Appalachian Power Company and Wheeling Power Company v. Public Service Commission of West Virginia ( 2024 )


Menu:
  •          IN THE SUPREME COURT OF APPEALS OF WEST VIRGINIA
    September 2024 Term                            FILED
    _______________                     November 13, 2024
    released at 3:00 p.m.
    No. 24-75                          C. CASEY FORBES, CLERK
    SUPREME COURT OF APPEALS
    _______________                          OF WEST VIRGINIA
    APPALACHIAN POWER COMPANY and
    WHEELING POWER COMPANY,
    Petitioners,
    v.
    PUBLIC SERVICE COMMISSION
    OF WEST VIRGINIA,
    Respondent.
    ________________________________________________________
    Appeal from the Public Service Commission of West Virginia
    Case Nos. 21-0339-E-ENEC, 22-0393-E-ENEC, and 23-0377-E-ENEC
    AFFIRMED, in part; REVERSED, in part; and REMANDED
    ________________________________________________________
    Submitted: September 4, 2024
    Filed: November 13, 2024
    William C. Porth, Esq.                        Jessica M. Lane, Esq.
    Anne C. Blankenship, Esq.                     Susan M. Stewart, Esq.
    Robinson & McElwee PLLC                       Public Service Commission
    Charleston, West Virginia                     of West Virginia
    Charleston, West Virginia
    Keith D. Fisher, Esq.                         Counsel for Respondent
    American Electric Power
    Service Corporation                           Robert F. Williams, Esq.
    Charleston, West Virginia                     Heather B. Osborn, Esq.
    Charleston, West Virginia
    Elbert Lin, Esq.                              Counsel for Amicus Curiae
    Hunton Andrews Kurth LLP                      The Consumer Advocate Division of the
    Richmond, Virginia                            Public Service Commission of West
    Counsel for Petitioners                       Virginia
    Barry A. Naum, Esq.                     H. Brann Altmeyer, Esq.
    Steven W. Lee, Esq.                     Jacob C. Altmeyer, Esq.
    Spilman Thomas & Battle, PLLC           Phillips, Gardill, Kaiser,
    Mechanicsburg, Pennsylvania             & Altmeyer, PLLC
    Wheeling, West Virginia
    Susan J. Riggs, Esq.                    Counsel for Amicus Curiae
    Spilman Thomas & Battle, PLLC           The West Virginia Coal
    Charleston, West Virginia               Association, Inc.
    Counsel for Amicus Curiae
    West Virginia Energy Users Group
    JUSTICE HUTCHISON delivered the Opinion of the Court.
    SYLLABUS BY THE COURT
    1.     “‘“The principle is well established by the decisions of this Court that
    an order of the public service commission based upon its finding of facts will not be
    disturbed unless such finding is contrary to the evidence, or is without evidence to support
    it, or is arbitrary, or results from a misapplication of legal principles.” United Fuel Gas
    Company v. Public Service Commission, 
    143 W.Va. 33
    , (
    99 S.E.2d 1
    ).’ Syl. Pt. 5, Boggs
    v. Pub. Serv. Comm’n, 
    154 W.Va. 146
    , 
    174 S.E.2d 331
     (1970).” Syl. Pt. 1, Sierra Club v.
    Pub. Serv. Comm’n of W. Va., 
    241 W. Va. 600
    , 
    827 S.E.2d 224
     (2019).
    2.     “‘The detailed standard for our review of an order of the Public
    Service Commission contained in Syllabus Point 2 of Monongahela Power Co. v. Public
    Service Commission, 
    166 W.Va. 423
    , 
    276 S.E.2d 179
     (1981), may be summarized as
    follows: (1) whether the Commission exceeded its statutory jurisdiction and powers; (2)
    whether there is adequate evidence to support the Commission’s findings; and, (3) whether
    the substantive result of the Commission’s order is proper.’ Syl. Pt. 1, Cent. W.Va. Refuse,
    Inc. v. Pub. Serv. Comm’n of W.Va., 
    190 W.Va. 416
    , 
    438 S.E.2d 596
     (1993).” Syl. Pt. 2,
    Sierra Club v. Pub. Serv. Comm’n of W. Va., 
    241 W. Va. 600
    , 
    827 S.E.2d 224
     (2019).
    i
    HUTCHISON, Justice:
    In Expanded Net Energy Cost (“ENEC”) proceedings before the Public
    Service Commission of West Virginia (“Commission”), Appalachian Power Company
    (“APCo”) and Wheeling Power Company (“WPCo”) (collectively “petitioners”), public
    utilities providing electric service to West Virginia customers, sought to recover
    approximately $552.9 million in an accumulated monthly under-recovery balance for the
    period March 1, 2021, through February 28, 2023. In its January 9, 2024, order, the
    Commission disallowed recovery of approximately $231.8 million of the requested amount
    because the Commission concluded it was incurred as the result of imprudent and
    unreasonable decisions by petitioners relating to their inadequate stockpiling of coal
    necessary to fuel their respective coal-fired electric generating facilities. The lack of
    adequate fuel, the Commission found, caused petitioners to restrict self-generation during
    periods when self-generation would have been less expensive than purchasing energy
    which, in turn, required petitioners to rely on more expensive alternative purchased power.
    The Commission ordered that the remaining balance of the requested under-recovery
    (approximately $321.1 million) be assessed to consumers through an ENEC rate increment
    over a ten-year period, including a 4% carrying charge, to begin September 1, 2024.
    Upon our review of petitioners’ appeal of the Commission’s order, we affirm
    the order to the extent the Commission determined that petitioners failed to manage their
    power plant operations in a reasonable, prudent, and efficient manner during the period
    under review resulting in their failure to maintain adequate fuel supplies—specifically, as
    1
    they relate to the Commission’s ruling that petitioners acted imprudently and unreasonably,
    we affirm the order’s findings of fact, conclusions of law, and the Commission’s reasons
    therefor as stated in its order, and we adopt and incorporate by reference the order to that
    limited extent. However, we reverse the Commission’s order insofar as it disallowed
    $231.8 million of the requested under-recovery balance because the Commission’s
    calculation was based upon certain extra-record evidence of which petitioners were not
    afforded notice or an opportunity to be heard, in violation of their constitutional right to
    due process of law. Accordingly, we remand the matter for further proceedings for the
    specific and sole purpose of affording petitioners the opportunity to address that evidence
    in connection with the quantification of ENEC costs that were incurred as the result of
    1
    petitioners’ imprudent decisions during the time period under review.
