Great Lakes Excavating, Inc. v. Dollar Tree Stores, Inc. ( 2022 )


Menu:
  •                                                                    
    2022 WI 44
    SUPREME COURT               OF   WISCONSIN
    CASE NO.:              2019AP2095
    COMPLETE TITLE:        Great Lakes Excavating, Inc.,
    Plaintiff-Appellant-Petitioner,
    v.
    Dollar Tree Stores, Inc.,
    Defendant-Respondent,
    AMCON Design and Construction Co., LLC,
    Riverworks Development Corporation and John H.
    Burkemper,
    Defendants,
    Riverworks City Center, LLC,
    Intervenor-Respondent.
    REVIEW OF DECISION OF THE COURT OF APPEALS
    Reported at 
    397 Wis. 2d 10
    , 
    959 N.W.2d 351
    PDC No: 2021 WI App23 - Published
    OPINION FILED:         June 22, 2022
    SUBMITTED ON BRIEFS:
    ORAL ARGUMENT:         April 7, 2022
    SOURCE OF APPEAL:
    COURT:              Circuit
    COUNTY:             Milwaukee
    JUDGE:              William S. Pocan
    JUSTICES:
    REBECCA GRASSL BRADLEY, J., delivered the majority opinion of
    the Court, in which ZIEGLER, C.J., ROGGENSACK, HAGEDORN, and
    KAROFSKY, JJ., joined. DALLET, J., filed a dissenting opinion,
    in which ANN WALSH BRADLEY, J., joined.
    NOT PARTICIPATING:
    ATTORNEYS:
    For the plaintiff-appellant-petitioner, there were briefs
    filed by John E. Machulak and Machulak, Robertson & Sodos, S.C.,
    Milwaukee. There was an oral argument by John E. Machulak.
    For the intervenor-respondent, there was a brief filed by
    Steven       J.   Slawinski,   Jessica   K.   Haskell   and   O’Neil,   Cannon,
    Hollman,   DeJong   &   Laing   S.C.,   Milwaukee.   There   was   an   oral
    argument by Steven J. Slawinski.
    2
    
    2022 WI 44
    NOTICE
    This opinion is subject to further
    editing and modification.   The final
    version will appear in the bound
    volume of the official reports.
    No.    2019AP2095
    (L.C. No.   2019CV2945)
    STATE OF WISCONSIN                      :            IN SUPREME COURT
    Great Lakes Excavating, Inc.,
    Plaintiff-Appellant-Petitioner,
    v.
    Dollar Tree Stores, Inc.,                                      FILED
    Defendant-Respondent,
    JUN 22, 2022
    AMCON Design and Construction Co., LLC,
    Riverworks Development Corporation and John H.               Sheila T. Reiff
    Clerk of Supreme Court
    Burkemper,
    Defendants,
    Riverworks City Center, LLC,
    Intervenor-Respondent.
    REBECCA GRASSL BRADLEY, J., delivered the majority opinion of
    the Court, in which ZIEGLER, C.J., ROGGENSACK, HAGEDORN, and
    KAROFSKY, JJ., joined. DALLET, J., filed a dissenting opinion,
    in which ANN WALSH BRADLEY, J., joined.
    REVIEW of a decision of the Court of Appeals.            Reversed and
    cause remanded.
    No.     2019AP2095
    ¶1     REBECCA GRASSL BRADLEY, J.                  Great Lakes Excavating,
    Inc. (Great Lakes) seeks review of a court of appeals decision1
    affirming an order of the circuit court,2 which granted partial
    summary     judgment      to    Riverworks       City   Center,    LLC     (Riverworks)
    after finding Great Lakes fully waived its construction lien.
    Before signing a form lien waiver document titled "Waiver of
    Lien to Date," the owner of Great Lakes crossed off the words
    "to Date," replaced them with the handwritten word "Partial,"
    and   initialed     next       to   the   change.       Great     Lakes    argues      this
    change "specifically and expressly" limited the lien waiver to
    the       amount     received——$33,448——in               accordance             with     the
    requirements of 
    Wis. Stat. § 779.05
    (1), and asserts extrinsic
    evidence reveals all parties intended the waiver to be partial.
    Alternatively, Great Lakes contends equitable estoppel precludes
    Riverworks from asserting Great Lakes waived its lien in full.
    Riverworks maintains the form constituted a full waiver of Great
    Lakes' lien rights because it failed to satisfy the statutory
    procedure to limit the waiver.
    ¶2     We    hold    the      waiver   document      satisfied        
    Wis. Stat. § 779.05
    (1) (2019–20)3 by "specifically and expressly" limiting
    the waiver to "a particular portion of . . . labor, services,
    1Great Lakes Excavating, Inc. v. Dollar Tree Stores, Inc.,
    
    2021 WI App 23
    , 
    397 Wis. 2d 210
    , 
    959 N.W.2d 351
    .
    2The Honorable William S. Pocan, Milwaukee County Circuit
    Court, presided.
    3All subsequent references to the Wisconsin Statutes are to
    the 2019-20 version unless otherwise indicated.
    2
    No.    2019AP2095
    materials, plans, or specifications" in the amount of $33,448.
    Accordingly, we reverse the decision of the court of appeals.
    I.      BACKGROUND
    ¶3      In this construction lien waiver dispute, Riverworks
    contracted with AMCON Design and Construction Co. (AMCON) to
    construct a commercial building and parking lot in Milwaukee,
    Wisconsin,          called    the   Riverworks        City      Center     project       (the
    Project).4          Dollar Tree Stores, Inc. (Dollar Tree) was slated as
    the anchor tenant.                AMCON subcontracted with Great Lakes to
    perform excavating work for installation of the parking lot.
