Powerbrace Corporation v. Grede Holdings LLC ( 2019 )


Menu:
  •        COURT OF APPEALS
    DECISION                                                NOTICE
    DATED AND FILED                            This opinion is subject to further editing. If
    published, the official version will appear in
    the bound volume of the Official Reports.
    August 14, 2019
    A party may file with the Supreme Court a
    Sheila T. Reiff                    petition to review an adverse decision by the
    Clerk of Court of Appeals               Court of Appeals. See WIS. STAT. § 808.10
    and RULE 809.62.
    Appeal No.        2018AP1548                                                    Cir. Ct. No. 2014CV739
    STATE OF WISCONSIN                                             IN COURT OF APPEALS
    DISTRICT II
    POWERBRACE CORPORATION,
    PLAINTIFF-RESPONDENT,
    V.
    GREDE HOLDINGS LLC,
    DEFENDANT-APPELLANT.
    APPEAL from a judgment of the circuit court for Kenosha County:
    ANTHONY MILISAUSKAS, Judge. Affirmed.
    Before Neubauer, C.J., Gundrum and Stark, JJ.
    Per curiam opinions may not be cited in any court of this state as precedent
    or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3).
    No. 2018AP1548
    ¶1       PER CURIAM. This case involves the breach of a commercial
    contract. The trial court found that Grede Holdings, LLC, supplied defective
    materials to Powerbrace Corporation, Powerbrace gave Grede proper notice of the
    defects, Grede did not avail itself of inspection opportunities, and Powerbrace
    therefore is entitled to recover its contractual damages. The court’s findings are
    amply supported by the record. We affirm the judgment.
    ¶2       Powerbrace assembles and sells “brake beams,” an integral safety
    component of trains’ brake systems. Attached to the brake beams are duct-iron
    casting brake heads, which Grede manufactured for Kenosha-based Powerbrace
    until 2003. Powerbrace later moved its brake line assembly to Saltillo, Mexico.
    ¶3       In the summer of 2011, to fill a rush demand, Powerbrace contacted
    Grede.        The parties entered into a one-year Supply Agreement for Grede to
    provide 255,000 brake heads to Powerbrace by August 2012.                      Grede’s sales
    representative, Chuck Glasgow, and Powerbrace’s vice president of purchasing,
    John Vitkus, negotiated the deal. Under the Agreement, Grede warranted that the
    supplied brake heads would be free from defects in terms of material and
    workmanship and would conform to Powerbrace’s specifications and designs.
    Within a month after delivery began, however, Powerbrace found defects in
    virtually every shipment.1 Per their agreement, Powerbrace gave Grede written
    notice of defects and rejections.
    1
    Most of the defects, which need not be detailed here, apparently were caused by
    Grede’s inability to control the pouring temperature. The point is that any of the defects could
    have affected the working of a train’s brakes, with potentially catastrophic results.
    2
    No. 2018AP1548
    ¶4      By early 2012, Powerbrace had rejected as defective 17,877
    delivered brake heads. In March 2012, for the first time since Powerbrace’s
    August 2011 complaints, a Grede representative inspected the brake heads at the
    Saltillo plant and confirmed the defects. Around the time the Supply Agreement
    ended in August 2012, a second Grede representative went to Saltillo, confirmed
    and documented the defects with photographs, and told Powerbrace to scrap the
    parts. Powerbrace instead stored the brake heads at the Saltillo plant, where they
    still were available for inspection at the time of trial.
    ¶5      Powerbrace attempted to discuss the defective parts with Grede in
    February 2013. Grede instructed its employees not to speak with Powerbrace. In
    August 2013, Powerbrace tried to mitigate its damages by testing some of the
    rejected brake heads to see if they were usable in after-market applications. When
    put into assembly, they cracked due to the same quality issues for which they
    previously had been rejected and about which Grede had been given notice. When
    Vitkus tried to contact Glasgow after the failed mitigation run, Glasgow would not
    return his calls. Powerbrace filed suit in February 2014.
    ¶6      After a court trial, the court found that the parties were bound by the
    “pretty clear” Supply Agreement, that the defects were due to material and
    workmanship issues, that Grede either had received or waived proper notices of
    the defects, and that Powerbrace was entitled to damages for Grede’s breach. It