    I.    Factual and Procedural Background
    Introduction
    The John Amos and Mountaineer Plants, owned and operated by APCo, and
    the Mitchell Plant, in which WPCo owns a 50% undivided interest, are coal-fired electric
    generating facilities.
    1
    The Consumer Advocate Division of the Public Service Commission of West
    Virginia, the West Virginia Energy Users Group, and the West Virginia Coal Association,
    Inc., as amici curiae, submitted briefs in this appeal and the Court has considered them in
    conjunction with the parties’ arguments.
    2
    ENEC cases are filed annually with the Commission to enable petitioners “to
    adjust rates for fuel related generation costs and certain purchased power and transmission
    related costs[;]” they are “specialized and limited rate proceeding[s]” that allow petitioners
    “to avoid filing a full base rate case to reflect changes in those cost components.”2
    ENEC rates are “based on projections of future ENEC cost elements. An
    important element of the ENEC procedure [is] an over[-] or under-recovery mechanism
    whereby companies using the ENEC procedure would defer costs that exceeded or were
    less than their ENEC revenues and request recovery of under-recoveries or rate crediting
    3
    of over-recoveries (true-up mechanism).” Normally, the Commission reviews over- or
    under-recovery balances and builds them into rates annually so that accumulated balances
    even out from year to year. However, this “true-up mechanism” “is subject to Commission
    review of the incurred costs and determination that the costs resulted from prudent actions
    on the part of the utility and were reasonable. Absent such a finding, there [is] no guarantee
    4
    that under-recoveries [will] be passed on to customers.”
    Indeed, the present matter involves petitioners’ effort to recover ENEC costs
    of $552.9 million, which reflect accumulated monthly net under-recoveries from March 1,
    2021, through February 28, 2023. Following the completion of a Commission-ordered
    2
    May 13, 2022, Commission Order, Case No. 21-0339-E-ENEC *3.
    3
    
    Id.
    4
    
    Id.
    3
    review of whether petitioners acted reasonably and prudently in incurring the requested
    ENEC costs and the holding of an evidentiary hearing, the Commission determined that
    petitioners did not act prudently and reasonably and so it disallowed the recovery of $231.8
    million of the $552.9 million under-recovery balance that petitioners requested. The
    Commission authorized a prospective recovery of the remaining $321.1 million requested
    in under-recoveries amortized over ten years beginning September 1, 2024, with a carrying
    charge of 4%.
    In disallowing the recovery of $231.8 million, the Commission determined
    that petitioners “failed to manage their fuel supplies and power plant operations in a
    reasonable, prudent, and efficient manner” during the relevant time period and that, had
    they acted prudently, they “would not have experienced the unreasonably low inventory
    levels [of coal] that they now use to excuse their inability to maximize the use of their coal-
    fired power plants.” Instead of generating energy at their own plants, petitioners purchased
    excessive “amounts of power from the PJM market5 at prices that were at the highest level
    5
    PJM Interconnection, LLC “operates a competitive wholesale electricity market
    and manages the reliability of its transmission grid. . . . In managing the grid, PJM centrally
    dispatches generation and coordinates the movement of wholesale electricity in all or part
    of” West Virginia, twelve other states, and the District of Columbia. Petitioners purchase
    energy from PJM. According to petitioners, APCo also owns and operates its own gas-
    fired electric generating facilities and hydroelectric facilities, but they also purchase power
    from various facilities (hydroelectric, wind, solar and coal-fired) under “purchased power
    agreements.”
    4
    in PJM History.”6 The Commission deemed this conduct “unreasonable and the result of
    imprudent decisions regarding coal inventories, coal procurement, bidding into the PJM
    energy market, and minimization of out-of-service time.” If petitioners had planned and
    operated their plants prudently, the Commission found, they could have reduced their
    ENEC costs in West Virginia by at least $231.8 million during the relevant time period.
    Understanding petitioners’ challenge to the Commission’s decision requires
    understanding that the 2023 ENEC filing is heavily intertwined with petitioners’ previous
    two ENEC filings (the 2021 and 2022 cases). Therefore, we generally recount below, in
    simplest terms, the Commission’s orders entered in those cases because they document the
    6
    APCo and WPCo are vertically integrated load-serving utilities with their own
    power supply. As explained in the order, in ENEC proceedings, there are references to
    “sales to” and “purchases from” PJM. For vertically integrated load-serving utilities with
    their own power supply such as petitioners,
    the term “sale” refers to self-generated power that is delivered
    from the power plants into the transmission system and is
    accounted-for as a “sale” into PJM. The term “purchase” refers
    to the load of the utility which is taken from the transmission
    system and is accounted-for as a “purchase.” In effect, the total
    net transaction of a load serving vertically integrated utility . .
    . is self-generation to serve load with an accounting performed
    by PJM. For example, if the load is 10 million Megawatt Hour
    (MWh) and the self-generation is 10 million MWh during a
    period when the PJM locational marginal price (LMP) is $40
    per MWh, although the accounting may be referred to as a $400
    million sale to PJM and a $400 million purchase from PJM, the
    net purchase from PJM would be zero and the only ENEC cost
    remaining to be paid by load would be the cost of the self-
    generation.
    5
    record and explain the Commission’s decision to order a review of the under-recoveries
    that were incurred for reasonableness and whether petitioners prudently managed their fuel
    supply and purchased power decisions.
    Case No. 21-0339-E-ENEC
    The Commission became concerned as to the cause of petitioners’ growing
    ENEC under-recovery beginning with their 2021 ENEC filing (Case No. 21-0339-E-
    ENEC), which revealed petitioners were planning to purchase large amounts of more
    expensive energy from PJM rather than maximizing generation from their own plants at a
    lower cost. Petitioners proposed to increase ENEC rates to produce an additional $73
    million in annual ENEC revenues. Of that amount, $55.4 million was for under-recovery
    7
    of fuel costs, including $32 million in deferred under-recovery collection from 2020, and
    $17.6 million in projected costs for the forecast period (September 1, 2021, through August
    31, 2022). The Commission conducted an evidentiary hearing.
    In its order entered September 2, 2021, the Commission observed that
    petitioners’ “projected ENEC costs include significant amounts of purchased power which
    7
    In Case No. 20-0262-E-ENEC (the 2020 ENEC case), petitioners requested an
    additional $82 million in annual ENEC revenues. An ENEC rate increase of approximately
    $50.1 million beginning September 1, 2020, was agreed to in recognition of the health and
    economic hardships caused by the COVID-19 pandemic. The remaining $32 million
    petitioners originally requested in that case was deferred until the 2021 ENEC case.