    The original contract amount for this work was $37,165, but once
    the    installation          started,     Great     Lakes      encountered       poor    soil
    quality necessitating additional excavating work.                           As a result,
    and following a series of change orders, the amount AMCON owed
    Great Lakes ultimately totaled $222,238.
    ¶4      After completing its work on the Project, Great Lakes
    invoiced AMCON for $222,238 and, when no payment was received,
    served Riverworks and Dollar Tree with a notice of intent to
    file a claim for a construction lien.                       At that point, and upon
    AMCON's invitation, the owner of Great Lakes, Duwayne Bruckner
    (Bruckner),         went     to   AMCON's    office       to    collect    payment.         A
    representative          from      AMCON     told    Bruckner       only     $33,448       was
    available for payment, and presented to Bruckner a preprinted
    lien       waiver    form,     titled     "Waiver    of     Lien   to     Date"    for    his
    This case comes to us on review of a partial grant of
    4
    summary judgment.   The facts as stated are undisputed by the
    parties.
    3
    No.    2019AP2095
    signature.        The    printed    body       of   the   document   provided,     in
    relevant part:
    The   undersigned,    for   and   in    consideration   of
    $33,448.00 Dollars and other good and valuable
    consideration,    the    receipt    whereof    is   hereby
    acknowledged, does hereby waive and release any and
    all lien or claim of, or right to, lien, under the
    statutes of the State of WI, relating to liens of
    mechanics, laborers and materialmen, with respect to
    and upon the foregoing described property, and the
    improvements   thereon,    and   with    respect  to   any
    statutory lien bond, and on the material, fixtures,
    apparatus or machinery furnished, and on the moneys,
    funds or other considerations due or to become due
    from the Company, on account of labor, services,
    material, fixtures, apparatus or machinery furnished
    to this date by the undersigned for the foregoing
    described property.
    Prior to signing the waiver and accepting the $33,448 check,
    Bruckner crossed off "to Date" in the document title, replaced
    it with the handwritten word, "Partial," and initialed next to
    the modification.         Bruckner made no other changes to the form.
    ¶5    Following unsuccessful efforts to receive payment for
    the outstanding amount due, Great Lakes filed a "Subcontractor
    Claim for Lien" pursuant to 
    Wis. Stat. § 779.06
     and sued for the
    balance     of   $188,790.        Riverworks        moved   for   partial    summary
    judgment as to the claim for foreclosure of the lien, which
    Dollar Tree joined, on the grounds that Great Lakes did not
    comply with 
    Wis. Stat. § 779.05
    (1)'s procedure for limiting the
    waiver to a particular portion of the work, resulting in a full
    waiver of its lien rights.            The circuit court agreed, granting
    Riverworks' motion because "[m]erely changing the title of the
    lien     waiver,        without    additional         explanation,         does   not
    4
    No.    2019AP2095
    specifically        and    expressly     limit      the     waiver    to    apply       to    a
    particular portion of such labor, services, materials, plans, or
    specifications."5
    ¶6      The    court      of   appeals       affirmed,       concluding      neither
    "crossing off 'to Date' and writing in 'Partial' in the title of
    the document" nor referencing "$33,448 Dollars" in the document
    "specifically and expressly limit the waiver to a particular
    portion    of     the     work,"     "such    as    the     labor    in    the    original
    contract, which totaled $37,165."                   Great Lakes Excavating, Inc.
    v.   Dollar     Tree      Stores,    Inc.,     
    2021 WI App 23
    ,    ¶¶21–22,      
    397 Wis. 2d 210
    , 
    959 N.W.2d 351
    .                 The court emphasized the waiver's
    "broad[]"       statement       that   Great       Lakes     waived       "any    and    all
    lien . . . on account of labor, services, material, fixtures,
    apparatus or machinery furnished to this date[.]"                                Id., ¶22.
    Great     Lakes     moved    for     reconsideration,         which       the    court       of
    appeals denied.           We granted Great Lakes' petition for review.
    II.    STANDARD OF REVIEW
    ¶7      This      court    reviews      a     grant     of     summary      judgment
    independently, "using the same methodology of the circuit court
    5Because Dollar Tree's involvement in the case was based
    solely on Great Lakes' claim for foreclosure against Riverworks,
    the circuit court's July 31, 2019 order dismissing the
    foreclosure claim had the effect of disposing of all claims
    between Great Lakes and Dollar Tree.          The order did not
    explicitly dismiss Dollar Tree, so Great Lakes and Dollar Tree
    stipulated   to   Dollar   Tree's   dismissal   from   the case,
    acknowledging in the stipulation that Great Lakes would appeal
    the dismissal.     Great Lakes appealed the orders dismissing
    Dollar Tree and granting partial summary judgment to Riverworks,
    and Riverworks intervened.     Great Lakes maintains additional
    claims against Riverworks not at issue in this appeal.
    5
    No.     2019AP2095
    and the court of appeals."                         Kemper Indep. Ins. Co. v. Islami,
    
    2021 WI 53
    , ¶13, 
    397 Wis. 2d 394
    , 
    959 N.W.2d 912
     (quoting Talley
    v. Mustafa, 
    2018 WI 47
    , ¶12, 
    381 Wis. 2d 393
    , 
    911 N.W.2d 55
    ).
    "Summary      judgment              is    appropriate       when    there     is   no    genuine
    dispute of material fact and the moving party is entitled to
    judgment      as       a       matter      of    law."       
    Id.
        (quoting       Talley,      
    381 Wis. 2d 393
    , ¶12).
