Black Diamond Energy, Inc., a Delaware Corporation v. Encana Oil and Gas (Usa) Inc., a Delaware Corporation , 2014 Wyo. LEXIS 69 ( 2014 )


Menu:
  •                IN THE SUPREME COURT, STATE OF WYOMING
    
    2014 WY 64
    APRIL TERM, A.D. 2014
    May 20, 2014
    BLACK DIAMOND ENERGY, INC., a
    Delaware Corporation,
    Appellant
    (Plaintiff),
    v.                                                   S-13-0151
    ENCANA OIL AND GAS (USA) INC., a
    Delaware Corporation,
    Appellee
    (Defendant).
    Appeal from the District Court of Johnson County
    The Honorable John G. Fenn, Judge
    Representing Appellant:
    Greg L. Goddard, Goddard, Wages & Vogel, P.C., Buffalo, Wyoming; J. David
    Jorgenson, Sneed Lang PC, Tulsa, Oklahoma. Argument by Mr. Jorgenson.
    Representing Appellee:
    Darin B. Scheer, Farson, Wyoming; Erin K. Murphy, Bjork Lindley Little PC,
    Denver, Colorado. Argument by Mr. Scheer.
    Before KITE, C.J., and HILL, VOIGT*, BURKE, and DAVIS, JJ.
    Justice Voigt retired effective January 3, 2014.
    NOTICE: This opinion is subject to formal revision before publication in Pacific Reporter Third.
    Readers are requested to notify the Clerk of the Supreme Court, Supreme Court Building,
    Cheyenne, Wyoming 82002, of typographical or other formal errors so correction may be made
    before final publication in the permanent volume.
    KITE, Chief Justice.
    [¶1] Black Diamond Energy, Inc. (BDE) brought a breach of contract action against
    Encana Oil and Gas (USA) Inc. (Encana). Encana counterclaimed. After a trial, the jury
    found BDE breached the contract but awarded Encana no damages. BDE appeals
    claiming the district court erred in giving a breach of contract instruction and verdict
    form that did not fit the facts of this case. BDE also claims the district court erred in
    excluding its expert testimony and reports, and evidence involving a well in a different
    oil and gas unit. We affirm.
    ISSUES
    [¶2]   Restated, the issues BDE asks the Court to consider are:
    A.     Whether, under the circumstances of this case, the District Court erred by
    instructing the jury that when a party materially breaches the contract the other party is
    not required to continue to perform the contract.
    B.     Whether, under the circumstances of this case, the District Court erred by
    giving the jury a verdict form requiring it to find which party breached the contract first.
    C.    Whether the district court erred in excluding BDE’s expert witness
    testimony and reports on damages.
    D.     Whether the district court erred in excluding evidence concerning Encana’s
    failure to apply surplus funds paid on a well in another unit to BDE’s shortfalls on well
    expenses in the unit covered by the contract in this case.
    FACTS
    [¶3] BDE is a Delaware corporation with its principal place of business in Buffalo,
    Wyoming. Encana is a Delaware corporation with its principal place of business in
    Denver, Colorado. In August of 2006, BDE and Encana entered into a farmout
    agreement (FOA) involving the development of oil and gas interests in Sublette County,
    Wyoming.
    [¶4] Pursuant to the FOA, BDE was to cause wells to be drilled on land located in the
    Crimson Unit on which Encana owned undivided working interests to oil and gas leases.
    In exchange for exploring the lands for oil and gas, BDE was to earn working interests in
    the Encana leases. Encana was to act as well operator on the initial test well in the unit,
    meaning that it would perform the drilling, completion and production or plugging and
    abandoning operations. BDE was required to pre-pay Encana $1.4 million toward the
    costs of drilling the initial test well. After the initial test well, BDE had the option to act
    as well operator on the additional wells or could request that Encana act as well operator.
    1
    In either event, the FOA required BDE to pay the full costs of the drilling and completion
    operations for the eight test wells up to an amount specified in the FOA.1
    [¶5] Paragraph 1 of the FOA required BDE to meet several minimum requirements in
    order to earn working interests in the Encana leases. BDE was to:
    A.     Cause a minimum of eight test wells to be drilled and
    completed as a producer or plugged and abandoned;
    B.     Spend at least $12 million on the drilling and
    completion of the test wells;
    C.     Locate one test well in each of four designated
    quadrants within the unit;
    D.    Commence the first test well by September 30, 2006,
    and each subsequent well within 120 days of the last well
    commenced;
    E.     Adhere to all material financial obligations under the
    FOA and the Crimson Unit Operating Agreement.
    [¶6] Upon meeting all of these requirements, BDE’s right to earn an interest in the
    Encana leases would vest. BDE could then make a written request to Encana for an
    assignment of earned leasehold interest. If Encana was satisfied that BDE’s interest had
    vested and if BDE had complied with all other provisions of the FOA, Encana was
    required to assign to BDE fifty percent of Encana’s leasehold interest throughout the
    entire Crimson Unit to the base of the Lance formation.2
    [¶7] The FOA also provided, however, that BDE’s interest could vest even if BDE failed
    to meet requirements D or E.3 In that event, upon receipt of BDE’s written request for
    assignment and presentation of satisfactory evidence that each test well had been
    completed, and provided that BDE had complied with other provisions of the FOA,
    1
    In the event BDE elected to have Encana act as well operator, the FOA provided that if costs exceeded
    $1.5 million on a particular test well, Encana would pay fifty percent of the excess costs from $1.5
    million to $2 million and 100% of excess costs above $2 million. If costs reached or exceeded $2.5
    million, Encana had the discretion to plug and abandon the test well.
    2
    The FOA required test wells to be drilled to the base of the Lance Pool or to such depth as necessary to
    thoroughly test the Lance formation. Accordingly, the 50% interest assigned to BDE was to the base of
    the Lance formation.
    3
    Although not at issue here, the FOA also provided that if BDE met requirements A and B but did not
    meet requirement C, BDE’s interest would not vest in the entire Crimson Unit but only in the drilled test
    blocks.
    2
    Encana was to assign to BDE fifty percent of Encana’s leasehold interest in the test
    blocks4 in which test wells had been drilled.
    [¶8] Pursuant to the terms of the FOA, BDE prepaid $1.4 million for the initial test well
    and Encana drilled and completed it. Thereafter, BDE exercised its option and requested
    that Encana act as well operator on the remaining test wells. In accordance with the
    terms of the FOA, Encana charged BDE for the costs it incurred in drilling and
    completing the test wells and BDE was required to remit payment to Encana.
    [¶9] By December of 2007, eight test wells had been drilled and BDE had spent over $12
    million dollars. However, four of the wells had not been completed as a producer or
    plugged and abandoned. Ultimately, the last of the eight test wells was not completed
    until late 2008.
    [¶10] Meanwhile, in late 2007, Encana sent a letter to BDE confirming earlier
    discussions between the parties concerning BDE’s failure to remit payments for drilling
    costs to Encana in a timely manner. The letter memorialized Encana’s understanding that
    BDE had committed to bringing its account current by the end of the year. In April of
