Mechanical, Inc. v. Venture Electrical Contractors, Inc. ( 2020 )


Menu:
  •                                                                             2020 WI APP 23
    COURT OF APPEALS OF WISCONSIN
    PUBLISHED OPINION
    Case No.:              2018AP2380
    Complete Title of Case:
    MECHANICAL, INC.,
    PLAINTIFF-RESPONDENT,
    V.
    VENTURE ELECTRICAL CONTRACTORS, INC.,
    DEFENDANT-APPELLANT.
    Opinion Filed:          April 22, 2020
    Submitted on Briefs:    September 12, 2019
    JUDGES:                 Neubauer, C.J., Reilly, P.J., and Gundrum, J.
    Concurred:
    Dissented:
    Appellant
    ATTORNEYS:              On behalf of the defendant-appellant, the cause was submitted on the
    briefs of Scott R. Halloin of Halloin Law Group, S.C., Milwaukee.
    Respondent
    ATTORNEYS:              On behalf of the plaintiff-respondent, the cause was submitted on the
    brief of Roy E. Wagner, Smitha Chintamaneni, and Lauren A.
    Triebenbach of von Briesen & Roper, S.C., Milwaukee.
    
    2020 WI App 23
    COURT OF APPEALS
    DECISION                                            NOTICE
    DATED AND FILED                        This opinion is subject to further editing. If
    published, the official version will appear in
    the bound volume of the Official Reports.
    April 22, 2020
    A party may file with the Supreme Court a
    Sheila T. Reiff               petition to review an adverse decision by the
    Clerk of Court of Appeals          Court of Appeals. See WIS. STAT. § 808.10 and
    RULE 809.62.
    Appeal No.          2018AP2380                                              Cir. Ct. No. 2015CV1472
    STATE OF WISCONSIN                                          IN COURT OF APPEALS
    MECHANICAL, INC.,
    PLAINTIFF-RESPONDENT,
    V.
    VENTURE ELECTRICAL CONTRACTORS, INC.,
    DEFENDANT-APPELLANT.
    APPEAL from an order of the circuit court for Waukesha County:
    WILLIAM J. DOMINA, Judge. Affirmed.
    Before Neubauer, C.J., Reilly, P.J., and Gundrum, J.
    ¶1      NEUBAUER, C.J. At issue in this construction dispute is whether
    the economic loss doctrine bars a negligence claim seeking purely economic
    losses—delay damages—by one subcontractor against another with whom there
    No. 2018AP2380
    was no contract. Each subcontractor did enter a subcontract with the general
    contractor that addressed their individual obligations, duties of care, schedules of
    work, changes, and remedies for delays. Because the complaining subcontractor’s
    negligence claim is rooted in the duties imposed by the interrelated construction
    contracts, contract law provides the remedies for the economic loss at issue,
    foreclosing tort remedies. The economic loss doctrine bars the negligence claim.
    We affirm.
    BACKGROUND
    ¶2      Rising three stories high, spreading over 92,000 square feet, the
    construction project at issue involved $36,436,603 for design, labor, and material
    work to build an integrated research laboratory addition to the existing Great Lakes
    Research Facility for the University of Wisconsin-Milwaukee. In 2012, the State of
    Wisconsin by the Department of Administration, and represented by the Wisconsin
    Division of State Facilities (State) awarded the prime construction contract to J.P.
    Cullen & Sons, Inc., as the general contractor. Cullen hired Mechanical, Inc., to
    install the HVAC systems, and Venture Electrical Contractors, Inc., to install the
    electrical systems, under separate but similar subcontracts, both dated August 20,
    2012.       Venture’s subcontract was for $4,491,812 and Mechanical’s was for
    $9,190,000.
    ¶3      Identical in all relevant respects, both subcontracts incorporated the
    prime contract between the State and Cullen.1 The subcontracts identified the
    1
    The subcontractors assumed toward Cullen all duties and obligations Cullen owed under