    ¶8     This         case      also       requires    the    interpretation        of    
    Wis. Stat. § 779.05
    (1).                    "Issues    of     statutory     interpretation        and
    application present questions of law."                             James v. Heinrich, 
    2021 WI 58
    , ¶15, 
    397 Wis. 2d 517
    , 
    960 N.W.2d 350
     (citing Police Ass'n
    v. City of Milwaukee, 
    2018 WI 86
    , ¶17, 
    383 Wis. 2d 247
    , 
    914 N.W.2d 597
    ).
    III. DISCUSSION
    A.        Construction Lien Statutes
    ¶9     "A construction lien is a remedy created by statute to
    insure       payment            to       contractors,        subcontractors,          tradesmen,
    laborers, and materialmen who have furnished labor or materials
    in good faith for improvement of another's property."                                     Hoida,
    Inc.    v.    M    &       I    Midstate         Bank,     
    2004 WI App 191
    ,      ¶20,    
    276 Wis. 2d 705
    , 
    688 N.W.2d 691
     (quotation marks omitted).                                  Statutes
    governing construction liens were first enacted more than "150
    years       ago    to           encourage          construction         by    protecting        the
    contractors and subcontractors of building projects."                                    Kraemer
    Bros.,      Inc.   v.          Pulaski       St.    Bank,    
    138 Wis. 2d 395
    ,        399,   
    406 N.W.2d 379
     (1987).
    6
    No.     2019AP2095
    ¶10    The lien laws of this state have consistently been
    described     as     "remedial    in     character,"          with    the     purpose       of
    "protecting the claims of tradesmen, laborers and materialmen
    for   work   and     materials    supplied."            Bayland       Bldgs.,       Inc.    v.
    Spirit   Master      Funding     VIII,    LLC,     
    2017 WI App 42
    ,     ¶2,    
    377 Wis. 2d 149
    , 
    900 N.W.2d 94
     (quoting Wes Podany Constr. Co. v.
    Nowicki, 
    120 Wis. 2d 319
    , 324, 
    354 N.W.2d 755
     (Ct. App. 1984));
    see also Goebel v. Nat'l Exchangors, Inc., 
    88 Wis. 2d 596
    , 606,
    
    277 N.W.2d 755
     (1979); Tri-State Mech., Inc. v. Northland Coll.,
    
    2004 WI App 100
    , ¶8, 
    273 Wis. 2d 471
    , 
    681 N.W.2d 302
     ("[O]ne of
    the general purposes of construction lien laws is to protect
    subcontractors of building projects." (citing Kraemer Bros., 
    138 Wis. 2d at 399
    )).        Because     construction             liens     are    "purely
    statutory,"        "[o]ne     pursuing         rights     under        the         Wisconsin
    construction lien law must follow the statute or lien rights
    fail."   Wes Podany Constr. Co., 120 Wis. 2d at 324.
    ¶11    Construction      liens     can     be    waived        under    
    Wis. Stat. § 779.05
    (1).       That statute provides in relevant part:
    Any waiver document shall be deemed to waive all lien
    rights of the signer for all labor, services,
    materials,    plans,   or   specifications   performed,
    furnished, or procured, or to be performed, furnished,
    or procured, by the claimant at any time for the
    improvement to which the waiver relates, except to the
    extent that the document specifically and expressly
    limits the waiver to apply to a particular portion of
    such    labor,    services,   materials,   plans,    or
    specifications.
    The   statute      further     directs    that        "[a]ny       ambiguity       in     such
    document     shall    be    construed     against       the    person       signing       it."
    7
    No.    2019AP2095
    § 779.05(1).         The lien waiver statute, created in 1968 as 
    Wis. Stat. § 289.05
    (1)         and     renumbered           in   1979,     was     "primarily      a
    codification of what was common practice in the construction
    industry."         Druml       Co.,       Inc.       v.    City     of     New     Berlin,       
    78 Wis. 2d 305
    ,      310,       
    254 N.W.2d 265
                (1977)      (citing         Walter   B.
    Raushenbush, Wisconsin Construction Lien Law 1974 (1975)); see
    also § 3, ch. 351, Laws of 1967; 
    Wis. Stat. § 289.05
    (1) (1967–
    68); § 57, ch. 32, Laws of 1979.
    B.         The Lien Waiver Document
    ¶12    Resolution       of     this    dispute          revolves     around        whether
    Great Lakes "follow[ed] the statute" in limiting its lien waiver
    to the $33,448 received in consideration for the waiver, by
    replacing "to Date" with "Partial" in the document title.                                       See
    Wes     Podany    Constr.          Co.,    120       Wis. 2d at          324;      
    Wis. Stat. § 779.05
    (1).          Riverworks asserts this handwritten modification
    creates an ambiguity because the printed body of the waiver
    document otherwise constitutes a full waiver under which Great
    Lakes "waive[s] and release[s] any and all lien or claim of, or
    right to, lien, . . . on account of labor, services, material,
    fixtures, apparatus or machinery furnished to this date," and as
    of    that    date,    all    of     the     work     had      been    completed.           Under
    § 779.05(1), Riverworks argues the resulting ambiguity must be
    "construed       against       the     person        signing        it."          Great     Lakes
    disagrees, arguing the waiver is unambiguously a partial waiver
    because there is no competing interpretation of the document.
    We    agree   with     Great       Lakes     that     the      waiver      document       is    not
    ambiguous and satisfies § 779.05(1) as a partial waiver of the
    8
    No.    2019AP2095
    lien with respect to only the $33,448 paid.6                          The handwritten
    term       "Partial,"    in    conjunction      with     the    specific         amount     of
    consideration, indicates the lien was waived only to the extent
    of that portion of the total amount owed.