    2008, Encana again contacted BDE concerning unpaid invoices which, according to
    Encana’s accounting department, totaled over $1 million and were ninety days late. By
    letter dated August 28, 2008, Encana informed BDE that Encana considered BDE to be in
    default under the FOA by failing to remit payments to Encana for the costs Encana had
    incurred in acting as operator on BDE’s behalf. According to Encana, BDE’s failure to
    meet its financial obligations meant BDE’s interest in the leaseholds would vest only in
    the test blocks in which wells had been drilled and completed. Encana asked BDE to
    remit payment of all amounts due by September 30, 2008, and make all future payments
    in a timely manner. In the event BDE’s account became past due in the future, Encana
    stated it would offset revenues to which BDE was entitled from producing wells in the
    Crimson Unit against BDE’s account. Encana also proposed to complete the four
    remaining test wells before the end of October.
    [¶11] BDE did not respond to the letter and two weeks later Encana sent another letter
    advising that if BDE did not agree to Encana’s August 28 proposal by the following day,
    Encana would terminate the FOA. BDE signed and returned the letter along with a check
    for the amount it considered due. Encana claimed the check did not cover the full
    amount BDE owed and, by email dated October 14, 2008, terminated the FOA effective
    September 30, 2008. BDE responded that the amount due Encana was significantly
    lower than Encana claimed, Encana’s delay in completing the wells caused BDE to
    experience a severe cash shortage and BDE hoped to be in a position to make further
    payments to Encana in two weeks.
    4
    There were four quadrants, or exploration areas, in the Crimson Unit. There were twenty-two test
    blocks within the Unit.
    3
    [¶12] Thereafter, the parties continued to exchange correspondence concerning the
    amounts allegedly due and any assignments BDE may have earned. No assignment of
    interest was ever made to BDE and, in May of 2011, BDE filed a complaint against
    Encana. BDE alleged that it had satisfied the requirements of the FOA and earned the
    right to the assignment of interest in Encana’s leaseholds in the entire Crimson Unit.
    BDE alleged Encana had refused to execute and deliver the assignments on the grounds
    that BDE had failed to meet its financial obligations as required by paragraph 1E of the
    FOA. BDE alleged Encana was treating the requirement in 1E as a condition precedent
    to its obligation to assign the interests to BDE, contrary to the terms of the agreement.
    BDE claimed Encana’s reason for refusing to make the assignments was pretextual and
    that in actuality BDE had overpaid Encana. BDE sought rescission of the FOA and
    repayment of all amounts it had paid to Encana. Alternatively, BDE sought an
    accounting that would allow it to determine its damages for Encana’s breach of contract.
    BDE also asserted claims for fraud and quantum meruit and sought damages in the
    amount it had paid to Encana.
    [¶13] Encana denied BDE’s claims and filed a counterclaim. Encana alleged that it had
    performed its obligations under the FOA in good faith and attempted to accommodate
    BDE’s inability to meet its financial obligations to no avail. Encana sought a judgment
    declaring that BDE’s failure to meet its financial obligations precluded BDE from
    earning any assignment of interest in the Crimson Unit leaseholds. Alternatively, Encana
    sought judgment declaring that even if BDE had met its financial obligations it was not
    entitled to assignment of any interest until “Well Payout” occurred. Encana also sought
    judgment determining whether BDE retained the right to meet its financial obligations
    and, if so, what interest it would be entitled to if it met those obligations. In addition to
    seeking declaratory judgment on those issues, Encana asserted claims against BDE for
    breach of contract and breach of the covenant of good faith and fair dealing and sought
    damages.
    [¶14] Both parties filed motions for summary judgment. BDE sought partial judgment
    holding that as a matter of law Encana breached the FOA by not assigning BDE the
    interests to which it was entitled. BDE argued that the FOA unambiguously required
    Encana to assign interests to BDE, the district court only had to determine whether the
    agreement was breached, and the undisputed facts showed Encana did not make the
    assignments. Ruling on BDE’s motion, the district court concluded the FOA provided
    that BDE was to receive assignments even if BDE did not meet the minimum
    requirements. However, the court concluded, it could not “say as a matter of law that
    BDE is entitled to assignments of some or all of the wells or Encana’s interests” because
    questions of fact existed as to “which party breached the [FOA] first and whether these
    4
    supposed breaches were excused.”             On that basis, the district court denied BDE’s
    motion.5
    [¶15] In its summary judgment motion, Encana sought a judgment holding: 1) the
    phrase “completed as a producer” in the FOA meant the well casings were perforated and
    fracked and the wells were hooked up to the production line; 2) Encana had the right to
    terminate the FOA as a result of BDE’s repeated failure to pay its bills; 3) the fraud claim
    lacked specificity, was barred by the economic loss rule, did not satisfy the elements of
    fraud and was not supported by clear and convincing evidence; 4) rescission was not an
    available remedy; and 5) BDE was not entitled to 50% of Encana’s interest in the entire
    Crimson Unit. The district court held as a matter of law the phrase “completed as a
    producer” meant a well capable and ready to produce gas, including perforation and
    fracking, but did not require that the well be hooked up to the pipeline. The district court
    concluded a factual question existed as to when the wells were completed. The district
    court also concluded issues of fact existed as to whether BDE breached the FOA, whether
    Encana’s delay in fracking the wells and failure to submit invoices to BDE excused any
    breach by BDE, when vesting occurred and whether Encana was entitled to unilaterally
    terminate the FOA. The district court dismissed the fraud claim, finding it unsupported
    by any evidence. The district court held rescission was not an available remedy as a
    matter of law and genuine issues of material fact existed as to whether BDE was entitled
    to 50% of Encana’s interest in the entire Crimson Unit.
    [¶16] The matter proceeded to trial before a jury in 2013. BDE attempted to show that it
    paid for the drilling of eight wells in the designated test blocks and spent $12 million as
    required by the FOA. BDE also attempted to show that although eight wells were drilled,
    Encana delayed completion of four of them in breach of the FOA. BDE claimed it had
    substantially performed its financial obligations at the time of Encana’s breach. BDE
    sought damages in the amount it had paid to Encana for well operations less any amounts
    Encana had paid to BDE from well production.
    [¶17] Encana attempted to prove that BDE breached the FOA by failing to timely remit
    payments for drilling operations. Encana also attempted to show that BDE had breached
    the FOA long before the delay in completing the last four wells occurred. Encana also
    attempted to show that it was not obligated under the terms of the FOA to complete the
    wells or assign interests to BDE if BDE did not meet its financial obligations; therefore,
