William Insulation Company Inc v. JH Kelly LLC ( 2021 )


Menu:
  • 1 2 3 4 5 UNITED STATES DISTRICT COURT 6 WESTERN DISTRICT OF WASHINGTON AT TACOMA 7 WILLIAM INSULATION COMPANY, CASE NO. C21-05083 BHS 8 INC., ORDER GRANTING 9 Plaintiff, DEFENDANT’S MOTION TO v. DISMISS 10 JH KELLY LLC, and CLEARWATER 11 PAPER CORPORATION, 12 Defendants. 13 This matter comes before the Court on Defendant Clearwater Paper Corporation’s 14 motion to dismiss, Dkt. 27. The Court has considered the pleadings filed in support of 15 and in opposition to the motion and the remainder of the file and grants the motion for the 16 reasons stated below. 17 I. BACKGROUND 18 Clearwater, a Delaware corporation headquartered in Washington, engaged 19 Defendant JH Kelly LLC (“JHK”), a Washington corporation headquartered in 20 Washington, as the general contractor for construction improvements at its paper pulp 21 factory in Lewiston, Idaho. Dkt. 26, ¶¶ 3, 4, 9. JHK then hired Plaintiff William 22 1 Insulation Company, Inc. (“WIC”), a Wyoming corporation headquartered in Wyoming, 2 as a subcontractor to perform industrial piping, equipment insulation, and abatement 3 work and to erect scaffolding for the project. Id. ¶¶ 2, 9. WIC and JHK executed a Master 4 Subcontract Agreement (“MSA”) and two addenda. Id. ¶¶ 15, 21, 23. The second 5 addendum reflected the parties’ agreement that WIC would perform the work for 6 $2,194,918.00. Id. ¶ 23. Clearwater was not a party to the MSA. 7 WIC alleges that at the time it executed the addenda, the design plans for the 8 project were not finalized, and subsequent changes in the project necessitated an 9 increased scope of work, increased its costs, and required additional manpower. Id. ¶ 24. 10 WIC submitted 43 change orders to JHK, encompassing all changed and additional work 11 on the project. Id. ¶¶ 29–30. WIC alleges that JHK paid only some of these orders in full, 12 even after WIC sent a formal application and certificate for payment. Id. ¶¶ 30, 37. 13 Section 4.9 of the MSA, “Venue,” provides in part that “[i]f any suit or action is 14 filed by any party to enforce this Subcontract or otherwise with respect to the subject 15 matter of this Subcontract, this Subcontract and all Work hereunder shall be interpreted 16 under the laws of the State of Washington . . . .” Dkt. 20-2 at 7. Similarly, Section 4.11, 17 “Governing Law,” provides that “[t]he law of the State of Washington shall govern this 18 subcontract.” Id. 19 WIC sought payment from JHK but the parties could not reach an agreement. Dkt. 20 26, ¶ 43. WIC sued, bringing claims for breach of contract, breach of the duty of good 21 faith and fair dealing, and quantum meruit against JHK, and for unjust enrichment against 22 1 both JHK and Clearwater. Dkt. 1. WIC seeks damages in excess of $750,000. Id. ¶¶ 54, 2 57, 64, 72. 3 Clearwater moved to dismiss on March 2, 2021, arguing that WIC could not 4 maintain an unjust enrichment claim against it because Idaho’s statutory mechanic’s lien 5 is an exclusive, legal remedy and both Washington and Idaho law bar a plaintiff from 6 pursuing equitable remedies when an adequate legal remedy is available. Dkt. 18. 7 Because it was not a registered contractor, WIC could not avail itself of Idaho’s 8 mechanic’s lien. The Court granted Clearwater’s motion to dismiss, holding that WIC’s 9 inability to invoke Idaho’s mechanic lien was a problem of its own making and that did 10 not render the remedy inadequate. Dkt. 24 at 13–15. The Court granted WIC leave to 11 amend its complaint, concluding that it was not clear that WIC’s claims against 12 Clearwater could not be saved by amendment. Id. at 16. 13 WIC’s amended complaint alleged that Clearwater itself acted as a general 14 contractor on the project, adding assertions against Clearwater that many were previously 15 only asserted against JHK. See, e.g., Dkt. 26, ¶¶ 10, 11, 26, 32, 33. As in WIC’s original 16 complaint, the only claim asserted against Clearwater is unjust enrichment. Id. ¶¶ 58–64. 