    1.   The Waiver is Unambiguously Partial
    ¶13     In    construing    the   lien      waiver       document,         we    first
    address      the    inconsistency    between       the     printed        terms    and      the
    handwritten language.             Read in isolation, the printed text of
    the    waiver        document,     waiving       all     lien       rights       to     date,
    constitutes a full lien waiver; it is undisputed that all of the
    work on the Project had been completed at the time Bruckner
    signed the waiver form.             The handwritten addition of "Partial"
    in the document title, replacing the printed words "to Date,"
    conflicts       with     the   preprinted       language       in   the    body        of   the
    document indicating Great Lakes "does hereby waive and release
    any and all lien . . . on account of labor, services, material,
    fixtures, apparatus or machinery furnished to this date" with
    respect to the Riverworks property.
    Riverworks argued in its briefing, "The lien waiver
    6
    contains no language relating the $33,448 to a particular
    portion of the work performed by Great Lakes."      The court of
    appeals invalidated the waiver on this same basis.     See Great
    Lakes Excavating, 
    397 Wis. 2d 210
    , ¶¶21–22.     Riverworks later
    conceded at oral argument that a reference to a monetary value
    can satisfy the statutory requirement to limit the waiver to a
    "particular portion" of the work.      As we explain further in
    Section III.B.2, we agree that limiting the lien waiver in this
    case to a specific dollar amount satisfies 
    Wis. Stat. § 779.05
    (1) irrespective of Riverworks' concession.
    9
    No.    2019AP2095
    ¶14   Because a lien waiver document is a release, we apply
    contract principles to resolve this conflict.                       See Druml Co., 
    78 Wis. 2d at 311
     (holding that a claimant's letter constituted a
    waiver under the lien waiver statute because it was "clear in
    its intent to release the lien claim"); Marx v. Morris, 
    2019 WI 34
    , ¶63, 
    386 Wis. 2d 122
    , 
    925 N.W.2d 112
     ("A release is to be
    treated as a contract." (quoting Gielow v. Napiorkowski, 
    2003 WI App 249
    , ¶14, 
    268 Wis. 2d 673
    , 
    673 N.W.2d 351
    )).                              Riverworks
    contends a construction lien waiver is not a contract because
    
    Wis. Stat. § 779.05
    (1) does not "require" "an offer, acceptance,
    and consideration."            While the statute does not require these
    elements, nothing in the statutory text strips the release in
    this case of its contractual nature.                    The lien waiver satisfies
    each   element     of   a     contract;     accordingly,          contract    principles
    apply to its interpretation.
    ¶15   "[I]n accord with the general rule that all parts of a
    contract     are   to    be    given     effect,       the   courts     must    seek   to
    reconcile inconsistencies between the changed or added terms and
    the    printed     matter.          When,    however,        the    printed    contract
    provisions irreconcilably conflict with the provisions added by
    the parties, the added provisions will control."                         11 Williston
    on Contracts § 32:13 (4th ed.).                       The handwritten and printed
    terms in the waiver document are irreconcilable:                         the document
    is either a partial lien waiver or a full lien waiver, but it
    cannot be both.         "Where written provisions are inconsistent with
    printed      provisions       (of    a    contract),         an    interpretation      is
    preferred      which     gives      effect       to    the    written    provisions."
    10
    No.    2019AP2095
    Tollefson v. Green Bay Packers, 
    256 Wis. 318
    , 322, 
    41 N.W.2d 201
    (1950) (quoting Restatement, Contracts § 236(e)); see also Hicks
    Pub. Co. v. Wis. Cent. Ry. Co., 
    138 Wis. 584
    , 
    120 N.W. 512
    , 514
    (1909) ("It is a canon of construction that where a contract 'is
    written in part and printed in part, as where it has been filled
    in   upon   a    printed    form,    the    parties    usually    pay    much   more
    attention       to   the   written   parts      than   to   the   printed   parts.
    Accordingly, if the written provisions cannot be reconciled with
    the printed, the written provisions control.'").                   In accordance
    with black letter contracts law, we reconcile this inconsistency
    by giving effect to the handwritten terms.7
    7Remarkably, the dissent claims contract principles should
    not be applied to a contract.          Dissent, ¶32.    Legislative
    enactments concerning contracts do not displace the entire body
    of legal principles governing them. "To accomplish a change in
    the common law, the language of the statute must be clear,
    unambiguous,    and    peremptory."       Fuchsgruber   v.    Custom
    Accessories, Inc., 
    2001 WI 81
    , ¶25, 
    244 Wis. 2d 758
    , 
    628 N.W.2d 833
    .    "[L]egislation in derogation of the common law
    should be strictly construed so as to have minimal effect on the
    common law rule."     Augsburger v. Homestead Mut. Ins. Co., 
    2014 WI 133
    ,   ¶40,    
    359 Wis. 2d 385
    ,    
    856 N.W.2d 874
        (citing
    Fuchsgruber, 
    244 Wis. 2d 758
    , ¶25; NBZ, Inc. v. Pilarski, 
    185 Wis. 2d 827
    , 836, 
    520 N.W.2d 93
     (Ct. App. 1994)).          Wisconsin
    Stat. § 779.05(1) directs our treatment of ambiguity in lien
    waivers, but it does not abrogate the entire suite of common law
    contract principles.     Because the legislature removed a tool,
    the dissent abandons the whole toolbox. This is not the law.