    the prime contract to the State to the extent of the subcontractors’ work. Cullen had all rights and
    remedies against the subcontractors that the State had under the prime contract against Cullen.
    2
    No. 2018AP2380
    standard of care: Each subcontractor was required to “use its best care, skill, and
    diligence in supervising, directing, and performing” its work.
    ¶4      The subcontracts specified the duties and obligations each
    subcontractor owed associated with the timely performance of the work, including
    a schedule of work and a commitment to perform the work in a timely manner.2
    Both subcontracts addressed work and schedule changes in an identical manner.3
    ¶5      Both subcontractors “recognize[d]” that delays could occur. In that
    event, extensions were to be provided, but that was the subcontractor’s “sole
    remedy.” Each subcontractor expressly agreed that it would not be entitled to make
    a claim for “damages or additional compensation based on delay, hindrance of work,
    impacts on progress, season changes, disruption, loss of productivity or efficiency,
    or schedule changes resulting from any cause whatsoever.”
    ¶6      Under its subcontract, Venture sought recovery of over $1,000,000
    from Cullen for costs it incurred because of delays and untimely performance. In
    addition to Mechanical, Venture blamed other subcontractors for its losses. Cullen
    denied the claim on the grounds that it was untimely, Venture’s damages were self-
    2
    Under the subcontracts, all work was to be performed on schedule and in strict
    compliance with the plans and specifications. Shop drawings were to be submitted and punch lists
    completed within specific time limits. The contractor and subcontractors were required to
    communicate to promptly set the work schedules. Each subcontractor was responsible for its
    performance, including the “methods, techniques, means, and sequences for coordinating and
    completing” the work.
    3
    If the contractor did not believe the work would be completed timely, the subcontractor
    was to bear the expense to get it done via overtime, additional shifts, etc.; changes could be made
    in the schedule without additional compensation; all participants were to cooperate with others and
    a subcontractor was to immediately advise the general contractor of any interference by another
    subcontractor.
    3
    No. 2018AP2380
    induced, and the subcontract precluded recovery for delay. Venture did not persist
    in asserting this claim against Cullen.
    ¶7     Unrelated to Mechanical’s work for Cullen, Venture asked
    Mechanical to install concrete embeds to support electrical conduit. Mechanical
    billed Venture $11,961.31 for this work but allegedly did not get paid. When
    Mechanical subsequently brought this suit against Venture seeking to recover its
    $11,961.31, Venture counterclaimed in negligence, now seeking almost $1,100,000
    for delay-related damages solely from Mechanical.
    ¶8     Venture alleged that Mechanical owed Venture a duty to comply with
    Mechanical’s schedules under its subcontract and to timely perform its project work.
    Venture contended that Mechanical’s performance was untimely and out of
    sequence, breaching its duties and causing Venture to incur delay-related losses
    from overtime hours and cost overruns.
    ¶9     Mechanical moved for summary judgment dismissal of Venture’s
    negligence claim on the ground that it was barred by the economic loss doctrine.
    The circuit court granted Mechanical’s motion. Venture appeals.
    DISCUSSION
    Standard of Review
    ¶10    Under a given set of facts, whether the economic loss doctrine applies
    to bar a claim and whether a contract is primarily for goods or services are questions
    of law which we review de novo. Linden v. Cascade Stone Co., 
    2005 WI 113
    , ¶5,
    
