Eog Resources, Inc., a Delaware Corporation v. Jjlm Land, Llc, a Wyoming Limited Liability Company ( 2022 )


Menu:
  •                 IN THE SUPREME COURT, STATE OF WYOMING
    
    2022 WY 162
    OCTOBER TERM, A.D. 2022
    December 28, 2022
    EOG RESOURCES, INC., a Delaware
    corporation,
    Appellant
    (Defendant),
    v.                                                   S-22-0095
    JJLM LAND, LLC, a Wyoming limited
    liability company,
    Appellee
    (Plaintiff).
    Appeal from the District Court of Campbell County
    The Honorable Stuart S. Healy III, Judge
    Representing Appellant:
    Isaac Sutphin, P.C., Jeffrey S. Pope, Holland & Hart LLP, Cheyenne, Wyoming.
    Argument by Mr. Pope.
    Representing Appellee:
    Kendal R. Hoopes, Yonkee & Toner, LLP, Sheridan, Wyoming. Argument by Mr.
    Hoopes.
    Before FOX, C.J., and KAUTZ, BOOMGAARDEN, GRAY, and FENN, JJ.
    NOTICE: This opinion is subject to formal revision before publication in Pacific Reporter Third.
    Readers are requested to notify the Clerk of the Supreme Court, Supreme Court Building, Cheyenne,
    Wyoming 82002, of typographical or other formal errors so correction may be made before final
    publication in the permanent volume.
    KAUTZ, Justice.
    [¶1] JJLM Land, LLC (JJLM) sued EOG Resources, Inc. (EOG) for breach of the
    parties’ surface use and damage agreements and sought double damages under 
    Wyo. Stat. Ann. § 30-5-405
    (b) (LexisNexis 2021) (part of what we have referred to as the Wyoming
    Split Estate Act, 
    Wyo. Stat. Ann. §§ 30-5-401
     to 30-5-410 (LexisNexis 2021)). JJLM
    asserted EOG underpaid its obligations under the surface use and damage agreements.
    EOG admitted underpayment but argued the double damages statute did not apply because
    it had paid a portion of the amount owed. The district court granted summary judgment to
    JJLM. It concluded the double damages provision in § 30-5-405(b) applies when an oil
    and gas operator underpays an installment under a surface use and damage agreement and
    JJLM’s claim for double damages was not barred by the statute of limitations or laches.
    The court denied EOG’s subsequent motion to alter or amend judgment under Wyoming
    Rule of Civil Procedure (W.R.C.P.) 59(e). We affirm the district court’s summary
    judgment decision. We lack jurisdiction to review the court’s denial of EOG’s Rule 59(e)
    motion. We grant JJLM’s request for its attorney fees and costs on appeal.
    ISSUES
    [¶2]   The dispositive issues are:
    1.     Did the district court err by deciding § 30-5-405(b) applies when an oil and
    gas operator underpays an installment owed to a surface owner under a surface use and
    damage agreement?
    2.     Did the district court err by concluding JJLM’s claim for double damages
    was not barred by the statute of limitations?
    3.    Did the district court abuse its discretion by determining JJLM’s claim for
    double damages was not barred by laches?
    4.    Do we have jurisdiction to review the district court’s denial of EOG’s Rule
    59(e) motion?
    5.     Is JJLM entitled to its attorney fees and costs on appeal?
    FACTS
    [¶3] In February 2011, JJLM’s predecessor, the Drake Family Revocable Land Trust
    (Trust), entered into a “Surface and Damage Agreement” (2011 SDA) with EOG’s
    predecessor, Yates Petroleum Corporation (Yates). Under this agreement, the Trust
    granted Yates the right to enter and use the Trust’s ranch lands in Campbell County for its
    oil and gas operations; in exchange, Yates agreed to compensate the Trust for any damage
    1
    caused by its operations, including making annual rental payments to the Trust for each
    surface disturbance drilled or constructed on the lands (e.g., wells, access roads, and
    pipelines). The parties amended the 2011 SDA three times between September 2013 and
    November 2015. The amendments added land to be covered by the 2011 SDA and
    increased the amounts of the annual rental payments owed by Yates to the Trust.
    [¶4] Sometime between September 2013 and September 2015, the Trust transferred the
    ranch lands to JJLM. In October 2016, EOG took over Yates’ oil and gas operations on
    the ranch lands, including its payment obligations under the 2011 SDA. In November
    2019, JJLM and EOG executed a new “Surface Use and Damage Agreement” (2019 SUA),
    which superseded the 2011 SDA and created new annual payment obligations for EOG.
    [¶5] After the 2019 SUA went into effect, JJLM began closely monitoring EOG’s annual
    payments and determined they did not comply with the 2019 SUA. In July and August
    2020, JJLM asked EOG to correct the payments. When EOG did not respond to JJLM’s
    concerns, JJLM sent EOG a “Notice Pursuant to 
    Wyo. Stat. Ann. § 30-5-405
    (b)” (notice
    of default) which asserted EOG was in default under the 2019 SUA and demanded EOG
    timely cure the default or JJLM would file a lawsuit seeking double damages under § 30-
    5-405(b). EOG received the notice of default on September 14, 2020.
    [¶6] On December 8, 2020, after EOG failed to timely cure the default, JJLM sued EOG
    for breach of contract and double damages under § 30-5-405(b). EOG answered the
    complaint and asserted various affirmative defenses, including that JJLM’s claim for
    double damages was barred by the statute of limitations and laches. In March 2021, EOG
    admitted it owed $377,978.91 to JJLM under both the 2011 SDA and the 2019 SUA and
    filed a motion to deposit that amount with the court pursuant to W.R.C.P. 67 (“If any part
    of the relief sought is a money judgment or the disposition of a sum of money . . ., a party
    -- on notice to every other party and by leave of court -- may deposit with the court all or
    part of the money . . ., whether or not that party claims any of it.”). It disputed, however,
    JJLM’s claim for double damages under § 30-5-405(b). The district court granted EOG’s
    Rule 67 motion, and EOG deposited the funds with the court.
