Kohler Co. v. DNR ( 2023 )


Menu:
  •                                                                             
    2024 WI App 2
    COURT OF APPEALS OF WISCONSIN
    PUBLISHED OPINION
    Case No.:              2021AP1187
    Complete Title of Case:
    KOHLER CO.,
    PETITIONER-APPELLANT,
    V.
    WISCONSIN DEPARTMENT OF NATURAL RESOURCES,
    RESPONDENT-RESPONDENT,
    CLAUDIA BRICKS AND FRIENDS OF THE BLACK RIVER FOREST,
    INTERVENORS-RESPONDENTS.
    Opinion Filed:          December 5, 2023
    Submitted on Briefs:    March 15, 2022
    Oral Argument:
    JUDGES:                 Stark, P.J., Hruz and Gill, JJ.
    Concurred:
    Dissented:
    Appellant
    ATTORNEYS:              On behalf of the petitioner-appellant, the cause was submitted on the
    briefs of Deborah C. Tomczyk, Jessica Hutson Polakowski and Monica
    A. Mark of Reinhart Boerner Van Deuren s.c., Madison.
    Respondent
    ATTORNEYS:              On behalf of the respondent-respondent, the cause was submitted on
    the brief of Joshua L. Kaul, attorney general, and Gabe Johnson-Karp,
    assistant attorney general.
    On behalf of the intervenors-respondents, the cause was submitted on
    the brief of Christa O. Westerberg and Leslie A. Freehill of Pines Bach
    LLP, Madison.
    2
    
    2024 WI App 2
    COURT OF APPEALS
    DECISION                                               NOTICE
    DATED AND FILED                           This opinion is subject to further editing. If
    published, the official version will appear in
    the bound volume of the Official Reports.
    December 5, 2023
    A party may file with the Supreme Court a
    Samuel A. Christensen               petition to review an adverse decision by the
    Clerk of Court of Appeals            Court of Appeals. See WIS. STAT. § 808.10 and
    RULE 809.62.
    Appeal No.          2021AP1187                                                 Cir. Ct. No. 2019CV199
    STATE OF WISCONSIN                                            IN COURT OF APPEALS
    KOHLER CO.,
    PETITIONER-APPELLANT,
    V.
    WISCONSIN DEPARTMENT OF NATURAL RESOURCES,
    RESPONDENT-RESPONDENT,
    CLAUDIA BRICKS AND FRIENDS OF THE BLACK RIVER FOREST,
    INTERVENORS-RESPONDENTS.
    APPEAL from an order of the circuit court for Sheboygan County:
    L. EDWARD STENGEL, Judge. Affirmed.
    Before Stark, P.J., Hruz and Gill, JJ.
    ¶1       GILL, J. In anticipation of building a new golf course, Kohler
    Company sought approval from the Department of Natural Resources (DNR) for a
    No. 2021AP1187
    “wetland individual permit” to discharge dredged material or fill material into 3.69
    acres of wetlands. Following a lengthy process, the DNR granted Kohler’s permit
    request. Claudia Bricks and Friends of the Black River Forest (collectively, the
    FBRF) then filed a petition for a contested case hearing, which the DNR granted.
    Following the hearing, an administrative law judge (ALJ) issued a decision and
    order reversing the DNR’s issuance of the permit, finding, among other things, that
    the DNR did not have enough information at the time it issued the permit to
    adequately analyze the “significant adverse impact[s]” to wetland functional values
    (WFVs), water quality, or “other significant adverse environmental consequences.”
    See WIS. STAT. § 281.36(3n)(c)3. (2021-22).1 Thereafter, the DNR adopted the
    ALJ’s decision as its own final decision, and Kohler petitioned for judicial review.
    The circuit court affirmed the ALJ’s decision.
    ¶2      On appeal, Kohler argues that the ALJ: (1) erred when he considered
    the entire proposed project when assessing the permit application, including
    wetlands and unregulated activities not related to the specific 3.69 acres of wetlands
    to be filled; (2) incorrectly found that the DNR did not have enough information at
    the time it issued the permit; (3) made findings that were unsupported by substantial
    evidence (namely, that the proposed project would cause cumulative impacts and
    that nutrients and pesticides would reach the groundwater and wetlands and would
    cause significant adverse impacts); (4) improperly reversed the DNR’s decision
    instead of modifying the permit; and (5) erred when he required the DNR and
    Kohler to make “quantitative findings” with regard to secondary impacts.
    1
    All references to the Wisconsin Statutes are to the 2021-22 version unless otherwise
    noted. WISCONSIN STAT. § 281.36 has been amended numerous times since Kohler’s permit
    application process began in February 2017. See 2017 Wis. Act 21; 2017 Wis. Act 58; 2017 Wis.
    Act 59; 2017 Wis. Act 115; 2017 Wis. Act 118; 2017 Wis. Act 183; 2019 Wis. Act 59. None of
    the amendments are relevant to the issues on appeal.
    2
    No. 2021AP1187
    ¶3      We first conclude that WIS. STAT. § 281.36(3n)(b) and (c) require the
    DNR to consider the entirety of a “proposed project” when addressing a wetland
    individual permit, not just the wetlands within a proposed project. By its plain
    meaning, § 281.36(3n)(c) instructs the DNR to determine whether a proposed
    project will result in “significant adverse impact[s]” to WFVs and water quality, and
    whether the proposed project will result in “other significant adverse environmental
    consequences.” As we will explain, this review necessarily requires the DNR to
    consider impacts beyond the physical footprint of directly impacted wetlands. For
    example, the DNR must consider “[p]otential secondary impacts” to WFVs and the
    “net positive or negative environmental impact of the proposed project.” See
    § 281.36(3n)(b)3., 5. This conclusion is affirmed by WIS. ADMIN. CODE § NR
    103.03(1) (July 2015),2 which defines WFVs to include the value of habitats for
    birds and “scenic beauty.”
    ¶4      Second, we conclude that the ALJ’s decision that the DNR did not
    have enough information at the time it issued the permit to adequately analyze the
    “significant adverse impact[s]” to WFVs, water quality, or “other significant
    adverse environmental consequences” is supported by substantial evidence.
    Furthermore, the ALJ’s decision did not “depend[]” on a finding that significant
    cumulative impacts to WFVs would occur if the project was approved and
    completed.     See WIS. STAT. § 227.57(6).           Specifically, the ALJ’s ultimate
    conclusion that the DNR did not have the information necessary to make a WIS.
    STAT. § 281.36(3n)(c)3. determination did not depend on the finding that significant
    cumulative impacts to WFVs could result from the proposed project’s construction.
    Additionally, we conclude that there was substantial evidence to support the ALJ’s
    2
    All references to WIS. ADMIN. CODE ch. NR 103 are to the July 2015 register unless
    otherwise noted.
    3
    No. 2021AP1187
    finding that the DNR lacked information to determine whether nutrients and
    pesticides would reach the groundwater and wetlands, and whether the nutrients and
    pesticides would cause significant adverse impacts.
    ¶5      We further conclude that the ALJ did not err by reversing the DNR’s
    decision without first modifying the permit because Kohler never raised that issue
    with the ALJ and therefore forfeited any argument that the ALJ should have
    modified the permit. Lastly, we determine that the ALJ did not require the DNR or
    Kohler to make “quantitative findings” with regard to secondary impacts. We
    therefore affirm the circuit court’s order affirming the ALJ’s decision reversing the
    DNR’s issuance of the wetland individual permit to Kohler.
    BACKGROUND
    I. The property
    ¶6      Kohler owns a 247-acre property in the City of Sheboygan.3 The
    undeveloped property is bordered by Lake Michigan to the east, the Black River to
    the west, and the Kohler-Andrae State Park to the south, and it is currently zoned as
    suburban residential.
    3
    The property was formerly in the Town of Wilson, but it was annexed to the City of
    Sheboygan in August 2017.
    4
    No. 2021AP1187
    ¶7       The property includes eighty-one wetlands totaling approximately
    forty-seven acres,4 which the DNR categorized into four wetland types5: floodplain
    forest wetlands (44.167 acres), interdunal wetlands (0.4886 acres), ephemeral/relic
    ridge and swale wetlands (hereinafter, “relic ridge and swale wetlands”) (0.104
    acres), and Great Lakes ridge and swale wetlands (2.686 acres).
    ¶8       According to the wetland individual permit issued to Kohler, the
    interdunal wetlands and both types of ridge and swale wetlands on the property “are
    4
    The ALJ stated in his decision that there are 44.91 acres of wetlands on the project site.
    As noted in the ALJ’s decision, however, “[s]ome of the wetland assessment documents assess the
    wetlands on the entire project site, not just the Kohler property. Thus[,] the acreage numbers for
    the wetlands are not consistent throughout the record.” For example, the DNR stated in the final
    Environmental Impact Statement (EIS) that “[t]here are 67 Great Lakes Ridge and Swale wetlands
    delineated on the site, totaling approximately 5.24 acres.” However, the DNR’s Wisconsin
    Wetland Rapid Assessment Methodology (WRAM) documents for the Great Lakes ridge and swale
    wetlands stated that there are 2.686 acres.
    On appeal, neither the FBRF nor the DNR cite how many total acres of wetlands exist on
    the project site. Kohler, on the other hand, states in its brief-in-chief that there are 124.12 acres of
    wetlands on the project site. After searching the record, it appears that this number includes acreage
    belonging to the state park that is not part of the project site.
    Based on our review of the record, including the initially issued permit, and because no
    party previously challenged the total acreage calculation in the DNR’s WRAM documents, we will
    use the approximate forty-seven-acre figure and the subsequent individual calculations for each
    wetland found in the WRAM documents. Furthermore, because we use the figures from both
    Kohler’s 247-acre property and the approximate acreage of land from the Kohler-Andrae State
    Park, we will refer to both collectively as “the property.”
    5
    Similar to the total acreage of wetlands on the property, the types of wetlands on the
    property have been characterized differently. For example, Dr. Quentin Carpenter—a senior
    lecturer (emeritus) at the University of Wisconsin-Madison and a witness for the FBRF—wrote in
    his prefiled testimony that there are three types of wetlands on the property: ridge and swale
    wetlands; interdunal wetlands; and forested seep wetlands. Likewise, Dr. John Jansen—a senior
    geophysicist and hydrogeologist at Collier Consulting and a witness for the FBRF—wrote in his
    prefiled testimony that the property contains: Great Lakes ridge and swale wetlands; Great Lakes
    interdunal wetlands; and a “wetland complex with alder thicket, southern sedge meadow, seepage
    slope and northern hardwood swamp.” The final EIS identified the wetlands as Jansen identified
    them. Like the acreage discrepancies, we will rely on the DNR’s wetland characterizations
    contained in the WRAM documents, as no party disputes these characterizations on appeal. We
    also note that most of the testimony at the contested hearing referred to the wetland types in the
    manner we have in the body of this opinion.
    5
    No. 2021AP1187
    considered high to exceptional quality and globally rare.” Similarly, the DNR found
    that the floodplain forest wetlands on the property are “high quality and rare in the
    region because of the loss of ash trees and increase of invasive species.” In addition
    to the wetlands, the DNR stated that the property “is almost entirely forested with
    mature trees and has not been logged in over 150 years.”
