged findings of fact to the conclusions of law, any alleged factual differences in the
    corporate forms of the contracting parties are irrelevant on appeal. See id. Thus, ARE’s
    18
    No. 57985-5-II
    disappointed bidder standing cannot be maintained based merely on UW’s contract execution with
    LS W27 instead of Wexford.
    Similarly, ARE’s second argument about the alleged non-finalization of the contracts also
    fails. The superior court explicitly included in its findings of fact that “UW and Wexford have
    executed the contracts . . . that were procured and negotiated in connection with the Site W27
    development.” CP at 1469. ARE did not challenge this finding of fact, thus again, it is a verity.
    Harris, 133 Wn. App. at 136. Using these findings, the superior court made the following
    conclusions of law, rejecting the argument that something further had to happen before the
    contracts would be deemed executed:
    4. The Court concludes that the Leases bind UW and Wexford to the terms of the
    proposed W27 development, subject only to a litigation contingency that allows
    Wexford to terminate the Amended and Restated Agreement to Lease.
    5. Any remaining or future agreements or contracts between UW and Wexford
    associated with Site W27 development flow from the agreement that has already
    been signed. [ARE] lacks disappointed bidder standing to challenge such contracts
    to the extent they flow from any agreements related to Site W27 in existence at the
    time of trial.
    CP at 1471.
    Although ARE is correct that some additional documents and agreements may be necessary
    before this development is completed, the main contracts for the development that ARE fought to
    be the developer for—the agreement to lease, the ground lease, and the building lease—have all
    been sufficiently signed and completed. Even if the contracts are deemed to “self-execut[e]” at a
    later time or require other documents and actions to later be completed, the parties have already
    executed the contracts. CP at 1470. Simply put, ARE does not have disappointed bidder standing
    19
    No. 57985-5-II
    because it did not bring its suit prior to the “bright-line cutoff point.” Dick Enterprises, 
    83 Wn. App. at 571
    .
    The superior court’s findings of fact sufficiently support its conclusion of law that ARE
    lacks standing as a disappointed bidder for Claim 3.
    C. ARE DID NOT ESTABLISH STANDING AS A TAXPAYER
    ARE also argues it had standing to bring Claim 3 because it had standing as a taxpayer.
    We disagree and hold that the superior court’s findings of fact support its conclusion of law that
    ARE lacked taxpayer standing.
    When challenging a government entity’s discretionary acts, as opposed to allegedly
    unlawful acts, a taxpayer can establish standing by demonstrating: (1) taxpayer status, (2) a prior
    demand of the attorney general, and (3) a special injury. See Friends of N. Spokane County Parks
    v. Spokane County, 
    184 Wn. App. 105
    , 120-22, 
    336 P.3d 632
     (2014). A “special injury” is not
    required for taxpayer standing when a government’s allegedly unlawful act is being challenged.
    Id. at 122.
    To show a “special injury,” the taxpayer “ ‘must show that [it] has a unique right or interest
    that is being violated, in a manner special and different from the rights of other taxpayers.’ ” Id.
    at 120 (quoting Am. Legion Post No. 32 v. City of Walla Walla, 
    116 Wn.2d 1
    , 7, 
    802 P.2d 784
    (1991)); Greater Harbor 2000 v. City of Seattle, 
    132 Wn.2d 267
    , 281, 
    937 P.2d 1082
     (1997). “The
    taxpayer must show that the action complained of interferes with the taxpayer’s legal rights or
    privileges.” Greater Harbor 2000, 
    132 Wn.2d at 281-82
    . Generally, the special injury must have
    a causal link between the use of the taxes and the government’s discretionary action. See generally
    74 AM. JUR. 2d Taxpayers’ Actions § 26 (2d ed. 2023) (explaining that a special injury is a “special
    20
    No. 57985-5-II
    interest in the taxation-derived fund by reason of which the taxpayer's own property rights are put
    in jeopardy”); cf. Dick Enterprises, 
    83 Wn. App. at 573
     (disappointed bidder did not have taxpayer
    standing when it “d[id] not allege harm to taxpayers”); cf. Am. Legion Post No. 32, 