17 Clearwater now moves to dismiss WIC’s amended complaint, arguing WIC’s 18 claim against Clearwater fails for two reasons. Dkt. 27 at 1–2. First, Clearwater argues 19 that, as the Court held in its order dismissing Clearwater as a defendant, Dkt. 24, the 20 Idaho mechanic’s lien law is an adequate statutory remedy. Dkt. 27 at 2. Second, 21 Clearwater argues that WIC cannot assert unjust enrichment because it was not registered 22 as a contractor in Idaho or Washington at any relevant time. Id. 1 WIC responds that this Court must apply Washington law under the MSA 2 (between JHK and WIC) and, under Washington’s conflict of law analysis, the 3 substantial interest test. Dkt. 30 at 7–11. WIC also asserts it is currently registered as a 4 contractor in the state of Washington, though WIC does not and apparently cannot allege 5 that it was registered at the time of contracting or when the work was performed.1 Id. at 4. 6 But WIC also argues that it does not matter whether it was a registered contractor 7 because Clearwater was also a contractor, permitting WIC to sue under a Washington 8 common law exception permitting unregistered contractors to sue other contractors. Id. at 9 11–16. Finally, WIC argues that the Court erred in concluding that Idaho’s mechanic lien 10 is a legal remedy and therefore the existence of such a remedy should not hinder WIC 11 from seeking a legal remedy under Washington law. Id. at 16–21. 12 II. DISCUSSION 13 A. Standard on Motion to Dismiss 14 Dismissal under Fed. R. Civ. P. 12(b)(6) may be based on either the lack of a 15 cognizable legal theory or the absence of sufficient facts alleged under a cognizable legal 16 theory. Balistreri v. Pacifica Police Dep’t, 901 F.2d 696, 699 (9th Cir. 1990). A 17 plaintiff’s complaint must allege facts to state a claim for relief that is plausible on its 18 face. See Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009). A claim has “facial plausibility” 19 when the party seeking relief “pleads factual content that allows the court to draw the 20 21 1 WIC’s Motion to Take Judicial Notice, Dkt. 29, is GRANTED. But the fact that WIC is currently a registered contractor in Washington does not negate the requirement in RCW 22 18.27.080 that the suing contractor be registered at the time the parties contracted. 1 reasonable inference that the defendant is liable for the misconduct alleged.” Id. Although 2 the court must accept as true the Complaint’s well-pled facts, conclusory allegations of 3 law and unwarranted inferences will not defeat an otherwise proper 12(b)(6) motion to 4 dismiss. Vazquez v. Los Angeles Cnty., 487 F.3d 1246, 1249 (9th Cir. 2007); Sprewell v. 5 Golden State Warriors, 266 F.3d 979, 988 (9th Cir. 2001). “[A] plaintiff’s obligation to 6 provide the ‘grounds’ of his ‘entitle[ment] to relief’ requires more than labels and 7 conclusions, and a formulaic recitation of the elements of a cause of action will not do. 8 Factual allegations must be enough to raise a right to relief above the speculative level.” 9 Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555 (2007) (citations and footnotes omitted). 10 This requires a plaintiff to plead “more than an unadorned, the-defendant-unlawfully- 11 harmed-me-accusation.” Iqbal, 556 U.S. at 678 (citing id.). 12 B. Idaho Mechanic’s Lien 13 In its prior order on JHK and Clearwater’s motion to dismiss, the Court held that 14 WIC was barred from pursuing a claim against Clearwater because the Idaho mechanic’s 15 lien was an exclusive, legal remedy. Dkt. 24 at 13–15. There, the Court accepted the 16 premise that Idaho’s mechanic’s lien is a legal remedy and held that “unjust enrichment is 17 unavailable if adequate legal remedies exist.” Id. at 14. 18 Clearwater argues the Court should apply this same logic again and dismiss WIC’s 19 amended complaint. Dkt. 27 at 5–6. WIC argues that the Court erred in its order because 20 even though mechanic’s liens are statutory in nature, they provide equitable rather than 21 legal remedies. Dkt. 30 at 16–17. WIC cites to seven recorded Washington cases holding 22 1 as much, spanning from 1890 to 2013. Id. The Court agrees that its previous holding was 2 in error. 