    when BDE did not pay its bills, Encana was not required to continue to perform under the
    FOA by completing the wells or making assignments. Encana asserted that when it
    terminated the agreement in October 2008, BDE had not met two of the requirements
    under the contract—causing eight wells to be completed and meeting its financial
    obligations—leaving Encana with no obligation to assign any interests to BDE. Encana
    5
    BDE has not appealed the district court’s ruling on its summary judgment motion. We, therefore, do not
    consider whether the ruling was correct.
    5
    also attempted to prove it did not complete the last four test wells until after it terminated
    the FOA because of BDE’s actions.
    [¶18] During the instruction conference after both parties had presented their evidence,
    the district court indicated it intended to give the following breach of contract instruction:
    Instruction No. 24
    If a party materially breaches the contract, the non-
    breaching party is no longer required to continue performing
    under the contract.
    BDE objected to the instruction, arguing that a party cannot continue to accept
    performance by the other party after a breach and then later declare it had no obligation to
    perform under the contract after the breach. BDE argued the law requires a party either
    to declare the breach and terminate the contract or continue to perform the contract. In
    the context of this case, BDE asserted Encana could not claim BDE breached the contract
    at some date by failing to pay its bills, continue to accept payments from BDE after the
    alleged breach and later declare Encana was not required to complete the wells or assign
    interests on the basis of BDE’s earlier breach. The district court gave the instruction over
    BDE’s objection.
    [¶19] The district court also gave the jury the following verdict form:
    1. Please find which party by a preponderance of the
    evidence breached the contract and/or the implied
    covenant of good faith and fair dealing?
    ______ Encana                           ______ [BDE]
    2. What are the damages proven by a preponderance of the
    evidence by the non-breaching party?
    $______________
    BDE objected to the verdict form on the basis that the FOA did not make Encana’s
    performance conditional on BDE’s performance, or vice versa, and neither party had
    taken that position in presenting its case. BDE argued the jury should be allowed to
    decide whether Encana breached the FOA and, if so, the amount of BDE’s damages and
    to decide whether BDE breached the FOA and, if so, the amount of Encana’s damages.
    The district court gave the verdict form quoted above over BDE’s objection.
    [¶20] After deliberating, the jury returned a verdict finding that BDE breached the FOA
    but Encana proved no damages. BDE filed a motion for a new trial claiming among
    6
    other things that the verdict form contradicted the express terms of the parties’
    agreement. Specifically, BDE asserted the verdict form permitted a finding, contrary to
    the terms of the FOA, that upon BDE’s failure to meet its financial obligations, Encana
    was not required to assign BDE any leasehold interest. After a hearing, the district court
    denied the motion. BDE appealed to this Court.
    DISCUSSION
    1. Jury Instruction
    [¶21] BDE contends the district court erred in giving Instruction No. 24 which, as set
    forth in paragraph 18 above, told the jury that if a party materially breached the contract,
    the non-breaching party was no longer required to continue performing. While
    conceding that this is a correct statement of the law generally, BDE argues the instruction
    was not appropriate under the facts of this case. BDE asserts, as it did in the district
    court, that a party cannot assert a breach occurred, fail to declare the breach, continue to
    accept performance by the other party and then refuse to perform its part of the bargain.
    Citing Richard A. Lord, Williston on Contracts § 39:32 (4th ed. 2000), BDE asserts the
    law applicable in the context of this case is that a victim of a breach must either declare
    the breach or move ahead with the contract; it cannot continue to receive benefits under
    the contract and then refuse to perform its part of the bargain. As applied to this case,
    BDE contends the jury should have been instructed that if BDE breached the FOA by
    failing to remit payments due, Encana either had to declare the breach and terminate the
    FOA at the time or continue to accept payments from BDE and perform Encana’s part of
    the bargain by assigning the leasehold interests BDE had earned. Because Encana
    continued to accept payments, BDE argues, Encana was obligated to complete the wells
    and assign the leasehold interests.6
    [¶22] Encana responds that Wyoming law is clear—“the party first committing a
    substantial breach of contract cannot complain that the other party thereafter fails to
    perform, and where one party to a contract repudiates it or refuses to perform, the injured
    party is not obligated to perform its promises.” Williams v. Collins Communications,
    Inc., 
    720 P.2d 880
    , 891 (Wyo. 1986). Applying the controlling law, Encana contends
    that upon BDE’s failure to remit payments to Encana for costs incurred in drilling and
    6
    Citing PBS Enterprises, Inc. v. CWCapital Asset Management LLC, 
    2008 WY 53
    , ¶ 9, 
    183 P.3d 1140
    ,
    1142 (Wyo. 2008), BDE also quotes the rule that where the parties mutually adopt a mode of performing
    their contract differing from its strict terms, or mutually relax its terms by adopting a loose mode of
    executing it, neither party can later claim a breach based upon lack of strict compliance. The difficulty
    with applying this rule in the present case is that there was no evidence Encana agreed to relax the terms
    of the FOA or to adopt a mode of performing it different from its terms. That is, there was no evidence
    Encana agreed to BDE failing to remit payments due. To the contrary, the evidence showed that Encana
    expected timely payments of all amounts due. Perhaps for that reason, the district court declined to give
    BDE’s proposed instruction on mutual relaxation or modified performance.
    7
    completing the wells, BDE could not complain that Encana did not complete the wells
    and refused to make assignments.
    [¶23] We review a district court’s decision to give or refuse a particular jury instruction
    for an abuse of discretion. Glenn v. Union Pacific R.R. Co., 
    2011 WY 126
    , ¶ 39, 
    262 P.3d 177
    , 194 (Wyo. 2011), citing Pina v. Christensen, 
    2009 WY 64
    , ¶ 8, 
    206 P.3d 1298
    , 1300
    (Wyo. 2009).
    When examining the propriety of jury instructions, this
    Court reviews whether the instructions, taken as a whole,
    adequately and clearly advise the jury of the applicable law.
    The trial court is not obligated to give an instruction offered
    by a party as long as the jury is adequately instructed on the
    law as it pertains to that case. The trial court's ruling on an
    instruction will not constitute reversible error absent a
    showing of prejudice, and prejudice will not be said to result
    unless it is demonstrated that the instruction confused or
    misled the jury with respect to the proper principles of law.
    Sellers v. Dooley Oil Transport, 
    2001 WY 44
    , ¶ 9, 
    22 P.3d 307
    , 309 (Wyo.2001); Cervelli v. Graves, 
    661 P.2d 1032
    ,
    1036 (Wyo.1983). The burden is on the appellant to show
    prejudicial error. Daley v. Wenzel, 
    2001 WY 80
    , ¶ 29, 
    30 P.3d 547