    [¶7] JJLM filed a motion for summary judgment on its breach of contract claim and
    claim for double damages. JJLM argued that, because EOG admitted to owing
    $377,978.91 for breaching the parties’ surface use and damage agreements and failed to
    cure the default after notification, it was entitled to an additional $377,978.91 in damages
    under § 30-5-405(b).
    [¶8] In response, EOG claimed that during Summer 2020, it had completed an audit of
    the payments made to JJLM between 2016 and 2020 and determined it had sometimes
    underpaid, had on a few occasions overpaid, and missed three payments entirely. It blamed
    the payment errors on the transition from Yates’ accounting system to its own, a land swap
    by JJLM, and the new payment obligations created by the 2019 SUA. After netting out the
    2
    overpayments, EOG admitted it owed $377,978.91. It argued, however, that JJLM was not
    entitled to double that amount under § 30-5-405(b) because the statute applies only when
    an operator does not pay any portion of an installment owed under a surface use and
    damage agreement, not when an operator does not pay enough. Because it had only missed
    three payments totaling $50,528.50, EOG maintained JJLM was only entitled to receive
    that amount under § 30-5-405(b). Even assuming § 30-5-405(b) applied to underpayments,
    EOG argued JJLM’s claim for double damages was barred by the one-year statute of
    limitations contained in 
    Wyo. Stat. Ann. § 1-3-105
    (a)(v)(D) (LexisNexis 2021) and/or
    laches.
    [¶9] The district court granted summary judgment to JJLM on its breach of contract
    claim and its entire claim for double damages under § 30-5-405(b). It determined it was
    undisputed that the 2011 SDA and 2019 SUA were enforceable contracts, EOG did not
    make the required payments under those agreements, and JJLM suffered damages in the
    amount of $377,978.91 due to EOG’s breach. The court also decided JJLM was entitled
    to double damages on the entire delinquency because § 30-5-405(b) applies not only when
    an operator does not pay an installment owed under a surface use and damage agreement
    but also when an operator underpays an installment. It rejected EOG’s statute of limitations
    and laches defenses and awarded JJLM $755,957.82 in total damages.
    [¶10] EOG subsequently filed a motion to alter or amend the judgment under Rule 59(e)
    seeking to reduce the damages awarded to JJML by $59,370.00. It claimed that although
    it agreed it owed $377,978.91, that amount included ten payments, totaling $59,370.00,
    which were not yet due when JJLM sent EOG the notice of default. According to EOG,
    the district court erred in awarding double damages for those payments because JJLM had
    no basis to demand payment for amounts not yet due. The next day, EOG supplemented
    its Rule 59(e) motion, claiming it found additional payments that were not due until after
    JJLM sent the notice of default, and therefore damages should be reduced by $180,878.19.
    The district court summarily denied EOG’s Rule 59(e) motion.
    [¶11] While its Rule 59(e) motion was pending, EOG filed a notice of appeal from the
    district court’s summary judgment decision. After the district court denied its Rule 59(e)
    motion, EOG did not amend its notice of appeal to include the court’s denial of its Rule
    59(e) motion.
    STANDARD OF REVIEW
    [¶12] “We review a district court’s summary judgment ruling de novo.” Statzer v. Statzer,
    
    2022 WY 117
    , ¶ 10, 
    517 P.3d 574
    , 578 (Wyo. 2022) (citing Spence v. Sloan, 
    2022 WY 96
    ,
    ¶ 22, 
    515 P.3d 572
    , 579 (Wyo. 2022), and Miller v. Sweetwater Cnty. Sch. Dist. #1, 
    2021 WY 134
    , ¶ 13, 
    500 P.3d 242
    , 246 (Wyo. 2021)). We also review de novo the district
    court’s interpretation of § 30-5-405(b) and its determination that JJLM’s claim for double
    damages under § 30-5-405(b) was not barred by the statute of limitations. Guy v. Lampert,
    3
    
    2016 WY 77
    , ¶ 13, 
    376 P.3d 499
    , 502-03 (Wyo. 2016) (statutory interpretation) (citation
    omitted); Inman v. Boykin, 
    2014 WY 94
    , ¶ 21, 
    330 P.3d 275
    , 281 (Wyo. 2014) (statute of
    limitations) (citations omitted). We review for an abuse of discretion the district court’s
    laches decision. Seherr-Thoss v. Teton Cnty. Bd. of Cnty. Comm’rs, 
    2014 WY 82
    , ¶ 60,
    
    329 P.3d 936
    , 955 (Wyo. 2014) (laches) (citation omitted). “‘A court abuses its discretion
    when it acts in a manner which exceeds the bounds of reason under the circumstances. The
    party who is attacking the trial court’s ruling has the burden to establish an abuse of
    discretion, and the ultimate issue is whether the court could reasonably conclude as it did.’”
    Meiners v. Meiners, 
    2019 WY 39
    , ¶ 9, 
    438 P.3d 1260
    , 1266 (Wyo. 2019) (quoting
    McBride-Kramer v. Kramer, 
    2019 WY 10
    , ¶ 11, 
    433 P.3d 529
    , 532 (Wyo. 2019), and Three
    Way, Inc. v. Burton Enters., Inc., 
    2008 WY 18
    , ¶ 16, 
    177 P.3d 219
    , 225 (Wyo. 2008)).
    “Whether this Court has jurisdiction is a question of law that we review de novo.” Martin
    v. Hart, 
    2018 WY 123
    , ¶ 17, 
    429 P.3d 56
    , 62 (Wyo. 2018) (citing Inman v. Williams, 
    2008 WY 81
    , ¶ 10, 
    187 P.3d 868
    , 874 (Wyo. 2008)).