    ¶9     The property contains three separate aquifers: a shallow sand aquifer,
    a Silurian dolomite aquifer, and a deep Cambian-Ordovician aquifer. According to
    the final EIS, all of the wetlands on the site are “directly connected” to the shallow
    sand aquifer, which has “a depth to groundwater” level “of only a few feet.” The
    Silurian dolomite aquifer is approximately 120 feet below the ground surface but it
    “is typically under artesian conditions with water levels well above the top of the
    aquifer and, in many instances, at or above the ground surface.” The deep Cambian-
    Ordovician aquifer is approximately 750 to 950 feet below the ground surface.
    ¶10    According to the final EIS, all of the wetlands “are hydrologically
    connected to Lake Michigan.” Furthermore, the interdunal wetlands and both types
    of ridge and swale wetlands “are dependent on groundwater for recharge and
    maintenance of water levels and water quality.” Conversely, the floodplain forest
    wetlands “are dependent on both groundwater and surface water runoff to maintain
    water levels and determine water quality.”
    II. The proposed project
    ¶11    Kohler proposes to construct and operate an 8,000-yard, eighteen-hole
    golf course on the property. Kohler’s stated goal for this project is to build a world-
    class golf course that is rated in the top fifty golf courses in the world and has the
    potential to host major championship golf events.
    6
    No. 2021AP1187
    ¶12     All of the parties on appeal agree that the proposed project would
    completely fill 3.69 acres of wetlands, specifically: 0.1 acre of relic ridge and swale
    wetlands, 1.36 acres of Great Lakes ridge and swale wetlands, and 2.23 acres of
    forested floodplain wetlands.        As part of the project, Kohler would clear
    approximately 100 to 120 acres of forested land cover in order to build, among other
    things, fairways, greens, and tees. Much of the disturbed area would be replaced
    with “turfgrass,” specifically “Creeping Bentgrass,” a type of grass commonly used
    on golf courses.
    III. Procedural history
    ¶13     As discussed in more detail below, Kohler applied for, and received,
    a wetland individual permit to fill the 3.69 acres of wetlands needed to construct the
    golf course. The FBRF subsequently filed a petition for administrative review,
    which the DNR granted. On review, the ALJ reversed the DNR’s decision to grant
    Kohler the permit. Kohler petitioned for judicial review, and the circuit court
    affirmed the ALJ’s decision to reverse the issuance of the permit. Kohler now
    appeals.
    DISCUSSION
    ¶14     “When an appeal is taken from a circuit court order reviewing an
    agency decision, we review the decision of the agency, not the circuit court.” Hilton
    ex rel. Pages Homeowners’ Ass’n v. DNR, 
    2006 WI 84
    , ¶15, 
    293 Wis. 2d 1
    , 
    717 N.W.2d 166
    . In this case, the DNR did not petition for judicial review of the ALJ’s
    decision and therefore adopted the decision as its own pursuant to WIS. STAT.
    § 227.46(3)(a), and WIS. ADMIN. CODE § NR 2.155(1) (Feb. 2019).6 See also
    6
    All references to the WIS. ADMIN. CODE ch. NR 2 are to the February 2019 register
    unless otherwise noted.
    7
    No. 2021AP1187
    Hilton, 
    293 Wis. 2d 1
    , ¶14; Meteor Timber, LLC v. DHA, 
    2022 WI App 5
    , ¶20,
    
    400 Wis. 2d 451
    , 
    969 N.W.2d 746
     (2021), review denied (WI Apr. 13, 2022)
    (No. 2020AP1869). “Accordingly, we review the ALJ’s decision as the [DNR’s]
    final decision.” See Meteor Timber, 
    400 Wis. 2d 451
    , ¶20.
    ¶15    WISCONSIN STAT. § 227.57 establishes the procedure for judicial
    review of agency decisions. “Unless the court finds a ground for setting aside,
    modifying, remanding or ordering agency action or ancillary relief under a specified
    provision of this section, it shall affirm the agency’s action.” Sec. 227.57(2).
    ¶16    Our review of an agency’s factual findings is limited. Under WIS.
    STAT. § 227.57(6),
    [i]f [an] agency’s action depends on any fact found by the
    agency in a contested case proceeding, the court shall not
    substitute its judgment for that of the agency as to the weight
    of the evidence on any disputed finding of fact. The court
    shall, however, set aside agency action or remand the case to
    the agency if it finds that the agency’s action depends on any
    finding of fact that is not supported by substantial evidence
    in the record.
    “Substantial evidence does not mean a preponderance of the evidence.” Meteor
    Timber, 
    400 Wis. 2d 451
    , ¶21 (citation omitted). Instead, “[a]n agency’s findings
    are supported by substantial evidence if a reasonable person could arrive at the same
    conclusion as the agency.” Clean Wis., Inc. v. PSC, 
    2005 WI 93
    , ¶46, 
    282 Wis. 2d 250
    , 
    700 N.W.2d 768
    .
    ¶17    “If we conclude ‘that the agency has erroneously interpreted a
    provision of law and a correct interpretation compels a particular action,’ we will
    ‘set aside or modify the agency action’ or ‘remand the case to the agency for further
    action under a correct interpretation of the provision of law.’” Town of Ledgeview
    8
    No. 2021AP1187
    v. Livestock Facility Siting Rev. Bd., 
    2022 WI App 58
    , ¶8, 
    405 Wis. 2d 269
    , 
    983 N.W.2d 685
     (citing WIS. STAT. § 227.57(5)). “When reviewing questions of law
    decided by an agency, including statutory interpretation, our review is de novo.”7
    DOR v. Microsoft Corp., 
    2019 WI App 62
    , ¶13, 
    389 Wis. 2d 350
    , 
    936 N.W.2d 160
    (citing Tetra Tech EC, Inc. v. DOR, 
    2018 WI 75
    , ¶84, 
    382 Wis. 2d 496
    , 
    914 N.W.2d 21
    ); § 227.57(11) (“Upon review of an agency action or decision, the court
    shall accord no deference to the agency’s interpretation of law.”). Pursuant to
    § 227.57(11), we accord no deference to an agency’s interpretation of law.
    However, “due weight shall be accorded [to] the experience, technical competence,
    and specialized knowledge of the agency involved.” Sec. 227.57(10); see also Tetra
    Tech, 
    382 Wis. 2d 496
    , ¶78 (“‘Due weight’ is a matter of persuasion, not
    deference.”).
    7
    “Until recently, we also deferred to administrative agencies’ conclusions of law in many
    circumstances.” Wisconsin Prop. Tax Consultants, Inc. v. DOR, 
    2022 WI 51
    , ¶8, 
    402 Wis. 2d 653
    , 
    976 N.W.2d 482
    . However, in Tetra Tech EC, Inc. v. DOR, 
    2018 WI 75
    , 
    382 Wis. 2d 496
    ,
    
    914 N.W.2d 21
    , our supreme court ended that practice, and the legislature has since codified the
    new approach under WIS. STAT. § 227.57(11). Wisconsin Prop. Tax Consultants, 
    402 Wis. 2d 653
    , ¶8.
    9
    No. 2021AP1187
    I. Wetland individual permit
    A. Wetland individual permit process
    ¶18     The DNR is required to issue a permit before an individual “may
    discharge dredged material or fill material into a wetland.”8                        WIS. STAT.
    8
    Kohler submitted supplemental authority pursuant to WIS. STAT. RULE 809.19(10),
    citing the recent United States Supreme Court decision in Sackett v. EPA, 
    598 U.S. 651
     (2023).
    According to Kohler, “federal and state laws regulating wetlands are inextricably intertwined,”
    Wisconsin “has been delegated authority to regulate ‘waters of the United States,’” and “[b]oth the
    text of the underlying [wetland individual permit] and the final decision of the [ALJ] … confirm
    that such permit was granted, not just pursuant to Wisconsin [law], but also pursuant to the [Clean
    Water Act (CWA)].” We interpret Kohler’s contention to be that Sackett dictates reversal of the
    ALJ’s decision because the wetlands on Kohler’s proposed golf course site are not subject to the
    CWA and, therefore, cannot be regulated as wetlands under Wisconsin law.
    It is true that Sackett altered the analysis for defining a wetland subject to the CWA.
    Sackett, 
    598 U.S. at 678-79
    ; see also 
    33 U.S.C. § 1362
    (7) (prohibiting the discharge of pollutants
    into “the waters of the United States”). Kohler’s argument fails to acknowledge, however, that
    Wisconsin law is not limited to regulating “waters of the United States.” Cf. Sackett, 
    598 U.S. 686
    (Thomas, J., concurring) (federal authority “over certain navigable waters is granted and limited by
    the Commerce Clause”).
    In Wisconsin, the legislature delegated to the DNR “general supervision and control over
    the waters of the state.” WIS. STAT. § 281.12(1). The “waters of the state” include wetlands. A
    “wetland” is “an area where water is at, near, or above the land surface long enough to be capable
    of supporting aquatic or hydrophytic vegetation and which has soils indicative of wet conditions.”
    WIS. STAT. §§ 23.32(1), 281.01(21). Importantly, WIS. STAT. § 281.36(4n)(c) provides that a
    wetland individual permit does “not apply to any discharge into a nonfederal wetland that occurs
    outside an urban area and to which” certain requirements apply, including that “[t]he discharge
    does not affect a rare and high quality wetland.” (Emphasis added.) A “nonfederal wetland”
    “means a wetland that is not subject to federal jurisdiction under 33 U.S.C. 1344.”
    Sec. 281.36(1)(br); Sackett, 
    598 U.S. at 675
     (explaining that § 1344 is part of the CWA). “A person
    who proposes a project that may affect a wetland [under one of the exceptions to a wetland
    individual permit] shall notify the [DNR] no fewer than 15 working days before initiating the
    project,” and submit one of two things “to show that the wetland … is eligible for”
    exemption: (1) “[a] statement issued by a professional who has investigated the wetland and who
    is qualified to give such an opinion”; or (2) “[a] wetland delineation prepared by a qualified
    professional showing the exact location and boundaries of the wetland.” Sec. 281.36(4n)(e)1.
    10
    No. 2021AP1187
    § 281.36(3b)(b). As relevant here, the DNR may issue a “wetland individual
    permit”9 only once it determines that “[t]he proposed project will not result in
    significant adverse impact to [WFVs], in significant adverse impact to water quality,
    or in other significant adverse environmental consequences.”10                       WIS. STAT.
    § 281.36(3n)(c)3. WFVs are identified as:
    (a) Storm and flood water storage and retention and the
    moderation of water level fluctuation extremes;
    (b) Hydrologic functions including the maintenance of dry
    season streamflow, the discharge of groundwater to a
    wetland, the recharge of groundwater from a wetland to
    another area and the flow of groundwater through a
    wetland;
    (c) Filtration or storage of sediments, nutrients or toxic
    substances that would otherwise adversely impact the
    quality of other waters of the state;
    (d) Shoreline protection against erosion through the
    dissipation of wave energy and water velocity and
    anchoring of sediments;
    (e) Habitat for aquatic organisms in the food web including,
    but not limited to fish, crustaceans, mollusks, insects,
    annelids, planktonic organisms and the plants and
    Here, even assuming that the affected wetlands on Kohler’s property are nonfederal under
    Sackett’s analysis of the CWA (meaning the wetlands meet the definition of nonfederal wetlands
    under WIS. STAT. § 281.36(1)(br)), the wetlands are not subject to any exemptions to a wetland
    individual permit. Kohler did not comply with the notification requirements in § 281.36(4n)(e)1.,
    and, even so, Kohler would be unable to demonstrate that the proposed discharge on its property
    will “not affect a rare and high quality wetland.” See § 281.36(4n)(c). As explained, it is
    undisputed that the wetlands on the property are “rare and high quality.” Kohler was therefore still
    required to obtain a wetland individual permit, and Sackett is inapplicable to this case.