    , 554-55 (Wyo.2001).
    Glenn, ¶ 
    39, 262 P.3d at 194-195
    , quoting Parrish v. Groathouse Constr., Inc., 
    2006 WY 33
    , ¶ 7, 
    130 P.3d 502
    , 505 (Wyo. 2006).
    [¶24] In the present case, the issue is whether instruction No. 24 advised the jury of the
    applicable law. We review the legal sufficiency of jury instructions de novo, asking first
    whether an instruction is erroneous, and second whether the error prejudiced a party.
    Pina, ¶ 
    6, 206 P.3d at 1300
    . Thus, even when reviewed de novo, errors of substantive
    law contained in the language of an instruction require reversal only if the error is
    prejudicial. 
    Id., quoting State
    Farm Mut. Auto. Ins. Co. v. Shrader, 
    882 P.2d 813
    , 832
    (Wyo. 1994).
    [¶25] Initially, we note that BDE did not offer a jury instruction setting forth the
    principles it relied on in objecting to instruction No. 24. Instead, on the breach of
    contract issue, BDE offered a variety of other instructions—instructions on breach of
    unambiguous contracts, interpretation of ambiguous contracts, written modification of
    contract, oral modification of contract, mutual mistake, substantial performance, mutual
    relaxation of contract terms and time for performance. The relevance of some of these
    proposed instructions is not clear given the facts of this case. In any event, no instruction
    8
    was offered for the district court’s consideration on the principles BDE argued in
    opposition to instruction No. 24.
    [¶26] Moreover, under Wyoming law, “the first party committing a substantial breach of
    contract cannot complain that the other party thereafter fails to perform, and where one
    party to a contract repudiates it or refuses to perform, the injured party is not obligated to
    perform its promises.” 
    Williams, 720 P.2d at 891
    . See also Winter v. Pleasant, 
    2010 WY 4
    , ¶ 12, 
    222 P.3d 828
    , 834 (Wyo. 2010) and Baker v. Speaks, 
    2008 WY 20
    , ¶ 14, 
    177 P.3d 803
    , 807 (Wyo. 2010), in which the Court reiterated that the party first committing a
    substantial breach of contract cannot complain that the other party fails to perform. The
    district court’s instruction in this case is consistent with Wyoming law.
    [¶27] BDE contends whether or not the instruction is a correct statement of Wyoming
    law, it should not have been given here because it did not fit the facts of this case. In this
    case, BDE asserts, the parties’ agreement expressly required Encana to perform by
    making assignments even if BDE was in breach by failing to meet its financial
    obligations. BDE points to paragraph 16 of the FOA, which stated in pertinent part:
    16. Leasehold earned if less than the Minimum
    Requirements are met. In the event that the Vesting Date
    occurs without all of the Minimum Requirements having been
    met, upon receipt of BDE’s written request for an
    assignment(s), such request to be received by EnCana no later
    than sixty (60) days following the Vesting Date, such notice
    providing evidence of Vesting to Encana’s satisfaction and
    upon receipt of evidence to EnCana’s satisfaction that each
    Test Well has been completed as a well capable of producing
    oil and/or gas or P&A’d as a dry hole, and provided that BDE
    has complied with other applicable terms and provisions of
    this Agreement, Encana shall assign to BDE fifty percent
    (50%) of EnCana’s leasehold interest in those Test Blocks in
    which Test Wells have been drilled (such assignment referred
    to herein as a “Leasehold Assignment”).
    [¶28] BDE asserts that when it failed to meet its financial obligations as required by
    paragraph 1E of the agreement, paragraph 16 took effect and Encana was required to
    assign to BDE fifty percent of Encana’s leasehold interest in the test blocks in which test
    wells had been drilled. In other words, whether or not BDE had paid its bills, paragraph
    16 triggered a required performance by Encana— assignment of 50% of its interest in test
    blocks where test wells were drilled. The effect of instruction No. 24, BDE contends,
    was to tell the jury that upon BDE’s failure to meet its financial obligations, Encana was
    not required to perform by assigning the interest—a result BDE contends was contrary to
    the express language of the parties’ agreement.
    9
    [¶29] The difficulty with BDE’s argument is that the issue of its entitlement to
    assignment of leasehold interests was left to the jury. In ruling on BDE’s motion for
    partial summary judgment, the district court concluded that although BDE “may” be
    entitled to an assignment under the FOA, the court could not “say as a matter of law that
    BDE is entitled to assignments” because questions of fact existed as to which party
    breached the FOA first and whether any such breaches were excused. There was,
    therefore, no legal ruling interpreting the FOA provisions concerning BDE’s right to
    assignments or Encana’s obligation to make them. The jury was left to interpret the
    provisions. We reiterate—BDE did not appeal the summary judgment decision.
    [¶30] Although BDE argues that paragraph 16 of the FOA required Encana to make
    assignments even if BDE failed to meet its financial obligations as required by paragraph
    1E, the jury may well have concluded otherwise. Paragraph 16 states that Encana’s
    obligation to make the assignments depends upon evidence that “each of the test wells
    has been complete. . . .” Thus, the jury may have interpreted the FOA to mean that BDE
    was entitled to partial assignment only if it had satisfied paragraph 1A by causing eight
    test wells to be drilled and completed. Given the evidence that eight wells were not
    completed, the jury may have concluded BDE was not entitled to partial assignment
    under paragraph 16.
    [¶31] Instruction No. 24 is a correct statement of Wyoming law. While trial courts are
    afforded substantial latitude to tailor the instructions to the facts of the case, Glenn, ¶ 
    41, 262 P.3d at 196
    , citing Budder v. State, 
    2010 WY 123
    , ¶ 7, 
    238 P.3d 575
    , 577 (Wyo.
    2010), the facts of the present case did not support departing from the Williams line of
    cases and giving the instruction urged by BDE. The district court did not abuse its
    discretion in giving instruction No. 24.
    2. Verdict Form
    [¶32] BDE contends the district court erred in giving the jury a verdict form asking it to
    determine which party breached the contract and the damages proven by the non-
    breaching party. BDE asserts the effect of the verdict form and instruction No. 24 was to
    erroneously instruct the jury that there could be only one breaching party and only one
    party entitled to damages. BDE asserts the district court should have given BDE’s
    proposed verdict form, which asked the jury to determine, first, whether Encana breached
    the FOA and, if so, what BDE’s damages were and, second, whether BDE breached the
    FOA and, if so, what Encana’s damages were. BDE contends its proposed verdict is
    consistent with the terms of the FOA, while the district court’s verdict form is contrary to
    those terms. Again focusing on paragraph 16, BDE argues that a breach by BDE of any
    of the minimum requirements of the FOA triggered, rather than excused, Encana’s
    obligation to perform by assigning leasehold interests to BDE. For the same reasons we
    concluded the district court did not err in giving instruction No. 24, we hold it did not err
    10
    in giving its proposed verdict form rather than the one BDE proposed. BDE’s proposed