    DISCUSSION
    A. Summary Judgment
    [¶13] EOG does not dispute that JJLM was entitled to summary judgment on its breach of
    contract claim. It maintains, however, the court erred by granting summary judgment to
    JJLM on its claim for double damages under § 30-5-405(b). Specifically, EOG argues the
    court erred by determining § 30-5-405(b) applied to underpayments of installments owed
    under a surface use and damage agreement and by deciding JJLM’s claim for double
    damages was not barred by the statute of limitations or laches.
    1. Section 30-5-405(b)
    [¶14] The double damages provision of the Split Estate Act provides:
    (b) An oil and gas operator who fails to timely pay an
    installment under any annual damage agreement negotiated
    with a surface owner is liable for payment to the surface owner
    of twice the amount of the unpaid installment if the installment
    payment is not paid within sixty (60) days of receipt of notice
    of failure to pay from the surface owner.
    Section 30-5-405(b) (emphasis added).
    [¶15] The district court determined the plain meaning of the statutory word “fails” is “to
    leave undone,” “to be deficient in,” or “to be unsuccessful.” The court decided:
    “Whichever variation on the definition one chooses, each leads to the same conclusion[.]
    If an oil and gas operator like EOG does not pay an installment, whether it fails to do so in
    4
    whole or in part, as [it is] required to do . . . under an SUA, and does not cure that deficiency
    within sixty days of being notified, . . . § 30-5-405(b) mandates payment to the surface
    owner of twice the unpaid amount.”
    [¶16] “When interpreting statutes, this Court searches for the legislature’s intent as
    reflected in the language of the statute.” Wyodak Res. Dev. Corp. v. Wyo. Dep’t of Revenue,
    
    2017 WY 6
    , ¶ 25, 
    387 P.3d 725
    , 732 (Wyo. 2017) (citing Vance v. City of Laramie, 
    2016 WY 106
    , ¶ 12, 
    382 P.3d 1104
    , 1106 (Wyo. 2016)). “‘If the statutory language is
    sufficiently clear and unambiguous, the Court simply applies the words according to their
    ordinary and obvious meaning.’” Id., ¶ 26, 150 P.3d at 732 (quoting DB v. State (In re
    CRA), 
    2016 WY 24
    , ¶ 16, 
    368 P.3d 294
    , 298 (Wyo. 2016)). “We give effect to each word,
    clause and sentence chosen by the legislature, and construe them in pari materia.” 
    Id.
    (citing Pedro/Aspen, Ltd. v. Bd. of Cnty. Comm’rs of Natrona Cnty., 
    2004 WY 84
    , ¶ 27, 
    94 P.3d 412
    , 420 (Wyo. 2004)).
    [¶17] Section 30-5-405(b) is not ambiguous and neither party argues otherwise. It renders
    an “oil and gas operator who fails to timely pay an installment under any annual damage
    agreement” liable for “twice the amount of the unpaid installment if the installment
    payment is not paid within sixty (60) days of receipt of notice of failure to pay from the
    surface owner.” (Emphasis added). EOG does not dispute it is an “oil and gas operator,”
    see 
    Wyo. Stat. Ann. § 30-5-401
    (a)(v) (LexisNexis 2021) (“‘[o]il and gas operator’ means
    a person engaged in oil and gas operations, his designated agents, contractors and
    representatives[]”), or that the payments at issue in this case were installments it owed
    JJLM under the parties’ surface use and damage agreements. Nor does it dispute that the
    definitions of “fail” cited by the district court are the plain and ordinary meaning of the
    word. However, it contends we should use the “to leave undone” definition of “fail”
    because utilizing the other definitions impermissibly reads words into the statute or results
    in the statute being ambiguous and unconstitutionally vague. Applying the “to leave
    undone” definition, EOG maintains the double damages provision applies only when an
    oil and gas operator leaves a payment entirely undone, i.e., does not make a payment at all.
    It claims that from 2016 to 2020, it made all but three payments. Although some of those
    payments were not the correct amount, EOG asserts it nevertheless made the payments and
    therefore did not leave them “undone.”
    [¶18] The plain and ordinary meaning of the word “fail” is “to leave undone:
    NEGLECT,” “to be deficient in:             LACK,” or “to be unsuccessful.”             See
    https://www.merriam-webster.com/dictionary/fail (last visited Dec. 9, 2022). “Undone”
    means “not done:         not performed or finished.”          See https://www.merriam-
    webster.com/dictionary/undone (last visited Dec. 9, 2022). “Deficient” means “lacking in
    some necessary quality or element” and “lack” means “to be deficient or missing” and “to
    be short or have need of something.”                         See https://www.merriam-
    webster.com/dictionary/deficient; https://www.merriam-webster.com/dictionary/lack (last
    visited Dec. 9, 2022). The plain meaning of “unsuccessful” is “not successful: not meeting
    5
    with       or       producing          success.”             See      https://www.merriam-
    webster.com/dictionary/unsuccessful (last visited Dec. 9, 2022). “Success” in turn means
    “favorable      or        desired       outcome.”             See     https://www.merriam-
    webster.com/dictionary/success (last visited Dec. 9, 2022). Under any of these definitions,
    even the “to leave undone” definition advocated by EOG, when an oil and gas operator
    underpays an installment owed to a surface owner under a surface use and damage
    agreement, it “fails to . . . pay” the installment. In such circumstances, the installment is
    “not done,” “not performed or finished,” is “lacking” or “short,” and does not meet “the
    desired outcome,” i.e., full payment of the installment.