    9
    The DNR may also issue “wetland general permits,” which are not at issue in this appeal.
    See WIS. STAT. § 281.36(3g). As such, we will refer to a “wetland individual permit” as a “permit”
    throughout this opinion when appropriate.
    10
    As we have done previously, we occasionally refer to the three considerations under
    WIS. STAT. § 281.36(3n)(c)3. collectively as “significant adverse environmental impacts.” See
    Meteor Timber, LLC v. DHA, 
    2022 WI App 5
    , ¶31 n.6, 
    400 Wis. 2d 451
    , 
    969 N.W.2d 746
     (2021),
    review denied (WI Apr. 13, 2022) (No. 2020AP1869).
    11
    No. 2021AP1187
    animals upon which these aquatic organisms feed and
    depend upon for their needs in all life stages;
    (f) Habitat for resident and transient wildlife species,
    including mammals, birds, reptiles and amphibians for
    breeding, resting, nesting, escape cover, travel corridors
    and food; and
    (g) Recreational, cultural, educational, scientific and natural
    scenic beauty values and uses.
    WIS. ADMIN CODE § NR 103.03(1)(a)-(g); see also Meteor Timber, 
    400 Wis. 2d 451
    , ¶31 n.6. In evaluating the impacts to WFVs under § 281.36(3n)(c)3., the DNR
    shall consider:
    1. The direct impacts of the proposed project to [WFVs].
    2. The cumulative impacts attributable to the proposed
    project that may occur to [WFVs] based on past impacts
    or reasonably anticipated impacts caused by similar
    projects in the area affected by the project.
    3. Potential secondary impacts of the proposed project to
    [WFVs].
    4. The impact on functional values resulting from the
    mitigation that is required under [§ 281.36(3r)].
    5. The net positive or negative environmental impact of the
    proposed project.
    Sec. 281.36(3n)(b).
    ¶19    As relevant to this appeal, after the DNR issues a decision on an
    application for a wetland individual permit, “[a]ny interested person may file a
    petition with the [DNR] for administrative review.”                     See WIS. STAT.
    § 281.36(3q)(b). If the DNR grants the petition for administrative review, it shall
    refer the matter to the division of hearings and appeals, and the hearing shall be
    treated as a contested case under WIS. STAT. ch. 227. Sec. 281.36(3q)(f)4., (g)1.
    When a party challenges the DNR’s initial granting of a permit, it has the burden to
    12
    No. 2021AP1187
    demonstrate by a preponderance of the evidence that the DNR erred in its decision.
    See § 281.36(3q)(g)5.; WIS. ADMIN. CODE § HA 1.17(2) (June 2023).
    B. Kohler’s wetland individual permit process
    ¶20     In 2014, Kohler began discussing the idea of developing a golf course
    on the property. Prior to the permit application process, Kohler submitted an
    Environmental Impact Report (EIR) to the DNR in April 2015, the DNR prepared
    a draft of the EIS, and the DNR conducted a public hearing on the draft in July 2016.
    In February 2017, the DNR and Kohler began the actual application process and
    held a pre-application meeting as required by WIS. STAT. § 281.36(3m)(a).
    ¶21     In March 2017, Kohler filed a permit application with the DNR
    pursuant to WIS. STAT. § 281.36. The DNR determined that the application was
    incomplete and requested additional information from Kohler, including a forest
    management plan, a vegetative buffer planting plan, a grading plan, an erosion
    control and stormwater management plan, a nutrient management plan, a pesticide
    management plan, and a water table map.
    ¶22     In January 2018, the DNR granted Kohler’s application and issued a
    wetland individual permit.11 In the permit, the DNR identified all WFVs associated
    with the project site:
    11
    In addition to a wetland individual permit, the DNR stated in the final EIS that in order
    to get full approval for the project, Kohler will need to receive six other permits and/or approvals
    from the DNR relating to: shore protection, endangered and threatened species protection,
    stormwater discharge, high-capacity well permits, conversion of Land and Water Conservation
    Fund Act (LAWCON) lands, and potential tribal consultation.
    13
    No. 2021AP1187
    a. Floristic integrity rated high to exceptional with the plant
    community integrity very high to exceptional with little
    to no existing stressors, rare plant community, and low
    level of invasive species present. The ridge and swale
    type of wetland is imperiled in the state because of its
    rarity. Native species generally dominate the swales
    with a low percent cover of invasive species present.…
    b. Human use values rated as exceptional due to the current
    use of property for trails and potential elsewhere.
    c. Wildlife habitat rated exceptional because of the unique
    habitat for rare species and large block of high quality,
    diverse wetland and contiguous habitat.
    d. Groundwater processes rated as high due to it being
    dependent on local groundwater fluctuations; intact
    recharge and discharge functions which have positive
    impacts on local groundwater and surface water quality.
    e. Fish and aquatic life habitat rated as high because it
    provides high value for amphibian use.
    f. Water quali[t]y protection rated as low due to the
    isolated nature of the wetlands.
    g. Shoreline protection is rated high in the forested
    floodplain wetland complex due to the dense vegetative
    cover along the banks of the Black River providing
    significant shoreline protection functions.
    h. Flood and stormwater support and shoreline protection
    are rated as low in the ridge and swale complex due to
    [their] isolated nature, and provide[] limited flood and
    stormwater storage functions. Flood and stormwater
    storage are rated as medium in the floodplain forest
    Outside of the DNR permitting process, the DNR stated in the final EIS that Kohler will
    need permits and/or approval from other state and federal governing bodies in order to build the
    proposed golf course, including from: the U.S. Army Corps of Engineers (relating to the CWA);
    the National Park Service (relating to LAWCON); the U.S. Fish and Wildlife Service (relating to
    the Federal Endangered Species Act and the Migratory Bird Treaty Act); the Federal Emergency
    Management Agency (relating to a conditional letter of map revision and letter of map revision);
    the Wisconsin State Historic Preservation Office (relating to an archaeologic consultation);
    Sheboygan County (relating to a shoreland-floodplain conditional use permit, sanitary permit,
    shoreland-wetland rezoning, erosion control permit, and county cutting notice); and the City of
    Sheboygan (relating to a conditional use permit, stormwater permit, erosion control permit,
    building permits, and architectural review board approval).
    14
    No. 2021AP1187
    because this wetland type provides moderate flood and
    stormwater storage functions.
    ¶23    The DNR stated in the permit that 3.69 acres of wetlands would be
    permanently lost, along with any WFVs associated with those wetlands.
    Particularly, the DNR concluded that the ridge and swale wetlands and interdunal
    wetlands “are ranked as S1 to S2, which means the communities are considered
    imperiled in Wisconsin and globally due to a restricted range and few populations
    or occurrences. This loss is expected to be irreversible and has high significance.”
    ¶24    In addition to WFVs associated with the 3.69 acres of wetlands that
    would be permanently lost, the DNR concluded that secondary impacts to WFVs
    “may affect 4.79 acres of wetland not covered by discharged material, and 0.03
    acres of temporary wetland impact.” Specifically, the DNR stated that possible
    secondary impacts to WFVs related to the 4.79 acres included “increased runoff of
    nutrients, herbicides, and pesticides, and foot and cart traffic in the remaining
    wetland complex”; “[p]ermanent alteration to wetland hydrology (change in grade
    and removal of trees); decrease in habitat from increased invasive species, nutrient
    loading, sediment deposition, potential disruption of wildlife use (breeding, nesting)
    and movement through operation of the golf course”; and “[d]ecrease in wooded
    cover converted to managed turf grass.” According to the permit, increased foot
    and cart traffic, as well as runoff, would be “likely to provide a conduit for invasive
    species establishment.” The DNR also noted that there could be secondary impacts
    to WFVs due to a “well that could draw down the water table.”
    ¶25    Like the direct impacts to WFVs, the DNR recognized that the
    secondary impacts to WFVs were “expected to be permanent and irreversible and
    the significance of those impacts is high. Secondary impacts to [WFVs] are not
    expected to be entirely offset under the proposed project.”
    15
    No. 2021AP1187
    ¶26     The DNR also considered cumulative impacts to WFVs, and it
    determined that “significant cumulative impacts” might occur. Cumulative impacts
    included the fact that approving a wetland individual permit for “an exceptional
    quality ridge and swale complex, a globally rare community,” could “lead to
    increased applications to fill rare, sensitive, and valuable wetland plant
    communities” as well as“[t]he potential for additional development of the site and
    further cutting of the wooded community.”
    ¶27     The permit also contained thirty-eight conditions that Kohler was
    required to comply with during and after construction, including the following:
    11. Construction shall be accomplished in such a manner as
    to minimize erosion and siltation into surface waters.
    Erosion control measures (such as silt fence and straw
    bales) must meet or exceed the technical standards of
    [WIS. ADMIN. CODE] ch. NR 151 [(July 2018)12].…
    ….
    13. All equipment used for the project including but not
    limited to tracked vehicles, barges, boats, hoses, sheet
    pile and pumps shall be de-contaminated for invasive
    and exotic viruses and species prior to use and after use.
    ….
    19. You shall conduct a post construction wetland boundary
    survey to document the wetland impacts. You shall
    develop a wetland restoration plan for [DNR] review and
    approval for any wetland impacts outside of the
    authorized fill areas[.] The wetland restoration plan shall
    include, but is not limited to, measurable performance
    standards and a maintenance and monitoring plan of no
    less than five years.
    20. You shall hire Independent Environmental Monitors
    (IEMs) approved by the [DNR]. The scope of work for
    12
    All references to the WIS. ADMIN. CODE ch. NR 151 are to the July 2018 register unless
    otherwise noted.
    16
    No. 2021AP1187
    the IEMs will be developed jointly with [Kohler and the
    DNR].
    ….
    22. Follow Best Management Practices [(BMPs)] for pest
    management and the Integrated Pest Management plan
    submitted to the [DNR] on October 27, 2017. Within 25
    feet of surface water or wetland boundaries …[,] use
    pesticides approved for aquatic use by [federal agencies]
    and minimize drift. In areas with a shallow groundwater
    aquifer[,] use chemicals that have a shorter half-life or
    that will not persist in aquatic environments where
    practicable.…
    23. The Nutrient Management Plan shall follow [WIS.
    ADMIN. CODE ch.] NR 151 and Technical Standard 1100
    for application timing and as described in the Integrated
    Golf Course Management Plan [(IGCMP)] submitted to
    the [DNR] on October 27, 2017.…
    ….
    25. Infiltration strips shall be installed and maintained
    according to the Stormwater Management Plan
    submitted with the application and dated December 7,
    2016.
    ….
    37. During any spectator events at the golf course, take
    practical measures to avoid impacts to remaining
    wetlands on the site.
    C. The FBRF’s petition for administrative review and the ALJ’s decision
    ¶28    In response to the DNR granting Kohler’s permit request, the FBRF
    filed a petition for administrative review under WIS. STAT. § 281.36(3q)(b) and
    requested a stay of discharge pending the administrative review.
