Stantec Consulting Services, Inc. v. Thrasher Environmental, Inc. ( 2013 )


Menu:
  •                                STATE OF WEST VIRGINIA
    SUPREME COURT OF APPEALS
    Stantec Consulting Services, Inc.,                                               FILED
    Plaintiff Below, Petitioner                                                    October 18, 2013
    RORY L. PERRY II, CLERK
    SUPREME COURT OF APPEALS
    vs) No. 12-1400 (Kanawha County 09-C-2192)                                    OF WEST VIRGINIA
    Thrasher Environmental, Inc.,
    and Dayton Carpenter,
    Defendants Below, Respondents
    MEMORANDUM DECISION
    Petitioner Stantec Consulting Services, Inc., by counsel Michael J. Schessler, appeals the
    order from the Circuit Court of Kanawha County granting judgment as a matter of law to
    respondents during trial. Respondents Thrasher Environmental, by counsel Kathryn K. Allen,
    and Dayton Carpenter, by counsel John B. Cromer, filed a joint response to which petitioner filed
    its reply.
    This Court has considered the parties’ briefs and the record on appeal. The facts and legal
    arguments are adequately presented, and the decisional process would not be significantly aided
    by oral argument. Upon consideration of the standard of review, the briefs, and the record
    presented, the Court finds no substantial question of law and no prejudicial error. For these
    reasons, a memorandum decision is appropriate under Rule 21 of the Rules of Appellate
    Procedure.
    In June of 2005, petitioner entered into a contract with the West Virginia Department of
    Environmental Protection (“DEP”) to develop a reclamation plan and design water treatment
    facilities to eliminate problems associated with the uncontrolled mine drainage at an abandoned
    mine site in Upshur County. The work directive from the DEP to petitioner contained no mention
    of the acceptable water treatment facility effluent discharge limits. However, in its proposal to
    the DEP, petitioner agreed to prepare construction plans and specifications for mediation of
    mining related environmental problems and referenced an effluent discharge goal of .5 mg/l of
    iron daily average. Evidence presented at trial affirmatively established that the DEP self-
    imposed technology-based standard for iron effluent discharge limits from abandoned mine sites
    was 3.0 mg/l.
    Petitioner, as prime engineer on the project, entered into a sub-consulting agreement with
    Thrasher Environmental, Inc. (“Thrasher”); the terms of that agreement are set forth in a letter
    dated July 6, 2005. This letter specifically states that the DEP proposes certain items to remove
    elevated iron concentrations to <0.5 mg/l iron average. However, this agreement also states that
    Thrasher was to design a water treatment process and plant to treat water containing 15 mg/l
    iron, 500 mg/l alkalinity, and a pH of 7.4 to 7.6 mg/l. Dayton Carpenter (“Carpenter”) agreed to
    1
    act as the consultant to petitioner. The sub-consulting services were only a portion of the
    engineering services undertaken by petitioner for the DEP. The sub-consulting agreement also
    provides that the results of water quality studies being conducted by the DEP approved
    environmental testing laboratory were to be reviewed by respondents.
    The project was built in accordance with the design plans, and it was placed into
    operation in October of 2007. At that time, the iron concentration levels coming into the plant
    were approximately 3.0 mg/l, representing a change in condition from the design parameters set
    forth by petitioner.1 Monthly test results since March of 2008 show water flowing into the
    treatment facility contained iron concentrations of 2.0 mg/l of iron or less, with limited
    exceptions. The DEP complained that petitioner failed to deliver a facility that conformed to the
    .5 mg/l iron effluent goal referenced in the contract between petitioner and the DEP. Petitioner
    claims that the problem was caused by respondents’ negligent design of the water treatment
    plant, which constituted a breach of the sub-consulting agreement. Petitioner undertook
    modifications to the facility in an attempt to satisfy the demands of the DEP. Despite these
    modifications, evidence presented at trial shows that since the redesigned and modified plant has
    been operational, the DEP has refused to accept the facility, the plant has not consistently met the
    DEP’s goal of .5 mg/l iron, and has not been able to consistently run the designed capacity of
    water flow.