    [¶19] EOG makes five primary arguments attempting to avoid the plain meaning of the
    statute. We reject each of these arguments. First, EOG argues if we use the “to be
    unsuccessful” definition of “fail,” we either have to modify the definition of fail to be
    “unsuccessful in whole or in part” or we have to impermissibly add “in whole or in part”
    into the statute. See Wyodak Res. Dev. Corp., ¶ 26, 387 P.3d at 732 (“A statute is not [to
    be] interpreted in a way that renders a portion of it meaningless or adds language to it.”)
    (citation omitted). According to EOG, because the legislature did not include those words
    in the statute, but could have easily done so, such omission must have been intentional. As
    we just explained, the plain and ordinary meaning of “fail” to pay under the “to be
    unsuccessful” definition includes underpayments. “The legislature thus incorporated
    [underpayments] in the statutory language it used. No additional language is needed to
    support this plain and ordinary interpretation.” WPX Energy Rocky Mountain, LLC v. Wyo.
    Dep’t of Revenue, 
    2022 WY 104
    , ¶ 27, 
    516 P.3d 449
    , 456 (Wyo. 2022).
    [¶20] Next, EOG maintains if we use the “to be deficient in” definition of “fail,” § 30-5-
    405(b) is ambiguous as to what quality of the payment must be deficient. While EOG
    concedes it is plausible to read the statute as applying to payments that are deficient in
    amount, it argues there are other possible readings of the statute. For example, it claims
    the “fails to pay” language of the statute could be read to mean the tendered payment was
    deficient because it did not include the information necessary to adequately account for the
    payment. The statutory phrase is “fails to pay,” not “fails to provide sufficient information
    for accounting purposes.” The only plausible reading of the statute is that the deficiency
    must be in the amount of the payment, which includes paying nothing and not paying
    enough.
    [¶21] Third, EOG argues if we interpret “fail” to pay to require the payment to be deficient
    in amount, the statute is unconstitutionally vague because it does not clarify what amount
    or percentage of underpayment triggers an operator’s liability for double damages under §
    30-5-405(b).
    A statute is impermissibly vague if people of common
    intelligence must necessarily guess at its meaning and would
    differ as to its application. Newport Int’l. Univ., Inc., [v. State
    6
    Dep’t of Ed., 
    2008 WY 72
    ,] ¶ 23, 186 P.3d [382,] 388 [(Wyo.
    2008)]. To succeed on a claim of vagueness, “the complainant
    must demonstrate that the law is impermissibly vague in all of
    its applications.” Vill. of Hoffman Estates v. Flipside, Hoffman
    Estates, Inc., 
    455 U.S. 489
    , 497, 
    102 S.Ct. 1186
    , 1193, 
    71 L.Ed.2d 362
     (1982). “If legislative intent can be ascertained
    with reasonable certainty, the statute will not be declared
    inoperative.” Haddenham v. City of Laramie, 
    648 P.2d 551
    ,
    555 (Wyo. 1982). “[L]ack of precision is not itself offensive
    to the requirements of due process.” Browning v. State, 
    2001 WY 93
    , ¶ 12, 
    32 P.3d 1061
    , 1066 (Wyo. 2001).
    Travelocity.com LP v. Wyo. Dep’t of Revenue, 
    2014 WY 43
    , ¶ 98, 
    329 P.3d 131
    , 152 (Wyo.
    2014). As we explained above, the plain language of § 30-5-405(b) unambiguously
    demonstrates the legislature intended it to apply to underpayments. Any underpayment,
    even an underpayment of $1.00, triggers the statute. Because the statute clearly delineates
    when an operator will be liable for double damages, it is not unconstitutionally vague.1
    [¶22] Fourth, EOG claims that to interpret § 30-5-405(b) to include underpayments results
    in the word “fail” meaning different things throughout the Split Estate Act. It points to
    
    Wyo. Stat. Ann. § 30-5-404
    (e) and (f) (LexisNexis 2021), which refer to a surface owner
    who “has failed to bring an action for damages within the required time period” and who
    “has failed to give written notice,” respectively. According to EOG, “failed” in these
    subsections can refer only to not bringing an action and not giving notice because it is
    impossible to partially do either of these things. Unlike in these subsections, the word
    “fails” in § 30-5-405(b) is immediately followed by the infinitive phrase “to timely pay.”
    And, unlike the infinitive phrases used in these subsections, a person can “fail to pay” in
    whole or in part.2
    1
    In a footnote in its brief, EOG argues: “If an operator can run afoul of the [Split Estate] Act by underpaying
    by $1.00, then the statute has an inherent[ly] absurd result because that result can serve no practical purpose
    for operator or surface owner. Bridle Bit Ranch Co. [v. Basin Elec. Power Co-Op], [
    2005 WY 108
    ,] ¶ 21,
    118 P.3d [996,] 1008 [(Wyo. 2005)] (stating courts should not interpret statutes to create absurd results).”
    We fail to see any absurdity because it is unlikely a surface owner would sue an operator for a single
    underpayment of $1.00, for a mere recovery of $2.00. EOG’s argument also ignores that a surface owner
    cannot seek double damages for an underpayment of a $1.00 without first providing notice of the default to
    the operator and the operator failing to cure the default.
    2
    EOG also relies on other statutes outside the Split Estate Act, but they are not helpful for two reasons.
    First, “[w]e construe a statutory provision to harmonize it with other provisions relating to the same subject
    matter.” Wyo. Dep’t of Corr. v. Watts, 
    2008 WY 19
    , ¶ 23, 
    177 P.3d 793
    , 799 (Wyo. 2008) (emphasis
    added). See also, Bridle Bit Ranch Co., ¶ 21, 118 P.3d at 1008 (“‘In interpreting statutes, . . . [a]ll statutes
    must be construed in pari materia and, in ascertaining the meaning of a given law, all statutes relating to
    the same subject or having the same general purpose must be considered and construed in harmony.’”
