Denbury Onshore, Llc and Denbury Resources Inc. N/K/A Denbury Inc. v. Apmtg Helium Llc ( 2020 )


Menu:
  •                 IN THE SUPREME COURT, STATE OF WYOMING
    
    2020 WY 146
    OCTOBER TERM, A.D. 2020
    December 4, 2020
    DENBURY ONSHORE, LLC and
    DENBURY RESOURCES INC. n/k/a
    DENBURY INC.
    Appellants
    (Defendants),
    S-19-0172
    v.
    APMTG HELIUM LLC,
    Appellee
    (Plaintiff).
    Appeal from the District Court of Sublette County
    The Honorable Marvin L. Tyler, Judge
    Representing Appellant:
    Darin B. Scheer, James R. Belcher, and Casey R. Terrell of Crowley Fleck PLLP,
    Casper, Wyoming. Argument by Mr. Scheer.
    Representing Appellee:
    Scott P. Klosterman and Amy M. Iberlin of Williams, Porter, Day, and Neville, P.C.,
    Casper, Wyoming; Jason A. Neville of the Spence Law Firm, LLC, Casper,
    Wyoming. Argument by Mr. Neville.
    Before DAVIS, C.J., and FOX, KAUTZ, GRAY, JJ, and FENN, DJ.
    NOTICE: This opinion is subject to formal revision before publication in Pacific Reporter Third.
    Readers are requested to notify the Clerk of the Supreme Court, Supreme Court Building, Cheyenne,
    Wyoming 82002, of typographical or other formal errors so correction may be made before final
    publication in the permanent volume.
    KAUTZ, Justice.
    [¶1] Denbury Onshore, LLC (Denbury), a subsidiary of Denbury Resources Inc., agreed
    to deliver certain amounts of helium to APMTG Helium LLC (APMTG) each year.
    Denbury failed to deliver the agreed-upon amounts but claimed its nonperformance was
    excused by two force majeure events—the failure of its contractor to complete its natural
    gas processing plant and the ongoing failure of its supply wells due to sulfur deposition
    plugging the wellbores. After a bench trial, the district court found Denbury had failed to
    show its non-performance was excused by a force majeure event except for a period of 36
    days. It awarded APMTG over $35 million in damages and interest. Denbury appealed.
    We affirm.
    ISSUES
    [¶2]   We restate and reorder Denbury’s issues as follows:
    1. Did the district court err by denying Denbury’s request to terminate the
    parties’ agreement under the doctrines of frustration of purpose and/or
    impossibility of performance?
    2. Did the district court err in deciding Denbury had failed to prove its non-
    performance between April 23, 2013, and December 30, 2013, was
    excused by a force majeure event (Contractor Failure FM)?
    3. Did the district court err in deciding Denbury had failed to prove its non-
    performance after mid-August of 2014 was excused by a force majeure
    event (Well Failure FM)?
    FACTS
    Original Helium Feedgas Agreement (HFA I)
    [¶3] On January 30, 2009, APMTG, a joint venture between Air Products and Chemicals,
    Inc. (Air Products) and Matheson Tri-Gas, Inc. (Matheson), entered into a Helium Feedgas
    Agreement (HFA I) with Cimarex Energy Co. (Cimarex) and Riley Ridge, LLC (Riley
    Ridge). Under the agreement, Cimarex and Riley Ridge agreed to design, construct, and
    operate a natural gas processing plant (the Riley Ridge Plant or Plant) and to annually
    deliver specified quantities of helium to APMTG.1 APMTG, in turn, agreed to design,
    construct and operate its own gas processing plant and to purchase the specified quantities
    of helium from Cimarex and Riley Ridge. The HFA I required Cimarex and Riley Ridge
    1
    The parties’ agreements refer to “helium feedgas” and “contained helium.” We will simply refer to
    helium.
    1
    to deliver 200 million standard cubic feet (MMscf) of helium to APMTG the first and
    second years of the contract and 400 MMscf per year thereafter. Cimarex and Riley Ridge
    agreed to expand the Riley Ridge Plant on or before the start of the third year in order to
    meet their increased obligations. If they failed to deliver the required quantities in any
    given year, they were to pay APMTG liquidated damages pursuant to a designated formula.