3 Foreclosure of a mechanic’s lien is an equitable remedy in both Washington and 4 Idaho. See Alpine Indus., Inc. v. Gohl, 30 Wn. App. 750, 760 (1981) (“Actions to 5 foreclose mechanics’ and materialmen’s liens . . . are equitable proceedings.”); Jensen v. 6 Bumgarner, 137 P. 529, 530 (Idaho 1913) (“[T]his is a suit in equity to foreclose a 7 mechanic’s lien.”). While unjust enrichment is, in fact, unavailable if adequate legal 8 remedies exist, the same is not true for equitable remedies. Because the Idaho mechanic’s 9 lien is an equitable remedy, no adequate remedy at law exists,2 and WIC’s unjust 10 enrichment claim cannot be dismissed on that basis. Nevertheless, WIC cannot sue 11 Clearwater because Idaho law applies, and WIC is barred from suing Clearwater under 12 Idaho law. 13 C. Choice of Law 14 The parties disagree as to which state’s law should apply in this case. Clearwater 15 primarily argues that WIC’s claims are barred in both Washington and Idaho. 16 Alternatively, Clearwater argues that Idaho law should apply because Idaho has a greater 17 interest in having its law applied and Idaho law would bar WIC’s claim. Dkt. 27 at 12– 18 14. WIC argues that its claim is plausible under Washington law and that Washington 19 20 21 2 Unjust enrichment is also an equitable remedy in both states. See Young v. Young, 164 Wn.2d 477, 486 (2008); Stevenson v. Windermere Real Est./Cap. Grp., Inc., 275 P.3d 839, 844 22 n.4 (Idaho 2012). 1 law should apply because applying Washington law would better conform to the parties’ 2 expectation interests and the public policy of the two states. Dkt. 30 at 7–10. 3 The Court only performs a choice of law analysis if there is an actual conflict 4 between the laws of the two relevant jurisdictions. If an actual conflict exists, 5 Washington courts apply the law of the jurisdiction with the “most significant 6 relationship” to the dispute, including considering any choice of law agreement between 7 the parties. 8 1. Actual Conflict 9 “When parties dispute choice of law, there must be an actual conflict between the 10 laws or interests of Washington and the laws or interests of another state before 11 Washington courts will engage in a conflict of laws analysis.” Erwin v. Cotter Health 12 Ctrs., 161 Wn.2d 676, 692 (2007) (internal quotations omitted). A “real conflict” exists if 13 the result for a particular issue is different under the two states’ laws. Id. It is undisputed 14 that WIC’s unjust enrichment claim against Clearwater would be barred under Idaho law. 15 See Dkt. 30 at 7; Dkt. 27 at 6–7. Whether the Court must perform a choice of law 16 analysis therefore depends on whether WIC has a viable unjust enrichment claim against 17 Clearwater under Washington law. 18 a. Washington Registration Requirements 19 Clearwater argues that RCW 18.27.080 bars WIC’s unjust enrichment claim 20 because WIC was not a registered contractor at the time it contracted to perform work on 21 Clearwater’s mill. Dkt. 27 at 8–9. WIC argues that Clearwater acted as a contractor and 22 that this case therefore falls under an exception laid out in Bremmeyer v. Peter Kiewit 1 Sons Co., 90 Wn.2d 787, 791 (1978), which held that the bar against lawsuits by 2 unregistered contractors in the Washington Contractor Registration Act (“WCRA”) does 3 not apply in suits against other contractors. Dkt. 30 at 13. Clearwater argues that the 4 Bremmeyer exception does not apply because it is the owner of the mill and not in privity 5 of contract with WIC. Dkt. 27 at 10. 6 Under WCRA, a contractor commits a gross misdemeanor if the contractor offers 7 to do work or performs work as a contractor without being registered with the 8 Washington Department of Labor and Industries. RCW 18.27.020(2)(a). A contractor 9 also must be registered to bring suit for breach of contract or performance of work for 10 which registration is required. RCW 18.27.080. The suing contractor must have been 11 registered at the time the contract was formed. Id. A contractor is any entity that 12 “undertakes to . . . construct, alter, [or] repair . . . any building . . . or, who, to do similar 13 work upon his or her own property, employs members of more than one trade upon a 14 single job.” RCW 18.27.010(1)(a). This bar to recovery for unregistered contractors 15 “extends to alternative remedies such as unjust enrichment.” Bort v. Parker, 110 Wn. 16 App. 561, 570 (citing Stewart v. Hammond, 78 Wn.2d 216, 220 (1970)). 17 WIC is a contractor under WCRA’s definition because it contracted with JHK to 18 perform construction work on Clearwater’s paper pulp facility. As previously established, 19 WIC was not registered at any relevant time. Therefore, because WIC was an 20 unregistered contractor at the time it contracted with JHK, it cannot sue Clearwater for 21 unjust enrichment under Washington law unless the Bremmeyer exception applies. 