    (emphasis added) (quoting In Re Loberg, 
    2004 WY 48
    , ¶ 5, 
    88 P.3d 1045
    , 1048 (Wyo. 2004), and Bd. of
    Cnty. Comm’rs of Teton Cnty. v. Crow, 
    2003 WY 40
    , ¶¶ 40–41, 
    65 P.3d 720
    , 733–34 (Wyo. 2003)).
    Second, like the statutory subsections from the Split Estate Act relied upon by EOG, none of these other
    7
    [¶23] Finally, EOG argues interpreting § 30-5-405(b) as applying to underpayments strays
    from the obvious intent of the legislature to shift from the common law accommodation
    doctrine, which allowed a mineral developer to use a surface owner’s land to develop the
    minerals without having to compensate the surface owner for any damage, to ensuring
    surface owners are compensated, whether through a surface use agreement or the operator
    posting a bond. According to EOG, § 30-5-405(b) acts as the enforcement mechanism
    should an operator attempt to rely on the accommodation doctrine for nonpayment. It
    maintains the legislature did not intend it to apply to situations, like here, where an operator
    is not attempting to avoid payment but rather, due to accounting errors resulting from a
    change in ownership and the complexity of the parties’ surface use agreements, there is a
    good faith dispute between the parties as to the amount owed. Indeed, EOG argues that if
    we interpret § 30-5-405(b) to apply to situations where there is a good faith payment
    dispute between the parties, an absurd result ensues as an operator would have to pay the
    amount demanded by the surface owner to avoid double damages, thereby allowing surface
    owners to use § 30-5-405(b) as a weapon to force operators to comply with their demands.
    EOG claims this cannot be what the legislature intended.
    [¶24] Nothing in the language of § 30-5-405(b) indicates the legislature intended it to
    apply only when an operator is seeking to avoid payment altogether or otherwise indicates
    the legislature intended to exempt an operator from double damages if its failure to pay the
    full amount due results from a good faith dispute between the parties about the amount
    owed. Rather, § 30-5-405 is analogous to the penalties imposed by the Wyoming Royalty
    Payment Act on oil and gas lessees and operators who violate its provisions, see 
    Wyo. Stat. Ann. § 30-5-303
     (LexisNexis 2021). In Cabot Oil & Gas Corp. v. Followill, 
    2004 WY 80
    ,
    ¶ 11, 
    93 P.3d 238
    , 242 (Wyo. 2004), we explained:
    “The [Wyoming Royalty Payment] Act is a remedial statute
    and, as such, is to be liberally construed to achieve its remedial
    purpose. Moncrief v. Harvey, 
    816 P.2d 97
    , 105 (Wyo. 1991).
    The Act was enacted in 1982 to stop oil producers from
    retaining other people’s money for their own use. Independent
    Producers Marketing Corp. v. Cobb, 
    721 P.2d 1106
    , 1110
    (Wyo. 1986).”
    Given the remedial nature of § 30-5-405(b), the legislature obviously intended it to ensure
    surface owners are timely paid the full and correct amount to which they are entitled under
    a surface use agreement. If an operator disputes the amount owed, it can avoid double
    damages by paying under protest and suing the surface owner to recover any overpayment.
    statutes speak to a failure “to pay.” See, e.g., 
    Wyo. Stat. Ann. §§ 1-11-125
     (LexisNexis 2021) (“fail to
    attend”); 1-21-1005 (LexisNexis 2021) (“fails to appear”); 22-18-111(a)(vi) (“fail to fill any vacancy”), (b)
    (“fail to appoint”), 30-5-109(c)(ii) (LexisNexis 2021) (“failing to so consent”), (j)(iii) (“fails to respond”);
    39-15-108(c)(xii) (LexisNexis 2021) (“fails to file a [tax] return”).
    8
    [¶25] The district court correctly decided § 30-5-405(b) applies to oil and gas operators,
    like EOG, which underpay installments owed under surface use and damage agreements.
    2. Statute of Limitations
    [¶26] In the district court, EOG argued JJLM’s claim for double damages was barred by
    the statute of limitations contained in § 1-3-105(a)(v)(D), which requires actions “[u]pon a
    statute for a penalty or forfeiture” to be brought within one year. The district court rejected
    EOG’s argument, concluding a cause of action for double damages under § 30-5-405(b)
    does not accrue until the surface owner provides written notice of the failure to pay to the
    oil and gas operator and the operator fails to cure the default within 60 days. It found EOG
    received written notice of default from JJLM on September 14, 2020, and JJLM’s cause of
    action accrued sixty days later, on November 14, 2020, when EOG failed to cure the
    default. As a result, the court determined JJLM’s December 8, 2020, lawsuit was filed well
    within the one-year statute of limitations.
    [¶27] EOG claims the district court erred by determining JJLM’s claim for double
    damages for underpayments made from 2016 to November 2019 were not barred by the
    one-year statute of limitations contained in § 1-3-105(a)(v)(D). Although it acknowledges
    we have never applied this limitations period to a claim for double damages under § 30-5-
    405(b), it nevertheless maintains we are likely to apply the discovery rule and hold the one-
    year limitations period begins to run when a surface owner knows or has reason to know
    of the existence of a cause of action. Applying the discovery rule, EOG argues JJLM had
    reason to know of the payment issues as soon as it received each payment because (1) EOG
    included the lease number with each payment, (2) EOG met with JJLM to explain the
    nature of each payment, and (3) JJLM had copies of the 2011 SDA and 2019 SUA.
    According to EOG, because JJLM had all the information necessary to know how
    payments should be calculated at the time the payments were being made, it should have
    known at that time they were incorrect. Nevertheless, JJLM waited until December 2020
    to file suit.