    6
    could be prudent if it is clear that purchased power costs will be less expensive when
    compared to generation at the West Virginia power plants.” The Commission determined
    that petitioners projected ENEC costs that included utilizing their power plants at capacity
    factors8 well below that which should be the basis for such costs but that the evidence, as
    described more fully in its September 2, 2021, order, dictated that the public interest would
    be better served by petitioners maximizing generation from their own power plants. At a
    minimum, the Commission found, petitioners should be using a capacity factor of 69% for
    their projected ENEC costs. The Commission thus adjusted (i.e., reduced) petitioners’
    projected costs to reflect less purchased power and more self-generation and approved
    ENEC rates using a capacity factor of 69%. To aid the Commission in monitoring
    petitioners’ “success at increasing generation at its power plants,” it ordered petitioners to
    file monthly reports as closed entries in the case.9
    On September 13, 2021, petitioners filed a petition for reconsideration or
    clarification of the September 2, 2021, Commission Order. The Commission granted the
    petition to the extent it corrected a miscalculation in its prior order resulting in an increase
    8
    “Capacity factor” refers to the net generation over a period compared to the
    maximum possible generation over that period.
    9
    The Commission ordered that the reports show net generation from all APCo and
    WPCo power plants by month; retail and wholesale energy load by month; purchased
    power energy purchases by month and supplier; and purchased power demand and energy
    costs by month and supplier.
    7
    in petitioners’ ENEC rates by $31.4 million.10 The Commission also reopened the case for
    petitioners to explain the significant growth in the under-recovery of ENEC costs as
    reported by petitioners to the Commission and, as explained in its March 2, 2022, order,
    “to determine what is currently happening in the PJM markets and what is happening with
    the ability of [petitioners] to utilize their coal-fired power plants.” The Commission
    reviewed with alarm the monthly filings submitted by
    [petitioners] as closed entries in this case. Those filings
    indicate that there may have been significant deflections from
    the projections regarding purchased power volumes and
    purchased power costs and a failure to use lower cost
    generation in lieu of more expensive purchased power. As a
    result, the under-recoveries booked by [petitioners] is now
    reported to be at an alarming level.11
    The Commission’s decision to reopen the 2021 ENEC proceeding was
    supported by, among other things, specific data provided by petitioners in their closed entry
    reports, including evidence that, despite the set target of a minimum 69% capacity factor
    from their West Virginia plants, “which appear to be able to produce power at costs that
    are well below the cost of purchased power, the capacity factors have not approached that
    level in September, October, and November 2021.” Petitioners submitted additional
    evidence and an evidentiary hearing was conducted to address the growing under-recovery.
    10
    The Commission declined to address petitioners’ request for clarification
    concerning the requirement that petitioners operate their coal-fired power plants at a 69%
    capacity factor.
    11
    Petitioners reported that the actual under-recovery balance had grown to $176.1
    million as of November 30, 2021.
    8
    In a Commission Order entered on May 13, 2022, Commission Staff was
    directed to conduct an in-depth prudency review of the energy costs incurred by petitioners.
    In the order, the Commission reiterated its concern
    that [petitioners] have been over-relying on PJM energy
    market purchases in lieu of planning for maximum self-
    generation through utilization of the capacity they own, and
    which customers are paying for, at the John Amos,
    Mountaineer and Mitchell power plants. [Petitioners] claim
    that they plan on running their plants when it is economical to
    do so. However, for a variety of reasons including fuel
    shortages they did not do that at the worst possible time as the
    PJM energy market prices grew to unprecedented levels
    beginning in the fall of 2021 and continued at unprecedented
    levels through the winter of 2021/2022. [Petitioners] claim that
    when the PJM market prices exploded, they attempted to
    obtain more fuel for their plant, but to no avail. However, part
    of the fuel problem faced by [petitioners] was the result of their
    decision to allow fuel inventories to decline to levels which
    were unreasonably low.
    It is clear that reliance on the PJM energy markets is
    producing unreasonable cost levels and ENEC under-
    recoveries that [petitioners] now ask West Virginia customers
    to pay. The Commission recognized the excessive cost of
    relying on the PJM energy market in September 2021 when we
    ordered [petitioners] to increase self-generation in lieu of the
    PJM market and high cost purchased power contracts. If
    [petitioners] had been able to increase self-generation and
    foregone reliance on PJM energy, then the recent spate of
    under-recoveries would have been greatly reduced or
    eliminated. Instead, we now learn that utilization of their power
    plants was limited by unreasonably low fuel supplies and an
    inability to acquire fuel supplies to accommodate the
    maximum possible capacity utilization of their power plants.
    We were not told by [petitioners] at the initial stage of
    this proceeding that they were scraping the bottom of their coal
    inventory which would make it difficult for them to use their
    power plants at maximum levels no matter how much could be
    saved by self-generation. It is clear that [petitioners’] fuel
    9
    supply planning and overreliance on market purchases are self-
    inflicted wounds.
    ....
    It is not clear to us how [petitioners] were not more
    concerned in late 2020 and 2021 that rising gas prices and other
    modifications that have been driven by PJM policy changes in
    recent years would make the benefits of low PJM market prices
    a distant memory. Instead of allowing coal inventories to
    decline precipitously, [petitioners] should have been doing
    everything possible to use their plants more and increase fuel
    inventories at the same time.
    For these reasons, and other reasons reflected in its May 13, 2022, order, the Commission
    directed Commission Staff to conduct an in-depth review of the reasonableness of
    petitioners’ net ENEC costs and petitioners’ “policies and procedures for maximizing and
    maintaining adequate fuel inventory levels [and] bidding their plants into the PJM market
    to maximize economical self-generation[.]” The Commission further “require[d] evidence
    of proper and prudent plant maintenance and availability so that the benefits of self-
    generation can be realized when the opportunities arise.”
    The Commission deferred consideration of the reported under-recovery
    balance for rate-making purposes pending receipt of the prudency review; however, it
    granted petitioners recovery of an additional $93 million for projected increased costs “to
    prevent future possible rate shock to the customers” and noted that the recovered costs
    “will be subject to future review and may be subject to disallowance if the Commission
    determines that they are unreasonable and the result of imprudent management of
    generation assets, generation costs and purchased power expenses” by petitioners.