    verdict form was not consistent with the jury instructions the district court gave and BDE
    offered no instruction to support giving its proposed verdict form. Moreover, BDE’s
    argument assumes its interpretation of paragraph 16 is correct as a matter of law. The
    district court expressly held it could not say as a matter of law that BDE was entitled to
    an assignment. The jury was left to interpret the contract and it apparently concluded
    BDE breached the FOA and Encana was not required to assign interests.
    [¶33] Although we have concluded it was not error under the circumstances to give
    instruction No. 24 or the verdict form to the jury, we note that this was a complex case
    involving a highly technical and complicated agreement. Rather than obtaining legal
    rulings from the district court concerning the meaning of particular contract provisions
    and then having the court instruct the jury concerning those rulings, the jury was left to
    decipher important provisions of the contract. At the summary judgment stage, BDE
    asked the district court to rule broadly that its right to an assignment had vested as a
    matter of law; however, rather than relying on particular contract language, BDE argued
    mostly factual matters. When the verdict form was discussed, no one suggested asking
    the jury to determine whether specific provisions of the contract had been met. In a case
    this complex, it would have been helpful to have the jury decide, for example, which, if
    any, of the minimum requirements were met and whether BDE’s interest had vested.
    Instead, the jury was left to sort out not only what happened between the parties but what
    the contract meant. The verdict form BDE offered would not have clarified the issues for
    the jury. Although from the record it appears this case could have been presented to the
    jury differently, our task is to address the issues raised. Addressing those issues, we
    conclude the district court did not err as a matter of law or abuse its discretion in
    instructing or submitting the challenged verdict form to the jury.
    3. Exclusion of Expert Testimony and Reports
    [¶34] Prior to trial, the district court excluded the testimony and report of BDE’s expert
    witness, John Wheeler, on the ground that BDE failed to comply with the disclosure
    requirements stated in the scheduling order and W.R.C.P. 26(a)(2). During the trial, the
    district court also excluded a report, the Allen & Crouch report, on the ground that it was
    double hearsay. BDE contends it was error for the district court to exclude this evidence.
    Rulings on the admissibility of evidence are within the sound discretion of the trial court
    and will not be disturbed by this Court absent a clear abuse of discretion. City of Gillette
    v. Hladky Constr., Inc., 
    2008 WY 134
    , ¶ 84, 
    196 P.3d 184
    , 211 (Wyo. 2008). We begin
    by addressing the district court’s ruling as to Mr. Wheeler.
    a.     Wheeler report and testimony.
    [¶35] In its January 2012 scheduling order, the district court gave each party bearing the
    burden of proof on any issue until September 21, 2012, to designate any expert witnesses
    11
    the party intended to call to testify concerning the issue. The scheduling order expressly
    stated that W.R.C.P. Rule 26 (a)(2) applied except as indicated.7 Rule 26(a)(2) provides:
    (a) Required disclosures; . . .
    (2) Disclosure of expert testimony.
    (A) . . . a party shall disclose to other parties the
    identity of any person who may be used at trial to present
    evidence under Rules 702, 703, or 705 of the Wyoming Rules
    of Evidence
    (B) Except as otherwise stipulated or directed
    by the court, this disclosure shall, with respect to a witness
    who is retained or specially employed to provide expert
    testimony in the case or whose duties as an employee of the
    party regularly involve giving expert testimony, be
    accompanied by a written report prepared and signed by the
    witness or disclosure signed by counsel for the party. The
    report or disclosure shall contain a complete statement of all
    opinions to be expressed and the basis and reasons therefor;
    the data or other information considered by the witness in
    forming the opinions; any exhibits to be used as a summary
    of or support for the opinions; the qualifications of the
    witness, including a list of all publications authored by the
    witness within the preceding ten years; the compensation to
    be paid for the study and testimony; and a listing of any other
    cases in which the witness has testified as an expert at trial or
    by deposition within the preceding four years.
    (Emphasis added.)
    [¶36] On September 21, 2012, BDE emailed to Encana a letter listing seven expert
    witnesses that BDE intended to call. The first three witnesses were identified as follows:
    1.       Mr. Phil Grice, Lee Keeling & Associates, Tulsa,
    Oklahoma (http:lkaengineers.com)
    Mr. Grice will testify regarding valuation of oil and
    gas reserves in the Crimson Unit.
    2.       Mr. Gordan Romine, Lee Keeling & Associates, Tulsa,
    Oklahoma (http://lkaengineers.com)
    7
    The exceptions indicated in the scheduling order are not relevant to BDE’s expert.
    12
    Mr. Romine will testify regarding valuation of oil and
    gas reserves in the Crimson Unit.
    3.     Mr. John Wheeler, Lee Keeling & Associates, Tulsa,
    Oklahoma http://lkaengineers.com
    Mr. Wheeler will testify regarding geological analysis
    necessary to support an accurate valuation of oil and
    gas reserves in the Crimson Unit.
    The letter stated that the biographical information for the witnesses could be found at the
    links shown after the name. No other information concerning the experts or their
    opinions was provided.
    [¶37] On October 10, 2012, Encana filed a motion to exclude BDE’s expert testimony on
    the grounds that the September 21 letter did not comply with the scheduling order or
    W.R.C.P. 26(a)(2) because it did not include the experts’ reports, the expert opinions, the
    data the experts considered, exhibits the experts would use, a list of the experts’
    publications, the amount of compensation being paid to the experts, or a list of the
    experts’ prior testimony. Encana also asserted that for some of the witnesses, the links
    provided did not describe their training or experience. Encana asserted it was prejudiced
    by the lack of disclosure because the scheduling order gave Encana only until mid-
    November to designate counter experts which would be difficult if not impossible given
    the highly technical nature of Mr. Wheeler’s opinions. Encana argued the prejudice was
    exacerbated because Encana did timely disclose its expert’s opinions in compliance with
    the scheduling order and rule and so BDE had the benefit of that information months in
    advance of trial.
    [¶38] Also on October 10, 2012, BDE filed a motion asking for clarification or
    modification of the scheduling order along with a motion to compel Encana to produce its
    Crimson Unit reserve valuation. BDE asserted the scheduling order set a date for
    identifying experts but not for disclosing their reports and opinions; therefore, BDE
    assumed the report disclosure date was governed by W.R.C.P. 26(a)(2)(C), which
    provides that absent direction from the court, disclosures must be made ninety days
    before trial. BDE also claimed its failure to produce the expert reports and opinions was
    due at least in part to Encana’s delay in producing its internal valuation of the Crimson
    Unit reserves which BDE’s experts needed to prepare their reports. BDE asked the
