Gulfport Energy Corp. v. Harbert Private Equity Partners, LP ( 2020 )


Menu:
  •          IN THE SUPREME COURT OF APPEALS OF WEST VIRGINIA
    September 2020 Term
    _______________                          FILED
    November 18, 2020
    No. 19-0510                            released at 3:00 p.m.
    EDYTHE NASH GAISER, CLERK
    SUPREME COURT OF APPEALS
    _______________                            OF WEST VIRGINIA
    GULFPORT ENERGY CORPORATION
    Defendant Below, Petitioner
    v.
    HARBERT PRIVATE EQUITY PARTNERS, LP,
    Plaintiff Below, Respondent
    ____________________________________________________________
    Appeal from the Circuit Court of Wood County
    The Honorable Jason A. Wharton, Judge
    Civil Action No. 17-C-65
    REVERSED AND REMANDED
    ____________________________________________________________
    Submitted: October 27, 2020
    Filed: November 18, 2020
    J. Kevin West, Esq.                            Robert L. Bays, Esq.
    Steptoe & Johnson PLLC                         Bowles Rice LLP
    Columbus, Ohio                                 Parkersburg, West Virginia
    Melanie Morgan Norris, Esq.                    Counsel for Respondent Harbert Private
    Steptoe & Johnson PLLC                         Equity Partners, LP
    Wheeling, West Virginia
    Counsel for Petitioner Gulfport Energy
    Corporation
    CHIEF JUSTICE ARMSTEAD delivered the Opinion of the Court.
    SYLLABUS BY THE COURT
    1.    “In reviewing challenges to the findings and conclusions of the circuit
    court made after a bench trial, a two-pronged deferential standard of review is applied. The
    final order and the ultimate disposition are reviewed under an abuse of discretion standard,
    and the circuit court’s underlying factual findings are reviewed under a clearly erroneous
    standard. Questions of law are subject to a de novo review.” Syl. Pt. 1, Pub. Citizen, Inc.
    v. First Nat. Bank in Fairmont, 
    198 W. Va. 329
    , 
    480 S.E.2d 538
    (1996).
    2.    The existence of a valid and enforceable written contract governing a
    particular subject matter ordinarily precludes recovery in quasi contract for events arising
    out of the same subject matter.
    3.    As a species of quasi contract relief, unjust enrichment does not exist
    to provide an alternative means of recovery for breach of contract, nor does it exist to
    reduce contract disputes to a question of whether one party benefitted from the other party’s
    performance.
    i
    Armstead, Chief Justice:
    In 2012, Gulfport Energy Corporation (“Gulfport”) entered into a contract
    whereby Central Environmental Services, LLC, (“CES”) 1 agreed to provide transportation,
    waste disposal, and other services at Gulfport’s wells. When this business relationship
    ended in 2015, some of CES’s invoices remained unpaid. CES sued Gulfport in the Circuit
    Court of Wood County, alleging that Gulfport breached the contract and was unjustly
    enriched by CES’s performance. After a bench trial, the circuit court awarded CES
    $144,037.75, and Gulfport filed this appeal. Gulfport argues that the circuit court erred by
    awarding damages for unjust enrichment when the unpaid invoices were for services
    provided under the parties’ contract.
    Because we agree that a court may not award damages based on both unjust
    enrichment and breach of contract where such theories of recovery arise from the same set
    of facts, we reverse the circuit court and remand this case to the circuit court for further
    action in accordance with this opinion.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    Gulfport is an oil and gas producer with operations in West Virginia. On
    May 21, 2012, Gulfport entered into a Master Service Agreement (“MSA”) with CES. At
    the time, CES provided an array of transportation, waste disposal, and other environmental
    services. Under the parties’ arrangement, Gulfport would request certain services, and
    1
    After Gulfport filed this appeal, Harbert Private Equity Partners, LP,
    advised the Court that it had acquired CES and requested to be substituted as the respondent
    in this matter.
    1
    CES would provide them.       Afterward, CES would submit an invoice for payment.