    10
    Case No. 22-0393-E-ENEC
    On April 19, 2022, petitioners filed Case No. 22-0393-E-ENEC (“2022
    ENEC case”) requesting $297 million in ENEC revenues over and above the amount the
    Commission approved in the reopened 2021 ENEC case. By order entered February 3,
    2023, the Commission determined that reasonableness of the costs and revenues requested
    in the 2022 ENEC case “will depend on the prudence of [petitioners’] management of fuel
    supplies and purchased power decisions.” The Commission reiterated its concern relating
    to petitioners’ “historical and projected fuel and purchased power costs and continuing
    under-recoveries” and its belief that “self-generated power has been shown to be more
    economical than reliance on more expensive and less reliable purchased power.” The
    Commission also noted that it “based the projected costs underlying the current ENEC rates
    on maximizing self-generated power at [petitioners’] power plants which we determined
    should be capable of operating at a minimum 69 percent capacity factor.” As explained
    more fully in its February 3, 2023, order, the Commission stated that petitioners could most
    easily satisfy their burden of proving that they acted prudently and reasonably if they
    achieve the 69% annual capacity factor. However, the Commission cautioned that, if
    petitioners fail to achieve that minimum, then to demonstrate prudence, they would need
    to show that they (1) “maintain[ed] adequate economical fuel supplies, (2) ke[pt] plants
    available for generat[ing] the maximum amount of time, (3) maxim[ed] reduction . . . of
    outage times, . . . . and (4) effectively bid[] to clear the PJM energy market . . . .” Noting
    that it had recently granted a $93 million revenue increase, “which also [was] still subject
    11
    to a final determination based on the reasonableness of the underlying costs[,]” the
    Commission deferred a decision on the requested increase until the completion of the
    prudency review by Commission Staff.
    Case No. 23-0377-E-ENEC
    Petitioners filed Case No. 23-0377- E-ENEC (“2023 ENEC case”) on April
    28, 2023, requesting the recovery of approximately $641.7 million, including $552.9
    million in an under-recovery balance accumulated from March 1, 2021, through February
    28, 2023, (i.e., the months encompassed by the 2021, 2022, and 2023 ENEC cases) and a
    projected increase of ENEC costs in the amount of $88.8 million for the forecasted period
    12
    of September 1, 2023, through August 31, 2024.
    Also on April 28, 2023, Commission Staff filed its prudency review, entitled
    “Independent Technical Prudency Review of the Actions Affecting the Operations of
    Amos, Mountaineer, and Mitchell Coal Plants Case Nos. 22-0393-E-ENEC and 21-0339-
    E-ENEC” (“prudency report”), that was prepared by the firm Critical Technology
    Consulting (“CTC”). The Commission subsequently entered an order reopening the 2021
    and 2022 ENEC cases to hear evidence on the prudency report. The parties pre-filed
    12
    By order entered September 13, 2023, the Commission granted the requested
    $88.8 million in forecasted costs because no party challenged the methodology or
    reasonableness of the estimates and projections supporting it.
    12
    testimony and exhibits and a hearing was conducted over three days (September 5-7,
    2023).13
    In its highly detailed, thorough, and well-reasoned order, the Commission
    again observed that it was tasked with
    determin[ing] if [petitioners] prudently, efficiently, and
    reasonably used economic self-generation from their own
    power plants in lieu of higher cost net PJM power. In order to
    determine if excessive costs were incurred because of
    [petitioners’] decisions and actions that left them with
    insufficient supplies of coal for economical self-generation, it
    is also critical for the Commission to consider whether
    [petitioners] used the minimum amount of high-priced PJM
    energy market electricity over the period of review or whether
    the net power supplied through PJM transactions in lieu of self-
    generation was excessive.
    The Commission found that, despite petitioners’ past assurances that “their coal-fired
    plants are valuable assets that provide a physical hedge against high and volatile PJM
    energy prices,” petitioners, nonetheless, failed to “prudently maintain adequate fuel
    supplies and manage operations of their . . . plants” to provide that physical hedge. Noting
    “a clear decline in coal stockpiles from the end of 2020 to mid-2021” and specific increases
    in the PJM market prices over that same period, the Commission determined that
    petitioners “did not react prudently to the warning signals they were receiving.” As noted
    by the Commission, the prudency report found that petitioners’
    plants were dispatched by PJM at an aggregate 32.5 percent per
    year. CTC found that [petitioners’] coal plants are in good
    13
    The hearing on the prudency report was conducted immediately prior to the
    evidentiary hearing on the 2023 ENEC case.
    13
    condition and capable of dispatch. CTC found, however, that
    over the ten-year period prior to the report being filed with the
    Commission, [petitioners] placed an overreliance on net power
    supply from the PJM market and significantly reduced self-
    generation. Further [petitioners] did not appear to take
    seriously the Commission decision in the 2021 ENEC and
    2022 ENEC that directed [them] to self-generate more of their
    required power.
    As discussed in the Prudency Report and testimony,
    [petitioners] built up larger than normal coal stockpiles through
    2020. However, by May 2021, [petitioners] should have been
    concerned by the diminishing stockpiles of coal in inventory.
    [Petitioners] should have realized in May 2021, but no later
    than July 2021, that the coal shortages at their plants would
    prevent them from self-generating at a meaningful level to
    offset rising PJM Energy market prices. In July 2021, the
    stockpiles were critically short, yet no action was taken until
    September 20, 2021, when [petitioners] issued a coal supply
    Request for Purchase (RFP). By this point, it was already too
    late to replenish the stockpiles. Only one coal supplier
    responded in the affirmative to the RFP and even that offer was
    rescinded.
    The Commission further noted CTC’s concern that petitioners failed “to take seriously the
    Commission directive to increase the plant capacity factors to 69 percent.” 
    Id.
     Specifically,
    petitioners failed to
    ma[k]e changes in the fuel procurement process or bidding
    their energy into PJM to allow them to provide more self-
    generation and increase the capacity factor of their plants.
    [Petitioners] failed to tell a key employee, Mr. Dial, who was
    in charge of fuel procurement, of the 69 percent capacity factor
    target set forth in the September 2, 2021 Commission Order.
    Eighteen days later, Mr. Dial issued an RFP for more coal,
    unaware, pursuant to his testimony, of a need to not only
    replenish the stockpiles, but also to be able to meet the 69
    percent average generating rate target that had been established
    by the Commission.