    Petitioner filed suit against respondents for negligence and breach of contract, seeking to
    recover the costs it claims it incurred to redesign and reconstruct the facility to meet the .5 mg/l
    iron level goal. On September 24, 2012, the action went to jury trial. At the close of petitioner’s
    case-in-chief, respondents jointly moved for judgment as a matter of law pursuant to Rule 50 of
    the West Virginia Rules of Civil Procedure. Following oral argument on the motion, the circuit
    court granted judgment as a matter of law in favor of respondents (defendants below) and
    entered its order on October 11, 2012. In that order, the circuit court found that respondents’ duty
    to petitioner is set forth in the contract between petitioner and respondents and that petitioner
    failed to introduce expert testimony to establish that respondents breached the standard of care in
    performing the duties they were contractually obligated to perform. The circuit court found that
    the design parameters and water quality and quantity characteristics were given to respondents
    by petitioner, and respondents were entitled to rely on the information provided in their
    performance of services. The court also found that neither respondent was a party to the contract
    between petitioner and the DEP. The circuit court concluded that respondents performed the
    scope of work set forth under their sub-consulting agreement with petitioner. Petitioner accepted
    the work performed by respondents and incorporated the plans and specifications into its
    engineering plans delivered to the DEP. The DEP accepted the plans and specifications and
    authorized petitioner to proceed with the project under the same.
    The circuit court further found that petitioner failed to introduce evidence to support a
    prima facie showing that the water treatment process designed by respondents breached the
    generally accepted standard of care for engineers practicing in the same locality under similar
    circumstances; that petitioner failed to make a prima facie showing that respondents’ actions or
    inactions were the proximate cause of the injuries asserted by petitioner; and that petitioner failed
    to make a prima facie showing that respondents breached their contract with petitioner. The court
    1
    As set forth herein, the influent iron level reportedly impacts the effluent iron level
    following treatment in the water treatment plant.
    2
    ultimately concluded that when viewed in the light most favorable to petitioner, there was no
    legally sufficient evidentiary basis for a reasonable jury to find for petitioner.2 It is from this
    order that petitioner appeals.
    “The appellate standard of review for the granting of a motion for a [judgment as
    a matter of law] pursuant to Rule 50 of the West Virginia Rules of Civil
    Procedure is de novo. On appeal, this court, after considering the evidence in the
    light most favorable to the nonmoving party, will sustain the granting of a
    [judgment as a matter of law] when only one reasonable conclusion as to the
    verdict can be reached. But if reasonable minds could differ as to the importance
    and sufficiency of the evidence, a circuit court’s ruling granting a directed verdict
    will be reversed.” Syllabus Point 3, Brannon v. Riffle, 197 W.Va. 97, 
    475 S.E.2d 97
     (1996).
    Syl. Pt. 5, Smith v. First Cmty. Bancshares, Inc., 212 W.Va. 809, 
    575 S.E.2d 419
     (2002). Rule
    50(a)(1) of the West Virginia Rules of Civil Procedure states, “[i]f during a trial by jury a party
    has been fully heard on an issue and there is no legally sufficient evidentiary basis for a
    reasonable jury to find for that party on that issue, the court may determine the issue against that
    party and may grant a motion for judgment as a matter of law against that party . . . .”
    Petitioner asserts six assignments of error, the majority of which relate to the factual
    findings of the circuit court in its order granting judgment as a matter of law in favor of
    respondents. However, these factual findings are reviewed under the clearly erroneous standard.
    Clearly erroneous is a “highly deferential” standard of review. Tennant v. Marion Health Care
    Foundation, Inc., 194 W.Va. 97, 106, 
    459 S.E.2d 374
    , 383 (1995). Findings of fact are not to be
    made de novo by an appellate court: “[u]nder this standard, appellate courts cannot presume to
    decide factual issues anew. Our precedent ordains that deference be paid to the trier's assessment
    of the evidence.” Fraternal Order of Police, Lodge No. 69 v. City of Fairmont, 196 W.Va. 97,
    100 n.4, 
    468 S.E.2d 712
    , 715 n.4 (1996). See also Hanlon v. Logan County Bd. of Ed., 201
    W.Va. 305, 311, 
    496 S.E.2d 447
    , 453 (1997). “[C]lear-error review ordinarily heralds a rocky
    road for an appellant.” Fraternal Order of Police, 196 W.Va. at 100 n.4, 468 S.E.2d at 715 n.4.
    Reversal of a factual finding under the clearly erroneous standard should not be done lightly.
    Woo v. Putnam County Bd. of Educ., 202 W.Va. 409, 412, 
    504 S.E.2d 644
    , 647 (1998).