    According to the MSA, invoices were to be submitted “as [w]ork is completed” (unless
    Gulfport approved a different arrangement) and were required to show “appropriate
    approvals of [Gulfport] personnel[.]”
    When the parties ceased doing business together in 2015, a substantial
    number of invoices remained unpaid. The parties attempted to resolve their differences
    and, as a result of these efforts, Gulfport paid CES approximately $100,000 for disputed
    invoices that it found were substantiated. Nevertheless, some disputed invoices remained,
    and in 2017, CES sued Gulfport for breach of contract. CES later amended its complaint
    to add a cause of action for unjust enrichment. Both causes of action were based on the
    same alleged injury: Gulfport’s failure to pay invoices valued at $191,287.15. None of
    these invoices, however, reflected approval by Gulfport personnel.
    After discovery, the circuit court conducted a one-day bench trial. CES
    offered testimony from Jeff Harper, its chief executive officer. Regarding the missing
    Gulfport approvals, Mr. Harper explained that the parties worked around the clock and that
    Gulfport employees who requested services were not always available to sign or stamp
    invoices when CES sought approval. According to Mr. Harper, sometimes the employees
    were not on shift and at other times they had left the company. Mr. Harper said that
    Gulfport employees were reluctant to sign for services that someone else had requested.
    He also testified that CES made additional efforts to obtain the appropriate approvals from
    Gulfport, and he believed that Gulfport paid at least some unsigned invoices.
    2
    Mr. Harper’s testimony also addressed Gulfport’s claim that the disputed
    invoices were “stale” as untimely submitted under the terms of the MSA. Though he did
    not separately address each invoice, he testified that in the normal course of CES business,
    invoices were generated soon after services were rendered.           On cross-examination,
    however, he conceded that he had no documentary evidence to establish when the invoices
    were submitted to Gulfport.
    When CES rested its case, Gulfport moved for judgment as a matter of law
    under Rule 52(c) of the West Virginia Rules of Civil Procedure. 2 The circuit court found
    that there was sufficient evidence to go forward with the trial and denied the motion.
    In its case in chief, Gulfport offered two witnesses, Elaina Moscato, its
    drilling engineer technician, and Roger Wilson, its billing and operations manager. Ms.
    Moscato testified that she and others had spent “upwards of 60” hours going over CES’s
    invoices and other evidence and, setting aside problems of timeliness and missing
    2
    West Virginia Rule of Civil Procedure 52(c) [1998] provides that:
    [i]f during a trial without a jury a party has been fully
    heard on an issue and the court finds against the party on that
    issue, the court may enter judgment as a matter of law against
    that party with respect to a claim or defense that cannot under
    the controlling law be maintained or defeated without a
    favorable finding on that issue, or the court may decline to
    render any judgment until the close of all the evidence. Such a
    judgment shall be supported by findings of fact and
    conclusions of law as required by subdivision (a) of this rule.
    3
    signatures, could only validate invoices worth approximately $33,000. 3 She claimed that
    a relevant Gulfport employee, which she referred to as a “company man,” 4 was always
    onsite and always available and that a CES driver could contact the guard shack or someone
    at Gulfport’s office if he could not find a company man. She also claimed that CES
    representatives attended meetings where invoice policies were explained to them. Mr.
    Wilson testified that the disputed invoices were untimely. He also testified that Gulfport
    company men had authority to refuse approval in certain circumstances.
    During trial, CES conceded that it had no documents to support disputed
    invoices for $39,042.90 and that one invoice for $5,692.00 was incorrect. The circuit court
    subsequently determined that some invoices charged for equipment and materials that were
    not reimbursable under the MSA. The circuit court deducted $2,514.50 for those charges
    and, finding liability, awarded CES judgment for $144,037.75.