    283 Wis. 2d 606
    , 
    699 N.W.2d 189
    .
    The Economic Loss Doctrine
    4
    No. 2018AP2380
    ¶11    A judicially created doctrine, the economic loss rule was first adopted
    in Wisconsin in Sunnyslope Grading, Inc. v. Miller, Bradford & Risberg, Inc., 
    148 Wis. 2d 910
    , 
    437 N.W.2d 213
     (1989). In Sunnyslope, when a backhoe failed to
    perform properly, the buyer sued the manufacturer in tort, seeking damages for costs
    of parts, extra labor, and lost profits. 
    Id. at 914-15
    . The manufacturer had provided
    a limited warranty, which also limited its liability for costs and disclaiming other
    consequential damages. 
    Id. at 913-14
    . The supreme court rejected the buyer’s
    claim that the manufacturer owed, beyond the warranty, an independent or
    additional duty to the buyer for the claimed damages. 
    Id. at 915
    . The court held
    that a buyer cannot recover solely economic losses under a tort theory, particularly
    when, as in that case, the manufacturer’s warranty had addressed and precluded such
    losses. 
    Id. at 921
    .
    ¶12    The subject of much litigation since, the economic loss doctrine
    essentially provides that “a party to a contract may not pursue tort remedies to
    recover solely economic losses arising out of the performance or nonperformance
    of the contract.” Ferris v. Location 3 Corp., 
    2011 WI App 134
    , ¶12, 
    337 Wis. 2d 155
    , 
    804 N.W.2d 822
    ; see Hinrichs v. DOW Chem. Co., 
    2020 WI 2
    , ¶31, 
    389 Wis. 2d 669
    , 
    937 N.W.2d 37
     (describing the “upshot” of the doctrine as the
    requirement that dealing parties must “pursue only their contractual remedies” when
    seeking economic loss) (citation omitted)). The doctrine was born out of the
    bedrock distinctions between contract and tort law and the intent to sustain them,
    and these distinctions arise chiefly from the source of the party’s duty. The sources
    differ markedly. See Daanen & Janssen, Inc. v. Cedarapids, Inc., 
    216 Wis. 2d 395
    , 404, 
    573 N.W.2d 842
     (1998).
    ¶13    A struck bargain is the source of the legal obligation imposed in
    contract law. See 
    id. at 404
    . Aiming to facilitate exchanges and to protect the
    5
    No. 2018AP2380
    interests expected by each party to the bargain in allocating risks and costs, contract
    law holds the parties to their mutual, consensual promises, ensuring that each
    negotiated benefit is received. 
    Id.
    ¶14    On the other hand, the protection of society is the source of the legal
    obligations imposed in tort law. 
    Id. at 405
    . “Tort law is rooted in the concept of
    protecting society as a whole from physical harm to person or property,” and it aims
    to guard against unexpected or overwhelming misfortunes.            Id.; Linden, 
    283 Wis. 2d 606
    , ¶7.
    ¶15    Honoring the distinction between tort and contract law, the economic
    loss rule generally holds purchasers to their contract remedies for loss to the product
    or work itself (i.e., economic loss), but not losses due to other property damage or
    physical injury. Secura Ins. v. Super Prods. LLC, 
    2019 WI App 47
    , ¶13, 
    388 Wis. 2d 445
    , 
    933 N.W.2d 161
    . Applicable here, economic losses arising from
    alleged inadequate performance of a contract include costs associated with delays
    and lost profits. 
    Id.
    The Economic Loss Doctrine Applies to Interrelated Contracts
    ¶16    Sunnyslope applied the economic loss doctrine to parties in a direct
    two-party contract. Here, Venture did not have a contract with Mechanical. Venture
    argues the doctrine is inapplicable because they were contractual strangers with no
    opportunity to allocate economic risk. We disagree.
    ¶17    Under Wisconsin law, the economic loss doctrine applies when the
    claimant seeks economic loss that arises from duties under interrelated contracts,
    even where there is no direct two-party contractual relationship. See Linden, 
    283 Wis. 2d 606
    , ¶¶17, 32.
    6
    No. 2018AP2380
    ¶18    In Linden, the supreme court held that the economic loss doctrine
    applied even if there was no direct contract, or privity, with the defendant when the
    duties of the defendant arose out of interrelated contracts.      In that case, the
    contractual relationships were interrelated through a “vertical” chain:           the
    homeowners contracted with a general contractor to build a house, who in turn
    contracted with several subcontractors, including one to apply stucco to the exterior
    and another to place shingles on the roof. Id., ¶2. Subsequently, the homeowners
    sued the general contractor, asserting contract and negligence claims for alleged
    defects in the house, particularly water infiltration. Id., ¶3. They also sued the
    subcontractors, asserting that the stucco and shingle subcontractors negligently
    caused the water infiltration damages. Id.
    ¶19    The supreme court held that the economic loss doctrine precluded the
    homeowners’ claims against the subcontractors. Id., ¶32. The court found that the
    controlling contract was the one entered into between the homeowners and the
    general contractor, and under that contract the homeowners had the ability to
    bargain for coverage of the risk of faulty workmanship in any aspect of the house.
    Id., ¶17. The homeowners had contractual remedies against the general contractor,
    who in turn had contractual remedies against the subcontractors. Id. The court
    found that, “[a]t its core, the [homeowners’] complaint is that the house they
    received is not the house for which they contracted.” Id. (citation omitted).
    ¶20    The court applied the economic loss doctrine because permitting the
    homeowners to sue the subcontractors in tort would erode the distinction between