    AA finding [of fact] is clearly erroneous when, although there is evidence to
    support the finding, the reviewing court on the entire evidence is left with the
    definite and firm conviction that a mistake has been committed. However, a
    reviewing court may not overturn a finding simply because it would have decided
    the case differently, and it must affirm a finding if the circuit court=s account of
    the evidence is plausible in light of the record viewed in its entirety.@
    2
    In addition to granting judgment as a matter of law, the circuit court addressed
    respondents’ counterclaim to recover sums allegedly due and owing to them by petitioner for
    services performed under the contract. The circuit court held the counterclaim in abeyance and
    found that if the matter is retried, respondents would be permitted to present those claims to the
    jury on retrial.
    3
    Syl. Pt. 1, in part, In re Tiffany Marie S., 196 W.Va. 223, 
    470 S.E.2d 177
     (1996). “Where there
    are two permissible views of the evidence, the factfinder=s choice between them cannot be
    clearly erroneous.” Frymier-Halloran v. Paige, 193 W.Va. 687, 695 n.13, 
    458 S.E.2d 780
    , 788
    n.13 (1995) (quoting Anderson v. City of Bessemer City, N.C., 
    470 U.S. 564
    , 574 (1985)
    (Citation omitted)).
    “[W]e should not reverse a trier of fact on a question of credibility when the trier of fact
    had the advantage of hearing the testimony.” State v. Stuart, 192 W.Va. 428, 433, 
    452 S.E.2d 886
    , 891 (1994). “The clearly erroneous rule loses none of its rigor ‘when the [lower] court=s
    findings do not rest on credibility determinations, but are based instead on physical or
    documentary evidence or inferences from other facts.’” Fraternal Order of Police, 196 W.Va. at
    100, n.4, 468 S.E.2d at 715, n.4 (quoting Anderson v. City of Bessemer City, 470 U.S. at 574).
    “We will disturb only those factual findings that strike us wrong with the ‘force of a five-week-
    old, unrefrigerated dead fish.’” Brown v. Gobble, 196 W.Va. 559, 563, 
    474 S.E.2d 489
    , 493
    (1996) (quoting United States v. Markling, 
    7 F.3d 1309
    , 1319 (7th Cir.1993)).
    I.      Considering the evidence in the light most favorable to the nonmoving party.
    Petitioner first argues that the circuit court erred in granting respondents’ motion for
    judgment as a matter of law because the court failed to resolve all reasonable doubts and
    inferences in favor of petitioner and substituted its judgment, assuming the role of the jury.
    Petitioner argues that by granting respondents’ motion, the circuit court failed to provide every
    reasonable and legitimate inference fairly arising from the testimony and evidence submitted and
    failed to view the same in the light most favorable to petitioner. In order to establish a prima
    facie case of professional negligence in West Virginia, a plaintiff must show that a defendant has
    been guilty of some act or omission in violation of a duty owed to the plaintiff and that such act
    or omission caused the injury complained of. Aikens v. Debow, 208 W.Va. 486, 490, 
    541 S.E.2d 576
    , 580 (2000); Tolley v. ACT Indus., Inc., 212 W.Va. 548, 558, 
    575 S.E.2d 158
    , 168 (2002). In
    the instant case, the expert testimony presented by petitioner failed to establish that respondents
    deviated from the standard of care for engineers in the design of a water treatment facility. In its
    order granting judgment as a matter of law, the circuit court stated that petitioner’s expert
    witness testified that she had never independently designed a wastewater treatment facility; she
    had no opinion on how the treatment process facility should have been designed; and she
    acknowledged that when the iron levels in the water flowing into the plant were elevated by the
    addition of ferric chloride to the design parameters given to respondents, the plant, as designed,
    met DEP goals. Based on the record before this Court, considering the evidence in the light most
    favorable to petitioner, we find that only one conclusion as to the verdict can be reached.
    Therefore, we find that the circuit court did not err in granting respondents’ motion for judgment
    as a matter of law.
    II.     No contractual obligation to meet the .5 mg/l iron goal.
    Petitioner’s next assignment of error is that the circuit court erred in granting
    respondents’ motion when it concluded that respondents owed no contractual obligation to
    petitioner or the DEP to meet discharge specifications of .5 mg/l iron and that Thrasher
    performed the scope of their work set forth in the sub-consulting agreement with petitioner.