    The circuit court memorialized its findings of fact and conclusions of law in
    a trial order that quotes the MSA at length and applies its provisions. However, the trial
    order does not find or conclude that Gulfport breached the MSA. Instead, the order finds
    “that the work set forth in the invoices . . . was provided for the benefit of Gulfport Energy”
    and cites Realmark Developments, Inc. v. Ranson, 
    208 W. Va. 717
    , 
    542 S.E.2d 880
    (2000)
    (per curiam), for the proposition that “[u]nder the law of unjust enrichment, if benefits have
    3
    These invoices were in addition to the invoices worth approximately
    $100,000 that were validated and paid before litigation.
    4
    Ms. Moscato testified that a “company man” is a “consultant” who works
    for Gulfport at a Gulfport drilling site.
    4
    been received and retained under such circumstances that it would be inequitable and
    unconscionable to permit the party receiving them to avoid payment therefor[], the law
    requires the party receiving the benefits to pay their reasonable value.” 5
    Gulfport appeals from the circuit court’s May 1, 2019 trial order.
    II. STANDARD OF REVIEW
    In this appeal, we review a circuit court order that was entered following a
    bench trial.
    In reviewing challenges to the findings and conclusions
    of the circuit court made after a bench trial, a two-pronged
    deferential standard of review is applied. The final order and
    the ultimate disposition are reviewed under an abuse of
    discretion standard, and the circuit court’s underlying factual
    findings are reviewed under a clearly erroneous standard.
    Questions of law are subject to a de novo review.
    5
    Specifically, the Realmark court explained:
    The law of unjust enrichment indicates that if one person
    improves the land of another either through the direction of
    services to the land, or through the affixation of chattels to the
    land, that person is entitled to restitution for the improvements
    if certain other circumstances are present. The Court has also
    indicated that if benefits have been received and retained under
    such circumstance that it would be inequitable and
    unconscionable to permit the party receiving them to avoid
    payment therefor, the law requires the party receiving the
    benefits to pay their reasonable 
    value. 208 W. Va. at 721
    –22, 542 S.E.2d at 884–85 (citation and footnote omitted).
    5
    Syl. Pt. 1, Pub. Citizen, Inc. v. First Nat. Bank in Fairmont, 
    198 W. Va. 329
    , 
    480 S.E.2d 538
    (1996). With this standard of review in mind, we will proceed to consider Gulfport’s
    assignments of error.
    III. ANALYSIS
    In this appeal, Gulfport raises five assignments of error. Gulfport contends
    that the circuit court erred (1) by awarding judgment based on unjust enrichment, (2) by
    basing its decision on Realmark, 
    208 W. Va. 717
    , 
    542 S.E.2d 880
    , (3) by denying
    Gulfport’s motion for judgment as a matter of law, (4) by applying West Virginia law, and
    (5) by failing to balance the equities when it awarded equitable relief. We will combine
    the first two assignments of error and address them together.
    A. Unjust Enrichment
    Gulfport contends that the circuit court erred by awarding damages based on
    unjust enrichment. As Gulfport observes, the amended complaint in this matter sets forth
    two causes of action, breach of contract and unjust enrichment. Gulfport argues that these
    causes of action are incompatible because “[t]he subject matter of CES’[s] claim against
    Gulfport—namely submission and payment of invoices for roll-off and transportation
    services allegedly provided to Gulfport—falls precisely within the scope of the MSA.”
    According to Gulfport, the “law preclude[s] . . . recovery under a theory of unjust
    enrichment where an express contract exists[.]”
    CES responds that the circuit court actually awarded damages for breach of
    contract. According to CES, the circuit court assessed the breach of contract claim and,
    6
    after rejecting Gulfport’s defense that the invoices were not signed, awarded judgment to
    CES based on a determination that Gulfport “failed to perform its contractual
    obligations[.]” Unjust enrichment—according to CES—was merely an alternative basis
    for awarding judgment: “The court noted in its opinion that it believed . . . that unjust
    enrichment would, if applied, support the recovery.” (Emphasis added.) Gulfport also
    contends that, “[b]ecause both parties alleged a breach of contract, Judge Wharton could
    have found the contract to be unenforceable, which would have . . . allowed CES to recover
    under quantum meruit.” (Emphasis added.)