    14
    Though petitioners had presented testimony during the hearing on the petition for
    reconsideration in the 2021 ENEC case that they issued the September 2021 RFP as a result
    of the September 2, 2021, Commission Order, the evidence revealed that, even after entry
    of the March 2, 2022, Commission Order on the petition for reconsideration, petitioners
    had yet to inform Mr. Dial “to procure sufficient coal that would allow [petitioners] to
    achieve the 69 percent capacity factor target if PJM energy prices continued to increase
    above earlier projected prices and far above the low levels of PJM market prices in 2020.”
    Indeed, the Commission determined that the evidence showed that petitioners failed to
    procure enough coal to generate at a 69% annual capacity factor.
    As stated in the order, the Commission considered petitioners’ position
    “regarding the unexpectedness and exigency of the situation they found themselves in
    when market prices skyrocketed, and [that] they were caught with insufficient coal supply
    to maximize their use of their lower cost generation.” However, the Commission “[could]
    not agree that [petitioners] are blameless and without fault in building up an ENEC under-
    recovery of over $550 million.” The Commission determined that
    having insufficient supplies of coal in inventory and scheduled
    for delivery into [petitioners’] plants led to the lowest level of
    generation in the last twenty years during a period when the
    PJM LMP spiked to the highest levels experienced in the last
    twenty years. This “perfect storm” led to an inability to
    maximize economic generation while using excessive amounts
    of PJM power. The burden of a significant portion of the
    resulting excessive costs must fall on [petitioners] because
    their fuel supply failures and related market offer strategies that
    lead to rejection of their power plants for dispatch by PJM
    directly caused the excessive ENEC costs.
    15
    (Footnotes omitted). The Commission found that “ENEC under-recoveries were climbing
    dramatically due to over-reliance on third-party power supplies at rising cost levels that
    could have been offset by self-generation if [petitioners] had acted reasonably and
    prudently in a timely manner[,]” and that petitioners “demonstrated an imprudent lack of
    ongoing attention to assure that they had a continuous supply of coal to maintain adequate
    stockpiles of coal to maximize generation when it was cheaper than PJM energy prices.”
    Indeed, the Commission determined that the evidence showed that petitioners failed in
    “their responsibility to structure their coal supply contracts in a manner that would allow
    them to respond to rising PJM LMPs by increasing the utilization of their power plants
    without running out of coal” by entering into “a mix of long-term, medium-term, and short-
    term contracts and spot purchases when necessary.”
    Concluding that petitioners’ imprudent management resulted in their
    incursion of “excessive net ENEC costs that should not be shouldered entirely by
    customers,” the Commission disallowed $231.8 million of the requested ENEC under-
    recoveries. The Commission authorized a prospective recovery of the remaining $321.1
    million in under-recoveries over ten years beginning September 1, 2024, with a carrying
    charge of 4%.
    It is from this order that petitioners now appeal.
    II. Standard of Review
    This Court has previously recognized the highly specialized knowledge and
    expertise of the Commission in considering complex cases such as this:
    16
    This Court’s standard of reviewing the Commission’s
    order in this case is highly deferential given that this case
    involves complex issues and arcane concepts that fall within
    the special competence of the Commission and are governed
    by Commission precedent. This Court previously has
    recognized that “[a] public utility commission has broad
    powers in supervising and regulating the actions of utilities
    within its jurisdiction in the respects provided for in the
    statutory or constitutional provisions by which its authority is
    conferred.” United Fuel Gas Co. v. PSC, 
    154 W.Va. 221
    , 241,
    
    174 S.E.2d 304
    , 316 (1969) (citation omitted). Further, this
    Court has recognized that “on questions of expediency, or as
    to what would be best in the interest of the petitioner, or the
    public served . . . the Legislature intended that the judgment of
    the [Public Service] Commission should prevail.” United Fuel
    Gas Co. v. PSC, 
    73 W.Va. 571
    , 591, 
    80 S.E. 931
    , 939 (1914).
    W. Va. Citizen Action Grp. v. Pub. Serv. Comm’n of W. Va., 
    233 W. Va. 327
    , 331–32, 
    758 S.E.2d 254
    , 258–59 (2014). (Emphasis added). Further,
    “‘The principle is well established by the decisions of
    this Court that an order of the public service commission based
    upon its finding of facts will not be disturbed unless such
    finding is contrary to the evidence, or is without evidence to
    support it, or is arbitrary, or results from a misapplication of
    legal principles.’ United Fuel Gas Company v. Public Service
    Commission, 
    143 W.Va. 33
    , (
    99 S.E.2d 1
    ).” Syl. Pt. 5, Boggs
    v. Pub. Serv. Comm’n, 
    154 W.Va. 146
    , 
    174 S.E.2d 331
     (1970).
    “The detailed standard for our review of an order of the
    Public Service Commission contained in Syllabus Point 2 of
    Monongahela Power Co. v. Public Service Commission, 
    166 W.Va. 423
    , 
    276 S.E.2d 179
     (1981), may be summarized as
    follows: (1) whether the Commission exceeded its statutory
    jurisdiction and powers; (2) whether there is adequate evidence
    to support the Commission’s findings; and, (3) whether the
    substantive result of the Commission’s order is proper.” Syl.
    Pt. 1, Cent. W.Va. Refuse, Inc. v. Pub. Serv. Comm’n of W.Va.,
    
    190 W.Va. 416
    , 
    438 S.E.2d 596
     (1993).
    17
    Syl. pts. 1 and 2, Sierra Club v. Pub. Serv. Comm’n of W. Va., 
    241 W. Va. 600
    , 
    827 S.E.2d 224
     (2019). See Monongahela Power Co., 166 W.Va. at 425, 276 S.E.2d at 181
    (“[B]ecause the Commission is experienced with the intricacies of the rate-making process
    we will ordinarily not substitute our judgment for that of the Commission on controverted
    evidence.”). With these standards to guide us, we now consider petitioners’ appeal.
    II.    Discussion
    A.
    Petitioners’ first two assignments of error are related and will be addressed
    together. Petitioners argue that the Commission used an incorrect legal standard when
    assessing whether the accumulated under-recovery balance for the period March 1, 2021,
    through February 28, 2023, was the result of unreasonable and imprudent decision-making
    by petitioners and that the Commission further erred in concluding that petitioners acted
    imprudently and unreasonably.
