Astar Abatement, Inc. v. Marshall University Board of Governors/Stephanie Smith ( 2013 )


Menu:
  •                             STATE OF WEST VIRGINIA
    SUPREME COURT OF APPEALS
    Astar Abatement, Inc.,                                                            FILED
    May 17, 2013
    Petitioner Below, Petitioner                                                RORY L. PERRY II, CLERK
    SUPREME COURT OF APPEALS
    vs) No. 12-0135 (Cabell County 11-C-264)                                      OF WEST VIRGINIA
    Marshall University Board of Governors
    and Stephanie Smith, Director of Purchasing,
    Respondents Below, Respondents
    MEMORANDUM DECISION
    Petitioner Astar Abatement, Inc. (“Astar”), by counsel Charles M. Johnstone, II and
    Sarah A. Stewart, appeals the Circuit Court of Cabell County’s “Final Order,” entered December
    28, 2011, that denied Astar’s petition for a writ of mandamus against respondents, the Marshall
    University Board of Governors and Stephanie Smith, Director of Purchasing (together denoted
    “MU”), for their alleged failure to find Astar to be the lowest responsible and responsive bidder
    for a contract to provide asbestos abatement and demolition services at Marshall University. MU,
    by counsel Jendonnae Houdyschell, filed a response in support of the circuit court’s order. Astar
    filed a reply.
    This Court has considered the parties= briefs and the record on appeal. The facts and legal
    arguments are adequately presented, and the decisional process would not be significantly aided
    by oral argument. Upon consideration of the standard of review, the briefs, and the record
    presented, the Court finds no substantial question of law and no prejudicial error. For these
    reasons, a memorandum decision is appropriate under Rule 21 of the Rules of Appellate
    Procedure.
    On November 29, 2010, respondents issued a “Request for Bids” (“RFB”) for an open-
    ended “Asbestos Abatement Contract MU” (“contract”) worth more than $25,000. The RFB
    stated that MU sought “to establish an open-ended contract for on-call service, to be used on an
    as-needed basis, to remove and/or encapsulate Asbestos Containing Materials and to provide
    building/structural component demolition.” The contract was for a period of one year, with the
    option to extend for up to five years.
    The RFB required bidders to submit unit prices for 302 bid items within twenty-seven
    categories. The RFB apprised bidders that MU would evaluate the bids based on “unit price.”
    Both Astar and Master Mechanical Insulation, Inc. (“MMI”)1 timely submitted their bids in
    December of 2010. Astar claims that it submitted the lowest unit price bid for 205 of the 302
    1
    Astar contends that MMI ceased to exist on December 22, 2010, and, from that date forward,
    became Atlantic Plant Services, Inc. and/or Burmeck Industries, Inc.
    1
    required items and had a total unit price bid of $4,092.54. Astar claims that MMI had the lowest
    unit price on 97 of the 302 items and had a total unit price bid of $7,039.29.
    MU states that its RFBs are governed by West Virginia Code §§ 18B-5-3 to -7 and its
    purchasing policy, Policy No. FA-9. MU adds that it follows the guidelines found in the West
    Virginia Higher Education Policy Commission’s Purchasing Procedures Manual, although it is
    not required to do so.
    MU evaluated the bids two ways: first, by evaluating the unit-prices within categories;
    and second, by applying the unit prices to nine scenarios that represented actual, past MU
    projects. Six of the nine scenarios involved asbestos remediation; the remaining three involved
    demolition. Respondent Stephanie Smith and Brian Carrico, Marshall University’s Director of
    Health and Safety, found MMI to be the lowest responsible and responsive bidder. On January 7,
    2011, MU notified all bidders it was recommending that MMI be awarded the contract.
    Astar filed a protest on January 14, 2011. At a February 1, 2011, meeting on Astar’s
    protest, Astar was told that the award to MMI would be upheld and that 75% of the work under
    the contract would be demolition-related.
    On February 4, 2011, Astar notified MU that it would continue to protest the award.
    Thereafter, Astar made a “Request for Appeal and Hearing.” A formal reconsideration hearing
    was held on March 29, 2011. Thereafter, Karen Kirtley, Marshall University’s Senior Vice-
    President of Finance and Administration, advised Astar that she was upholding the decision to
    award the contract to MMI.
    On April 19 or 20, 2011, MU awarded the open-ended contract to MMI. On April 21,
    2011, MU notified all bidders of the award.
    Astar filed its “Verified Petition For Writ Of Mandamus and Injunctive Relief” in the
    circuit court on April 27, 2011. Following a May 2, 2011, hearing, the circuit court denied
    Astar’s motion for injunctive relief but issued a rule to show cause against MU. Thereafter, two
    hearings were held on the matter.
    On December 28, 2011, the circuit court ruled that a writ of mandamus should not issue
    because (1) Astar had failed to prove the elements required for the writ and (2) had not met its
    burden of showing “fraud, collusion, or such an abuse of discretion that it is shocking to the
    conscience” in MU’s award of the contract to MMI pursuant to Syllabus Point 3 of State ex rel.
    E. D. S. Fed. Corp. v. Ginsberg, 
    163 W.Va. 647
    , 
    259 S.E.2d 618
     (1979).
    On appeal, Astar argues that the circuit court erred in denying its petition for a writ of
    mandamus.
    “Mandamus is a proper remedy to compel tribunals and officers exercising
    discretionary and judicial powers to act, when they refuse so to do, in violation of
    their duty, but it is never employed to prescribe in what manner they shall act, or
    2
    to correct errors they have made.” Syllabus Point 1, State ex rel. Buxton v.
    O'Brien, 
    97 W.Va. 343
    , 
    125 S.E. 154
     (1924).
    Syl. Pt. 6, State ex rel. Affiliated Const. Trades Found. v. Vieweg, 
    205 W.Va. 687
    , 
    520 S.E.2d 854
     (1999).
    “‘A writ of mandamus will not issue unless three elements coexist—(1) a clear
    legal right in the petitioner to the relief sought; (2) a legal duty on the part of
    respondent to do the thing which the petitioner seeks to compel; and (3) the
    absence of another adequate remedy.’ Syllabus Point 1, State ex rel. Billy Ray C.
    v. Skaff, 
    190 W.Va. 504
    , 
    438 S.E.2d 847
     (1993); Syllabus Point 2, State ex rel.
    Kucera v. City of Wheeling, 
    153 W.Va. 538
    , 
    170 S.E.2d 367
     (1969).” Syllabus
    point 2, Staten v. Dean, 
    195 W.Va. 57
    , 
    464 S.E.2d 576
     (1995).
    Syl. Pt. 2, Ewing v. Bd. of Educ. of Cnty. of Summers, 
    202 W.Va. 228
    , 
    503 S.E.2d 541
     (1998).
    Pursuant to Ewing, Astar argues that (1) it had a clear legal right to be awarded the
    contract because it was the lowest responsible and responsive bidder; (2) MU had a legal duty to
    award the contract to Astar; and (3) a writ of mandamus requiring MU to award the contract to
    Astar is the only adequate legal remedy for the damages Astar sustained as a result of MU’s
    failure to award Astar the contract.
    “A de novo standard of review applies to a circuit court’s decision to grant or deny a writ
    of mandamus.” Syl. Pt. 1, Harrison Cnty. Comm'n v. Harrison Cnty. Assessor, 
    222 W.Va. 25
    ,
    