    [¶28] We have yet to decide whether § 1-3-105(a)(v)(D) applies to causes of action under
    § 30-5-405(b) but, even assuming it does, JJLM’s suit was timely. Section 1-3-
    105(a)(v)(D) provides:
    (a) Civil actions other than for the recovery of real
    property can only be brought within the following periods after
    the cause of action accrues:
    ...
    (v) Within one (1) year, an action . . .:
    ...
    9
    (D) Upon a statute for a penalty or
    forfeiture, except that if a different limitation is prescribed in
    the statute by which the remedy is given the action shall be
    brought within the period prescribed by the statute.
    “A cause of action accrues for statute of limitation purposes when all elements of the cause
    of action are present, including damages.” Lucky Gate Ranch, L.L.C. v. Baker & Assocs.,
    Inc., 
    2009 WY 69
    , ¶ 20, 
    208 P.3d 57
    , 65 (Wyo. 2009) (citing McCreary v. Weast, 
    971 P.2d 974
    , 979 (Wyo. 1999)). See also, Gillis v. F & A Enterprises, 
    934 P.2d 1253
    , 1255 (Wyo.
    1997) (“Generally, a cause of action accrues as soon as a right to maintain an action
    arises—when the plaintiff could have first filed and prosecuted the action to successful
    completion.” (citing DeWitt v. Balben, 
    718 P.2d 854
    , 858 (Wyo. 1986)) (other citations
    omitted).
    [¶29] Under the plain language of § 30-5-405(b), cited above, a cause of action for double
    damages does not accrue until (1) the operator fails to timely pay or underpays an
    installment, (2) the surface owner provides notice of the default, and (3) the operator fails
    to cure the default within 60 days of receiving the notice. In this case, EOG admitted that
    between 2016 and 2020, it underpaid and did not pay several installments owed to JJLM
    under the parties’ surface use and damage agreements. JJLM sent notice of default to EOG,
    and EOG received that notice on September 14, 2020. EOG had 60 days, or until
    November 14, 2020, to cure the default. When EOG did not cure the default by that date,
    a cause of action under § 30-5-405(b) accrued. EOG filed suit less than a month later and
    well within the one-year limitations period.
    [¶30] EOG resists this result. It claims the cause of action created by § 30-5-405(b) is for
    an operator’s failure to timely pay, which accrues when the failure to timely pay occurs.
    While a surface owner must first send notice of default prior to seeking double damages,
    EOG argues sending notice does not change that a cause of action exists. Accordingly,
    EOG argues the notice requirement is nothing more than a condition precedent to filing
    suit, not related to a statute of limitations. EOG is mistaken. The cause of action for an
    operator’s failure to timely pay an installment under a surface use and damage agreement
    is breach of contract, which is subject to a ten-year statute of limitations. Section 1-3-
    105(a)(i). JJLM brought its breach of contract claim well within the ten-year statute of
    limitations.
    [¶31] EOG argues that by holding the statute of limitations for a claim for double damages
    does not begin to run until the surface owner provides notice and the operator fails to cure,
    we are essentially finding the notice requirement of § 30-5-405(b) tolls the statute of
    limitations. It claims this interpretation creates an absurd result because a surface owner,
    even after discovering a failure to pay, could indefinitely toll the statute of limitations by
    not sending the notice. The notice requirement does not toll the statute of limitations.
    Rather, the statute of limitations for double damages under § 30-5-405(b) does not begin
    10
    to run until the surface owner provides notice and the operator fails to cure. As a result, a
    surface owner cannot indefinitely toll the statute of limitations by not sending notice. And,
    because the statute of limitations does not begin to run until the operator fails to cure, it is
    the operator, not the surface owner, which controls whether a cause of action for double
    damages ever comes into existence.
    [¶32] The district court correctly decided EOG’s claim for double damages under § 30-5-
    405(b) was not barred by the one-year statute of limitations contained in § 1-3-
    105(a)(v)(D).
    3. Laches
    [¶33] We have described laches as follows:
    “Laches bars a claim when a party has delayed in enforcing its
    rights to the disadvantage of another.” Windsor Energy Grp.,
    L.L.C. v. Noble Energy, Inc., 
    2014 WY 96
    , ¶ 12, 
    330 P.3d 285
    ,
    288 (Wyo. 2014) (citing Dorsett v. Moore, 
    2003 WY 7
    , ¶ 9, 
    61 P.3d 1221
    , 1224 (Wyo. 2003)). “The defense of laches is based
    in equity and whether it applies in a given case depends upon
    the circumstances.” Id., ¶ 12, 330 P.3d at 288–89 (quoting
    Ultra Resources, Inc. v. Hartman, 
    2010 WY 36
    , ¶ 123, 
    226 P.3d 889
    , 929 (Wyo. 2010)). “Two elements must be proven
    to establish laches: 1) inexcusable delay; and 2) injury,
    prejudice, or disadvantage to the defendants or others.” Id., ¶
    12, 330 P.3d at 289 (citing Moncrief, 775 P.2d at 1025). “The
    existence of laches is primarily determined not by lapse of time
    but by considerations of justice.” Merrill v. Rocky Mountain
    Cattle Co., 
    26 Wyo. 219
    , 
    181 P. 964
    , 974 (1919) (citation
    omitted).
    Tram Tower Townhouse Ass’n v. Weiner, 
    2022 WY 58
    , ¶ 44, 
    509 P.3d 357
    , 367 (Wyo.
    2022).
    [¶34] The district court determined EOG could not show JJLM inexcusably delayed in
    bringing its suit because neither party discovered EOG’s payment issues until around the
    time of the 2019 SUA. Although the parties attempted to resolve the issues, those efforts
    proved unsuccessful in Summer 2020 and JJLM filed suit a few months later, in December
    2020. The court also found EOG had not shown it was prejudiced by any delay because
    EOG was aware from its own audit in Summer 2020 that it had underpaid JJLM in the
    amount of $377,978.91, was notified of the default in September 2020, and was given an
    opportunity to cure. Nevertheless, EOG failed to cure the default. Thus, the court found
    any prejudice suffered by EOG was of its own making.