    Having reviewed the circuit court’s trial order, we find that CES is mistaken.
    First, the circuit court did not find that the MSA was unenforceable; on the contrary, it
    found that CES provided services “pursuant to the terms of” the MSA and quoted the MSA
    at length. In addition, the circuit court did not find that Gulfport breached the MSA, nor
    did it rule on Gulfport’s defense that the invoices were not signed. The word “breach”
    never appears in the circuit court’s order, nor does the word “violate” or “violation,” except
    in reference to costs that CES improperly billed to Gulfport. The circuit court did find that
    Gulfport employees “were somewhat transitory in nature and could not always be found
    for the approvals required by” the MSA. However, this is not the same thing as finding
    that CES could not obtain necessary approvals or the same thing as concluding that
    7
    Gulfport breached the MSA by preventing CES from performing this aspect of its duties. 6
    Finally, the circuit court’s order appears to say that it was granting judgment based, in part,
    on unjust enrichment. In each instance where the circuit court awarded money based on
    disputed invoices, it justified this result with an express finding that the work reflected in
    the invoices was done “for the benefit of Gulfport.” The circuit court repeated this
    conclusion at the end of the trial order, immediately before it invoked Realmark and its
    rule that unjustly enriched parties must pay “reasonable value” for benefits received. The
    circuit court concluded that “the reasonable value of the services was $144,037.75.”
    6
    As noted above, Gulfport contends that the circuit court should have granted
    judgment as a matter of law. In support of this claim, Gulfport asserts that Mr. Harper
    admitted that the disputed invoices did not reflect Gulfport approval and that approvals
    could be obtained at Gulfport’s office. When a circuit court grants or denies a motion for
    judgment as a matter of law, we view “the evidence in the light most favorable to the
    nonmovant party[.]” Syl. Pt. 1, in part, Waddy v. Riggleman, 
    216 W. Va. 250
    , 
    606 S.E.2d 222
    (2004). We refuse to sustain an order granting judgment as a matter of law unless
    “only one reasonable conclusion as to the verdict can be reached.”
    Id. Mr. Harper explained
    that the relevant Gulfport employees were sometimes unavailable or reluctant to
    sign for services that other Gulfport employees had requested. He also testified that CES
    made additional efforts to obtain the appropriate approvals from Gulfport and that he
    believed that Gulfport paid at least some unsigned invoices. Viewing Mr. Harper’s
    testimony in the light most favorable to CES, we find that this testimony could suggest that
    Gulfport’s employees prevented CES from satisfying a necessary contingency for payment
    under the MSA or that Gulfport and CES modified the terms of the MSA by their course
    of conduct. We have held that “[a] party to a contract is not discharged by a breach,
    occasioned by its own failure of duty.” Ashland Coal & Coke Co. v. Hull Coal & Coke
    Corp., 
    67 W. Va. 503
    , 516, 
    68 S.E. 124
    , 129 (1910). We have also held that
    “[m]odification of a contract may be implied from a subsequent agreement or the conduct
    of the parties.” Syl. Pt., Azure v. Hunter, 
    101 W. Va. 191
    , 
    132 S.E. 726
    (1926). Though
    we do not decide whether CES has proved these defenses to Gulfport’s motion, we do find
    that “reasonable minds could differ as to the importance and sufficiency of” Mr. Harper’s
    testimony. 
    Waddy, 216 W. Va. at 252
    , 606 S.E.2d at 224, syl. pt. 1, in part. Accordingly,
    we find that the circuit court did not err when it refused to grant Gulfport’s motion for
    judgment as a matter of law.