    The liquidated damages were capped at $8 million per year, and total liquidated damages
    for the life of the contract could not exceed APMTG’s final investment to construct its
    plant, which APMTG predicted would be $38.6-$42.9 million.
    [¶4] The HFA I “estimated” that Cimarex and Riley Ridge would begin delivering
    helium to APMTG on December 1, 2010, but required delivery to begin no later than
    December 1, 2011, absent “delays caused by any Force Majeure” or unless the parties
    otherwise agreed in writing. The life of the agreement was 20 years.
    [¶5] Section 17 of the HFA I excused a party’s failure to perform its obligations under
    the agreement “to the extent that such failure is caused by Force Majeure.” “Force
    Majeure” was defined in § 17.1 as
    any event outside the reasonable control of a Party that could
    not have been avoided or overcome by that Party’s exercise of
    reasonable care and due diligence and shall include without
    limitation the following: strike, lockout, concerted act of
    workers or other industrial disturbance; fire, explosion, flood,
    blizzard, extreme weather conditions or other natural
    catastrophe; epidemic or pandemic; civil disturbance, riot or
    armed conflict (whether declared or undeclared); acts of
    terrorism; curtailment, shortage, rationing or allocation of
    normal sources of supply of labor, materials, transportation,
    energy or utilities; accident; act of God; delay(s) or failure of
    performance of contractor(s) (of any tier) or vendor(s);
    sufferance of or voluntary compliance with act of government
    and government regulations and/or orders (whether or not
    valid); cancellation by the U.S. Bureau of Land Management,
    Department of the Interior, of the “Contract for Extraction and
    Sale of Federal Helium”; embargo; natural or mechanical
    supply well failure (in whole or in part) and machinery or
    equipment breakdown. Notwithstanding anything herein to
    the contrary, the following events shall not be considered Force
    Majeure events: the concentration of helium contained in the
    Helium Feedgas below that defined in Clause 9.1; and loss of
    markets for natural gas or Helium.
    2
    (Emphasis added). Section 17.3 of the HFA I required the party “whose performance under
    this Agreement is affected by Force Majeure [to] promptly Notify the other Party of the
    occurrence, and the effect and likely duration of the Force Majeure event, and . . . keep the
    other Party informed of any changes to those circumstances.” Section 17.4 required the
    party claiming force majeure to “as soon as practicable after the commencement of the
    Force Majeure, proceed with diligence and do all things reasonably practicable at its own
    cost to overcome and/or remedy the situation, and to recommence performance of its
    obligations, provided that . . . neither Party shall be required to incur any extraordinary
    costs or make more than commercially reasonable investments.”
    Failure of Contractor Force Majeure
    [¶6] Cimarex was the majority owner and operator of the Riley Ridge Plant project;
    Riley Ridge owned only a minority interest in the project. As operator, Cimarex made the
    day-to-day decisions about how to run the project. It hired BCCK Engineering
    Incorporated (BCCK) pursuant to a turn-key contract to engineer, design and construct the
    Riley Ridge Plant in Big Piney, Wyoming, and bring it to “mechanical completion,” which
    was expected to occur by December 2011.
    [¶7] In July 2010, Denbury purchased Riley Ridge’s interests in the Riley Ridge Plant
    and assumed all of its rights and obligations under the HFA I. About a year later, in June
    2011, Denbury acquired Cimarex’s interests in the Plant and the HFA I, as well as
    Cimarex’s rights and obligations under the construction contract with BCCK. Two months
    later, on August 1, 2011, Denbury officially took over as operator of the Riley Ridge Plant
    project from Cimarex, which meant it began making the day-to-day decisions about how
    to run the Plant and Cimarex’s employees became Denbury’s employees. At that time,
    BCCK had completed the engineering design of the Riley Ridge Plant and was in the
    process of constructing the Plant.
    [¶8] The next month, Denbury notified APMTG it was “experiencing delays in the
    construction and commissioning of [the Riley Ridge Plant]” and estimated it would begin
    delivering helium on November 15, 2011. However, that did not occur. In January 2012,
    after discovering BCCK had not performed in accordance with industry standards,
    Denbury removed BCCK from the Riley Ridge Plant project and began using its own
    personnel and contractors to correct BCCK’s deficiencies and complete the Plant.