    11
    [¶35] EOG argues the district court erred by concluding JJLM’s claim was not barred by
    laches. It claims there was inexcusable delay because JJLM sat on its rights by waiting
    between two and four years to bring its claims relating to the 2016-2018 payments even
    though it had the information to allege these claims as soon as the payments were received.
    EOG also asserts it was prejudiced by the delay because it enabled JJLM to make a more
    expansive claim for double damages. According to EOG, had JJLM acted earlier, EOG
    would have had notice of the errors in its accounting system and acted sooner to ensure
    proper payment as its “goal has always been to pay correctly, hence why it escrowed the
    undisputed amount with the [c]ourt.”
    [¶36] The district court did not abuse its discretion by determining laches did not bar
    JJLM’s claim for double damages. EOG failed to show JJLM inexcusably delayed in
    bringing suit after discovering EOG’s non-compliance with the 2019 SUA. While EOG
    faults JJLM for not discovering the default sooner, the record shows EOG’s oil and gas
    operations on JJLM’s land are extensive and include the drilling and operation of over 20
    oil and gas wells and the construction and maintenance of miles of access roads, pipelines,
    power lines, and other infrastructure. Yet, when it submitted a payment, EOG did not
    include any information regarding the payment other than a lease number, making it
    difficult for JJLM to determine for what surface disturbance the payment was being made.
    EOG, itself, apparently did not discover its errors until JJLM brought them to its attention,
    even though EOG was responsible for the accounting system change and had knowledge
    of the 2011 SDA and signed the 2019 SUA. Moreover, the majority of EOG’s default
    arose after execution of the 2019 SUA. JJLM brought these issues to EOG’s attention no
    later than Summer 2020, less than a year after they arose, and brought suit in December
    2020.
    [¶37] EOG also failed to show it was prejudiced by any delay in JJLM bringing suit.
    Again, EOG faults JJLM for exposing it to double damages. Yet, EOG acknowledged that,
    in Summer 2020, it completed an audit of the payments it made to JJLM between 2016
    and 2020, discovered it owed JJLM $377,978.91, and “had several checks cut to begin
    paying that amount to JJLM” prior to JJLM filing suit. EOG, however, did not cure the
    default then, or after being provided notice and an opportunity to cure. As the district court
    aptly stated, any prejudice was of JJLM’s “own making.” Ultra Res., Inc. v. Hartman,
    
    2010 WY 36
    , ¶ 128, 
    226 P.3d 889
    , 930 (Wyo. 2010) (concluding the district court correctly
    determined the defendants had failed to establish their laches defense because, inter alia,
    any prejudice they suffered “was of their own making”).
    [¶38] The district court did not abuse its discretion by determining JJLM’s claim for
    double damages was not barred by laches.
    B. W.R.C.P. 59(e) motion
    12
    [¶39] EOG argues the district court abused its discretion by denying its Rule 59(e) motion.
    JJLM argues we lack jurisdiction to review the court’s denial of EOG’s Rule 59(e) motion
    because EOG failed to file an amended notice of appeal with respect to that denial. We
    agree with JJLM.
    [¶40] On March 2, 2022, while EOG’s Rule 59(e) motion was still pending, EOG filed its
    notice of appeal with respect to the district court’s summary judgment order. Under
    Wyoming Rule of Appellate Procedure (W.R.A.P.) 2.02(c), this notice of appeal became
    effective upon the district court’s summary denial of EOG’s Rule 59(e) motion. Rule
    2.02(c) (“If a party files a notice of appeal after the court announces or enters a judgment,
    but before it disposes of [certain motions, including a W.R.C.P. 59(e) motion to alter or
    amend], the notice becomes effective to appeal a judgment or order, in whole or in part,
    upon entry of a final order disposing of the last such remaining motion.”). However, if
    EOG intended to also appeal from the court’s denial of its Rule 59(e) motion, it was
    required to file an amended notice of appeal identifying that denial as an order being
    appealed. Rule 2.02(c) (“If the appealing party also intends to challenge the order
    disposing of the last remaining motion or the deemed denial of [] such motion, that party
    must file an amended notice of appeal within the time prescribed by Rule 2.01.”) (emphasis
    added). It did not.
    [¶41] Moreover, W.R.A.P. 2.07 requires a notice of appeal to “identify the judgment or
    appealable order” being appealed. See also, Painovich v. Painovich, 
    2009 WY 116
    , ¶ 11,
    
    216 P.3d 501
    , 504 (Wyo. 2009) (“W.R.A.P. 2.07 sets forth the substance of what must be
    contained within the notice of appeal, including identifying the judgment or appealable
    order that is being appealed and attaching, as an appendix, the order or judgment that is
    being appealed.”). A notice of appeal “only perfects an appeal of the order(s) identified in
    the notice.” Evans v. Moyer, 
    2012 WY 111
    , ¶ 18, 
    282 P.3d 1203
    , 1209 (Wyo. 2012) (citing
    Nish v. Schaefer, 
    2006 WY 85
    , ¶ 23, 
    138 P.3d 1134
    , 1143 (Wyo. 2006)). Because EOG
    did not identify the court’s denial of its Rule 59(e) motion in its notice of appeal, we lack
    jurisdiction to review that denial. Id., ¶ 19, 282 P.3d at 1209 (“To the extent Ms. Evans’
    appeal challenges the district court’s rulings in the October 2011 order or the sufficiency
    of the accountings, those claims and arguments are not properly before us because Ms.