    8
    Because it appears that the circuit court awarded judgment based, at least in
    part, on unjust enrichment where the litigants were parties to an express contract, we
    conclude that the circuit court’s order must be reversed. We have held that “an unjust
    enrichment claim is inconsistent with a contractual dispute.” Hanlon v. AXA Equitable Life
    Ins. Co., No. 15-0337, 
    2016 WL 2968990
    , at *3 (W. Va. May 20, 2016) (memorandum
    decision). Indeed, the law is clear that “[t]he existence of an express contract covering the
    same subject matter of the parties’ dispute precludes a claim for unjust enrichment.” CGI
    Fed. Inc. v. FCi Fed., Inc., 
    295 Va. 506
    , 519, 
    814 S.E.2d 183
    , 190 (2018); accord Clark-
    Fitzpatrick, Inc. v. Long Is. R.R. Co., 
    70 N.Y.2d 382
    , 388, 
    516 N.E.2d 190
    , 193 (1987)
    (“The existence of a valid and enforceable written contract governing a particular subject
    matter ordinarily precludes recovery in quasi contract for events arising out of the same
    subject matter[.]”); Syl. Pt. 4, Ullmann v. May, 
    147 Ohio St. 468
    , 
    72 N.E.2d 63
    (1947) (“In
    the absence of fraud or bad faith, a person is not entitled to compensation on the ground of
    unjust enrichment if he received from the other that which it was agreed between them the
    other should give in return.”); Am. Biomedical Grp., Inc. v. Techtrol, Inc., 
    2016 OK 55
    , ¶
    27, 
    374 P.3d 820
    , 828 (“[A] party is not entitled to pursue a claim for unjust enrichment
    when it has an adequate remedy at law for breach of contract.”); 7 Knight Renovations, LLC
    7
    As noted above, Gulfport also contends, based on a choice-of-law provision
    contained in the MSA, that the circuit court erred by failing to apply Oklahoma law to the
    parties’ dispute. However, Gulfport did not raise this objection before the circuit court,
    and we refuse to consider it for the first time on appeal. Barney v. Auvil, 
    195 W. Va. 733
    ,
    741, 
    466 S.E.2d 801
    , 809 (1995) (“Our general rule is that nonjurisdictional questions not
    raised at the circuit court level, but raised for the first time on appeal, will not be
    considered.”).
    9
    v. Thomas, 
    525 S.W.3d 446
    , 454 (Tex. App. 2017) (“An action for quantum meruit
    generally cannot be brought when an express contract covers the materials or services
    provided.”). This rule flows from the very nature of unjust enrichment claims, which can
    “only exist in the absence of an agreement.” Ohio Valley Health Servs. & Educ. Corp. v.
    Riley, 
    149 F. Supp. 3d 709
    , 721 (N.D.W. Va. 2015). As the Supreme Court of Pennsylvania
    explained in Wilson Area School District v. Skepton, “parties in contractual privity . . . are
    not entitled to the remedies available under a judicially-imposed quasi[-]contract [i.e., the
    parties are not entitled to restitution based upon the doctrine of unjust enrichment] because
    the terms of their agreement (express and implied) define their respective rights, duties,
    and expectations.” 
    586 Pa. 513
    , 521, 
    895 A.2d 1250
    , 1254 (2006) (quoting Curley v.
    Allstate Ins. Co., 
    289 F. Supp. 2d 614
    , 620-21 (E.D.Pa.2003) (material in brackets inserted
    by the Wilson Area court). In light of this clear authority, we now hold that the existence
    of a valid and enforceable written contract governing a particular subject matter ordinarily
    precludes recovery in quasi contract for events arising out of the same subject matter. 8
    8
    We recognize that “[a] party claiming an alternative right of recovery may
    assert and prosecute both claims in the same action, leaving it to the court and jury to
    determine which he is entitled to, if either, and proof of one of them constitutes no
    abandonment of the other.” Cochran v. Craig, 
    88 W. Va. 281
    , 
    106 S.E. 633
    , syl. pt. 5; see,
    e.g., Missigman v. USI Ne., Inc., 
    131 F. Supp. 2d 495
    , 513–14 (S.D.N.Y. 2001) (“Where
    the complaint asserts claims on theories of both contract and quantum meruit and there is
    a genuine dispute as to the existence of a contract, the plaintiff need not make a pretrial
    election between these theories; he is entitled to have the case submitted on both theories.”)
    But a plaintiff cannot recover damages under both theories.