22 1 b. The Bremmeyer Exception 2 In Bremmeyer, the Washington Supreme Court held that RCW 18.27.080’s bar to 3 sue does not apply between a general contractor and a sub-contractor. 90 Wn.2d at 791. 4 The court explained that the purpose of WCRA is to protect the public—specifically, 5 “customers who themselves are not routinely in the business of acting as ‘contractors’ as 6 defined by RCW 18.27.010.” Id. at 790. In other words, WCRA was not intended to 7 protect contractors from each other. 8 Clearwater argues that the Bremmeyer exception does not apply for two reasons. 9 First, Clearwater asserts that Bremmeyer is distinguishable because it involved a suit by 10 an unregistered subcontractor against a contractor for a breach of the parties’ subcontract. 11 Dkt. 27 at 9–10. Here, Clearwater and WIC are not in privity of contract, and Clearwater 12 is instead the owner of the project and thus, according to Clearwater, “falls within the 13 class of the public that the WCRA is intended to protect.” Id. at 10–11. Second, 14 Clearwater argues that under RCW 18.27.090(11), Clearwater is both exempt from 15 WCRA registration requirements and is protected against suit by unregistered 16 contractors. Id. at 11. 17 WIC alleges that Clearwater acted as a general contractor for the project. See Dkt. 18 26. WIC argues that if Clearwater is a general contractor, WIC’s suit is proper under the 19 Bremmeyer exception, even if it was not registered. Dkt. 30 at 11–16. 20 First, Clearwater argues Bremmeyer does not apply because it was not in privity of 21 contract with WIC. The applicability of the Bremmeyer exception does not turn on 22 whether the plaintiff is in privity with the defendant. Rather, the Bremmeyer exception 1 draws a distinction between contractors and the general public; it holds that contractors, 2 unlike the general public, are not in the class of individuals WCRA was designed to 3 protect. Bremmeyer, 90 Wn.2d at 791 (“[T]he legislature did not intend to protect prime 4 contractors from actions initiated by unregistered subcontractors.”); see also Hinton v. 5 Johnson, 87 Wn. App. 670, 672 (1997) (“The CRA does not apply to actions between 6 contractors.”). Thus, Clearwater’s privity argument fails. 7 Second, Clearwater argues that Bremmeyer does not apply because it is an owner, 8 and thus it is both exempt from and protected under WCRA. There are multiple classes of 9 individuals and companies that are not required to register under WCRA, including: “An 10 owner who contracts for a project with a registered contractor.” RCW 18.27.090(11). 11 That exemption does not “deprive the owner of the protections of [WCRA].” Id. But an 12 owner who also acts as a contractor is still subject to suit under the Bremmeyer exception 13 if the owner is “regularly engaged in the business of contracting.” Hinton, 87 Wn. App. at 14 672. Under WCRA, “contractor” includes a corporation that “employs members of more 15 than one trade upon a single job or project or under a single building permit except as 16 otherwise provided in [WCRA].” RCW 18.27.010(1)(a). 17 Clearwater appears to qualify for the exemption under RCW 18.27.090(11) 18 because it is an owner who contracted for a project with JHK, a registered contractor. 19 Under that exemption, Clearwater is not required to register as a contractor and could still 20 sue others despite its lack of registration. But as WIC points out, whether Clearwater 21 qualifies for that exemption is irrelevant to the question of whether it can be sued as a 22 1 contractor under Bremmeyer. Dkt. 30 at 15–16. Thus, Clearwater’s exemption argument 2 also fails. 3 WIC’s amended complaint plausibly alleges that Clearwater is a “contractor” 4 under WCRA. Specifically, WIC claims that Clearwater employed both JHK and at least 5 one subcontractor—Valmet—for its pulp mill project. Dkt. 26 ¶¶ 9–11. WIC also asserts 6 that Clearwater directed much of the project, contracted with other trades to complete the 7 project, supervised and coordinated the work, served as the direct point of 8 communication between trades it hired and JHK, and directly superintended various 9 trades on the project. While WIC has not conclusively established that Clearwater acted 10 as a general contractor for this project, WIC has satisfied the Twombly/Iqbal standard to 11 plausibly assert that Clearwater acted as a general contractor. 