    In NBZ, the court of appeals determined covenants not to
    compete under 
    Wis. Stat. § 103.465
     are "subject to common law
    contract principles as well as [statutory] requirements."  NBZ,
    185   Wis. 2d at   836.    Section  103.465  "sets   forth  the
    requirements for a[] . . . covenant in an employment contract
    but does not address on its face the question of whether a
    restrictive covenant must be supported by consideration."   Id.
    at 835.      The court concluded such a covenant requires
    consideration   because the   statute  did  not   "abandon  the
    11
    No.       2019AP2095
    ¶16   The existence of an inconsistency between preprinted
    and   handwritten     contract      terms    is     distinct    from     contractual
    ambiguity; the latter exists if a document is "reasonably or
    fairly susceptible of more than one construction."                     Borchardt v.
    Wilk, 
    156 Wis. 2d 420
    , 427, 
    456 N.W.2d 653
     (Ct. App. 1990).                            By
    contrast, the presence of an inconsistency or conflict between
    terms    precludes   a     reasonable   interpretation          of   the    document;
    read together, the terms are irreconcilable.                     See, e.g., Ketay
    v.    Gorenstein,     
    261 Wis. 332
    ,     334,     53      N.W.2d.      6     (1952)
    (explaining the court cannot "reject certain portions of the
    contract" "unless it presents an irreconcilable inconsistency").
    The lien waiver in this case cannot be construed as a full
    waiver    because    the    handwritten      word    "Partial"       must   be     given
    principles by which a contract is formed in the first instance."
    Id. at 837.
    So too here. The lien waiver we construe in this case is a
    contract, "subject to common law contract principles as well as
    [statutory] requirements" under 
    Wis. Stat. § 779.05
    (1).     See
    id. at 836.   The rule giving controlling effect to handwritten
    terms over preprinted contract provisions is neither expressly
    abrogated by § 779.05(1) nor in conflict with it, and the
    policies underlying the principle are not "irrelevant to the
    legislature's choice" to recognize lien waivers as a statutory
    matter.   See Hinrichs v. DOW Chem. Co., 
    2020 WI 2
    , ¶55, 
    389 Wis. 2d 669
    , 
    937 N.W.2d 37
     (declining to apply common law
    principles because "the policies underlying the economic loss
    doctrine——the allocation of risk and the distinction between
    tort and contract law——are irrelevant to the legislature's
    choice to provide a purely statutory cause of action and remedy
    by way of § 100.18").        That "the common law contract
    rule . . . is irrelevant" to a non-contractual waiver does not
    negate its application to a contractual waiver.    See dissent,
    ¶32.
    12
    No.     2019AP2095
    effect.     Because the word "Partial" is handwritten, it governs
    over the preprinted language waiving all lien rights to date.
    ¶17     This        principle   that    handwritten        terms      control        over
    preprinted      provisions      "is     based    on     the    inference         that    the
    language inserted by handwriting . . . is a more recent and more
    reliable expression of [the parties'] intentions than is the
    language     of     a     printed     form."       Edwin       W.       Patterson,        The
    Interpretation and Construction of Contracts, 
    64 Colum. L. Rev. 833
    , 855 (1964) (citing Restatement, Contracts § 236(e) (1932)).
    "Since    the     parties    actually      chose   to    add       to   or      modify   the
    printed contract, the written terms presumably better reflect
    their    intention       than   those    contained       in    a    printed       contract
    intended for general use."               11 Williston on Contracts § 32:13
    (4th ed.).
    ¶18     Consistent with the principle that handwritten terms
    control over the form's printed provisions, the term "Partial"
    prevails over the language in the printed body of the document
    waiving all lien rights to date.                Resolving this conflict leaves
    no ambiguity as to whether the document is a full or partial
    waiver.     Because it can be only one or the other, there is no
    reasonable alternative construction of the document other than
    as a partial waiver.
    2.      The Waiver is "Specifically and Expressly" Limited to
    $33,448
    ¶19     Concluding that the document is a partial waiver does
    not alone resolve the case; ambiguity could exist if the lien
    waiver is not specifically and expressly limited to a particular
    13
    No.   2019AP2095
    portion of work.            This is not so in this case.                          "Partial"
    unambiguously applies to the "particular portion of such labor,
    services, materials, plans, or specifications" represented by
    the amount of the "$33,448 Dollars" written on the waiver form
    and received in consideration for the partial release.8                                  
    Wis. Stat. § 779.05
    (1).
    ¶20     Riverworks conceded during oral argument that a waiver
    could be limited to a dollar amount, and suggested Great Lakes
    could    have   satisfied      
    Wis. Stat. § 779.05
    (1)        by    agreeing     "I
    hereby    waive    my   lien      rights   to       the       extent   of    X    dollars."
    Although    this    would    have     been      a   clearer       limitation        of   the
    waiver,    we     decline    to    adopt        such      a    formulaic      reading     of
    8  The dissent claims our contract construction "rests on the
    false premise that when a party receives a certain amount of
    money in exchange for a waiver, it must be waiving its lien only
    up to that dollar amount," and suggests Great Lakes could have
    accepted the $33,448 "in exchange for waiving its lien claims
    related to the original contract amount of $37,165" or "any
    other dollar amount."     Dissent, ¶30.    Great Lakes could have
    chosen to limit its waiver as the dissent describes, which we
    would have honored had the lien waiver document so indicated.