    [¶9] On November 12, 2012, Denbury sent a letter to APMTG declaring force majeure
    under Article 17 of the HFA I due to “delay(s) or failure of performance of contractor(s)
    (of any tier) or vendor(s)” (hereinafter referred to as Contractor Failure FM). Denbury
    explained:
    Denbury has discovered through plant inspections by third
    party consultants who were hired to prepare for start-up and
    3
    commissioning . . . that there remained major uncompleted
    work at the plant. Whether caused by the contractor’s
    construction mismanagement, or the failure to design
    equipment and controls properly, the deeper that Denbury
    investigated the circumstances, it became apparent to both
    Denbury and its third party consultants that the plant was not
    even close to being in a condition for operations that would
    satisfy not only operational safety considerations, but also the
    required regulatory compliance. As you are also very aware,
    this plant will be handling a production stream that contains
    corrosive and toxic, hazardous constituents that require not
    only high-grade equipment, but also particular alarm and
    emergency shut-down systems. Much of this work had not
    even been addressed by the previous contractor. As a result,
    and even before Denbury officially terminated the construction
    contract, third party experts undertook the work of redesigning,
    refurbishing and revising equipment, controls and systems to
    get the process up to . . . standards for a safe processing
    operation in accordance with OSHA rules and regulations.
    The work is continuing and, based upon the latest
    information we have with our fast-track work schedule, the
    plant construction should be complete and ready for start-up by
    July 1, 2013.
    APMTG disagreed with Denbury’s declaration of force majeure and sent Denbury an
    invoice for $8 million based on Denbury’s failure to deliver the agreed-upon amounts of
    helium the first year of the HFA I.
    MOU and the Amended and Restated Helium Feedgas Agreement (HFA II)
    [¶10] After a series of negotiations, APMTG and Denbury entered into a “Memorandum
    of Understanding” (MOU) on April 25, 2013. Under the terms of the MOU, the parties
    agreed to execute an amended helium feedgas agreement, and Denbury agreed to pay
    APMTG an $8 million lump sum payment and $1.1 million for APMTG’s expenses in
    operating its gas processing plant between December 1, 2012, and August 1, 2013.
    [¶11] A month later, on May 23, 2013, the parties executed an “Amended and Restated
    Helium Feedgas Agreement” (HFA II). The HFA II required Denbury to begin delivering
    helium to APMTG no later than August 1, 2013, “except for delays caused by any Force
    Majeure” or if the parties agreed to a different date in writing. The HFA II, like the HFA
    I, was to terminate after 20 years. Denbury agreed to deliver 200 MMscf of helium per
    year the first three years and 400 MMscf per year thereafter. To meet the increased
    4
    quantities, Denbury was to start an expansion of the Riley Ridge Plant on or before January
    1, 2017. The HFA II provided the same liquidated damages provision as the HFA I,
    including the $8 million annual cap. It capped liquidated damages for the life of the
    contract at $46 million, which represented APMTG’s actual investment to construct its
    plant. The HFA II’s force majeure provisions mirrored those of the HFA I. The parties
    agreed the HFA II would be “construed in accordance with the laws of the State of New
    York.”
    Well Failure Force Majeure
    [¶12] The Riley Ridge Plant was designed around five gas wells, identified by numbers
    based on their location on the property. Wells known as 10-14, 17-34, and 20-14 were
    drilled to the Madison Formation and 16-24 and 16-31 went to the Big Horn Formation,
    which is below the Madison Formation. Both formations contain helium. The 10-14 and
    17-34 are older wells, having been drilled in approximately 1981. The remaining wells are
    newer; Cimarex drilled the 20-14 in 2008-2009 and Denbury drilled the 16-24 and 16-31
    in 2013-2014.
    [¶13] Prior to starting-up the Riley Ridge Plant, Cimarex and Denbury knew there was a
    risk of sulfur deposition due to the presence of hydrogen sulfide in Madison gas and the
    fact Exxon experiences sulfur deposition at its nearby Shute Creek Plant, which processes
    the same gas. They purposefully equipped the wells with larger and more expensive tubing
    in order to move any sulfur deposition to the surface, where it is easier to remediate. If
    sulfur deposition occurred downhole, they anticipated it could be treated with chemical
    solvents and a coil tubing (CT) operation.