12 c. Idaho Contractor Registration Act 13 The Idaho Contractor Registration Act (“ICRA”) provides that an unregistered 14 contractor, unless otherwise exempt from registration, cannot bring an action in any court 15 of the state “for the performance of any act or contract for which registration is required.” 16 Idaho Code § 54-5217(2). Unlike Washington, the Idaho Supreme Court held that this 17 registration requirement bars claims against all categories of defendants. Stonebrook 18 Constr., LLC v. Chase Home Fin., LLC, 277 P.3d 374, 377–78 (Idaho 2012). Idaho does 19 not have any case law that parallels the Bremmeyer exception. 20 While ICRA bars WIC from suing Clearwater in Idaho, the Bremmeyer exception 21 to WCRA, paired with WIC’s plausible allegation that Clearwater was a contractor, 22 1 would permit WIC to sue under Washington law. Therefore, there is an actual conflict 2 between the laws of Washington and the laws of Idaho. 3 2. Choice of Law Provision in MSA 4 Because an actual conflict exists, the next question is whether the choice of law 5 provision in the MSA between JHK and WIC applies to WIC’s claims against 6 Clearwater. The choice of law clause in the MSA states that Washington law shall govern 7 the terms of the contract. Dkt. 26, ¶ 20. WIC argues that the court must apply the choice 8 of law provision unless “the chosen state has no substantial relationship to the parties or 9 that application of the chosen law would be contrary to a fundamental policy of 10 Washington.” Dkt. 30 at 7. Clearwater argues that the MSA’s choice of law provision 11 does not apply between Clearwater and WIC because Clearwater is not a party to that 12 contract and has no contractual relationship with WIC whatsoever. Dkt. 27 at 13; Dkt. 32 13 at 12. 14 A contractual choice of law provision should generally be enforced “so long as 15 applying it does not violate the fundamental public policy of the forum state.” Freestone 16 Cap. Partners L.P. v. MKA Real Est. Opportunity Fund I, LLC, 155 Wn. App. 643, 658– 17 59 (2010). A contract cannot bind a nonparty. E.E.O.C. v. Waffle House, Inc., 534 U.S. 18 279, 294 (2002). That principle is true even in situations like here, where one of the 19 contracting parties and the non-contracting party share a close relationship not governed 20 by the relevant contract. Cf. Freestone Cap. Partners, 155 Wn. App. at 660–61 (holding 21 that a choice of law provision in a promissory note between a debtor and a lender did not 22 1 bind guarantors sued by the lender because the guarantors did not sign the promissory 2 note). 3 The MSA was executed by WIC and JHK. Dkt. 26, ¶ 15. Clearwater had a 4 separate agreement with JHK3 and had no contractual relationship with WIC. Id. ¶ 9. 5 Because Clearwater was not a party to the MSA, Clearwater is not bound by the choice of 6 law provision in the MSA. 7 3. Most Significant Relationship 8 Washington uses the most significant relationship test to determine choice of law 9 questions. FutureSelect Portfolio Mgmt., Inc. v. Tremont Grp. Holdings, Inc., 180 Wn.2d 10 954, 967 (2014) (en banc). In determining the “most significant relationship,” 11 Washington courts employ a two-step analysis. Id. at 968. First, courts evaluate the 12 parties’ contacts with each jurisdiction that are relevant to the instant cause of action. Id. 13 Second, courts consider the interests and public policies of the relevant jurisdictions. Id. 14 In this Court’s order determining choice of law as between JHK and WIC, the 15 Court examined choice of law principles under Restatement § 187 (Law of the State 16 Chosen by the Parties) and Restatement § 196 (Contracts for the Rendition of Services). 17 Dkt. 24 at 6–11. WIC similarly analyzes choice of law under § 196. Dkt. 30 at 8–10. But 18 as has already been decided, there is no contract governing this case. Thus, neither of 19 these sections of the Restatement govern the choice of law analysis in this case. 20 21 3 The contract between Clearwater and JHK is not in the record, and thus the Court is 22 unaware whether that contract contains a choice of law or choice of venue clause. 