    In determining that petitioners failed to prove that they managed their fuel
    supplies and power plant operations (including purchased power costs) in a reasonable,
    prudent, and efficient manner, the Commission noted that it considered petitioners’
    “contemporary action[s] . . . based on what [was] known or reasonably knowable at the
    time the action[s] [were] taken” as well as “a continuum of actions leading up to a decision
    point.” The parties agree that the well-settled legal standard requires the Commission to
    examine petitioners’ decisions leading up to and resulting in the ENEC costs they seek to
    18
    recover from ratepayers based upon facts and information available at the time such
    decisions were made. In past Commission proceedings, the Commission has stated:
    To find that a utility has acted imprudently, the
    Commission must have evidence before it to show that the
    utility’s decisions were unreasonable based on actual data that
    was available at the time the utility was making its decisions.
    Another way of saying this is that the Commission would have
    to determine that an alternative utility action was reasonable
    and should have been made based upon facts available at the
    time the decision was made. The Commission may not find
    imprudence based on outcomes or new facts that the utility
    14
    cannot have reasonably been expected to know, or assume.
    Petitioners argue that by also considering “a continuum of actions leading up
    to a decision point,” the Commission impermissibly deviated from the appropriate standard
    by effectively evaluating petitioners’ decision-making relating to their coal procurement
    efforts (or lack thereof) and consequent inability to economically operate their coal-fired
    power plants resulting in their purchasing of expensive energy from the PJM market “on
    the basis of ultimate outcomes considered with 20/20 hindsight.” According to petitioners,
    the Commission ignored evidence that petitioners’ coal procurement practices comported
    with industry standards and adapted to changing circumstances and that, not unlike coal-
    fired electric utilities located outside of West Virginia, petitioners were faced with what
    they characterize as unforeseeable and challenging circumstances over which they had no
    control, including that, beginning in the later months of 2021, natural gas and coal prices
    were increasing unexpectedly and coal was unavailable to purchase. Petitioners also point
    14
    In re Hope Gas, Inc., 
    2006 WL 2134651
     *12 (W. Va. P.S.C. April 3, 2006).
    19
    to evidence that large quantities of coal that they previously contracted to purchase were
    not delivered. Simply put, petitioners argue that they did not act imprudently based upon
    information that was known and knowable to them at the time and the fact that, during the
    time period at issue, they had insufficient supplies of coal to generate their plants causing
    them to purchase large amounts of power at high-cost levels to serve their customers was
    not their fault.
    The Commission counters that there was evidence presented that, beginning
    in the late spring of 2021, the coal market was tightening and the price of natural gas was
    increasing; that expert witness testimony presented in July of 2021 expressed concern over
    a significant amount of petitioners’ coal supply being concentrated with only two suppliers;
    that petitioners did not issue an RFP for coal until September 20, 2021, when petitioners’
    coal supply was already diminishing; that petitioners failed to inform their fuel
    procurement officer that petitioners were ordered by the Commission to target a 69%
    capacity factor and so the RFP did not request sufficient coal supplies to meet that target;
    that petitioners’ mix of coal contracts of varying lengths was not sufficient to ensure an
    adequate supply of coal; and that petitioners’ own projections in the 2021 ENEC case
    indicated that they were over-relying on purchased power even when cost levels were
    increasing from 2020 levels and it was more economical to self-generate. Noting that
    petitioners previously assured the Commission that their coal-fired plants would provide a
    physical hedge against high and volatile electric market prices, the Commission argues that
    petitioners failed to provide that physical hedge by imprudently disregarding trends and
    20
    market signals affecting their coal procurement practices.15 The Commission contends that
    the finding that petitioners were imprudent and unreasonable in their decision-making and
    that the resulting incursion of excessively high under-recoveries should not be passed on
    to customers was supported by the evidence and should be affirmed.
    Upon our considered review, and ever mindful that the complexity of the
    issues and subject matter falls within the special competence of the Commission, we afford
    great deference to the Commission’s thorough and well-reasoned conclusion that
    petitioners failed to manage their power plant operations in a reasonable, prudent, and
    efficient manner resulting in an inadequate stockpile of coal to fuel their facilities that, in
    turn, caused petitioners to purchase energy at cost levels that were much higher than what
    16
    it would have cost them to generate from their own plants. Petitioners have failed to
    establish that the Commission’s decision in this regard was arbitrary, contrary to the
    17
    evidence, without evidence to support it, or resulted from a misapplication of the law, and
    so, as they relate to the Commission’s determination that petitioners acted imprudently and
    15
    Cf. In re Hope Gas, Inc. dba Dominion Hope, 
    2013 WL 2370525
     *1 (W. Va.
    P.S.C. May 10, 2013) (regarding a gas utility’s burden of proving reasonable and prudent
    hedging actions, “the prudence of management decisions will not be evaluated with the
    benefit of 20/20 hindsight. . . .[H]owever, . . . at the time those hedging decisions are made,
    they must be based on a continuing and reasonable understanding of market conditions,
    market trends, and other factors that are shaping current and future gas supply and demand
    and that will likely impact future gas costs.”).
    16
    See W. Va. Citizen Action Grp., 
    233 W. Va. at 331-32
    , 
    758 S.E.2d at 258-59
    .
    17
    See Sierra Club, 
    241 W. Va. at 601
    , 
    827 S.E.2d at 225
    , syl. pt. 1.
    21
    unreasonably, we affirm the January 9, 2024, order’s findings of fact, conclusions of law,
    and the Commission’s stated reasons therefor, and adopt and incorporate them by reference
    into this opinion. We further find that the Commission’s determination that petitioners
    acted imprudently and unreasonably in their decision-making was made in light of
    information and circumstances that petitioners knew or should have known at the time their
    decisions were made, as more fully set forth in the Commission’s order.
    B.
    Petitioners’ next assignment of error challenges the Commission’s
    conclusion that $231.8 million of the $552.9 million accumulated under-recovery balance
    requested was the result of petitioners’ imprudent and unreasonable decision-making
    discussed above in Section A. The Commission ordered that this amount be disallowed for
    recovery in ENEC rates. At issue is whether the Commission violated petitioners’
    fundamental due process rights by relying on information outside of the evidentiary record
    in arriving at its disallowance calculation.
    Petitioners argue that the Commission improperly used coal reports that
    18
    petitioners submitted to the Commission on a monthly basis, but that were not made a
    part of the record in the proceedings below, to unilaterally modify an exhibit that petitioners
    submitted after the hearing had concluded. Specifically, on the third and final day of the
    18
    Electric utilities such as petitioners are required to submit to the Commission, on
    a monthly basis, certain information relating to their purchases of coal or other fuel. See
    
    W. Va. Code § 24-2-14
     (1975).