    4
    Petitioner argues that the evidence submitted clearly showed that Thrasher agreed to design the
    plant to treat influent water to reduce effluent water iron concentrations to .5 mg/l and failed to
    do so. Petitioner points to a letter it claims is direct evidence of Thrasher’s awareness that it had
    a contractual obligation or duty to the DEP and to petitioner to make the plant work. In this case,
    petitioner failed to introduce any testimony to support a breach of contract claim. This is based in
    part on the fact that the influent water flow at the time the plant operations differed so greatly
    from the parameters provided by petitioner to respondents. Therefore, the circuit court’s findings
    of fact addressed in this assignment of error were not clearly erroneous.
    III.    Design acceptance by the DEP and petitioner.
    Petitioner’s third assignment of error is that the circuit court erred by granting judgment
    to respondents because it inappropriately relied upon the acceptance of the design by petitioner
    and the DEP to dismiss claims of breach of contract and negligence. Petitioner asserts that West
    Virginia law allows petitioner to recover the costs it incurred to cure and conform the plant based
    on Thrasher’s breach of contract and/or failure to render professional services with ordinary skill,
    care, and diligence commensurate with that of professional engineers in similar circumstances.
    Respondents assert that the circuit court properly directed judgment because petitioner failed to
    establish a prima facie right of recovery and the judgment was not predicated upon the
    acceptance of the design by petitioner and the DEP. They also argue that petitioner’s and the
    DEP’s acceptance of the design proposed by respondents does not allay the circuit court’s
    finding that the prima facie burden was not met since it is not a material fact upon which the
    judgment rests. The circuit court found that petitioner accepted the work performed by
    respondents and incorporated the plans and specifications into its engineering plans delivered to
    the DEP. It also found that the DEP accepted the plans and specifications submitted by petitioner
    and authorized petitioner to proceed with the project under the submitted plans. It is undisputed
    that the facility was built according to those plans and that the plans were based on the design
    specifications provided by petitioner to respondents. Our review of the record shows that while
    the circuit court made these findings, there was ample evidence on the record to support the
    circuit court’s grant of judgment in favor of respondents without this factual finding. Therefore,
    we cannot conclude that the circuit court’s finding on this issue was clearly erroneous.
    IV.     Resolving all questions of fact as to applicable iron discharge standards in favor
    of petitioner.
    Petitioner’s fourth assignment of error also deals with what it claims is the circuit court’s
    failure to resolve all questions of fact in favor of respondent before granting judgment to
    respondents. Petitioner argues that the circuit court erred in granting judgment as to petitioner’s
    breach of contract claims by resolving all questions of fact as to the applicable iron discharge
    standard in favor of respondent, whereby conflicting evidence showed that Thrasher agreed to
    design the plant to meet the .5 mg/l discharge standard and failed to deliver the same. Petitioner
    is critical of the circuit court’s finding that a draft permit issued from the DEP authorized
    effluent discharge with limits of 3.0 mg/l iron and that that permit is consistent with the DEP’s
    self-imposed limit of 3.0 mg/l iron. Petitioner contends that the same is irrelevant because
    Thrasher agreed to a standard of .5 mg/l iron. However, petitioner’s argument ignores the
    undisputed fact that petitioner provided the design parameters to respondents and respondents
    5
    designed the water treatment system according to those parameters. See Parkette, Inc. v. Micro
    Outdoors Adver., LLC, 217 W.Va. 151, 
    617 S.E.2d 501
     (2005). Under the facts of this case, we
    cannot find that the circuit court’s finding on this issue meet the standard of being clearly
    erroneous.
    V.       The water treatment plant’s ability to meet the effluent discharge standard set
    forth in the contract between the DEP and petitioner.
    The fifth assignment of error is that the circuit court erred by granting judgment finding
    that there was no evidence introduced by petitioner to establish with reasonable certainty when,
    if ever, the redesigned and reconstructed plant would meet the effluent discharge standard set by
    the contract and accepted by the DEP. Petitioner argues that the circuit court improperly resolved
    questions of fact created by testimony, concluding that the DEP would not have enough water to
    operate the plant at its maximum capacity. Petitioner criticizes the circuit court’s conclusion that
    the plant did not meet the .5 goal during operation when, petitioner contends, evidence was
    introduced that showed the plant operated and met the effluent discharge goals at flow levels less
    than anticipated. It also argues that sufficient evidence was presented to permit a reasonable jury
    to decide whether the modifications were reasonable and effective and whether the plant would
    meet the effluent discharge goals. However, the evidence in the record shows that the redesigned
    and modified plant did not meet the .5 mg/l goal at the design flow rate and was not accepted by
    the DEP. The record also shows that the DEP representative and petitioner’s representative,
    Robert Simm, concede that the redesigned and modified plant has not operated at 1,000 gallons
    per minute and that it is unknown whether the plant will achieve the desired goal of .5 mg/l for a
    sustained length of time. Based on the testimony at trial and the concessions by the witnesses, we
    cannot find that the circuit court’s finding of fact regarding the plant meeting the effluent
    discharge standard of .5 mg/l iron will be met is clearly erroneous.