    ¶29    Prior to the administrative hearing, the parties narrowed the issues that
    are relevant to this appeal to: (1) whether the permit satisfied the standard set forth
    in WIS. STAT. § 281.36(3n)(c)3.; and (2) whether the DNR had sufficient
    information to consider that standard.
    17
    No. 2021AP1187
    ¶30     Following the hearing and briefing from the parties, the ALJ reversed
    the DNR’s decision to grant the permit. The ALJ concluded that the FBRF “carried
    their burden of proof to show that the [DNR] did not have sufficient evidence to
    support its determination” under WIS. STAT. § 281.36(3n)(c)3. That is, the DNR
    did not have sufficient evidence to support its finding that the “proposed project”
    would not result in significant adverse environmental impacts. See id. In reaching
    this conclusion, the ALJ defined the “proposed project” under § 281.36(3n)(c)3. as
    “the construction and operation of the proposed golf course.”13
    ¶31     Regarding secondary impacts to WFVs, the ALJ found that “there
    [were] no conditions in the permit addressing the adverse impacts to wildlife and
    stopover habitat resulting from the construction activities.” Accordingly, the ALJ
    held that the DNR’s “determination that the proposed project w[ould] not result in
    significant adverse impacts to [WFVs] cannot apply to the secondary impacts
    resulting from the tree clearing, grading, and soil conversion activities.”
    ¶32     With regard to water quality, the ALJ found that “[i]t is undisputed
    that the introduction of nitrates, phosphorus, pesticides, oil, grease, and other
    contaminants into the groundwater and wetlands will adversely impact [WFVs] and
    the water quality” on the property. According to the ALJ, the DNR did not consider
    whether operation of the course would affect “the levels of the chemicals and
    contaminants that [would] reach the groundwater and wetlands,” nor did it consider
    13
    The ALJ did not take issue with the DNR’s determination regarding the direct impacts
    of Kohler’s project to WFVs because the loss of the 3.69 acres of wetlands was to be properly
    mitigated “by the purchase of credits from the [DNR’s] in-lieu fee program.” See WIS. STAT.
    § 281.36(3r).
    18
    No. 2021AP1187
    the direction of the groundwater flow and the separation between the surface and
    groundwater.
    ¶33      Kohler commenced an action in the circuit court challenging the
    ALJ’s decision to reverse the DNR’s permit issuance.14                           See WIS. STAT.
    § 281.36(3q)(h)2. After briefing from the parties, the court denied Kohler’s request
    to overturn the ALJ’s decision and dismissed Kohler’s lawsuit.15
    II. The ALJ did not err in considering the entire proposed project, including
    wetlands that were not proposed to be filled, under WIS. STAT.
    § 281.36(3n)(b) and (c).
    ¶34      Kohler first contends that the ALJ exceeded the scope of WIS. STAT.
    § 281.36 when he reversed the DNR’s decision to issue a permit by considering
    “unregulated activities occurring outside the impacted wetlands.” In support of this
    argument, Kohler argues that WIS. STAT. ch. 281’s statutory scheme is solely
    concerned with water and that § 281.36 cannot be divorced from the chapter’s
    statutory scheme. We construe Kohler’s argument to be that the DNR does not have
    authority under § 281.36 to consider: (1) unregulated actions (such as tree
    clearing); or (2) other significant adverse environmental impacts to wetlands other
    14
    Kohler attempted to present additional evidence during the circuit court proceedings,
    and the court denied its motion to do so. Kohler does not challenge that decision in this appeal,
    and the additional issue of whether this additional evidence should have been denied is therefore
    not before us.
    15
    Because our review is limited to the ALJ’s decision, we will not give a detailed summary
    of the circuit court’s decision. Instead, we will rely on and cite the court’s decision in our analysis
    when appropriate.
    19
    No. 2021AP1187
    than the wetlands subject to discharge.16 Conversely, the FBRF contends that “to
    assess whether the [DNR] had sufficient information to determine whether the
    standards in … § 281.36(3n)(b)3. were satisfied, [the ALJ] was compelled to review
    the evidence and findings on the project’s secondary impacts to [WFVs] as directed
    by” the statute. The DNR echoes the FBRF’s argument in this regard. We agree
    with the FBRF and the DNR.
    ¶35     As previously noted, we independently review an ALJ’s interpretation
    of statutes and administrative code provisions. See Microsoft Corp., 
    389 Wis. 2d 350
    , ¶13; Milwaukee Acad. v. DCF, 
    2018 WI App 13
    , ¶11, 
    380 Wis. 2d 227
    , 
    908 N.W.2d 189
     (interpretation of administrative rules is “subject to principles of
    statutory construction” (citation omitted)). We begin with the language of the
    statute and give that language “its common, ordinary, and accepted meaning, except
    that technical or specially-defined words or phrases are given their technical or
    special definitional meaning.” State ex rel. Kalal v. Circuit Ct. for Dane Cnty.,
    
    2004 WI 58
    , ¶45, 
    271 Wis. 2d 633
    , 
    681 N.W.2d 110
    . “We interpret statutory
    language ‘in the context in which it is used; not in isolation but as part of a whole;
    in relation to the language of surrounding or closely-related statutes; and reasonably,
    to avoid absurd or unreasonable results.’” Citation Partners, LLC v. DOR, 
    2021 WI App 86
    , ¶16, 
    400 Wis. 2d 260
    , 
    968 N.W.2d 734
     (citation omitted).
    16
    We pause to address the scope of Kohler’s arguments as to this issue on appeal because
    its arguments in this regard are not entirely clear. In its reply brief, Kohler states that the FBRF
    and the DNR “mischaracterize” Kohler’s argument regarding the DNR’s review of a permit
    application under WIS. STAT. § 281.36. Kohler clarifies that it is not arguing that the DNR “can
    consider only direct impacts caused by wetland fill. The [DNR] must, of course, consider potential
    secondary and cumulative impacts ‘to [WFVs]’ stemming from a project.” Kohler contends “that
    the [DNR’s] authority to consider such impacts is expressly limited to impacts that bear on
    ‘[WFVs].’” According to Kohler, the ALJ “improperly considered the environmental
    consequences of unregulated actions throughout the 247-acre site, no matter their proximity to or
    impact on the 3.69 acres of wetlands to be filled.” Based on Kohler’s clarifications, we interpret
    Kohler’s argument as outlined in the body of this opinion.
    20
    No. 2021AP1187
    ¶36   We begin with the text of WIS. STAT. § 281.36(3n)(c)3., which
    expressly requires the DNR to consider “[t]he proposed project” in assessing
    significant adverse impacts to WFVs, water quality, and other environmental
    consequences. Neither “water quality” nor “environmental consequences” are
    defined by statute. However, § 281.36(3n)(b) identifies the factors the DNR must
    consider when assessing impacts to WFVs. Specifically, the statute expressly
    requires the DNR to consider, among other things, the “direct impacts to” WFVs,
    “cumulative impacts” to WFVs, “secondary impacts” to WFVs, and “net positive
    or negative environmental impact of the proposed project.” Sec. 281.36(3n)(b).
    ¶37   Both parties agree that direct impacts are those resulting from direct
    wetland fill. The ALJ defined secondary impacts as “[i]mpacts that are not the result
    of fill but result from how the land is used,” which closely matched testimony at the
    contested hearing that defined secondary impacts as “impacts which are closely
    linked or causally related to the activity but may occur over a longer period of time.”
    See also Meteor Timber, 
    400 Wis. 2d 451
    , ¶41 (secondary impacts identified in
    permit as those related to hydrology, presence of invasive species, and wildlife
    habitat); Kalal, 
    271 Wis. 2d 633
    , ¶46 (“[T]echnical or specially-defined words or
    phrases are given their technical or special definitional meaning.”). For example,
    the DNR concluded in the permit at issue that secondary impacts to WFVs included
    “[p]ermanent alteration to wetland hydrology (change in grade and removal of
    trees); decrease in habitat from increased invasive species, … potential disruption
    of wildlife use (breeding, nesting),” and “routine traffic along the proposed new
    greens.” WISCONSIN ADMIN. CODE § NR 103.03(1), gives a list of WFVs that shall
    be considered, including “[h]abitat for resident and transient wildlife species” and
    “[r]ecreational, cultural, educational, scientific and natural scenic beauty values and
    uses.”
    21
    No. 2021AP1187
    ¶38    It is clear that WIS. STAT. § 281.36 distinguishes between impacts
    resulting from the regulated conduct (i.e., the direct discharge into the wetlands) and
    impacts resulting from the proposed project (i.e., other impacts beyond direct
    discharge). See Paul G. Kent & Jordan K. Lamb, Wisconsin’s Wetland Reform Act,
    WIS. LAW., Feb. 1, 2013 (stating that prior to 2011 Wisconsin Act 118, “there was
    tension between looking exclusively at the immediate wetland impact and looking
    at both the immediate impact and overall environmental impacts. The Act provides
    some additional flexibility in this area”). Section 281.36(3n)(c)3. does not state that
    the DNR may issue a permit only once it determines that the “discharge” “will not
    result in significant adverse impact to [WFVs], in significant adverse impact to
    water quality, or in other significant adverse environmental consequences” to only
    the wetlands themselves. See § 281.36(3n)(c)3. Nor does § 281.36(3n)(b) provide
    that in evaluating the impacts to WFVs, the DNR must consider only the “secondary
    impacts” of the discharge. See § 281.36(3n)(b). Rather, § 281.36(3n)(c)3. requires
    the DNR to consider whether the “proposed project” will result in “significant
    adverse impact to [WFVs], in significant adverse impact to water quality, or in other
    significant adverse environmental consequences.” See § 281.36(3n)(c)3. This
    review, in turn, requires the DNR to evaluate, for example, “secondary impacts of
    the proposed project” to WFVs and the “net positive or negative environmental
    impact of the proposed project.” See § 281.36(3n)(b)3., 5.
    ¶39    Indeed, the legislature chose to use the word “discharge” and “wetland
    fill” in other areas of WIS. STAT. § 281.36, but it did not do so in § 281.36(3n)(b) or
    (c) when instructing the DNR on how to evaluate a wetland individual permit. See,
    e.g., § 281.36(3g)(d) (“In issuing wetland general permits under this subsection, the
    [DNR] shall establish requirements, conditions, and exceptions to ensure that the
    22
    No. 2021AP1187
    discharges will cause only minimal adverse environmental effects ….” (emphasis
    added)).17
    ¶40     If adopted, Kohler’s interpretation would create superfluous language
    in the statute. See Kalal, 
    271 Wis. 2d 633
    , ¶46 (“Statutory language is read where
    possible to give reasonable effect to every word, in order to avoid surplusage.”). It
    is undisputed that the direct impacts to WFVs on the property are those that stem
    from the proposed discharge of material into the 3.69 acres of wetlands. See Meteor
    Timber, 
    400 Wis. 2d 451
    , ¶40. Under Kohler’s interpretation, the DNR’s analysis
    would essentially end at the consideration of direct impacts to WFVs (e.g., the direct
    discharge of material into wetlands). All of the other considerations dictated by
    WIS. STAT. § 281.36 would be meaningless because after the direct impacts take
    place (i.e., the wetlands are filled with material), there would be no wetlands to be
    impacted and nothing left for the DNR to consider. For example, there would be no
    point in the DNR considering impacts to water quality because the only “water”
    17
    Kohler contends that WIS. STAT. § 281.36(3n)(c)3.’s reference to “other significant
    adverse environmental consequences” “is no basis to deny wetland permits due to activities
    unrelated to wetlands.” Citing a DNR guidance document, Kohler states that “other adverse
    environmental consequences” means that “‘where the only practicable alternatives that would avoid
    or minimize wetland impacts would cause other significant environmental harm’—such as
    ‘impact[ing] the last remaining upland habitat for an endangered species’—the [DNR] ‘may have
    to balance those impacts and allow the wetland to be developed.’” (First alteration in original.) A
    closer look at that document, however, demonstrates that “other adverse environmental
    consequences” apply to analyses beyond wetlands. Specifically, the document states that “[t]his
    sub-standard requires that the [DNR] look at issues other than wetland issues.”