    contract and tort law as well as diminish the freedom of contract between the
    homeowner and the general contractor, as the warranties and remedies worked out
    between the homeowners and the general contractor would be bypassed by a tort
    claim against the subcontractors. Id.; see also Mose v. Tedco Equities—Potter Rd.
    7
    No. 2018AP2380
    Ltd. P’ship, 
    228 Wis. 2d 848
    , 851-53, 
    598 N.W.2d 594
     (Ct. App. 1999) (despite
    absence of privity, economic loss doctrine precluded tort claim of purchaser of
    contaminated property against prior owner, where purchaser negotiated a reduced
    purchase price and agreement to remediate with seller/current owner).
    ¶21    Here, while there is an absence of a vertical relationship indirectly
    connecting the homeowners and subcontractors the way there was in Linden, this
    large construction project nonetheless involved multiple interrelated contracts,
    where each subcontractor allocated its risks, duties, and remedies in their contracts
    for the project as part of a single comprehensive scheme to construct a building.
    [C]onstruction projects are multi-party transactions, but
    rarely is it the case that all or most of the parties
    involved in the project will be parties to the same
    document or documents. In fact, most construction
    transactions are documented in a series of two-party
    contracts, such as owner/architect, owner/contractor, and
    contractor/subcontractor. Nevertheless, the conduct of most
    construction projects contemplates a complex set of
    interrelationships, and respective rights and obligations.
    Fundamentals of Construction Law 4-5 (Carina Y. Enhada et al., eds., 2001).
    ¶22    As in Linden, the policies underlying the economic loss doctrine in
    other nonprivity cases are equally applicable here, involving two horizontal
    subcontractors working on the construction of a building. Those policies are as
    follows: “(1) to maintain the fundamental distinction between tort law and contract
    law; (2) to protect commercial parties’ freedom to allocate economic risk by
    contract; and (3) to encourage the party best situated to assess the risk of economic
    loss ... to assume, allocate, or insure against that risk.” Daanen, 
    216 Wis. 2d at 403
    (the economic loss doctrine precludes a commercial purchaser from recovery in tort
    from a manufacturer for solely economic losses, where there was a vertical chain of
    contracts through a distributor).
    8
    No. 2018AP2380
    ¶23    Venture asserts the economic loss doctrine does not apply because the
    subcontracts were for services as opposed to a product, attempting to distinguish its
    negligence claim against a horizontal subcontractor from the vertical chain of
    contracts in Linden. See Linden, 
    283 Wis. 2d 606
    , ¶8 (economic loss doctrine does
    not apply to claims arising from the provision of services). We disagree.
    ¶24    As established in Linden, the analysis is undertaken when the parties
    have contractual agreements to determine the source of the parties’ duties. There,
    the court identified the applicable contractual bargain in order to determine what the
    owners-claimants purchased (either a house or services from the subcontractors) and
    in turn to determine the source of the various contractor’s obligations owing to the
    owners. Here, as discussed below, Venture’s claim is squarely based on duties
    Mechanical owed to Cullen, and in turn, the State.
    ¶25    The State’s purpose in hiring Cullen was to construct a building, just
    as in Linden. Here, the prime contract of the bargaining owner (State) was with the
    general contractor (Cullen), and indeed, the prime contract was incorporated into
    each of the subcontracts, explicitly providing that duties and remedies owing
    between the State and Cullen would also apply to the subcontractors, to the extent
    of their work. We agree with the circuit court’s analysis that the owner contracted
    to build a $36 million construction project for a building, an addition to the Great
    Lakes Research Facility.
    ¶26    The application of the economic loss rule to the general contract, and
    by extension, these two non-contracting subcontractors, encourages the
    subcontractors on construction projects with interrelated contracts to protect
    themselves from risks, holds them to the terms of their bargain, enforces their
    expectancy interests, and maintains the boundary between contract and tort law. “It
    9
    No. 2018AP2380
    is more appropriate to enforce a bargain than to allow an end run around a contract
    by using tort principles.” State Farm Mut. Auto. Ins. Co. v. Ford Motor Co., 
    225 Wis. 2d 305
    , 329, 
    592 N.W.2d 201
     (1999).4
    ¶27     As in Linden, Venture had the opportunity to address the risk of the
    economic loss it claims in this case. It had the opportunity to bargain and to define
    its rights and remedies, allocate risks and costs, or to decline to contract if
    unsatisfied with the terms. This is a commercially sophisticated party with notice
    that there were no direct contractual relationships with other subcontractors.
    ¶28     More to the point, here, Venture decidedly was aware that it would be
    bound by the duties and remedies associated with delays in its subcontract with
    Cullen.     Venture’s subcontract made clear that the subcontractors’ work, and
    potential delays, were interrelated—as a practical matter and by contract. The
    subcontracts each addressed in identical fashion the claimed breach here, the duties
    and standards of care: with provisions addressing timeliness, work schedules,
    4
    Venture largely relies on Trinity Lutheran Church v. Dorschner Excavating, Inc., 
    2006 WI App 22
    , ¶2, 
    289 Wis. 2d 252
    , 
    710 N.W.2d 680
    , where the economic loss doctrine did not apply