    116 Wn.2d at 8
     (party lacked taxpayer standing when it “provide[d] no argument demonstrating it has a unique
    legal right or privilege different from other taxpayers that was violated by Walla Walla’s levy and
    subsequent use of the . . . tax”).
    Here, after the bench trial, the superior court concluded that ARE’s alleged damages did
    not qualify as a “special injury.” The superior court’s findings of fact included that “[ARE]
    presented evidence at trial as to the costs incurred in responding to the W27 RFP and anticipated
    profits that it believes it would have earned had it been selected as the W27 developer.” CP at
    1470. ARE has not assigned error to this finding, and it is therefore a verity on appeal. Harris,
    133 Wn. App. at 136.
    Using this finding of fact, the superior court concluded that ARE’s only damages were
    those that were associated with being a disappointed bidder in the RFP selection process, not as a
    taxpayer with a special injury. The superior court’s conclusions of law included:
    7. The Court concludes that [ARE] lacks standing as a Washington State taxpayer
    to pursue its claims because it has failed to establish that it has incurred any “special
    injury” beyond that suffered by any other Washington taxpayer.
    8. The evidence of injury or damages presented by [ARE] included costs incurred
    in responding to the RFP and selection process and the alleged loss of its
    anticipated profits. These alleged losses or damages are only associated with
    [ARE] not being selected as the developer for the W27 project.
    9. [ARE] fails to establish any injury to taxpayers generally from the UW’s
    selection of Wexford’s bid. After an extensive process, the UW decisionmakers
    determined that the Wexford proposal was more financially advantageous. Plaintiff
    has not established a special injury as a taxpayer.
    21
    No. 57985-5-II
    CP at 1472 (emphasis added).
    ARE challenges these conclusions of law, arguing it may establish its taxpayer standing
    because it did sustain a special injury—injuries as a disappointed bidder. ARE claims Washington
    law supports its position that, if it is a taxpayer, its damages as disappointed bidder can constitute
    special injury.    ARE states, “Washington courts reject additional requirements for such
    disappointed bidders that are also Washington taxpayers, and as such enables those disappointed
    bidders to continue to challenge a procurement decision based on their taxpayer standing even
    after contract execution.” Appellants’ Opening Br. at 54 (emphasis omitted). ARE argues it can
    show it had a special injury by “demonstrating that the government act has a connection to the use
    of state appropriated funds (e.g., state tax dollars being used in connection with the project).”
    Appellants’ Opening Br. at 53. For these assertions, ARE cites Friends of North Spokane County
    Parks, 
    184 Wn. App. 105
    , and Dick Enterprises, 
    83 Wn. App. 566
    .
    Neither case supports ARE’s position. In Dick Enterprises, a taxpayer/disappointed bidder
    brought suit against a contractor when another bidder was selected, after the contract for services
    was executed. 
    83 Wn. App. at 569-70
    . The court held the disappointed bidder was too late to
    qualify for disappointed bidder standing. Id. at 572. But the disappointed bidder also argued it
    should have taxpayer standing because it would otherwise “irretrievably lose its rights to contract
    as the . . . bidder on the project.” Id. at 573 (internal quotation marks omitted). In rejecting that
    argument, the court determined the disappointed bidder also lacked taxpayer standing because it
    failed to adequately invoke taxpayer standing in its pleadings. Id. But nothing in the case supports
    22
    No. 57985-5-II
    ARE’s assertion that damages as a disappointed bidder can constitute special injury for the
    purposes of establishing taxpayer standing.11
    Similarly, Friends of North Spokane County Parks does not help ARE. Friends discusses
    and examines the Dick Enterprises decision, but it contains no discussion about the relationship
    between disappointed bidder status and the special injury necessary for standing as a taxpayer to
    challenge discretionary governmental decisions. 184 Wn. App. at 118. Friends is of marginal