    [¶14] On December 30, 2013, Denbury started-up the Riley Ridge Plant using the 10-14
    and 17-34 as supply wells. Less than four months later, on April 18, 2014, the 10-14
    stopped producing due to sulfur deposition plugging the wellbore. Denbury hired a third-
    party contractor to perform a CT operation to remediate the sulfur deposition. The
    operation was successful and the 10-14 began producing again on May 3, 2014. The
    success was short-lived. On June 15, 2014, the 10-14 again stopped producing due to sulfur
    deposition.
    [¶15] On April 23, 2014, the 17-34 was also shut-in due to sulfur deposition. A third-
    party contractor performed a chemical solvent treatment on the 17-34. The treatment did
    not restore the well to full production, so Denbury performed a CT operation on the 17-34
    on April 29. The CT operation successfully cleaned out the sulfur deposition, but during
    the operation the controller lost control of the CT string and it remained suspended in the
    well for 5-6 days. Before Denbury could pull the string out, it broke apart due to the harsh
    downhole environment and a portion of it fell to the bottom of the hole.
    5
    [¶16] On July 11, 2014, Denbury provided APMTG written notice of a new force majeure.
    In that notice, Denbury declared a force majeure “starting on June 15[, 2014,] continuing
    until about mid-August, at which time the [Riley Ridge Plant] is expected to be back on
    but at a potentially reduced rate” (hereinafter referred to as Well Failure FM). Denbury
    explained the 10-14 had been shut-in due to sulfur deposition since June 15, 2014, and it
    had ordered a CT unit to clean it. It stated the CT operation should begin on July 15 and
    take two days to complete, absent any delays. It also noted the 17-34 had been shut-in
    since April due to sulfur deposition and explained its attempts to remedy it with a chemical
    solvent treatment and a CT operation, the latter of which resulted in equipment being lost
    in the hole. It stated it had placed a snubbing unit in the 17-34 on June 2, 2014, to “remove
    all the remaining down-hole junk” and believed it was working. It estimated the well had
    a “good chance” of being back on production in August. Denbury promised to provide
    prompt notice when it could restart the Plant.
    [¶17] APTMG objected to Denbury’s declaration of force majeure, claiming the well
    conditions described by Denbury did not constitute force majeure under the HFA II because
    they “are within [Denbury’s] reasonable control and could have been avoided or overcome
    by the exercise of reasonable care and due diligence” under § 17.1. It also objected because
    Denbury’s July 11, 2014, letter did not constitute prompt notice of a force majeure under
    § 17.3.
    [¶18] On August 9, 2014, Denbury performed the second CT operation on the 10-14. The
    operation “got through the sulfur deposition zone” but the string broke and Denbury’s
    subsequent attempt to retrieve the string from the hole with a snubbing unit was only
    partially successful. Similarly, the snubbing unit in the 17-34 was not able to retrieve all
    of the lost string. CT string remains in both the 10-14 and 17-34. Dr. Bruce Craig, a
    metallurgist and Denbury consultant, strongly recommended against performing any
    further CT operations due to the harsh downhole conditions.
    [¶19] Denbury delivered only 4.3 MMscf of helium to APMTG between December 30,
    2013, and June 2014; Denbury has not delivered any other helium to APMTG. It also did
    not expand the Riley Ridge Plant by January 1, 2017, as it promised to do in the HFA II.
    District Court Proceedings
    [¶20] APMTG filed a complaint against Denbury alleging breach of contract, unjust
    enrichment, and breach of the implied covenant of good faith and fair dealing. Denbury
    agreed it had failed to provide the agreed-upon quantities of helium and to expand the Riley
    Ridge Plant but claimed its nonperformance was excused by the Contractor Failure FM
    and Well Failure FM.