    22
    proceedings, the Commission requested that petitioners submit evidence of their “market
    bids and cost-based bids in the PJM market, the corresponding LMP clearing prices, and
    the resulting market clearing volumes of their self-generation” covering the review period
    March 1, 2021, through February 28, 2023. Petitioners complied with the Commission’s
    request and timely submitted the exhibit (“Post-Hearing Exhibit 4”) after the proceedings
    had concluded. Petitioners argue that the Commission proceeded to calculate the $231.8
    million disallowance by supplanting the cost-based bid prices reflected in petitioners’
    exhibit with prices calculated by the Commission using information it obtained from the
    coal reports that were not presented as evidence during the hearing. Petitioners argue that,
    critically, exactly how the Commission used the information from the coal reports in its
    calculation of the disallowance is not apparent from the Commission’s order and so
    petitioners are unable to verify either the calculation’s accuracy or rebut its legitimacy.
    According to petitioners, the Commission used prices that were unrealistically low and
    without any basis in the actual evidentiary record. Petitioners contend that they had no
    notice that the Commission would be relying on this extra-record evidence and,
    importantly, were not afforded an opportunity to challenge or otherwise address the manner
    in which the Commission used it in calculating the extent to which, in the Commission’s
    view, petitioners acted imprudently and unreasonably. Petitioners argue that the
    Commission violated their fundamental due process rights.
    The Commission responds that the purpose of the proceedings was to
    ascertain the prudency of petitioners’ coal procurement practices and their “inability to
    23
    offset high-priced purchased power. . . with more economic self-generation,” and that
    petitioners knew that if the Commission determined that petitioners had acted imprudently
    in incurring excessive ENEC costs, then the next step would be for the Commission to
    quantify the extent to which those costs were imprudently incurred. Without addressing
    whether it was a violation of petitioners’ due process rights to inscrutably and significantly
    modify petitioners’ Post-Hearing Exhibit 4 with extra-record evidence (i.e., the coal
    reports), the Commission offers a lengthy explanation justifying the reasons why it found
    it necessary to resort to the use of the reports in calculating the disallowance of $231.8
    million. The Commission argues that petitioners were afforded a fair evidentiary hearing.
    It is beyond cavil that a proceeding “‘requiring the taking and weighing of
    evidence, determinations of fact based upon the consideration of the evidence, and the
    making of an order supported by such findings, has a quality resembling that of a judicial
    proceeding.’ . . . A functional analysis of the Commission’s proceedings leads unerringly
    to the conclusion that they . . . are quasi-judicial proceedings.” Appalachian Power Co. v.
    Pub. Serv. Comm’n, 
    162 W. Va. 839
    , 849-50, 
    253 S.E.2d 377
    , 384 (1979) (quoting Morgan
    v. U.S., 
    298 U.S. 468
    , 480 (1936)). As such, parties to the Commission’s proceedings are
    entitled to basic constitutional protections, including due process of law. See Syl. Pt. 2, in
    part, State ex rel. Ellis v. Kelly, 
    145 W. Va. 70
    , 
    112 S.E.2d 641
     (1960) (“‘Due process of
    law, within the meaning of the State and Federal constitutional provisions, extends to
    actions of administrative officers and tribunals. . . .”). “Procedural due process rights entitle
    an individual to representation by counsel, notice, an opportunity to be heard, and the right
    24
    to present evidence.” Marcus v. Holley, 
    217 W. Va. 508
    , 527, 
    618 S.E.2d 517
    , 536 (2005).
    “A due process analysis is founded upon the concept of fundamental fairness.” 
    Id.
    Ohio Bell Telephone Company v. Public Utilities Commission of Ohio, 
    301 U.S. 292
     (1937), involved administrative proceedings before the Public Utilities
    Commission of Ohio (“PUCO”) to set rates for Ohio Bell Telephone Company (“Ohio
    Bell”) customers. PUCO ordered Ohio Bell to file with it a complete inventory of all of its
    property so that a hearing could be held to determine “the fair value of said property” as of
    a date certain (June 30, 1925) and “the just and reasonable rates for the service thereby to
    be furnished” to customers. 
    Id. at 295
    . “A long investigation followed, the evidence being
    directed in the main to the value of the property on the basis of historical cost and cost of
    reproduction, and to the deductions chargeable to gross revenues for depreciation reserve
    and operating expenses generally.” 
    Id. at 295-96
    . Based upon the evidence, PUCO fixed a
    tentative value as of the date certain but then “[i]t undertook also to fix a valuation for each
    of the years 1926 to 1933.” 
    Id. at 296
    . In doing so, “it took judicial notice of price trends
    during those years” based upon property taxes; “building trends” from a recognized
    engineering construction magazine; labor trends; and court decisions, and “modif[ied] the
    value which it had found as of the date certain by the percentage of decline or rise
    applicable to the years thereafter.” 
    Id. at 297
    . Ultimately, PUCO determined that, based
    upon this evidence, Ohio Bell was in receipt of significant excess earnings and ordered a
    refund to customers. 
    Id. at 298
    .
    Ohio Bell protested, arguing that
    25
    the trend percentage accepted in the findings as marking a
    decline in values did not come from any official sources which
    [PUCO] had the right to notice judicially; that they had not
    been introduced in evidence; that the company had not been
    given an opportunity to explain or rebut them; and that by their
    use [PUCO] had denied a fair hearing in contravention of the
    requirements of the Fourteenth Amendment.”
    
    Id. at 298
    . PUCO reaffirmed its decision and the Supreme Court of Ohio affirmed.
    Ohio Bell appealed to the United States Supreme Court, which reversed the
    decision of the lower court, acknowledging that the lower tribunals took “judicial notice
    that there has been a depression, and that a decline in the market values is one of its
    concomitants.” 
    Id. at 301
    . However, the Supreme Court cautioned, “[h]ow great the decline
    has been for this industry or that, for one material or another, in this year or the next, can
    be known only to the experts, who may even differ among themselves.” 
    Id.
     Thus, “notice,
    even when taken, has no other effect than to relieve one of the parties to a controversy of
    the burden of resorting to the usual forms of evidence. ‘It does not mean that the opponent
    is prevented from disputing the matter by evidence if he believes it disputable.’” 
    Id.
     at 301-
    02 (citations omitted). Stated another way, when judicially noticed facts are “put in
    evidence upon a trial, the party against whom they are offered may see the evidence or hear
    it and parry its effect.” 
    Id. at 302
    . The Supreme Court instructed that
    [t]he fundamentals of a trial were denied to the appellant when
    rates previously collected were ordered to be refunded upon
    the strength of evidential facts not spread upon the record.