    But no such limitation can be reasonably gleaned from the
    document before us.      The dissent posits purely hypothetical
    intentions   possibly   underlying   Great   Lakes'  addition  of
    "Partial," which, according to the dissent, make the waiver
    ambiguous. In doing so, the dissent reaches beyond the four
    corners of the document to introduce ambiguity where it does not
    exist. There are myriad ways Great Lakes might have intended to
    limit its lien waiver, but we need not consider any of these
    speculative iterations because our review is confined to the
    four corners of the lien waiver document, which——as the dissent
    acknowledges——is "all the property owner has to go on[.]" Id.,
    ¶26. Confined to its four corners, the lien waiver document in
    this case yields but one reasonable interpretation, and while it
    does not mirror the model forms reproduced by the dissent, it
    nonetheless meets the statutory bar.
    14
    No.    2019AP2095
    § 779.05(1).         The statute specifies only that a partial lien
    waiver must be "specific[] and express[]."9                The partial waiver
    satisfies       § 779.05(1)    because    it   is    unambiguously      partial——
    waiving Great Lakes' lien rights only in the amount of "$33,448
    Dollars"——an amount representing the "particular portion" of the
    work to which the waiver applies.
    ¶21     In further support of this reading, as of the date the
    lien       waiver   was   signed,   no   one   contended   that    any    of   the
    $222,238 allegedly due to Great Lakes did not cover lienable
    work.       Prior to 2006, waivers of construction lien rights were
    limited to "labor and materials furnished or to be furnished by
    the claimant at any time for the improvement to which the waiver
    relates[.]"         
    Wis. Stat. § 779.05
    (1) (2003–04).             In 2006, the
    legislature amended § 779.05(1) to include "all labor, services,
    materials,      plans,    or   specifications       performed,   furnished,     or
    procured, or to be performed, furnished, or procured, by the
    claimant at any time for the improvement to which the waiver
    relates[.]"         2005 Wis. Act 204; § 779.05(1) (2005–06).             Because
    no party maintains that any portion of the fully completed work
    is not lienable, limiting the waiver to a specific dollar value
    does not create any additional ambiguity.
    Contrary to Riverworks' suggestion at oral argument that
    9
    we are left to "divine" what portion of work the waiver
    attempted to release, no divination is required. Construing the
    document as a partial waiver limited to $33,448 is the only
    reasonable interpretation of the contract.      Interpreting the
    waiver before us does not involve the kind of "guessing games"
    Riverworks and the dissent assert the statute is designed to
    avoid. See dissent, ¶31.
    15
    No.     2019AP2095
    ¶22    Because we conclude the lien waiver document within
    its   four    corners     satisfies       the      statutory       requirements       by
    specifically and expressly limiting the waiver to the $33,448
    Great Lakes received in consideration, we need not decide the
    other issues presented, including the propriety of considering
    extrinsic     evidence    of    intent,      or    whether   equitable        estoppel
    precludes Riverworks' claim.
    IV.    CONCLUSION
    ¶23    The    construction      lien    waiver      document    on     its   face
    satisfies the statutory requirements of 
    Wis. Stat. § 779.05
    (1)
    necessary to limit the waiver of Great Lakes' lien rights.                            The
    document "specifically and expressly" restricts the lien waiver
    to "a particular portion of such labor, services, materials,
    plans, or specifications"——the $33,448 received in consideration
    of the waiver.
    By    the    Court.—The   decision      of    the    court     of     appeals   is
    reversed, and the cause is remanded to the circuit court for
    further proceedings consistent with this opinion.
    16
    No.    2019AP2095.rfd
    ¶24    REBECCA FRANK DALLET, J.                      (dissenting).              This case
    presents     a    straightforward            application        of   a       straightforward
    statute.          The     majority's         reliance      on    common         law     contract
    principles is misguided, resulting in a decision at odds with
    the   legislature's          chosen         policy       regarding      construction-lien
    waivers.     I therefore respectfully dissent.
    ¶25    Wisconsin Stat. § 779.05(1) provides that if a party
    wants to limit a construction-lien waiver to only a portion of
    what it's owed, it must "specifically and expressly limit[] the
    waiver      to    apply    to     a    particular         portion       of      [the]     labor,
    services, materials, plans, or specifications" (emphases added).
    Such specificity is necessary because if the party limits the
    waiver in an ambiguous way, that ambiguity "shall be construed
    against     the    person       signing"       the       waiver.         Id.          Without    a
    specific,        express,       and     unambiguous         limitation,          the      waiver
    applies to "all [of that party's] lien rights."                                 Id. (emphasis
    added).
    ¶26    The    rationale          for     both      the    statute's         heightened-
    clarity requirement and its presumption in favor of a complete
    waiver      is    rooted     in       the    "reliance         placed     on      waivers       by
    owners . . . making          payouts."             See    Legislative          Council     Note,
    1967, 
    Wis. Stat. § 289.05.1
                       Wisconsin allows both general and
    subcontractors to file lien claims, regardless of whether the
    property owner is aware of the subcontractor's work.                               Thus, if a
    Section 289.05 was eventually renumbered as § 779.05, but
    1
    the relevant language was unchanged. See § 57, ch. 32, Laws of
    1979.
    1
    No.    2019AP2095.rfd
    property    owner       hires       a    general           contractor,       who        hires    a
    subcontractor,         who      hires           a     subcontractor,              that      last
    subcontractor has the same right to file a construction lien for
    its work as does the general contractor.                           And because a general
    contractor,      not     the     property           owner,        hires    and     supervises
    subcontractors,        the     owner         may     not     know    how        much     work   a
    subcontractor has performed or what they are owed for that work.
    In   addition,    the    property         owner       is    often    not     a    party    to    a
    construction-lien        waiver         between       contractors.              Thus,    when    a
    subcontractor      who       signed      a    lien      waiver       later       attempts       to
    foreclose on a lien, claiming that the waiver was only partial,
    all the property owner has to go on is what is within the four
    corners    of    the    waiver      document.               See    generally        Walter      B.