    That said, we are unpersuaded by Kohler’s reliance on the document. To begin, the
    document lacks a publication date or author. It is possible the DNR’s interpretation of the statutory
    text has changed over time. Second, while the parties agreed prehearing to admit the document,
    there was no testimony during the contested hearing regarding the document. Therefore, the
    information gaps described above remain. Lastly, we are not bound by guidance documents. “They
    are not law, they do not have the force or effect of law, and they provide no authority for
    implementing or enforcing standards or conditions.” Service Emps. Int’l Union, Loc. 1 v. Vos,
    
    2020 WI 67
    , ¶102, 
    393 Wis. 2d 38
    , 
    946 N.W.2d 35
    . They are nonbinding documents produced by
    the executive branch and are “nothing more than the knowledge and intentions of their authors.”
    
    Id.
     As always, our focus is on the text of the statute when interpreting statutory language.
    23
    No. 2021AP1187
    subject to consideration would be the water in the wetlands being filled with
    material. Because the wetlands would be filled, there would be no water quality to
    consider. Similarly, there would be no point in the DNR considering secondary
    impacts to WFVs because there would be no WFVs to consider. Because the
    wetland would be filled, there would be no hydrology to consider. Kohler fails to
    explain what the statute’s purpose of including other impacts would be if the DNR
    was not required to consider impacts beyond the direct discharge.
    ¶41    Kohler argues that the ALJ’s considerations in this case are
    “ordinarily beyond the [DNR]’s regulatory authority under the wetlands statute.”
    For example, Kohler contends that it would have been able to remove trees or
    “certain rare plants” without DNR approval if it had not sought the permit in this
    case. Kohler notes that Patricia Trochlell—a former DNR staff wetland ecologist
    who worked on this particular permit application while employed with the agency—
    testified that if “not for the application to [fill] 3.69 acres of wetlands, there would
    be nothing to restrict [Kohler] from clear cutting this property[.]” The DNR largely
    concedes this point, stating that “[t]here is no dispute that some of these activities,
    if undertaken alone, would not require a separate permit.”
    24
    No. 2021AP1187
    ¶42     Kohler’s argument that “[t]he [l]egislature did not grant the [DNR]
    boundless authority to regulate any aspect of a ‘project’” misses the mark. 18 As
    discussed above, WIS. STAT. § 281.36(3n)(b) and (c) require the DNR to consider
    the entire project, including its secondary impacts on WFVs, its impacts on water
    quality, and any significantly adverse environmental consequences. Therefore,
    even assuming, without deciding, that there is no regulation attached to, for
    example, tree clearing in absence of a wetland individual permit application, Kohler
    did apply for a wetland individual permit and therefore availed itself to the permit
    application statutory process and administrative code. The permit system created
    by the legislature permits the DNR to regulate construction and maintenance of the
    entire project.
    ¶43     Kohler also argues that an interpretation allowing the DNR to review
    an entire project, including “unregulated” activities, would yield absurd results.
    Particularly, Kohler states that this “interpretation would have the perverse effect of
    18
    We are similarly unpersuaded by Kohler’s reliance on certain language from the permit
    statutory scheme to argue that WIS. STAT. § 281.36 limits the DNR’s review to solely water-related
    activities. In making its argument, Kohler cites a number of provisions, including the legislative
    purpose stated in WIS. STAT. § 281.11, which in relevant part provides that the DNR “shall serve
    as the central unit of state government to protect, maintain and improve the quality and management
    of the waters of the state.” (Emphasis added.) Similarly, Kohler cites WIS. ADMIN. CODE
    § NR 103.03(1)’s language that “water quality related functional values or uses of wetlands[]
    within the range of natural variation of the affected wetland[] shall be protected” to argue, again,
    that the DNR is limited to “water quality” considerations. As argued by Kohler, while WIS. STAT.
    ch. 281 makes several references to “water” and “wetlands,” § 281.36 “does not mention grading
    or deforestation.”
    But WIS. STAT. § 281.36 is clear and unambiguous in its directive for the DNR. Simply
    because the statute does not refer to every type of possible impact does not mean we can ignore its
    clear meaning. In fact, we are “not at liberty to disregard the plain, clear words of the statute,”
    State ex rel. Kalal v. Circuit Ct. for Dane Cnty., 
    2004 WI 58
    , ¶46, 
    271 Wis. 2d 633
    , 
    681 N.W.2d 110
     (citation omitted), and we decline Kohler’s invitation to do so here. Furthermore, WIS. ADMIN.
    CODE § NR 103.03(1) explicitly directs the DNR to protect “water quality related functional values
    or uses of wetlands” of “the affected wetland.” (Emphasis added.) It does not limit the DNR’s
    considerations to directly filled wetlands because other wetlands on a project site can constitute
    “affected wetland[s].”
    25
    No. 2021AP1187
    incentivizing applicants to clear trees, destroy plants, and the like before applying
    for a wetland fill permit, rather than subjecting those otherwise-unregulated
    activities to the [DNR’s] scrutiny.”
    ¶44    Assuming but without deciding that Kohler’s cited unregulated
    activities are indeed unregulated, we conclude that the above interpretation does not
    produce absurd results. “It is a well-settled proposition that statutory language be
    read in context and in a reasonable manner so as ‘to avoid absurd or unreasonable
    results.’” State v. Matthews, 
    2019 WI App 44
    , ¶17, 
    388 Wis. 2d 335
    , 
    933 N.W.2d 152
     (citing Kalal, 
    271 Wis. 2d 633
    , ¶46).
    When the statutory language is clear and straightforward, a
    court would normally apply the plain meaning to the specific
    set of facts in the case. However, if that application leads to
    results that are absurd or unthinkable, then courts should
    “look beyond the plain meaning” to avoid the absurd results.
    Id., ¶17 (citation omitted). The standard for departing from clear statutory language
    is high, “as it entails departing from the literal language of the statute.” Id. It is not
    enough that an interpretation produces a “foolish” outcome. Id. (citation omitted).
    “Instead, a court so finding must be convinced that the result is so absurd that [the
    legislature], not the court, could not have intended such a result.” Id. (alteration in
    original; citation omitted).    Put differently, “it must be ‘unthinkable’ for the
    legislature ‘to have intended the result commanded by the words of the statute.’”
    Id. (citation omitted).
    ¶45    Our interpretation does not produce an absurd result in any sense.
    While Kohler may find the result “foolish,” the interpretation does not produce a
    result that the legislature could not have intended. See id. To the contrary, and as
    described in detail above, the legislature clearly intended for the DNR to consider
    impacts from a proposed project beyond direct wetland discharge. The notion that
    26
    No. 2021AP1187
    upon someone applying to fill wetlands, otherwise unregulated environmental
    activities are taken under consideration is a reasonable system. “We defer to the
    legislature on policy, and ‘judicial deference to the policy choices enacted into law
    by the legislature requires that statutory interpretation focus primarily on the
    language of the statute.’” Id., ¶22 (citation omitted).
    ¶46    In all, nothing in the permit statutory system limits the DNR from
    considering impacts only as they relate to the wetlands proposed to be filled. In
    fact, WIS. STAT. § 281.36(3n)(b) and (c) require the DNR to consider impacts
    beyond proposed wetland discharge.
    III. The ALJ’s finding that the DNR did not have enough information at the
    time it issued the permit is supported by substantial evidence, and its
    decision did not “depend[]” on its finding that significant cumulative
    impacts to WFVs would occur.
    ¶47    Kohler contends that the ALJ erroneously found that the DNR did not
    have sufficient evidence to support its finding that the proposed project would “not
    result in significant adverse impact to [WFVs], in significant adverse impact to
    water quality, or in other significant adverse environmental consequences.”
    Specifically, Kohler argues that the ALJ made “two critical findings” not supported
    by substantial evidence, thereby warranting reversal of the ALJ’s decision: First,
    the ALJ’s finding that the project would cause cumulative impacts; and, second, the
    ALJ’s finding that nutrients and pesticides would reach the groundwater and
    wetlands and cause significant adverse impacts.
    ¶48    As outlined previously, our review of agency fact finding is limited.
    We must defer to the agency’s factual findings, as long as they are supported by
    substantial evidence. See WIS. STAT. § 227.57(6). Moreover, Kohler must show
    that the ALJ’s ultimate decision “depend[ed]” on the challenged factual findings.
    27
    No. 2021AP1187
    See id. “Substantial evidence is less of a burden than preponderance of the evidence
    in that any reasonable view of the evidence is sufficient.” Robles v. Thomas Hribar
    Truck & Equip., Inc., 
    2020 WI App 74
    , ¶8, 
    394 Wis. 2d 761
    , 
    951 N.W.2d 853
    (citation omitted). In other words, we do not examine whether the ALJ’s findings
    are more likely than not correct. See State v. Loayza, 
    2021 WI 11
    , ¶40, 
    395 Wis. 2d 521
    , 
    954 N.W.2d 358
     (defining the preponderance of evidence standard). Instead,
    our review is limited to “whether, after considering all the evidence of record,
    reasonable minds could arrive at the same conclusion” as the ALJ. See Hilton, 
    293 Wis. 2d 1
    , ¶16.
    A. Cumulative impacts finding under WIS. STAT. § 281.36(3n)(b)2.
    ¶49    Regarding the cumulative impacts on WFVs, the ALJ adopted the
    DNR’s finding that significant cumulative impacts to WFVs could result from the
    project. The ALJ noted, however, that “[t]he basis for [the DNR’s] conclusion [was]
    not clear.” The ALJ cited the testimony of the DNR’s witness, Pamela Biersach—
    the director of the DNR’s Office of Business Services in the Fish, Wildlife and Parks
    Division—that granting the permit could generate more applications for filling
    wetlands and have a precedential effect for future applications. The ALJ stated,
    however, that precedent “is not identified as a component of cumulative impacts.”
    Citing Kohler’s permit application, the ALJ noted that Kohler does not plan on
    “additional development beyond the current proposed plan” and, “therefore, no
    future wetland impacts in the affected area are expected to be caused by the
    permitting of this [p]roject.”
    ¶50    Even if we agreed with Kohler that the ALJ’s finding regarding
    cumulative impacts to WFVs is not supported by substantial evidence, we conclude,
    for two reasons, that the ALJ’s overall decision did not “depend[]” on the
    cumulative impacts finding. First, the cumulative impacts analysis consisted of a
    28
    No. 2021AP1187
    single paragraph, separate from a much more in-depth and lengthy analysis of
    missing information regarding secondary impacts.