    district court to allow it until November 1, 2012, to disclose expert reports. On
    November 1, 2012, before the district court heard argument on the motions, BDE
    provided Encana with a full disclosure for Mr. Wheeler and indicated the other two
    witnesses identified in paragraph 36 above would not testify.
    13
    [¶39] The district court convened a hearing on the motions on November 15, 2012. On
    December 7, 2012, it issued an order granting Encana’s motion to exclude Mr. Wheeler’s
    testimony and denying BDE’s motion to modify the scheduling order. The district court
    denied BDE’s motion on the ground that counsel for BDE admitted at the hearing that
    they had misread the scheduling order which unambiguously required disclosure of
    reports and opinions with the expert designation and BDE failed to ask for an extension
    until after the deadline had expired.
    [¶40] In granting Encana’s motion, the district court cited W.R.C.P. 37(c)(1), which
    states:
    Rule 37. Failure to Make Disclosures or Cooperate in
    Discovery; Sanctions.
    …
    (c) Failure to disclose; ...
    (1) A party that without substantial justification fails to
    disclose information as required by Rule 26(a) …, is not,
    unless such failure is harmless, permitted to use as evidence
    at trial, at a hearing, or on a motion any witness or
    information not so disclosed. In addition to or in lieu of this
    sanction, the court, on motion and after affording an
    opportunity to be heard, may impose other appropriate
    sanctions. In addition to requiring payment of reasonable
    expenses, including attorney's fees caused by the failure,
    these sanctions may include any of the actions authorized
    under Rule 37(b)(2)(A), (B), and (C) and may include
    informing the jury of the failure to make the disclosure.
    [¶41] The district court concluded there was no substantial justification for BDE’s failure
    to disclose Mr. Wheeler’s report, stating “BDE had ample opportunity to comply with the
    deadlines in the scheduling order and to seek the Court’s assistance if needed discovery
    was not produced in a timely manner.” The district court further concluded BDE did not
    meet its burden of proving its failure to comply was harmless, stating: “Encana has
    demonstrated that it would be prejudiced if the Court were to allow Mr. Wheeler’s
    testimony, because it would be difficult or impossible to find a counter expert at this late
    date. BDE offered no evidence to the contrary.”
    [¶42] BDE asserts the district court erred in excluding the expert testimony and report.
    BDE maintains that the scheduling order required disclosure of expert witnesses in
    September 2012, but did not require delivery of expert reports at that time.8 BDE further
    8
    As noted in paragraph 39, the district court’s order states that counsel for BDE admitted at the hearing
    that they had misread the scheduling order which unambiguously required compliance with W.R.C.P.
    14
    contends its expert’s report and opinions were dependent on Encana’s reserve valuations,
    estimates which Encana refused to produce until BDE filed its motion to compel.
    [¶43] A district court is generally afforded broad discretion, both in the mechanisms
    adopted to control discovery and in its selection of appropriate sanctions for violations of
    discovery. Roemmich v. Roemmich, 
    2010 WY 115
    , ¶ 22, 
    238 P.3d 89
    , 95 (Wyo. 2010),
    citing Ruwart v. Wagner, 
    880 P.2d 586
    , 592 (Wyo. 1994). A court does not abuse its
    discretion if it reasonably could have concluded as it did. 
    Id. In the
    present case, the
    scheduling order clearly stated that W.R.C.P. 26(a)(2) applied. W.R.C.P. 26(a)(2) clearly
    requires disclosure of expert reports and opinions at the time experts are identified.
    There is no question BDE failed to comply with the order and the rule.
    [¶44] Although BDE argues its failure to comply was due in part to Encana’s failure to
    provide discovery, BDE did not file a motion to compel until the deadline for designating
    experts had passed. If, in fact, BDE needed documents from Encana in order for Mr.
    Wheeler to prepare his report, the proper course of action was to file a motion to compel,
    and for an extension, before the designation deadline. BDE did not request either until
    several weeks after the designation deadline.
    [¶45] BDE provided Mr. Wheeler’s report to Encana on November 1, 2012. The
    scheduling order gave the parties until November 16, 2012, to designate counter experts.
    Encana showed that fifteen days was not sufficient time for it to find a counter expert.
    The district court concluded BDE did not meet its burden of proving its failure to comply
    was harmless because it offered no evidence to refute Encana’s evidence that it was
    prejudiced. Rule 37 expressly provides that a party who fails to disclose information
    required by Rule 26 “is not permitted” to use the undisclosed information at trial unless
    the noncompliance is substantially justified or harmless. The disclosures required by
    W.R.C.P. 26(a)(2) are mandatory and a court does not abuse its discretion when it
    excludes expert testimony as a sanction for noncompliance. Wilson v. Tyrrell, 
    2011 WY 7
    , ¶ 52, 
    246 P.3d 265
    , 279-80 (Wyo. 2011). The district court in the present case
    reasonably concluded BDE’s failure to comply was not substantially justified or
    harmless. The district court reasonably exercised its discretion and the authority vested
    in it under Rule 37 when it excluded the testimony.
    b.      Allen & Crouch report.
    [¶46] Prior to trial, Encana sought a ruling excluding an exhibit listed in BDE’s pretrial
    memorandum, claiming it was unreliable, inadmissible hearsay and not a business record.
    The exhibit, the Allen & Crouch report, is a reserve analysis of BDE’s oil and gas
    26(a)(2). A transcript of the hearing is not included in the record on appeal, but we presume the district
    court’s statement is accurate. Having admitted before the district court that it misread the scheduling
    order which clearly required compliance with the rule, BDE’s assertion on appeal that the order did not
    require disclosure of Mr. Wheeler’s report at the time he was designated is duplicitous.
    15
    interests in three Wyoming counties, including the Crimson Unit in Sublette County. It
    was prepared for BDE in 2008 by an independent petroleum engineer. Mr. Allen, who
    prepared the report, was deceased at the time of trial. The district court reserved ruling
    until the report was offered into evidence at trial.
    [¶47] During the trial testimony of Eric Koval, the president of BDE and witness through
    whom BDE sought to introduce the report, the district court heard argument outside the
    presence of the jury concerning the report and ruled that it was inadmissible. The district
    court concluded that the report, although maintained in BDE’s business records, was
    prepared by an outsider and BDE did not have sufficient personal knowledge concerning
    the report and how it was generated to establish its trustworthiness. The district court
    also ruled that the report was essentially expert opinion and was not disclosed in
    accordance with the scheduling order.
    [¶48] BDE claims the district court’s ruling is erroneous. BDE asserts the report should
    have been treated as a business record despite the fact that it was prepared by a third
    party because it was integrated into BDE’s records and BDE relied upon it.
    [¶49] Encana responds that the district court properly excluded the report because it did