    Raushenbush, Wisconsin Construction Lien Law 8–12 (1975).                                   This
    explains the statute's requirements that a lien waiver "shall be
    deemed to waive all lien rights" unless it "specifically and
    expressly limits the waiver to apply to a particular portion" of
    the claimant's work.            See § 779.05(1); see also Robert J. Smith
    et al., Wisconsin Construction Law and Construction Liens 218
    (1989)    (cautioning        that       "care       should    always       be    taken"     when
    writing a partial lien waiver because any "attempt to hold back
    part of the claimant's rights will be construed against the
    claimant").
    2
    No.    2019AP2095.rfd
    ¶27      There is no one form a party must use to limit the
    scope   of   its   lien    waiver,     but   the   following     sample   forms
    demonstrate the specificity required under § 779.05.                 The State
    Bar's   Construction      Lien   Law   Handbook    contains    the   following
    example:
    3
    No.   2019AP2095.rfd
    Steven W. Martin & Bridget M. Hubing, Wisconsin Construction
    Lien Law Handbook app. II at 14 (4th ed. 2019).        One of the
    statute's drafters offers another option:2
    LIMITED WAIVER OF CONSTRUCTION LIEN
    For value received, the undersigned hereby waives all
    rights to or claims for a lien on the land hereafter
    described, for any and all work, materials, plans or
    specifications furnished between the ___ day of _____,
    [20]__, which was the last day of furnishing any labor
    or materials to which this waiver relates, for the
    improvement of said lands, said improvements being
    done for [owner] by [contractor], said lands being
    situated in _____ County, State of Wisconsin, and
    described                                            as
    follows:___________________________________________.
    It is expressly stipulated that this waiver applies
    only   to   work   done    or   materials,    plans or
    specifications furnished on or before the above-stated
    last date of furnishing any labor or materials to
    which this waiver relates, and that the work done or
    materials furnished by the undersigned for said job on
    or before said date was __________________________
    [describe].   The amount of compensation due or paid
    for such work, for which lien is hereby waived, is
    __________   [Here   insert   the   dollar   amount of
    compensation waived by this partial waiver].
    The right to assert construction lien rights for work
    done or materials furnished after said date on said
    job is hereby expressly reserved.
    Walter B. Raushenbush, Wisconsin Construction Lien Law 267–69
    (1975).   Both sample forms include specific spaces for the lien
    claimant to expressly limit the waiver to a certain "percentage
    performed,   dollar   value,   and/or   dates . . . necessary     to
    2 See Walter B. Raushenbush, Wisconsin Construction Lien
    Law, at iv (1975) (explaining Raushenbush's role in the
    statute's drafting process).
    4
    No.   2019AP2095.rfd
    accurately describe the [w]ork to which the [w]aiver relates,
    stating exceptions, if any."       See Martin & Hubing, supra.
    ¶28   Great Lakes' waiver stands in stark contrast to those
    samples   in   that   it   lacks     the   "careful   detailing,"     see
    Raushenbush, supra, at 268–69, of the particular portion of work
    covered by the waiver:
    The waiver plainly states that Great Lakes waived and released
    "any and all" liens or claims related to all of work Great Lakes
    "furnished to this date [March 20, 2017]."            Great Lakes had
    completed all of its work on the Riverworks project in November
    2016, so here, "to this date" encompasses the entirety of Great
    Lakes' work.   The only change Great Lakes made to the waiver was
    to the document's title, where it changed "Waiver of Lien to
    Date" to "Waiver of Lien Partial."
    5
    No.    2019AP2095.rfd
    ¶29     Nowhere,        however,           does     Great      Lakes'          waiver
    specifically and expressly identify what particular "part" of
    Great Lakes' lien claims were waived.                     The waiver is not limited
    to a certain dollar amount's worth of services, work completed
    up to a certain date (short of the date Great Lakes signed the
    waiver), or certain raw materials, for example.                               Rather, it
    expressly       states    that,     in     exchange      for    $33,448,     Great    Lakes
    waived "any and all" lien claims related to all work it had
    furnished to date——which, since it had already completed the
    project, encompassed the original contract as well as all of the
    subsequent change orders.                  See Tufail v. Midwest Hosp., LLC,
    
    2013 WI 62
    , ¶26, 
    348 Wis. 2d 631
    , 
    833 N.W.2d 586
     (explaining
    that courts "construe [an unambiguous] document according to its
    literal       terms"     because     we    "presume       the     parties'    intent     is
    evinced by the words they chose").                         Accordingly, § 779.05(1)
    mandates the court to construe the waiver as waiving all lien
    claims.
    ¶30     Great     Lakes      argues,       and     the     majority    mistakenly
    agrees, that because Great Lakes received $33,448 in exchange
    for the lien waiver, the waiver applies to $33,448 worth of the
    $222,238 Great Lakes claims it was owed for the project.                                 But
    that       argument    rests   on    the    false       premise    that    when   a   party
    receives a certain amount of money in exchange for a waiver, it
    must be waiving its lien only up to that dollar amount.3                                 For
    Had Great Lakes intended to limit its waiver to $33,448
    3
    worth of its services, it could have specifically and expressly
    done so by waiving its lien claims "to the extent of $33,448
    only of the $222,238 worth of services provided."    See Smith,
    supra, at 262.
    6
    No.   2019AP2095.rfd
    example, Great Lakes could have accepted AMCON's $33,488 payment
    in exchange for waiving its lien claims related to the original
    contract amount of $37,165.                 Or Great Lakes could have accepted
    $33,488 to waive its lien claims related to any other dollar
    amount.       The point is:             we don't know.4       And given that every
    other     term        in   the     document       indicates    a     complete    waiver,
    interpreting it as such is the only option.