1 Instead, choice of law for unjust enrichment claims is governed by Restatement 2 (Second) of Law on Conflict of Laws § 221 (Restitution). See Restatement (Second) of 3 Law on Conflict of Laws § 221 cmt. a (Am. Law Inst. 1971) (“The rule of this Section 4 applies to claims, which are based neither on contract nor on tort, to recover for unjust 5 enrichment.”); see also Vance v. Microsoft Corp., __ F. Supp. 3d __, 2021 WL 1401634, 6 at *5–6 (W.D. Wash. Apr. 14, 2021). In determining which jurisdiction has the most 7 significant relationship to the dispute under § 221, the Court must consider the principles 8 laid out in § 6 of the Restatement: 9 (a) the needs of the interstate and international systems, (b) the relevant policies of the forum, (c) the relevant policies of other interested states and 10 the relative interests of those states in the determination of the particular issue, (d) the protection of justified expectations, (e) the basic policies 11 underlying the particular field of law, (f) certainty, predictability and uniformity of result, and (g) ease in the determination and application of the 12 law to be applied. 13 Restatement (Second) of Law on Conflict of Laws § 6(2) (Am. Law Inst. 1971). 14 In applying the § 6 principles, courts are to consider the following contacts: 15 (a) the place where a relationship between the parties was centered, provided that the receipt of enrichment was substantially related to the 16 relationship, (b) the place where the benefit or enrichment was received, (c) the place where the act conferring the benefit or enrichment was done, (d) 17 the domicile, residence, nationality, place of incorporation and place of business of the parties, and (e) the place where a physical thing, such as 18 land or a chattel, which was substantially related to the enrichment, was situated at the time of the enrichment. 19 Restatement (Second) of Law on Conflict of Laws § 221(2) (Am. Law Inst. 1971). These 20 factors are “evaluated according to their relative importance with respect to the particular 21 issue.” Id. 22 1 WIC and Clearwater’s relationship was centered in Idaho, where the mill is 2 located. Clearwater similarly received the allegedly unjust enrichment in Idaho, and WIC 3 conferred it in Idaho; the benefit conferred was WIC’s work on Clearwater’s mill. The 4 only physical thing that is substantially related to the enrichment in this case is the mill, 5 located in Idaho. The only factor that weighs in favor of applying Washington law is that 6 Clearwater (but not WIC) is headquartered in Washington. 7 This analysis differs significantly from that involving JHK in this Court’s previous 8 order, especially when considering the § 6 factors. See Dkt. 24 at 4–11. There, the Court 9 focused mainly on the MSA’s choice of law provision. WIC had a reasonable expectation 10 that claims arising out of the MSA would be governed by Washington law, given the 11 choice of law provision in the contract. In contrast, WIC and Clearwater never 12 contracted, and thus it was not reasonable for WIC to expect claims against Clearwater, 13 in relation to a project conducted in Idaho, to be governed under Washington law. 14 Further, the Court stated in the previous order that the public policy interests of Idaho and 15 Washington in regulating contractors are relatively similar. 16 An actual conflict between Idaho and Washington law exists in this case. Idaho 17 has the most significant relationship to the unjust enrichment claim asserted by WIC 18 against Clearwater. The parties agree that WIC does not have a remedy under Idaho law. 19 See Dkt. 30 at 7; Dkt. 27 at 6–7. Therefore, Idaho law applies, and WIC’s unjust 20 enrichment claim against Clearwater is barred. 21 22 1 III. ORDER 2 Therefore, it is hereby ORDERED that Defendant Clearwater Paper 3 Corporation’s motion to dismiss, Dkt. 27, is GRANTED, and Plaintiff William 4 Insulation Company’s motion to take judicial notice, Dkt. 29, is GRANTED. The Clerk 5 shall terminate Clearwater as a defendant. 6 Dated this 22nd day of November, 2021. A 7 8 BENJAMIN H. SETTLE 9 United States District Judge 10 11 12 13 14 15 16 17 18 19 20 21 22

Document Info

Docket Number: 3:21-cv-05083

Filed Date: 11/22/2021

Precedential Status: Precedential

Modified Date: 11/4/2024