    ¶51     Second, and relatedly, cumulative impacts did not have any bearing
    on the ALJ’s decision. The ALJ was not ruling on the merits of the permit and
    whether the statutory requirements of WIS. STAT. § 281.36(3n)(c)3. were met.19 Nor
    did the ALJ rule on, or find, that the DNR lacked information regarding cumulative
    impacts. Instead, the ALJ ultimately concluded that the FBRF “carried [its] burden
    of proof to show that the [DNR] did not have sufficient evidence to support its
    determination that the project will not result in significant adverse impact to
    [WFVs], in significant adverse impact to water quality, or in other significant
    adverse environmental consequences” at the time the DNR decided to issue the
    permit.
    B. Significant adverse impacts to WFVs under WIS. STAT. § 281.36(3n)(c)3.
    ¶52     Next, we address Kohler’s argument that “the ALJ’s ruling must be
    overturned because there is no evidence that nutrients and pesticides applied to the
    golf course would reach the groundwater and wetlands such that significant adverse
    impacts will result.” In support, Kohler asserts that the ALJ “found that the
    ‘application of nutrients to the golf course at allowed levels will result in the
    mitigation of nitrogen and phosphorous into the groundwater’”; that “rain events
    and irrigation ‘will carry the nutrients, pesticides, and other contaminants applied to
    the golf course in the groundwater’”; and that “‘two to twelve percent of nitrogen
    19
    Kohler responds to this conclusion by arguing that the ALJ would not have made
    findings that “had no purpose” to its decision. Kohler does not, however, explain how or why
    cumulative impacts applied to the ALJ’s ultimate decision regarding the DNR’s lack of information
    and, in fact, admits that “[t]he ALJ’s overarching holding was that the [DNR] ‘did not have
    sufficient information to determine the proposed project will not result in significant adverse
    impact.’” We consider Kohler’s argument undeveloped on this issue. See State v. Pettit, 
    171 Wis. 2d 627
    , 646, 
    492 N.W.2d 633
     (Ct. App. 1992).
    29
    No. 2021AP1187
    applied to the course will leach below the root zone’ of the turf.” According to
    Kohler, the ALJ failed to cite any “evidence that pesticides and nutrients will reach
    the groundwater and wetlands in quantities significant enough to have any impact
    at all.”
    ¶53   Kohler misunderstands both the ALJ’s ruling and the issue on appeal
    with respect to our substantial evidence analysis. The ALJ’s decision did not
    “depend[]” on its findings of facts regarding the merits of the permit. Rather, the
    ALJ concluded that the DNR did not have sufficient evidence to support its
    determination that the project would not result in significant adverse impacts to
    WFVs at the time it decided to issue the permit. The ALJ did not conclude that the
    project will result in significant adverse impacts to WFVs, as Kohler contends.
    None of the three findings cited above by Kohler relate to the ALJ’s ultimate
    conclusion.
    ¶54   In addition, the ALJ’s finding that the DNR lacked evidence with
    respect to its findings regarding nutrients and pesticides is supported by substantial
    evidence. According to the ALJ, “[i]t is undisputed that the introduction of nitrates,
    phosphorus, pesticides, oil, grease, and other contaminants in the groundwater and
    wetlands will adversely impact [WFVs] and the water quality” on the property.
    Thus, the ALJ reasoned, and we agree, that “the critical question” in evaluating
    whether the operation of the golf course would result in significant adverse impacts
    was “the levels of the chemicals and contaminants that [would] reach the
    groundwater and wetlands” as well as the direction of the groundwater flow and the
    separation between the surface and groundwater.
    ¶55   The DNR sought to address these questions during the permit
    application process by requesting a water table map from Kohler, as well as
    30
    No. 2021AP1187
    stormwater, nutrient, and pesticide management plans. Importantly, however, the
    ALJ determined that “[a]t the time the [DNR] issued the permit, [it] had not received
    the final versions of the various management plans or a reliable water table map.”
    For example, Dr. Stuart Z. Cohen—the president of an “environmental and
    agronomic service company”—testified at the contested hearing on behalf of Kohler
    that a detailed IGCMP had yet to be finalized.20
    ¶56    While Kohler did supply a water table map on November 6, 2017, it
    was not “until very late in the application process.” Additionally, testimony at the
    hearing revealed that the map “may not be accurate” because, according to Jeff
    Quast—the president of Excel Engineering who was hired by Kohler to provide civil
    engineering services on the proposed project—the measurement information from
    test pits and monitoring wells used to generate the map was not submitted to the
    DNR. Furthermore, Quast testified that a cross-section groundwater map of the
    property was incorrect, and Quast admitted that some groundwater elevations
    submitted in the stormwater management plan were also incorrect.
    ¶57    The ALJ also criticized the permit for not providing mandatory
    conditions to limit the risk of the impacts from pesticides and nutrients. While the
    permit requires Kohler to use various BMPs in the operation of the course (e.g.,
    “spoon feeding” chemicals), Dr. Cohen described the BMPs as “a set of concepts.”
    For example, the permit allows Kohler to apply nitrogen at levels of eight pounds
    per 1,000 square feet for ongoing turf maintenance. Cohen testified that he expects
    Kohler to apply nitrogen at a much lower level, and he therefore did not conduct an
    analysis of whether application of nitrogen at the permitted level would adversely
    20
    An IGCMP was submitted to the DNR in the fall of 2017. According to Dr. Cohen, the
    IGCMP submitted to the DNR was a set of “basic concepts.”
    31
    No. 2021AP1187
    impact the groundwater or wetlands. According to the ALJ, the lower nitrogen
    levels considered by Cohen were “speculative and not a permit condition. The
    [DNR] must consider the impacts based on what Kohler is allowed to do, not on a
    best case scenario.”
    ¶58    Similarly, the ALJ discredited testimony from the hearing that the
    thatch and turf will capture the nutrients applied to the course. Doctor Cohen
    testified that the only way water carrying nutrients and other chemicals could reach
    the groundwater was if someone used a posthole digger to bypass the turf. The ALJ
    concluded, however, that this statement was contrary to Cohen’s other testimony
    that “two to twelve percent of the nitrogen applied to the course will leach below
    the root zone.” The ALJ also expressed skepticism regarding the thatch and turf’s
    capturing of nutrients because “at least three of the [BMPs] in the IGCMP are
    intended to improve water infiltration by bypassing the turf. These practices are
    aerification, topdressing, and verticutting.”
    ¶59    Even accepting that the thatch and turf would effectively capture
    nutrients applied to the course, the ALJ stated that “there [would] be no filter until
    the turf and thatch [were] established.” During the period of turf and thatch
    establishment, the permit allows higher applications of nitrogen and phosphorus
    because the sandy soils on the property are nutrient poor. As such, citing the
    testimony of Dr. Carpenter, the ALJ concluded that “[a] larger portion of the applied
    nutrients, particularly phosphorus, [would] leach through the permeable soil into the
    groundwater during the period when the turf [was] becoming established.”
    ¶60    Regarding pesticide usage on the property, the ALJ cited the final EIS,
    stating that “monitoring groundwater quality for pesticide contamination and
    minimizing pesticide use through implementation of an [Integrated Pest
    32
    No. 2021AP1187
    Management] plan are potential ways to reduce the potential negative effects of
    pesticide use.” (Formatting in original.) Yet, the ALJ reasoned that the permit
    “includes no condition requiring groundwater monitoring.” The ALJ disregarded
    Dr. Cohen’s additional pesticide evaluation, determining it was irrelevant because
    it was dated May 18, 2018—four months after the permit was issued and only two
    weeks before the administrative review hearing.
    ¶61    While the ALJ’s findings can be countered by other evidence in the
    record, the record supports the ALJ’s finding that the DNR did not have sufficient
    evidence to support its determination that the nutrients and pesticides applied as part
    of the project would not result in significant adverse impacts to WFVs. See Hilton,
    
    293 Wis. 2d 1
    , ¶16. We will not second-guess the ALJ’s ultimate decision because
    it is supported by substantial evidence.
    ¶62    Kohler specifically takes issue with the ALJ’s finding that any amount
    “of nitrogen or other contaminants entering the leachate” will have a significant
    adverse impact to WFVs. Kohler points to Dr. Cohen’s testimony that small
    amounts of these chemicals will have no impact. According to Kohler, it presented
    “substantial evidence … to show that any impact on wetlands [would] be
    insignificant.”
    ¶63    We first note that we are not considering whether Kohler presented
    “substantial evidence.” Instead, we are tasked with determining whether the ALJ’s
    finding regarding the DNR’s lack of information with respect to chemicals entering
    the groundwater is supported by substantial evidence. We conclude that it is.
    ¶64    The permit itself stated that “4.79 acres of secondary impacts may
    result from … increased runoff of nutrients, herbicides, and pesticides” and that
    33
    No. 2021AP1187
    “nutrient loading” was a secondary impact to WFVs. Additionally, the final EIS
    stated:
    The Kohler [p]roperty has predominantly sandy soils with
    high infiltration rates and high hydraulic conductivity. This
    combined with a shallow depth to the surficial groundwater
    aquifer increases the potential for pesticides and fertilizer to
    leach into the shallow aquifer which may additionally reach
    the Black River, Lake Michigan, and the associated
    wetlands.
    The final EIS also noted that “irrigation water and fertilizer run-off into
    the … wetlands would impact water quality by increasing nutrients and leading to
    changes in the plant assemblages.” Notably, the DNR did not specify a certain
    amount of chemicals that the wetlands would tolerate. Instead, it stated that “[i]t is
    unknown to what extent stormwater infiltration and nutrient and pesticide
    applications to fairways, tees and greens (for either establishment or maintenance)
    would impact groundwater quality in this permeable soil and shallow water table
    environment.”      Trochlell testified at the contested hearing that “any nutrient
    additions to these very sensitive wetlands will have an impact upon them.”
    ¶65   While Dr. Cohen may have disagreed with that finding, the ALJ was
    not obligated to follow Cohen’s lead and find that small amounts of chemicals
    would be harmless. Instead, the ALJ determined that the DNR was required to have
    more information before it could resolve: (1) whether chemicals would reach the
    wetlands through the soil; and (2) if so, whether those amounts would be harmful.
    Without this information, the ALJ found the DNR could not have meaningfully
    analyzed the secondary impacts to WFVs.
    ¶66   Kohler also argues that the permit conditions for BMPs would
    “undisputedly have a major effect on limiting nutrient and pesticide penetration into
    34
    No. 2021AP1187
    groundwater.”21 In support, Kohler cites to a number of statements made by the
    FBRF witnesses, such as Dr. Jansen, who stated, “I agree that slow release fertilizers
    generally will reduce the risk of contamination.”22 Kohler also cites to “empirical
    work” in the record.
    ¶67     Contrary to Kohler’s assertion, the effectiveness of the permit
    conditions for BMPs was significantly disputed at the contested hearing. For
    example, Dr. Jansen testified regarding condition 22—requiring Kohler to follow
    BMPs—and stated he had not “seen any evaluation by the DNR … that connects
    complying with these BMPs to compliance with water quality standards.” Doctor
    Carpenter also stated in his prefiled testimony that condition 22 “seems to be quite
    generic and contains no evidence that what is applied to the golf course will not end
    up in the wetlands.” Similarly, Trochlell stated in her prefiled testimony that
    condition 23—requiring Kohler to follow WIS. ADMIN. CODE ch. NR 151—is not
    sufficient to protect wetland water quality because “this rule was not designed to
    ensure [WFVs] are protected in all cases, and certainly not in this sensitive
    21
    Kohler also contends that the BMPs requiring “spoon feeding” will prevent chemicals
    from reaching the groundwater, and, therefore, the DNR did not need any further information.