    not meet the reliability requirements to be treated as a BDE business record. Encana
    asserts the rule BDE relies upon applies to records regularly, systematically and
    repetitively created in the course of business so that their reliability and accuracy is
    assured. The Allen report, Encana argues, was a one-time report created by an outside
    party on the basis of an undisclosed methodology and no BDE employee had personal
    knowledge of how it was prepared or what specific data and assumptions were used.
    Encana further contends that even if the report can be considered a BDE business record,
    the report lacked the trustworthiness W.R.E. 803(6)(b) requires.
    [¶50] Hearsay is a statement, other than one made by the declarant while testifying at the
    trial or hearing, offered in evidence to prove the truth of the matter asserted. W.R.E.
    801(c). Hearsay is generally not admissible. W.R.E. 802. One exception to the hearsay
    rule is that records kept in the course of a regularly conducted business activity may be
    admissible “unless the source of information or the method or circumstances or
    preparation indicate lack of trustworthiness.” W.R.E. 803(6).
    [¶51] This Court has recognized that an exhibit can be admitted as a business record of
    an entity even when that entity was not the maker of the exhibit, provided the other
    requirements of Rule 803(6) are met and the circumstances indicate that the records are
    trustworthy. Alloway v. RT Capital, Inc., 
    2008 WY 123
    , ¶ 16, 
    193 P.3d 713
    , 718 (Wyo.
    2008). The party objecting to the admission of a business record has the burden of
    establishing that a lack of trustworthiness should keep the document out of evidence.
    Mabe v. State, 
    2007 WY 172
    , ¶ 16, 
    169 P.3d 870
    , 874 (Wyo. 2007).
    16
    [¶52] Encana argued, as it does on appeal, that the Allen report was unreliable because it
    did not identify the methodology Mr. Allen used or assumptions he made in estimating
    the value of BDE’s reserves. As support for allowing the report into evidence as a
    business record, Mr. Koval stated that Mr. Allen was a professional engineer, had placed
    his professional stamp on the report, and had represented in the report that the values
    arrived at were derived from available data and generally accepted petroleum engineering
    practices. Neither Mr. Koval nor anyone else on BDE’s behalf identified the
    methodology Mr. Allen used or assumptions he made in formulating his opinions. BDE
    also did not describe its relationship with Mr. Allen, indicate how or why it acquired the
    report, or show that it was familiar with the methods Mr. Allen used in preparing the
    report. Absent foundation establishing that BDE had personal knowledge of the methods
    Mr. Allen used in preparing the report, the district court properly exercised its discretion
    in excluding the report. Mr. Koval’s statements, in essence asking the court to assume
    the methods were reliable based solely on the fact that Mr. Allen was a professional
    engineer, had affixed his stamp to the report and stated that he used generally accepted
    petroleum engineering practices, were insufficient to establish the requisite foundation.
    [¶53] Additionally, it is apparent from the transcript that the district court viewed the
    Allen report as expert opinion which BDE had not disclosed as required by the
    scheduling order. The district court viewed BDE’s attempt to use the Allen report
    through Mr. Koval as “a backdoor way” of getting expert testimony that was not properly
    disclosed into evidence. Although the district court ultimately excluded the report on the
    ground that BDE did not establish it as trustworthy under W.R.E. 803(6), the court had
    the discretion to exclude it based upon the untimely disclosure.
    4.     Exclusion of Evidence Concerning Sleeping Giant Well
    [¶54] In July of 2008, BDE pre-paid over $1 million to Encana to drill and complete a
    well located outside the Crimson Unit and not covered by the FOA. By late September
    of 2008, the well, the Sleeping Giant, had been plugged and abandoned and Encana was
    holding the balance of the monies BDE had paid to cover outstanding costs for plugging
    and abandoning the well. In October of 2008, BDE asked Encana to apply the Sleeping
    Giant funds to the amounts BDE owed on the Crimson Unit. Encana refused.
    [¶55] At trial, BDE sought to introduce evidence that Encana was holding unused funds
    BDE had paid for the Sleeping Giant well that could have been applied to the amounts
    BDE owed on the Crimson Unit. The district court declined to allow the evidence,
    concluding that the Sleeping Giant was a separate transaction that did not fall under the
    Crimson Unit FOA and Encana’s conduct with respect to the unused Sleeping Giant
    monies could not be the basis for claiming breach of the implied covenant of good faith
    arising from the FOA. The district court also declined to allow the pleadings to be
    amended during trial to add a claim for breach of the FOA or the implied covenant of
    17
    good faith based upon Encana’s refusal to apply funds from the Sleeping Giant to the
    amounts BDE owed under the FOA.
    [¶56] Wyoming law is clear that the implied covenant of good faith and fair dealing
    requires that parties to a contract not commit an act that would injure the rights of the
    other party to receive the benefit of their agreement. Scherer Constr., LLC v. Hedquist
    Const., 
    2001 WY 23
    , ¶ 19, 
    18 P.3d 645
    , 653 (Wyo. 2001). Compliance with the
    obligation to perform a contract in good faith requires that a party’s actions be consistent
    with the agreed common purpose and justified expectations of the other party. 
    Id. The covenant
    of good faith and fair dealing may not, however, be construed to establish new,
    independent rights or duties not agreed upon by the parties. 
    Id. [¶57] In
    his deposition, Mr. Koval testified that the Sleeping Giant was the subject of a
    separate agreement between BDE and Encana and was not one of the wells covered by
    the Crimson Unit FOA. Mr. Koval also testified that the Crimson Unit FOA did not
    contain any provision requiring Encana to apply monies BDE paid on transactions
    separate from the FOA toward amounts owed under the FOA. Likewise, Mr. Koval
    testified that the Sleeping Giant agreement did not contain a requirement that Encana
    apply any surplus paid for that well to amounts BDE owed under the FOA.
    [¶58] The Sleeping Giant transaction and the Crimson Unit FOA were entirely separate.
    Nothing in the FOA agreement justified an expectation by BDE that monies paid on the
    Sleeping Giant well would be used to cover unpaid expenses under the FOA. The
    covenant of good faith and fair dealing arising under the FOA could not be construed to
    establish a new, independent right of BDE or duty owed by Encana not agreed upon. The
    district court did not abuse its discretion when it denied the introduction of evidence
    concerning the Sleeping Giant transaction in this breach of the Crimson Unit FOA action.
    CONCLUSION
    [¶59] The district court did not abuse its discretion in instructing the jury or preparing
    and submitting the verdict form. The district court likewise did not abuse its discretion in
    excluding BDE’s expert witness and reports, or excluding evidence involving a separate
    transaction between the parties to show breach of the implied covenant of good faith and
    fair dealing. The judgment entered on the jury verdict is affirmed.
    18
    