    Evans did not identify that order in her notice of appeal.” (citing Painovich, ¶ 11, 216 P.3d
    at 504)). See also, Woodward v. Valvoda, 
    2021 WY 5
    , ¶ 35, 
    478 P.3d 1189
    , 1202 (Wyo.
    2021) (“Ms. Woodward’s notice of appeal did not identify an order denying her Rule 60(b)
    motion, which it must for this Court to have jurisdiction over it. W.R.A.P. 2.07(a)(2);
    6.01(b).”); State of Wyo., ex rel., Wyo. Dep’t of Workforce Servs., Workers Compensation
    Div. v. Beazer, 
    2016 WY 111
    , ¶ 26, 
    384 P.3d 267
    , 276 (Wyo. 2016) (concluding we lacked
    jurisdiction over the district court’s order awarding costs and attorney fees because the
    Wyoming Workers’ Safety and Compensation Division did not file a notice of appeal from
    that order).
    13
    [¶42] EOG claims, however, that a different result ensues because the district court
    granted its motion to consider its notice of appeal as “premature” under W.R.A.P. 2.04.3
    According to EOG, our rules of appellate procedure do not answer whether a premature
    notice of appeal also requires an amended notice of appeal when a party files the original
    notice “nearly simultaneous” with its Rule 59(e) motion. As a result, it claims the “logical
    reading of the procedure below is that EOG’s premature notice of appeal also served the
    same function as an amended notice because it covered the appropriate timeframe and
    orders. Therefore, this Court should retain appellate jurisdiction over the district court’s
    decision on EOG’s [R]ule 59 motion.”
    [¶43] It is unclear why the district court granted EOG’s motion to consider its notice of
    appeal as premature under Rule 2.04 when the court it had entered, not merely announced,
    its summary judgment order. Rule 2.04 (“A notice of appeal filed after the court announces
    a decision or order -- but before entry of the judgment or order -- is treated as filed on the
    date of and after the entry. A premature notice of appeal shall comply with Rule 2.07, to
    the extent possible.”). In any event, Rule 2.02(c) clearly required EOG to file an amended
    notice of appeal if it wished to challenge on appeal the court’s denial of its Rule 59(e)
    motion. It does not matter that EOG’s motion was filed “nearly simultaneous” with its
    notice of appeal. Without a notice of appeal identifying the district court’s denial of EOG’s
    Rule 59(e) motion, we are without jurisdiction to review that denial.
    C. Attorney Fees
    [¶44] In the district court, JJLM argued it was entitled to its attorney fees and costs under
    the 2019 SUA, which stated: “If Operator defaults under this agreement, Operator shall
    pay all costs and expenses, including a reasonable attorney’s fee, incurred by Owner in
    successfully enforcing this agreement.” EOG agreed JJLM was entitled to the fees and
    costs incurred in bringing its breach of contract claim, but claimed JJLM was not entitled
    to the fees and costs incurred in prosecuting its double damages claim because such claim
    does not constitute “enforcing” the 2019 SUA. The district court concluded JJLM’s claims
    could not be separated and awarded JJLM its requested fees. EOG did not appeal from the
    court’s award of fees. JJLM now seeks the attorney fees and costs it incurred in defending
    this appeal. Because EOG has not appealed from the district court’s determination that
    JJLM is entitled to its attorney fees and costs under the 2019 SUA and because EOG does
    not contest JJLM’s request for its appellate fees and costs in its reply brief, JJLM is also
    entitled to its attorney fees and costs on appeal. Cf. Levy v. Aspen S, LLC, 
    2021 WY 46
    , ¶
    32, 
    483 P.3d 852
    , 860 (Wyo. 2021) (“Because Mr. Levy is entitled to his attorney fees and
    costs under the easement’s fee-shifting provision, he is also entitled to the attorney fees
    and costs he incurred in this appeal.”); Kinstler v. RTB South Greeley, Ltd., LLC, 
    2007 WY 3
    EOG claims the parties and the district court exchanged emails concerning “how to handle . . .
    procedurally” the fact that both its notice of appeal and its Rule 59(e) motion left its counsel’s office “on
    the same date, one fax filed and one via mail.” It alleges the parties and the court agreed to treat EOG’s
    notice of appeal as premature under W.R.A.P. 2.04. The emails are not in the record.
    14
    98, ¶ 13, 
    160 P.3d 1125
    , 1129 (Wyo. 2007) (“Where a contract allows the award of
    attorney’s fees, that includes fees incurred on appeal.”); DeWitt, 718 P.2d at 864 (“[I]f
    attorney’s fees are expressly authorized by contract or statute, such provision also applies
    to fees incurred at the appellate level.”).
    CONCLUSION
    [¶45] The district court correctly determined § 30-5-405(b) applies when an oil and gas
    operator underpays an installment owed to a surface owner under a surface use and damage
    agreement. The court also properly concluded JJLM’s claim for double damages was not
    barred by either the statute of limitations or laches. We therefore affirm the district court’s
    grant of summary judgment to JJLM on its claim for double damages under § 30-5-405(b).
    We lack jurisdiction to review the court’s denial of EOG’s Rule 59(e) motion because EOG
    failed to effect an appeal from that denial. JJLM is entitled to its attorney fees and costs
    on appeal. We will decide the appropriate amount of appellate fees and costs after JJLM
    submits the proper documentation. See Levy, ¶ 32, 483 P.3d at 860 (citing Cline v. Rocky
    Mountain, Inc., 
    998 P.2d 946
    , 953 (Wyo. 2000) (“Generally, the appellate court, rather
    than the trial court, determines the proper amount of fees to be awarded for the legal work
    on appeal.”)).
    15
    

Document Info

Docket Number: S-22-0095

Filed Date: 12/28/2022

Precedential Status: Precedential

Modified Date: 12/28/2022