    [¶21] The case ultimately proceeded to a seven-day bench trial. Denbury bore the burden
    of proving its failure to provide the agreed-upon quantities of helium was excused by a
    6
    valid force majeure event. See Beardslee v. Inflection Energy, LLC, 
    904 F. Supp. 2d 213
    ,
    220 (N.D.N.Y. 2012), aff’d, 
    798 F.3d 90
     (2d Cir. 2015) (the party invoking a force majeure
    provision bears the burden of establishing it has been met) (citing Phillips Puerto Rico
    Core, Inc. v. Tradax Petroleum, Ltd., 
    782 F.2d 314
    , 319 (2d Cir. 1985)). The district court
    decided Denbury had failed to meet its burden except for a period of approximately 36
    days (from July 11, 2014, to mid-August 2014). As a result, it found in favor of APMTG
    on its breach of contract claim and awarded it over $35 million in liquidated damages and
    interest. The court concluded APMTG’s unjust enrichment claim was barred under New
    York law because the parties’ disputes were controlled by a contract and APMTG had
    failed to prove Denbury’s breach of the implied covenant of good faith and fair dealing
    was “not duplicative of its breach of contract claims.”
    [¶22] Denbury appealed. While this appeal was pending, Denbury Resources Inc. filed a
    voluntary petition for relief under Chapter 11 of the United States Bankruptcy Code in the
    United States Bankruptcy Court for the Southern District of Texas. Upon stipulation of
    the parties, the bankruptcy court granted relief from the automatic stay provisions for
    purposes of this appeal. Denbury Resources Inc. emerged from the bankruptcy case on
    September 18, 2020, and is now known as Denbury Inc.
    [¶23] Additional facts will be set out, as necessary, in the discussion of the issues.
    APPLICABLE LAW
    [¶24] The district court concluded the governing agreement was the HFA II and it was a
    valid and enforceable contract. Neither party challenges these conclusions on appeal. The
    HFA II states: “The provisions of this Agreement shall be construed in accordance with
    the laws of the State of New York.” We will enforce a contract’s choice-of-law provision
    and “apply foreign law when doing so is not ‘contrary to the law, public policy, or the
    general interests of Wyoming’s citizens.’” Finley Res., Inc. v. EP Energy E&P Co., L.P.,
    
    2019 WY 65
    , ¶ 9, 
    443 P.3d 838
    , 842 (Wyo. 2019) (quoting Res. Tech. Corp. v. Fisher Sci.
    Co., 
    924 P.2d 972
    , 975 (Wyo. 1996)). See also, Bradley v. Bradley, 
    2007 WY 117
    , ¶ 21,
    
    164 P.3d 537
    , 543 (Wyo. 2007). We will apply New York law when interpreting the HFA
    II; however, Wyoming law controls any procedural matters, including the applicable
    standard of review. See Smithco Eng’g, Inc. v. Int’l Fabricators, Inc., 
    775 P.2d 1011
    , 1018
    (Wyo. 1989) (“Clearly, the law of the forum controls procedural matters.”) (citations
    omitted).
    STANDARD OF REVIEW
    [¶25] Our standard of review on appeal following a bench trial in the district court is well-
    established:
    7
    The factual findings of a judge are not entitled to the limited
    review afforded a jury verdict. While the findings are
    presumptively correct, the appellate court may examine all of
    the properly admissible evidence in the record. Due regard is
    given to the opportunity of the trial judge to assess the
    credibility of the witnesses, and our review does not entail
    weighing disputed evidence. Findings of fact will not be set
    aside unless the findings are clearly erroneous. A finding is
    clearly erroneous when, although there is evidence to support
    it, the reviewing court on the entire evidence is left with the
    definite and firm conviction that a mistake has been
    committed. We review a district court’s conclusions of law de
    novo on appeal.
    Davis v. Harmony Dev., LLC, 
    2020 WY 39
    , ¶ 31, 
    460 P.3d 230
    , 240 (Wyo. 2020) (quoting
    Ekberg v. Sharp, 
    2003 WY 123
    , ¶ 10, 
    76 P.3d 1250
    , 1253 (Wyo. 2003)) (other citations
    omitted). The district court’s interpretation of the HFA II is a conclusion of law reviewed
    de novo. See Larson v. Burton Constr., Inc., 
    2018 WY 74
    , ¶ 16, 
    421 P.3d 538
    , 544 (Wyo.
