Adams v. McKay , 63 Wis. 404 ( 1885 )


Menu:
  • Cole, C. J.

    We are unable to perceive bow tbe defendant could have been prejudiced by allowing tbe witness Kyle to answer tbe question put to him whether tbe sleds remained outside nearly a week after they were finished before they were removed by tbe defendant. Tbe question was objected to as leading. Tbe witness, however, answered that tbe third and fourth sets remained out there nearly a week, and added that tbe first five sets remained out there nearly a month, before Knox took his three sets away. This evidence was not at all material, to the issues being tried. By tbe original contract tbe plaintiff admits tbe five sets of sleds were to be completed, ready for debvery at bis shop, by tbe first of December, 1880. His contention, is that the sleds Avere finished tbe last of October, when tbe defendant inspected and accepted them and paid $150 on tbe contract; that afterwards, in November, be sold Knox three sets of tbe sleds, with tbe knowledge and consent of tbe defendant, upon an agreement that be would manufacture three other sets of like structure and material, in beu of those sold Knox, and have them completed, ready for delivery, by tbe middle of December. Tbe defendant denies that there was any extension of tbe time for com*406pleting the contract, and claims that the sleds were to be finished, ready for delivery, by the first of December. There is no pretense that the plaintiff had the sleds ready for delivery at that time. The question litigated, therefore, was whether the defendant had agreed that the time for finishing the sleds should be extended. On that question the evidence of the witness was not important. The plaintiff was bound to show a valid excuse for failing to perform his contract as originally made. It is true, one question litigated was, what damage, if any, the defendant had sustained by reason of the delay in finishing the sleds by the first of December. Rut the question put to the witness had but little bearing upon that issue, and it was evidently not intended' to refer to it. We therefore think the defendant was not prejudiced by the court overruling the objection to the question.

    . The other errors assigned for a reversal of the judgment relate to an exception to a portion of the charge; also to one taken to the refusal of the court to give an instniction, or 4 instructions, asked on the part of the defendant. That portion of the charge specifically excepted to is the following: where the court told the jury that “the plaintiff is entitled to recover the amount you find due him for the delivery of these sleds and other articles, with interest from the time they were delivered.” It is said this charge took from the jury every question in the case, and was equivalent to a direction to find for the plaintiff the amount claimed by him. But this is not a fair criticism upon the 'charge, for in the very next sentence the learned .circuit judge added, “I mean, by saying the amount you find ‘due him, that if you find that the defendant suffered damage, that you should take the amount of the damage out of the plaintiff’s claim, and allow the plaintiff interest on the balance.” It would be very unfair to take a detached sentence of the charge and found error upon it. The charge *407should be considered together, and a fair construction given to it. If this is done, it will be seen that there is no error in it of which the defendant can complain.

    We have referred already to the fact that the defendant claimed that the plaintiff had not performed his contract, and that he had sustained damages in his logging operations by reason of such non-performance! It was admitted that the five sets of sleds were not completed ready for delivery on the first of December. But the question was, Had the defendant waived a delivery at that time, and agreed to accept three sets of sleds if not finished until a later period in the month? That question was fully litigated on the trial, and the jury found in favor of the plaintiff on that issue. So the question as to the defendant’s damages resulting from the failure of the plaintiff to have all the sleds .ready for delivery according to the original contract, was fully gone into; and the court told the jury distinctly in another part of the charge that the plaintiff was entitled to recover the value of the manufactured articles, which he had made for and delivered to the defendant, unless the jury should find that such articles were not delivered pursuant to the contract and that in consequence of such nondelivery the defendant had sustained damages in his logging business. Also, if the jury should find that the defendant had sustained damages on account of such non-delivery, such damages should be deducted out of the plaintiff’s claim. We do not think the jury could have been misled by the charge excepted to.

    The defendant asked the court to give certain instructions bearing upon the particular items of damages which he was entitled to recover for failure on the part of the plaintiff to perform' his contract. These instructions were refused, probably because the court considered its general charge sufficiently specific and full upon that point. It is by no means clear that it is not. Besides; the jury found against *408the defendant on Ms claim for damages; so Ms instructions on that subject are of little importance. But there is a further answer to the objection based on the refusal of the court to give these instructions. The record does not show that any exception was taken on the trial to the refusal of the court to give the instructions. The only exception taken was afterwards, when exceptions were filed to the charge. The exception was too late. This precise point was so decided in Firmeis v. State, 61 Wis. 140, and requires no further comment.

    The issues in this case seem to have been fairly submitted, under a proper charge, and we see no reason for settmg aside the judgment. It is therefore affirmed.

    By the Gourt.— Judgment affirmed.

Document Info

Citation Numbers: 63 Wis. 404

Judges: Cole

Filed Date: 6/1/1885

Precedential Status: Precedential

Modified Date: 7/20/2022