    ¶31     Great        Lakes   also     argues    that    its    handwritten     edit
    reflects its and AMCON's intent for the waiver to be a partial
    one, and therefore Riverworks (who hired AMCON) should be held
    to that understanding.                  The problem with that argument is two-
    fold.     First, Riverworks was not a party to the waiver and the
    record does not indicate that AMCON was Riverworks' agent, such
    that Riverworks would be bound by AMCON's actions.                           See Romero
    v. W. Bend Mut. Ins. Co., 
    2016 WI App 59
    , ¶38, 
    371 Wis. 2d 478
    ,
    
    885 N.W.2d 591
     (summarizing general agency principles).                             Plus,
    because Riverworks was not a party to the waiver, it has no way
    of knowing what Great Lakes intended other than by reading the
    document——which says that Great Lakes waived "any and all" lien
    claims for all of its work.                  See Tufail, 
    348 Wis. 2d 631
    , ¶26.
    Second, even if crossing out "to date" and writing "partial" in
    the   title      is    enough      to    indicate    that    Great   Lakes    and   AMCON
    intended the document to waive only part of Great Lakes' lien
    4All we can do is guess about what Great Lakes' handwritten
    edit to the waiver's title means.      But even if we knew what
    "partial" meant, it would still be at odds with the rest of the
    waiver's text, making the waiver at best ambiguous.           And
    § 779.05(1) requires the court to resolve any ambiguity against
    Great Lakes.
    7
    No.      2019AP2095.rfd
    claims,       we——and       Riverworks——are           still     left        to     guess     the
    particular portion of work to which Great Lakes is waiving its
    lien claims.         The point of § 779.05(1), however, is to eliminate
    such a guessing game from how courts or third-parties understand
    a lien waiver.            As one of the statute's drafters explained, the
    statute tilts heavily in favor of construing lien waivers as
    waiving       all     lien        claims      because      other,       less        stringent
    possibilities present "serious problems of proof" regarding the
    portion       of    work     to       which    a     partial    waiver        would    apply.
    Raushenbush,         supra,      at    102–03.        Great    Lakes'       position       would
    circumvent the statute's text and must therefore be rejected.
    ¶32    Instead of focusing on the text of § 779.05(1), the
    majority wrongly relies upon default principles of contract law.
    It   claims        that   the     handwritten        "term"    places       the    waiver    in
    irreconcilable conflict with itself, and therefore we must apply
    the common law rule that a handwritten provision controls over a
    conflicting printed provision.                      For starters, Great Lakes did
    not change a "term" of the contract; it changed part of the
    title while leaving all of the substantive terms unchanged.                                  But
    more importantly, common law contract rules are irrelevant here
    because a construction lien is a "purely statutory right" that
    "cannot be maintained" outside of the relevant statutory rules.
    See Goebel v. Nat'l Exchangors, Inc., 
    88 Wis. 2d 596
    , 606, 
    277 N.W.2d 755
             (1979)     (quoting        Rees    v.   Ludington,         
    13 Wis. 308
    ,
    311-12    (1860);         Scott    v.    Christianson,         
    110 Wis. 164
    ,        167,   
    85 N.W. 658
     (1901) ("The lien being purely a statutory right, it
    must     be    pursued      as     the     statute      directs,       or     it    fails.").
    Section 779.05 provides the statutory rule for how to construct
    8
    No.    2019AP2095.rfd
    and   interpret      lien   waivers.     Under   that   rule,    a   waiver   is
    binding even without consideration——that is, even if the waiver
    is not a contract.5          Accordingly, the common law contract rule
    the majority references is irrelevant.               See Goebel, 88 Wis. at
    606; see also Hinrichs v. DOW Chem. Co., 
    2020 WI 2
    , ¶55, 
    389 Wis. 2d 669
    ,      
    937 N.W.2d 37
        (explaining     that     common      law
    principles     are    "irrelevant"      when   the   legislature     enacts    a
    statute directly addressing the same issue).
    ¶33   Concluding that Great Lakes waived all of its lien
    claims would undoubtedly be a harsh result.                But just because
    Great Lakes waived its lien claims does not mean that it can't
    try to recover what it's owed under the construction contract.
    See § 779.05(1) (explaining that a lien waiver "is a waiver of
    lien rights only, and not of any contract rights of the claimant
    otherwise existing").          Moreover, the legislature has made the
    policy choice that construction-lien waivers should be treated
    as complete waivers unless they contain specific and express
    limitations.      The legislature can change that policy by amending
    the statute to allow a party to limit a waiver in the way Great
    Lakes attempted to here.           See Kohn v. Darlington Cmty. Schs.,
    
    2005 WI 99
    , ¶43, 
    283 Wis. 2d 1
    , 
    698 N.W.2d 794
    .                 As § 779.05(1)
    reads now, Great Lakes' claim fails.             I would therefore affirm
    the court of appeals' decision.
    5Although a waiver doesn't have to be a contract, Great
    Lakes' waiver is one because it gave up something of value——all
    of its lien claims——in exchange for consideration.      But the
    lien-waiver statute applies whether or not the lien waiver is a
    contract. See Goebel, 88 Wis. at 606; Christianson, 110 Wis. at
    167.
    9
    No.    2019AP2095.rfd
    ¶34   I   am   authorized   to    state   that   Justice    ANN   WALSH
    BRADLEY joins this opinion.
    10
    No.   2019AP2095.rfd
    1