    in a construction context. In Trinity, a church separately contracted for an addition with one prime
    contractor to coordinate the construction project and to hire various subcontractors, including an
    excavator for piping, and then the church separately hired another prime contractor, an excavator,
    to do the footings. Id., ¶6. When a damaged lateral resulted in water pouring through the church,
    the court found that the economic loss doctrine did not bar the contribution claim brought by the
    church’s excavator against the other prime contractor, after the church sued both the excavator and
    the prime contractor for negligence (which was permitted because its coordinating role rendered it
    a service provider under the economic loss doctrine). Id., ¶¶5, 14, 20. The court found there was
    “no contractual relationship of any kind between the two parties,” noting that the two prime
    contractors were hired independently from one another, coincidentally working on a common
    project, having their own individual non-interrelated contracts with the church. Id., ¶¶18, 20. The
    court found they had no opportunity to negotiate and allocate risk between them for the loss. While
    the court declined to decide the case on other grounds, we note that the case appears to have
    involved damage to other property, water damage to the church (the construction project was for
    an addition) from the damaged water lateral. Id., ¶¶5, 24, n.6. In contrast, this case involves solely
    economic loss, and an integrated construction project, with contracts that were interrelated through
    a bargaining process in which the terms were identical and negotiated as part of a single bid package
    from Cullen.
    10
    No. 2018AP2380
    changes, and delays, requesting change orders, extensions, and remedies in the event
    of delays. In short, although their contractual duties ran to Cullen/UWM, the
    network of interrelated contracts addressed the duties that Mechanical allegedly
    breached and Venture’s rights in the event of delays. We see no reason to free
    Venture from its contractual bargain and allow it to pursue a tort claim to recover
    what are effectively contract damages.
    ¶29     Our conclusion is a natural progression from Sunnyslope and its
    progeny, including Linden. However, we find support from various cases with facts
    similar to those presented here—where there is no privity, or indirect privity through
    a vertically integrated chain—and the economic loss arises from contractual duties
    the parties had an opportunity to address. See, e.g., BRW, Inc. v. Dufficy & Sons,
    Inc., 
    99 P.3d 66
    , 70, 74 (Colo. 2004) (economic loss doctrine precluded tort claims
    in large construction case involving claim by subcontractor against other contractors
    with whom there was no privity, where allegedly breached duties were contained
    within the network of interrelated contracts); Indianapolis-Marion Cty. Pub. Lib.
    v. Charlier Clark & Linard, P.C., 
    929 N.E.2d 722
    , 736, 740 (Ind. 2010) (despite no
    direct privity, the court determined that the reasons for applying the doctrine to all
    participants in a “network or chain of contracts in a major construction project are
    compelling”); Travelers Indem. Co. v. Crown Corr, Inc., 
    2011 WL 6780885
    , *11
    (D. Ariz. Dec, 27, 2011) (the economic loss doctrine applied to interrelated
    construction contracts where “the parties have had an opportunity to bargain for
    their rights”).5
    5
    Several of these cases from other states apply the economic loss doctrine to professionals,
    regardless that they may have independent duties of care distinguishing them from, for example,
    electrical contractors. We identify these construction cases as exemplars for the application of the
    economic loss doctrine to noncontracting parties on a construction project involving a network of
    interrelated contracts. We do not address application to professionals.
    11
    No. 2018AP2380
    ¶30     In conclusion, the contract between the owner (State) and the general
    contractor (Cullen) controls and was for construction of a building for purposes of
    the economic loss doctrine. Regardless of the absence of a vertical chain of
    contracts between the horizontal subcontractors, the economic loss doctrine bars a
    negligence claim for economic loss solely between them.                   The network of
    interrelated contracts contained their duties of care and contractual remedies. Thus,
    there is no independent tort duty owing from Mechanical to Venture to timely
    perform its contract with Cullen, or to avoid the risk of economic loss to Venture.
    Finding otherwise would eliminate the contract/tort distinction. It would undermine
    the expectancy protection afforded to Cullen and Mechanical when they agreed
    upon and defined the duties, risks, and costs. Finally, letting Venture ignore its own
    contract to prosecute a tort claim would discourage other parties who are typically
    best situated to evaluate the risk of economic loss and take appropriate measures.
    Because the reasons for the doctrine are present, the doctrine bars the tort claim.6
    6
    Venture cites to Hatleberg v. Norwest Bank Wisconsin, 
    2005 WI 109
    , 
    283 Wis. 2d 234
    ,
    
    700 N.W.2d 15
    , and Milwaukee Partners v. Collins Engineers, Inc., 
    169 Wis. 2d 355
    , 
    485 N.W.2d 274
     (Ct. App. 1992), and the RESTATEMENT (SECOND) OF TORTS § 552 (1977), which relates to a
    professional incurring liability for supplying false information. This case involves neither.
    Venture’s reference to the RESTATEMENT (SECOND) OF TORTS § 324A is equally inapplicable as
    there is no physical injury at issue here.
    12
    No. 2018AP2380
    By the Court.—Order affirmed.
    13
    

Document Info

Docket Number: 2018AP002380

Filed Date: 4/22/2020

Precedential Status: Non-Precedential

Modified Date: 9/9/2024