    [PUCO] had given notice that the value of the property would
    be fixed as of a date certain. Evidence directed to the value at
    that time had been laid before the triers of the facts in thousands
    of printed pages. To make the picture more complete, evidence
    had been given as to the value at cost of additions and
    26
    retirements. Without warning or even the hint of warning that
    the case would be considered or determined upon any other
    basis than the evidence submitted, the Commission cut down
    the values for the years after the date certain upon the strength
    of information secretly collected and never yet disclosed. The
    company protested. It asked disclosure of the documents
    indicative of price trends, and an opportunity to examine them,
    to analyze them, to explain and to rebut them. . . . Upon the
    strength of these unknown documents refunds have been
    ordered for sums mounting into millions, [PUCO] reporting its
    conclusion, but not the underlying proofs. The putative debtor
    does not know the proofs today. This is not the fair hearing
    essential to due process. It is condemnation without trial.
    
    Id. at 300
    .19 This Court has likewise cautioned,
    Although we recognize that the Public Service
    Commission may, in accordance with the well-developed
    principles governing official notice, occasionally go beyond
    the confines of the record for information bearing upon its
    decision, we state unequivocally that we do not favor this
    procedure except in extremely limited circumstances. The
    Commission places its decisions and orders in a precarious
    position when it bases them on extra-record adjudicative facts
    without advising a party that it intends to do so and without
    affording the party the opportunity for cross-examination and
    rebuttal. This is particularly true where there is no cogent or
    compelling reason for the Commission’s failure to offer
    evidence on the record.
    19
    Accord Union Elec. Co. v. F.E.R.C., 
    890 F.2d 1193
    , 1202-03 (D.C. Cir. 1989)
    (provision of the federal Administrative Procedure Act providing that “[w]hen an agency
    decision rests on official notice of a material fact not appearing in the evidence of record,
    a party is entitled . . . to an opportunity to show the contrary” that “encompasses a chance
    not only to dispute the facts noticed but also to ‘parry [their] effect,’ i.e., to offer evidence
    or analysis contesting the Commission’s inferences.”)
    27
    Kanawha Valley Transp. Co. v. Pub. Serv. Comm’n of W. Va., 159 W. Va 88, 98, 
    219 S.E.2d 332
    , 339 (1975). See 
    id. at 88
    , 219 S.E.2d at 334, syl. pt. 5 (holding that “[p]arties
    to a [certificate of convenience and necessity] revocation hearing before the Public Service
    Commission should be fully informed of the evidence submitted or to be considered and
    should be given an opportunity to cross-examine witnesses, to inspect documents and offer
    evidence in rebuttal.”).
    We agree with petitioners that it was fundamentally unfair for the
    Commission to consult and rely on evidence that was neither mentioned nor admitted into
    the record below to significantly adjust the cost-based bid prices that petitioners submitted
    in their exhibit to quantify the not insignificant disallowance of $231.8 million. That the
    coal reports were submitted to the Commission by petitioners as a matter of course20 is of
    no moment—even if it were appropriate for the Commission, on its own, to reach into its
    20
    On March 22, 2024, the Commission filed a motion to supplement the appellate
    record with the coal reports to which the Commission cited in its January 9, 2024, order.
    Although the motion states that the coal reports “were used by the Commission in making
    its decision” in this case and that “the coal reports were inadvertently omitted from the
    Commission record previously filed with th[is] Court[,]” in connection with the instant
    appeal, the Commission does not dispute that the coal reports were not actually introduced
    or otherwise addressed during the course of the proceedings below. Further, despite the
    Commission’s suggestion during oral argument that the Commission took judicial notice
    of the reports, see W.Va. R. Evid. 201, there is no indication in the Commission’s order
    that it did so. Regardless, the Commission fails to address petitioners’ argument that they
    were not afforded notice and an opportunity to be heard as to how the Commission used
    the reports in quantifying the disallowance. See Ohio Bell, 
    301 U.S. at 301-02
    . The
    Commission states simply: “The disingenuous attempt by Petitioners to claim no
    knowledge of their own reports and to claim that the Commission should not consider
    information filed by the Petitioners themselves is absurd. Petitioners are most certainly
    aware of the coal reports that they prepare and file with the Commission.”
    28
    records for this factual information, the Commission does not dispute that the manner in
    which it used the information in the reports to calculate the disallowance was not disclosed
    to petitioners. Simply put, petitioners had no opportunity to examine, analyze, rebut, or
    “parry its effect,” Ohio Bell, 
    301 U.S. at 302
    , and the Commission has offered no cogent
    or compelling reason for its failure to offer this evidence on the record. Kanawha Valley
    Transp., 159 W. Va at 98, 219 S.E.2d at 339. Due process “is ultimately measured by the
    concept of fundamental fairness.” State ex rel. Blankenship v. Richardson, 
    196 W. Va. 726
    ,
    739, 
    474 S.E.2d 906
     919 (1996). Because petitioners were entitled to, but not afforded,
    notice of how the Commission used the information gleaned from the reports and the
    opportunity to examine, analyze, rebut, and “parry its effect,”21 we remand this matter to
    the Commission for that specific and singular purpose.22
    IV. Conclusion
    Based upon all of the foregoing, we affirm the Commission’s order insofar
    as it concluded that petitioners failed to manage their power plant operations in a
    reasonable, prudent, and efficient manner, and we adopt and incorporate by reference the
    21
    To be clear, the Court takes no position as to whether the Commission’s use and
    manner of use of the coal reports were appropriate. Rather, our concern is that basic
    concepts of fundamental fairness dictate that petitioners should have been given notice and
    an opportunity to be heard on this evidence.
    22
    Because we have ordered that this matter be remanded to the Commission, we
    decline to address petitioners’ remaining assignment of error that the Commission
    exceeded its authority in ordering that the remaining under-recovery balance be recovered
    through an ENEC rate increment over a period of ten years, with a 4% carrying charge.
    29
    Commission’s findings of fact, conclusions of law, and reasons stated therefor in the order
    to that limited extent. We reverse the order insofar as it disallowed $231.8 million of the
    requested under-recoveries and remand this matter to the Commission for the specific and
    sole purpose of affording petitioners the opportunity to address the coal reports that the
    Commission relied upon in quantifying the disallowance.
    Affirmed, in part; Reversed, in part; and Remanded.
    30
    

Document Info

Docket Number: 24-75

Filed Date: 11/13/2024

Precedential Status: Precedential

Modified Date: 11/13/2024