    VI.      Resolving questions of fact as to the reasonable necessity of the changes made by
    petitioner.
    Petitioner’s sixth and final assignment of error is that the circuit court erred by granting
    judgment because it improperly resolved questions of fact as to the reasonable necessity of the
    changes made by petitioner when faced with competing evidence of alternate means to cure the
    plant, the effectiveness of those changes, or that the conduct of respondents caused petitioner to
    incur costs and expenses to remedy the defects in Thrasher’s design of the plant. Petitioner
    contends that evidence was presented showing how Thrasher’s design of the plant would not
    meet the .5 mg/l standard and that modifications were necessary, reasonable, and effective in
    getting the plant to meet that standard at varying flow rates. Petitioner argues that this was
    sufficient to establish a prima facie claim that respondents’ actions or inactions were the
    proximate cause of the injuries asserted by petitioner, that the costs incurred by petitioner to
    redesign and reconstruct the facility were reasonable and necessary, and that petitioner made a
    prima facie showing that respondents breached their contract with petitioner.
    “Compensatory damages recoverable by an injured party incurred through the
    breach of a contractual obligation are those as may fairly and reasonably be
    considered as arising naturally - that is, according to the usual course of things -
    6
    from the breach of the contract itself, or such as may reasonably be supposed to
    have been in the contemplation of both parties at the time they made the contract,
    as the probable result of its breach.” Syllabus Point 2, Kentucky Fried Chicken of
    Morgantown, Inc. v. Sellaro, 158 W.Va. 708, 
    214 S.E.2d 823
     (1975).
    Syl. Pt. 1, Desco Corp. v. Harry W. Trushel Const. Co., 186 W.Va. 430, 
    413 S.E.2d 85
     (1991).
    In order to recover a second category of damages, consequential damages, a plaintiff must show
    that at the time of the contract the parties could have reasonably anticipated that these damages
    would be a probable result of a breach. Id. at 434, 413 S.E.2d at 89. Petitioner does not allege
    that the parties could have reasonably anticipated that the alleged damages would be a probable
    result of a breach. Further, petitioner failed to present evidence to support its claim for
    compensatory damages, as petitioner failed to present sufficient evidence as to the reasonable
    necessity of the redesign of the plant necessary to allow a jury to address this issue. For these
    reasons, we again find that the circuit court’s factual findings on this issue were not clearly
    erroneous.
    As set forth above, this Court considers the evidence before it in the light most favorable
    to petitioner, the nonmoving party, and will sustain the granting of a judgment as a matter of law
    when only one reasonable conclusion as to the verdict can be reached. Syl. Pt. 3, Brannon v.
    Riffle, 197 W.Va. 97, 
    475 S.E.2d 97
     (1996). Syl. Pt. 5, First Cmty. Bancshares, Inc., at 812, 575
    S.E.2d at 421. In this case, petitioner provided certain parameters to defendants to be used in the
    design of the water treatment plant. One of those parameters was an influent iron level of 15
    mg/l. However, the record shows that the influent iron levels at the time of operation are
    substantially lower than the levels provided by petitioner to respondents at the time of the
    agreement, approximately 6.25 to 8.49 mg/l. The evidence also shows that after treatment, prior
    to the redesign, the iron levels in the influent water met the legal standards set by the DEP. The
    expert testimony introduced by plaintiff failed to establish prima facie negligence or breach of
    contract. Therefore, considering the evidence in the light most favorable to petitioner, we find
    that the only reasonable conclusion as to the verdict is that respondents are entitled to judgment.
    For the foregoing reasons, we affirm.
    Affirmed.
    ISSUED: October 18, 2013
    CONCURRED IN BY:
    Justice Robin Jean Davis
    Justice Menis E. Ketchum
    Justice Allen H. Loughry II
    DISSENTING:
    Chief Justice Brent D. Benjamin
    Justice Margaret L. Workman
    7