    10
    Returning to the facts of this case, we find that the substance of CES’s unjust
    enrichment claim falls squarely within the subject matter of the MSA. Both theories of
    recovery asserted by CES arise from Gulfport’s failure to pay for services rendered under
    the MSA, and based on the circuit court’s order, payment for these services was the only
    relief considered by the court and the only relief that it granted. 9           Under these
    circumstances, the MSA established the parties’ rights and duties and provides an adequate
    remedy at law for breach of contract. We additionally hold that, as a species of quasi
    contract relief, unjust enrichment does not exist to provide an alternative means of recovery
    for breach of contract, nor does it exist to reduce contract disputes to a question of whether
    one party benefitted from the other party’s performance. Accordingly, we find that CES’s
    unjust enrichment claim was entirely eclipsed by its claim for breach of contract, and no
    award of unjust enrichment damages was possible.
    Our decision in Realmark, 
    208 W. Va. 717
    , 
    542 S.E.2d 880
    , does not compel
    a different conclusion. In Realmark, the parties entered into a written lease agreement that
    provided an option to purchase.
    Id. at 719, 542
    S.E.2d at 882. The tenants made substantial
    improvements to the property, but they failed to provide written notice to the landlord that
    they wished to exercise their option.
    Id. After the term
    ended and the tenants eventually
    surrendered the property, the landlord sold the property and sued the tenants for unpaid
    9
    The amount that the circuit court awarded ($144,037.75) plus the amounts
    that the circuit court expressly refused to award ($39,042.90, $5,692.00, and $2,514.50)
    equal $191,287.15, which is the exact amount that CES requested in the amended
    complaint for both breach of contract and unjust enrichment.
    11
    rent and taxes.
    Id. The tenants counterclaimed,
    arguing that the landlord perpetrated a
    fraud on them by making an oral promise to finance their purchase of the property and then
    refusing to provide financing and selling the property for a substantial profit.
    Id. at 719- 20, 542
    S.E.2d at 882-83. The landlord denied making such a promise, and the circuit court
    granted summary judgment for the landlord.
    Id. at 720, 542
    S.E.2d at 883.
    On appeal, we reversed the circuit court and remanded the case for trial,
    noting that a mistake of law can provide a basis for restitution damages.
    Id. at 722, 542
    S.E.2d at 885. We wrote,
    In the present case, it is the Ransons’ claim that they believed
    that Realmark Developments, Inc., was legally obligated to
    assist them in financing their purchase of the property in
    question. While they may have been legally mistaken, their
    belief, if factually established, may entitle them to restitution
    under the restitution count of their amended counterclaim.
    Id. Unlike Realmark, this
    is not a case where CES claims that it was defrauded
    by Gulfport or held a mistaken belief about Gulfport’s obligations under the MSA. This is
    a straightforward dispute about whether the MSA requires Gulfport to pay CES for the
    work described in the disputed invoices. Accordingly, Realmark has no bearing on the
    parties’ dispute, and the circuit court erred when it invoked Realmark to support an award,
    based in part, on unjust enrichment. 10
    10
    Because we find that the circuit court erred by awarding damages based in
    part on unjust enrichment, we need not consider whether the circuit court also erred by
    (continued . . .)
    12
    It is evident that the circuit court based its holding, at least in part, on the
    theory of unjust enrichment and, as we have discussed above, such holding cannot stand
    when the court also makes reference to the contract between the parties. Accordingly, we
    reverse and remand this matter to the circuit court. We direct the circuit court to clarify its
    holding and make findings of fact and conclusions of law, including findings regarding the
    parties’ respective duties and right to recovery, if any, pursuant to the MSA.
    IV. CONCLUSION
    Based on the foregoing, we reverse the circuit court’s award of unjust
    enrichment damages, and we remand this case to the Circuit Court of Wood County for
    further action in accordance with this opinion.
    Reversed and Remanded.
    failing to balance the equities. Moreover, because we are reversing the circuit court’s order
    and remanding this matter for further action, we decline to address Gulfport’s remaining
    assignments of error.
    13