    658 S.E.2d 555
     (2008). We review a circuit court’s underlying factual findings and conclusions
    of law in a mandamus case under a clearly erroneous standard. O’Daniels v. City of Charleston,
    
    200 W.Va. 711
    , 715, 
    490 S.E.2d 800
    , 804 (1997) (citing Staten v. Dean, 
    195 W.Va. 57
    , 62, 
    464 S.E.2d 576
    , 581 (1995)).
    Our review of the record reflects no clear error by the circuit court in denying petitioner’s
    motion for a writ of mandamus. The circuit court reviewed MU’s bid evaluation process, the
    reasons MU used that particular bid process, and the results of the process, and correctly
    determined that Astar had failed to meet the Ewing standard for the issuance of a writ of
    mandamus. Having reviewed the circuit court’s “Final Order” entered on December 28, 2011, we
    hereby adopt and incorporate the circuit court’s well-reasoned findings and conclusions as to the
    assignments of error raised in this appeal. The Clerk is directed to attach a copy of the circuit
    court’s order to this memorandum decision.
    For the foregoing reasons, we affirm the circuit court’s order.
    Affirmed.
    3
    ISSUED: May 17, 2013
    CONCURRED IN BY:
    Justice Margaret L. Workman
    Justice Menis E. Ketchum
    Justice Allen H. Loughry II
    DISSENTING:
    Chief Justice Brent D. Benjamin
    Justice Robin Jean Davis
    4