    also found there were no side agreements by which Powerbrace could recover
    collateral costs. After off-setting the $34,000 Powerbrace still owed Grede for
    3
    No. 2018AP1548
    delivered, nondefective parts, the court entered judgment in Powerbrace’s favor
    for $365,502.94.2 Grede appeals.
    ¶7        We first address our standard of review. Grede correctly describes
    this as “a simple case of holding two companies to the terms of their commercial
    supply contract.” That is exactly what the trial court did. While Grede urges de
    novo review of the court’s application of facts to the Supply Agreement and to the
    law of waiver, it devotes its brief to a challenge to the court’s factual findings.
    “Findings of fact shall not be set aside unless clearly erroneous, and due regard
    shall be given to the opportunity of the trial court to judge the credibility of the
    witnesses.” WIS. STAT. § 805.17(2) (2017-18).3
    ¶8        The court found that, based upon the exhibits and the credible
    testimony of the witnesses, the brake heads were defective. The exhibits included
    numerous e-mails from Powerbrace to Grede describing the various flaws, as well
    as photos, some taken by a Grede representative clearly showing the defects.
    ¶9        Glasgow, Grede’s sole witness, testified that the defective brake
    heads were caused by old and worn tooling, although he never physically
    examined the rejected brake heads himself. He said that when the parties were
    negotiating the Supply Agreement, he expressed his concern to Vitkus about using
    worn tooling on a rush order but Powerbrace refused to pay to replace it.
    2
    Powerbrace disputed the $34,000 off-set at trial but does not appeal that ruling.
    3
    All references to the Wisconsin Statutes are to the 2017-18 version unless otherwise
    noted.
    4
    No. 2018AP1548
    ¶10    Vitkus testified that he recalled no discussions about worn tooling
    and e-mail communication exhibits submitted at trial did not raise worn tooling as
    a concern by Grede. Also, Powerbrace’s senior project engineer testified that
    workmanship and the process itself, not tooling, is what caused shrinkage in the
    rejected brake heads. The court’s finding that Grede produced a defective product
    due to material and workmanship issues is not clearly erroneous.
    ¶11    The court also found that Powerbrace gave timely notice of defect at
    least twenty-nine times, the first just a month after the parties signed the Supply
    Agreement. The evidence was that Glasgow acknowledged receiving notice of the
    defects, two Grede representatives inspected and confirmed the defects, one
    representative compiled a photo album showing the flawed products, and Grede
    often did not respond to contacts from Powerbrace. The court’s finding as to
    notice is well-supported in the record.
    ¶12    Grede contends the court relieved Powerbrace of the notice
    requirement in regard to the defects discovered as a result of the August 2013 parts
    run, such that it had no opportunity to verify those defects. Powerbrace already
    had provided notice to Grede of those defective parts and was endeavoring to
    mitigate its damages by putting them into other applications.           Because the
    defective parts still were unusable, whether due to the same or new defects,
    Powerbrace was not obligated to give Grede yet another round of notices.
    ¶13    Finally, the court found that it was “quite clear” from the testimony
    that Grede had ample opportunity to inspect the brake heads; that Grede waited at
    least six months after the first notice of defect to do so; that once inspected, Grede
    decided it was too costly to ship the brake heads back to its plant and told
    Powerbrace to scrap them; and that, in fact, the products still were in Mexico and
    5
    No. 2018AP1548
    accessible to Grede.4 The court concluded that, as Powerbrace “went out of [its]
    way” to make the break heads available for inspection, Grede waived whatever
    further opportunity it had to inspect because it “basically ha[s] walked away from
    [its] responsibility to inspect the products and to make a determination as to
    damages.” The court’s findings are not clearly erroneous. We affirm.
    By the Court.—Judgment affirmed.
    This opinion will not be published.                See WIS. STAT. RULE
    809.23(1)(b)5.
    4
    Grede has a plant in Monterrey, Mexico, about an hour from Saltillo.
    6
    

Document Info

Docket Number: 2018AP001548

Filed Date: 8/14/2019

Precedential Status: Non-Precedential

Modified Date: 9/9/2024