    relevance, in any event, because the case involved an allegation of “unlawful” governmental action
    which, unlike discretionary governmental action, does not require special injury to obtain taxpayer
    standing. Id. at 122, 124.
    None of the cases cited by ARE support its argument that disappointed bidder damages
    alone can constitute special injury for tax payer standing for discretionary governmental decisions.
    We presume that no such Washington cases exist. DeHeer v. Seattle Post-Intelligencer, 
    60 Wn.2d 122
    , 126, 
    372 P.2d 193
     (1962) (“Where no authorities are cited in support of a proposition, the
    court is not required to search out authorities, but may assume that counsel, after diligent search,
    has found none.”). Thus, ARE fails to show that damages incurred solely as a disappointed bidder,
    11
    ARE also cites to Dick Enterprises to argue that a special injury can be shown by
    “demonstrating that the government act has a connection to the use of state appropriated funds
    (e.g., state tax dollars being used in connection with the project).” Appellants’ Opening Br. at 53.
    And again, ARE is mistaken; ARE’s citation to Dick Enterprises is to the part of the opinion
    analyzing whether the plaintiff had standing as a disappointed bidder, which has no relevance to
    whether a connection between government acts and the use of state appropriated funds shows
    special injury for taxpayer standing. Indeed, such an injury would not be “special,” but a general
    injury applicable to ARE and to all other taxpayers. See Greater Harbor 2000, 
    132 Wn.2d at 281
    (“ ‘[T]he taxpayer must show . . . a unique right or interest that is being violated, in a manner
    special and different from the rights of other taxpayers.’ ”) (second alteration in original) (quoting
    Am. Legion Post No. 32, 
    116 Wn.2d at 7
    )).
    23
    No. 57985-5-II
    even if that bidder is a taxpayer, are within the category of damages that create “special injury”
    necessary for taxpayer standing.
    Indeed, such a holding would create a loophole for disappointed bidders (who also happen
    to pay taxes) when they miss the deadline to challenge a bid decision. As explained above,
    disappointed bidders are barred from challenging the result of a competitive bid after the contracts
    for the bids have been executed. Dick Enterprises, 
    83 Wn. App. at 571-72
    . Dick Enterprises
    explains that post-contracting relief for disappointed bidders competes with the public interest of
    preventing excessive taxation. Id. at 569, 572 (“[E]ven where the wrongful award of a contract
    violates a bidder’s interest in a fair forum, the bidder may not sue for damages. To allow damages
    would violate the public interest by subjecting taxpayers to further penalties when they are already
    injured by paying too high a price under an illegal contract.”). Such a loophole allowing standing
    for all disappointed bidders who are also taxpayers would utterly frustrate the policies behind
    cutting off disappointed bidder standing at the time of contract execution.
    With these principles in mind, we hold that damages as a disappointed bidder alone,
    without more, are not sufficient to show special injury for taxpayer standing.
    At the end of the day, ARE has only shown damages that can be fairly categorized as
    disappointed bidder damages. And apart from those damages, ARE has failed to articulate any
    possible damages that would not also be suffered by all taxpayers. Such damages, if any, would
    not be a special injury. Thus, ARE lacks standing as a taxpayer for Claim 3.
    Because ARE did not have either disappointed bidder standing or taxpayer standing, the
    superior court did not err by dismissing ARE’s Claim 3.
    24
    No. 57985-5-II
    CONCLUSION
    We hold the superior court did not err when it granted summary judgment on Claims 1
    and 2. We also hold the superior court’s conclusions of law determining ARE lacked standing and
    dismissing ARE’s Claim 3 are supported by the findings of fact. Accordingly, we affirm the
    superior court.
    PRICE, J.
    We concur:
    MAXA, P.J.
    VELJACIC, J.
    25
    

Document Info

Docket Number: 57985-5

Filed Date: 12/5/2023

Precedential Status: Precedential

Modified Date: 12/5/2023