Document Info

Docket Number: S-13-0151

Citation Numbers: 2014 WY 64, 326 P.3d 904, 2014 WL 2091260, 2014 Wyo. LEXIS 69

Judges: Kite, Hill, Burke, Davis

Filed Date: 5/20/2014

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (16)

Cervelli v. Graves , 1983 Wyo. LEXIS 300 ( 1983 )

Alloway v. RT Capital, Inc. , 2008 Wyo. LEXIS 128 ( 2008 )

Scherer Construction, LLC v. Hedquist Construction, Inc. , 2001 Wyo. LEXIS 28 ( 2001 )

Roemmich v. Roemmich , 2010 Wyo. LEXIS 123 ( 2010 )

Budder v. State , 2010 Wyo. LEXIS 131 ( 2010 )

Winter v. Pleasant , 2010 Wyo. LEXIS 4 ( 2010 )

Parrish v. Groathouse Construction, Inc. , 2006 Wyo. LEXIS 36 ( 2006 )

Pina v. Christensen , 2009 Wyo. LEXIS 61 ( 2009 )

Williams v. Collins Communications, Inc. , 1986 Wyo. LEXIS 567 ( 1986 )

Pbs Enterprizes, Inc. v. Cwcapital Asset Management LLC , 2008 Wyo. LEXIS 55 ( 2008 )

State Farm Mutual Automobile Insurance Co. v. Shrader , 1994 Wyo. LEXIS 110 ( 1994 )

City of Gillette v. Hladky Const., Inc. , 2008 Wyo. LEXIS 139 ( 2008 )

Wilson v. Tyrrell , 246 P.3d 265 ( 2011 )

Sellers v. Dooley Oil Transport , 2001 Wyo. LEXIS 57 ( 2001 )

Glenn v. Union Pacific Railroad , 2011 Wyo. LEXIS 131 ( 2011 )

Daley v. Wenzel , 2001 Wyo. LEXIS 96 ( 2001 )

View All Authorities »