    According to Kohler, “[o]ne cannot both ‘spoon feed’ fertilizer and dramatically over-apply
    fertilizer at the same time.” Kohler does not cite to the record or any other authority to support its
    assertion. Additionally, Dr. Jansen testified that “spoon feeding” as used in the BMPs is
    subjective: “[T]hat’s how [Kohler] described it, but they’re talking about a pound per 1,000 square
    feet. We have references that show that that rate can lead to 3.8 parts per million … in the
    lysimeters.”
    22
    As has been the case throughout Kohler’s briefing, Kohler’s citations here to the FBRF’s
    witnesses’ testimony are either taken out of context or are completely misleading. One example is
    Kohler’s citation to Dr. Jansen’s testimony. Kohler claims that Jansen agreed that, in Kohler’s
    words, “turf [is] effective at absorbing nutrients and pesticides.” To the contrary, Jansen actually
    said, “I’ll agree that turf does a better job of absorbing nutrients and pesticides than some other
    things like row crops. But it is not an excellent system for removing nitrogen and pesticides. It
    can easily be bypassed.”
    35
    No. 2021AP1187
    environment.” Additionally, Dr. Cohen described the BMPs as a set of concepts,
    not mandatory conditions. The testimony above comports with the IGCMP. For
    example, one BMP states that Kohler will “[u]se slow release or organic fertilizers
    with 50% or less soluble Nitrogen when possible.” (Emphasis added.) As such, the
    ALJ’s determination regarding the permit conditions for BMPs is supported by
    substantial evidence.23
    ¶68     Regarding the ALJ’s findings on phosphorus, Kohler argues that
    “even [the FBRF’s] own witnesses confirmed that phosphorous will not pose a
    problem.”      This assertion completely ignores Dr. Carpenter’s testimony that
    phosphorous is “always … a potential problem mix. It’s a more powerful agent
    generally in change than even nitrogen because it acts at lower levels.” Carpenter
    went on to state that phosphorous will need to be applied at a higher rate initially in
    order to establish the golf course grasses. According to Carpenter, “because you
    can’t apply [phosphorous] by the dropper at the root, you’re going to have granules
    of phosphate material hitting empty, sandy patches” and eventually dissolving into
    water. Carpenter also stated he did not believe phosphorous would be an easily
    managed problem on the proposed golf course. Therefore, the ALJ’s finding that
    the DNR did not have sufficient evidence to support its determination pursuant to
    WIS. STAT. § 281.36(3n)3. at the time it decided to issue the permit is supported by
    substantial evidence.
    ¶69     Next, Kohler contends that the ALJ’s finding regarding nitrogen is not
    supported by substantial evidence because Kohler “expressly committed to applying
    far less than eight pounds of nitrogen per one thousand square feet.” Doctor Cohen
    23
    Kohler cites “its longstanding focus on environmental preservation” and its “minimalist
    approach to pesticides and fertilization.” Kohler does not explain how this history affects the ALJ’s
    findings, and we will not consider it further. See Pettit, 171 Wis. 2d at 646.
    36
    No. 2021AP1187
    testified at the contested hearing that Kohler will use less than that amount based on
    “35 years of experience and talking to the superintendents of the Kohler golf
    courses.” According to Cohen, Kohler will apply “[l]ess than 3 pounds per 1,000
    square feet over the managed turf.”
    ¶70    We disagree that the testimony of a witness—who does not work for
    Kohler—is an “express[] commit[ment]” on behalf of Kohler. In any event, the ALJ
    concluded that Dr. Cohen’s testimony about nitrogen levels was “speculative and
    not a permit condition.” Kohler does not explain how this finding is not supported
    by substantial evidence.
    ¶71    Kohler also argues that it “presented undisputed evidence about how
    its irrigation systems further defend against groundwater contamination.”
    According to Kohler, the only opposition to Kohler’s irrigation system related to
    quickly changing weather and how a computerized irrigation system will not be able
    to adapt in such situations. We disagree that this affects our conclusion. While
    there was testimony supporting Kohler’s claim, there was also evidence disputing
    the irrigation system’s effectiveness.
    ¶72    In all, Kohler provides no basis for us to conclude that the ALJ’s
    finding that the DNR lacked sufficient information to meaningfully analyze the
    proposed project pursuant to WIS. STAT. § 281.36(3n)3. is not supported by
    substantial evidence. In other words, “after considering all the evidence of record,
    reasonable minds could arrive at the same conclusion” as the ALJ did in this case.
    See Hilton, 
    293 Wis. 2d 1
    , ¶16.
    ¶73    Kohler attempts to refute the above evidence by arguing that the ALJ
    declined to consider evidence that Kohler argues would have met the requirements
    of WIS. STAT. § 281.36(3n)(c). In other words, Kohler argues that although the ALJ
    37
    No. 2021AP1187
    determined that the DNR lacked sufficient information to issue the permit, the ALJ
    should have considered additional evidence that Kohler submitted during the
    contested hearing.
    ¶74     According to Kohler, the ALJ identified three areas of information
    that the DNR lacked at the time it issued the permit: (1) the levels of nitrogen to be
    applied to the course; (2) the types of pesticides to be applied to the course, as well
    as pesticide impacts; and (3) whether Kohler planned on using groundwater
    monitoring to avoid potential pesticide impact.24
    ¶75     Kohler states that it “definitively” provided sufficient information at
    the contested hearing for the ALJ to determine all three of these issues. For
    example, Kohler cites the IGCMP and the pesticide risk assessment that were
    introduced at the contested hearing. Citing the fact that contested hearings are akin
    to trials, Kohler argues that “[t]he ALJ erred as a matter of law in ignoring this
    evidence merely because it was developed as part of the contested[]case hearing.
    This rule flatly misapplies the very nature of contested[]case proceedings, the
    purpose of which is to adjudicate disputed facts in a trial-like manner.” In making
    these arguments, Kohler posits that the ALJ “repeatedly considered new evidence
    presented by the [FBRF] during the contested[]case hearing” but ignored the
    additional evidence presented by Kohler.
    24
    Although not necessary to our decision on this issue, we note that the ALJ also found
    other pieces of information lacking from the permit process, including that the DNR lacked a
    reliable water table map. Additionally, the DNR and the FBRF argue that Kohler’s submitted
    evidence did not resolve the deficiencies in the information the ALJ noted. Because we decide this
    issue on narrower grounds, we need not address whether Kohler’s supplemental information
    provided the DNR with sufficient information to make a decision under WIS. STAT. § 281.36. See
    Patrick Fur Farm, Inc. v. United Vaccines, Inc., 
    2005 WI App 190
    , ¶8 n.1, 
    286 Wis. 2d 774
    , 
    703 N.W.2d 707
    .
    38
    No. 2021AP1187
    ¶76    Kohler ignores the fact that all three issues the ALJ identified related
    to whether the DNR had sufficient information to issue a permit at the time the
    decision was made. The evidence submitted by the DNR and Kohler at the
    contested hearing attempted to fill the information gaps that the DNR did not have
    at the time the permit was issued. Put differently, the DNR and Kohler were
    attempting to retroactively fix errors in the permit process.
    ¶77    For example, Kohler submitted Exhibit 208, titled “Ground Water
    Contamination Risk Assessment Screen for Pesticides at the Proposed Kohler Golf
    Course in Sheboygan.” Doctor Cohen testified that he prepared the report, that he
    performed the risk assessment “[a] few weeks” before the contested hearing, that its
    purpose was essentially to confirm that Kohler “would comply with condition 22 of
    the permit,” and that the DNR did not have the exhibit before it when it made the
    permit decision. By submitting exhibits prepared after the permit was granted,
    Kohler tacitly acknowledged that the DNR was missing information at the time it
    issued the permit.
    ¶78    Conversely, the evidence submitted by the FBRF of which Kohler
    complains was presented in order to display the deficiencies in the DNR’s decision
    based on information the DNR did not have at the time it issued the permit. For
    example, the FBRF submitted a number of exhibits regarding internal DNR
    communications about Kohler’s permit application. Exhibits 9, 25, and 26, for
    example, were internal DNR emails from staff members concerning missing
    information that the DNR was requesting from Kohler but, according to the FBRF,
    was never received. As such, the ALJ’s factual findings are supported by substantial
    evidence.
    IV. The ALJ did not err in reversing the DNR’s decision instead of modifying
    the permit sua sponte.
    39
    No. 2021AP1187
    ¶79     Kohler also contends that the ALJ erred by not modifying the permit’s
    conditions to account for what the ALJ perceived as deficiencies. According to
    Kohler, the ALJ violated WIS. STAT. § 281.36(3n)(c) by not modifying the permit
    sua sponte after concluding that the permit lacked sufficient conditions.25 Kohler
    argues that the ALJ “had the power” and “the obligation” to modify the permit.
    Specifically, Kohler reasons that the ALJ was required to make findings “that may
    be adopted as the final decision in the case.” See WIS. STAT. § 227.46(2). This
    requirement is particularly crucial, says Kohler, because the DNR did not petition
    for judicial review and therefore adopted the ALJ’s decision as its own. In other
    words, Kohler states that the ALJ “stood in the shoes of the [DNR]” as the final
    decision maker.
    ¶80     We conclude the ALJ did not possess the authority to modify the
    permit conditions sua sponte. WISCONSIN STAT. § 281.36(3q)(g) states that an
    administrative hearing on a challenge to a DNR wetland permit “shall be treated as
    a contested case under [WIS. STAT.] ch. 227.” Prior to the hearing, a notice shall be
    sent out defining the issues to be decided. See WIS. STAT. § 227.44(2)(c). We have
    previously held that a failure to provide notice for a contested hearing under
    § 227.44(2)(c) of all of the issues involved can constitute a deprivation of a party’s
    due process rights. See Bracegirdle v. DRL, 
    159 Wis. 2d 402
    , 411-12, 419-20, 464
    25
    Kohler contends in its brief-in-chief that “[t]he ALJ expressly acknowledged that ‘[t]he
    permit could be amended’ … ‘either by stipulation or order.’” The ALJ’s statement, as cited by
    Kohler, is taken out of context. The statement was made in response to an objection the FBRF
    made regarding an updated IGCMP which Kohler was using in an attempt to elicit witness
    testimony. The FBRF noted that the IGCMP in question was not the same IGCMP cited in the
    permit. In response, the ALJ inquired of Kohler whether “at some point is this, I guess, the
    upgraded or updated plan that would be in place if the permit was approved?” Kohler answered in
    the affirmative, and the ALJ stated that—in the context of whether the permit was approved after
    the contested hearing—“[t]he permit could be amended. The condition could be amended either
    by stipulation or order.”
    40
    No. 2021AP1187
    N.W.2d 111 (Ct. App. 1990) (board violated nurse’s right to fair notice and
    opportunity to be heard when it found that she violated conduct not charged).
    ¶81    Here, the parties limited the issues to: (1) whether the permit satisfied
    the standard set forth in WIS. STAT. § 281.36(3n)(c)3.; and (2) whether the DNR had
    sufficient information to make a decision under that standard. Missing from this list
    is whether the ALJ could, or should, amend the conditions if it found them lacking
    in scope. The ALJ therefore did not possess the authority to raise an issue sua sponte
    without it first being presented as an issue under WIS. STAT. § 227.44(2)(c).
    ¶82    Kohler relies on Clean Wisconsin, Inc. v. DNR, 
    2021 WI 71
    , 
    398 Wis. 2d 386
    , 
    961 N.W.2d 346
    , to argue that the ALJ “ignored his statutory
    obligation” by not amending the permit in this case. Clean Wisconsin involved the
    DNR granting a Wisconsin Pollutant Discharge Elimination System (WPDES)
    permit to a dairy operation applicant. Id., ¶1. Petitioners challenged the permit
    based on missing conditions. Namely, the permit lacked two conditions related to
    the “maximum number of animal units” and “monitoring to evaluate impacts to
    groundwater.” Id., ¶4. Following a contested hearing, an “ALJ determined that,
    based on the facts presented, the DNR had ‘clear regulatory authority’ to impose the
    two conditions disputed in this action upon [the dairy operator’s] … WPDES
    permit.” Id., ¶7. The ALJ “ordered” the DNR to modify the permit to include the
    two conditions. Id., ¶¶8-9. On review, our supreme court concluded that the DNR
    had the authority to impose the two conditions. See id., ¶40.
    ¶83    We conclude that Clean Wisconsin is inapposite to the case at hand
    because in Clean Wisconsin the permit was lawfully issued from its inception. The
    ALJ in Clean Wisconsin did not conclude the permit was unlawfully issued.
    Conversely, the ALJ in this case found exactly that—i.e., that the DNR did not have
    41
    No. 2021AP1187
    sufficient information to issue the permit.                Furthermore, the ALJ in Clean
    Wisconsin merely ordered the DNR to modify the permit; the ALJ did not modify
    the permit.
    ¶84     The issue here is better framed as whether the DNR “is authorized to
    issue an amended permit when there is no valid permit to amend.” See Meteor
    Timber, 
    400 Wis. 2d 451
    , ¶90. Ultimately, we need not answer that particular
    question because we conclude that the issue of amending the permit’s conditions
    was not presented to the ALJ under WIS. STAT. § 227.44(2)(c). We also note,
    however, that like the permit applicant in Meteor Timber, Kohler points to no law
    supporting the proposition that an ALJ is authorized to amend a wetland permit after
    concluding that it was not lawfully issued and was therefore invalid.26 “In the
    absence of any such citation, and in light of our conclusion that the [DNR’s]
    decision to issue the permit was properly reversed, we conclude that the” ALJ did
    not err by not revising the DNR’s permit after concluding that the agency
    improperly issued the permit in the first place.27 See Meteor Timber, 
    400 Wis. 2d 451
    , ¶90.
    26
    Notably, Kohler does not raise an argument on appeal regarding WIS. ADMIN. CODE
    § NR 2.14(2), which states that “[e]vidence submitted at the time of hearing need not be limited to
    matters set forth in pleadings, petitions or applications. If variances of this nature occur, then the
    pleadings, petitions or applications shall be considered amended by the record.” We therefore will
    not consider the relevance of § NR 2.14(2) further.
    27
    Following the issuance of our decision in Meteor Timber, the FBRF filed a citation of
    supplemental authority, and Kohler responded. Kohler attempts to distinguish Meteor Timber by
    arguing that unlike in Meteor Timber, here “the [DNR] determined that Kohler’s application was
    complete and issued the permit in compliance with [WIS. STAT.] § 281.36(3m)(i); it did not purport
    to issue a permit that by its own terms required the submission of additional information necessary
    for the [DNR] to make the prerequisite determinations for permit issuance.” We disagree. In both
    Meteor Timber and this case, the DNR unlawfully issued a permit. Therefore, as we held in Meteor
    Timber, the question becomes whether the ALJ can amend an invalid permit. The DNR’s
    subjective reasoning does not guide our analysis.
    42
    No. 2021AP1187
    ¶85    Even if we concluded that the ALJ could have amended the permit
    and erred in failing to do so, Kohler forfeited this argument by not raising it before
    the ALJ. See DOJ v. DWD, 
    2015 WI App 22
    , ¶18, 
    361 Wis. 2d 196
    , 
    861 N.W.2d 789
     (“Because our review of an administrative agency’s decision contemplates
    review of the record developed before the agency, a party’s failure to properly raise
    an issue before the administrative agency generally forfeits the right to raise that
    issue before a reviewing court.”); see also Amazon Logistics, Inc. v. LIRC, 
    2023 WI App 26
    , ¶72, 
    407 Wis. 2d 807
    , 
    992 N.W.2d 168
    .
    ¶86    Without citation, Kohler argues it could not have forfeited the
    amendment issue during the administrative proceedings because it was not the
    petitioner. Although unclear, it appears Kohler is relying on case law that states a
    respondent on appeal may raise any argument that would support the circuit court’s
    action, even if the argument was not previously raised in the circuit court. See State
    v. Holt, 
    128 Wis. 2d 110
    , 124-25, 
    382 N.W.2d 679
     (Ct. App. 1985), superseded by
    statute on other grounds, WIS. STAT. § 940.225(7).         Here, Kohler is not the
    respondent on appeal, and we are reviewing an ALJ decision. Kohler’s argument
    that we should not apply the forfeiture doctrine under the circumstances of this case
    is undeveloped and unsupported by legal authority. We will not develop an
    argument on its behalf. See State v. Pettit, 
    171 Wis. 2d 627
    , 646, 
    492 N.W.2d 633
    (Ct. App. 1992).
    V. The ALJ did not err in making a single reference to “quantitative findings.”
    ¶87    Lastly, Kohler focuses on a single sentence in the ALJ’s decision to
    argue that the decision is based on a misrepresentation of law because the ALJ,
    according to Kohler, “required” the DNR to make “quantitative findings as to at
    what point the secondary adverse impacts would become significant,” which is not
    43
    No. 2021AP1187
    a required analysis in the wetland permitting process.28                Kohler argues that
    “[a]nalyzing secondary impacts of a future project necessarily involves some level
    of uncertainty, and certain impacts cannot be quantified at all.”
    ¶88     In full, the ALJ’s reference to quantitative findings reads:
    The [DNR] did not make any quantitative findings as to at
    what point the secondary adverse impacts would become
    significant or explain how the [permit] conditions would
    reduce the adverse impacts below the level of significance
    either in the permit itself or through [DNR] staff testimony
    at the hearing.
    (Emphasis added.) According to Kohler, the ALJ’s statement is significant as it
    involved a “key issue in the contested case,” and it contends the ALJ concluded
    “that the [DNR’s] decision to grant the permit failed for a lack of quantitative
    findings.” We disagree.
    ¶89     When considered in the context of the ALJ’s entire discussion of
    secondary impacts, it is clear the ALJ did not “require” Kohler or the DNR to
    produce a quantitative analysis of secondary impacts.                Instead, the ALJ was
    concerned with the lack of information regarding significant adverse impacts. The
    remainder of the paragraph cited by Kohler reads:
    The [DNR] may be confident that Kohler’s management
    plans will ultimately be sufficient to protect the wetlands;
    however the [DNR] should be making its determinations
    based on completed plans, not trusting that management
    plans that will be prepared will adequately protect the
    groundwater and wetlands. Once the golf course is
    constructed[,] the adverse impacts will be permanent and
    irreversible. The [DNR] is required to make a determination
    28
    The DNR urges this court not to consider Kohler’s argument in this regard because
    Kohler fails to frame the issue as reviewable error under WIS. STAT. § 227.57. We, conclude,
    however, that Kohler challenges the ALJ’s decision as an incorrect interpretation of law, and we
    will analyze the merits of that claim. See § 227.57(11).
    44
    No. 2021AP1187
    that the project will not result in significant adverse impacts.
    It is unable to do so based on incomplete information.
    Kohler contends that the processing of the instant permit was
    unusually long and thorough. The process has been long,
    but it was still incomplete at the time the [DNR] closed the
    application process.
    (Emphasis added.) It is clear that the ALJ’s single reference to “quantitative
    findings” was based on a much larger critique of the DNR’s lack of information
    regarding secondary impacts.         The ALJ correctly stated that the DNR was
    “required” to make a determination that the project would not result in significant
    adverse impacts to WFVs.
    ¶90    In further support of its argument, Kohler cites to other isolated
    references that the ALJ made regarding “levels” and “amounts” of chemicals. These
    citations further demonstrate, however, that the ALJ was not requiring Kohler or the
    DNR to provide specific numerical findings regarding what level of, for example,
    nitrogen would reach the wetlands. Generally speaking, the ALJ noted that the
    “critical question [was] the levels of … chemicals and contaminants that [would]
    reach the groundwater and wetlands.” The ALJ did not say that the DNR or Kohler
    was required to provide the specific numbers that would reach the groundwater or
    wetlands, but only that the information before the DNR lacked sufficient specificity
    for the DNR to determine whether whatever level did reach the groundwater would
    be significant.
    ¶91    The ALJ expressly stated that the
    [i]mportant pieces of information needed to predict these
    levels [(i.e., the levels that would cause significant adverse
    impacts to WFVs) are] the levels at which nutrients will be
    applied to the course, the identity of the pesticides that will
    be used by Kohler, the direction of groundwater flow, and
    the separation between the surface and the groundwater.
    45
    No. 2021AP1187
    Nowhere did the ALJ state that the DNR or Kohler was “required” to make
    “quantitative findings” as to what chemicals would reach the groundwater or
    wetlands and in what amounts. Instead, the ALJ’s focus was on the lack of
    information regarding levels applied to the course and the other information noted
    like the groundwater flow. Without this information, it was impossible for the DNR
    to know whether the operation of the golf course would result in significant adverse
    impacts to WFVs.
    ¶92    As described, the ALJ’s reference to quantitative findings was just
    that—a reference. Despite Kohler’s best efforts to characterize the statement as the
    be-all and end-all finding, the statement did not constitute the reason the ALJ
    decided the DNR lacked sufficient information on secondary impacts to issue the
    permit. The statement came after a lengthy discussion of the information regarding
    pesticides and nutrients to be used on the site that was missing when the DNR issued
    the permit. For the reasons stated, there was no error of law.
    46
    No. 2021AP1187
    CONCLUSION
    ¶93    In all, we conclude that WIS. STAT. § 281.36(3n)(b) and (c) require
    the DNR to consider impacts and activities beyond regulated, direct wetland fill.
    See also WIS. ADMIN. CODE § NR 103.03(1). Additionally, the ALJ’s decision is
    supported by substantial evidence. Namely, the ALJ’s decision that the DNR did
    not have the information necessary to make a § 281.36(3n)(c)3. determination is
    supported by substantial evidence—i.e., one that reasonable minds could reach—
    and the decision did not “depend[]” on cumulative impact findings. Further, the
    ALJ did not err in reversing the DNR’s decision without modifying the permit.
    Lastly, the ALJ did not require Kohler or the DNR to make “quantitative findings”
    with regard to secondary impacts.
    By the Court.—Order affirmed.
    47
    

Document Info

Docket Number: 2021AP001187

Filed Date: 12/5/2023

Precedential Status: Precedential

Modified Date: 9/9/2024