    2018) (“Contract interpretation presents questions of law which we review de novo.”).2
    DISCUSSION
    1.      Frustration of Purpose and/or Impossibility of Performance
    [¶26] Denbury requested termination of the HFA II under the doctrines of frustration of
    purpose and impossibility of performance due to its chronic force majeure status.3 The
    district court denied its request because § 2.5 of the HFA II provided the exclusive remedy
    for termination of the agreement and nothing in the plain language of that provision
    allowed a party to terminate the HFA II based on those doctrines. Denbury argues the
    2
    Denbury suggests the district court’s findings pursuant to Wyoming Rule of Civil Procedure 52(a) are not
    sufficient to indicate the factual basis for its decision on the contested matters. Because neither party
    requested findings under Rule 52(a)(1)(A), the district court was required only to find generally for
    APMTG. See Rule 52(a)(1). See also, Kimzey v. Kimzey, 
    2020 WY 52
    , ¶ 38, 
    461 P.3d 1229
    , 1241 (Wyo.
    2020). Moreover, while the district court admittedly did not “include all findings and/or conclusions
    supported by the testimony and evidence adduced at trial,” it did “include[] those findings and/or
    conclusions necessary to explain the Court’s determinations of the issues to the parties.” The court’s
    findings more than adequately explained the factual basis for its decision.
    3
    Denbury also refers to impracticability of performance, but it appears that doctrine is synonymous to the
    impossibility of performance doctrine. See Matter of Liquidation of New York Agency & Other Assets of
    Bank of Credit & Commerce Int’l, S.A., 
    90 N.Y.2d 410
    , 424 (N.Y. 1997) (referring to
    “impossibility/impracticability of performance”); Reed Found., Inc. v. Franklin D. Roosevelt Four
    Freedoms Park, LLC, 
    964 N.Y.S.2d 152
    , 156 (N.Y. App. Div. 2013) (referring to “[t]he defense of
    impossibility or impracticability of performance”). We will refer simply to impossibility of performance.
    8
    district court erred in concluding the parties waived these doctrines merely by including a
    standard 90-day termination provision for uncured default. We agree with the district court
    with additional reasons.
    [¶27] First, it is unclear whether the doctrines of frustration of purpose and impossibility
    of performance allow for termination of a contract under New York law. While older New
    York cases suggest they do, more recent cases indicate they merely excuse a party’s non-
    performance. Compare Reed Found., Inc. v. Franklin D. Roosevelt Four Freedoms Park,
    LLC, 
    964 N.Y.S.2d 152
    , 156 (N.Y. App. Div. 2013) (“The defense of impossibility or
    impracticability of performance is ‘applied narrowly’ such that performance is excused
    ‘only when the destruction of the subject matter of the contract or the means of performance
    makes performance objectively impossible’ and that ‘the impossibility must be produced
    by an unanticipated event that could not have been foreseen or guarded against in the
    contract.’”) (emphasis added) (quoting Kel Kim Corp. v. Central Markets, Inc., 
    70 N.Y.2d 900
    , 902 (N.Y. App. Div. 1987)), and PPF Safeguard, LCC v. BCR Safeguard Holding,
    LCC, 
    924 N.Y.S.2d 391
    , 394 (N.Y. App. Div. 2011) (“For a party to a contract to invoke
    frustration of purpose as a defense for nonperformance, the frustrated purpose must be so
    completely the basis of the contract that, as both parties understood, without it, the
    transaction would have made little sense.”) (emphasis added) (quotations and citations
    omitted), with 119 Fifth Ave., Inc., Taiyo Trading Co., Inc., 
    73 N.Y.S.2d 774
    , 776 (N.Y.
    Sup. Ct. 1947), aff’d sub nom. 
    87 N.Y.S.2d 430
     (N.Y. App. Div. 1949) (“The general
    principle underlying [the frustration of purpose doctrine] is that, where the purpose of a
    contract is completely frustrated and rendered impossible of performance by a supervening
    event or circumstance which was not within the contemplation of the parties and which
    could not have been anticipated and guarded against, the contract is discharged.”)
    (emphasis added), and Robitzek Investing Co., Inc. v. Colonial Beacon Oil Co., 
    40 N.Y.S.2d 819
    , 822 (N.Y. App. Div. 1943) (“Where there is complete frustration of
    performance of a contract by act of the government, cancellation is permissible.”)
    (emphasis added) (citation omitted).
    [¶28] Even if the doctrines allow for termination of a contract under New York law, they
    are not available where “the event which prevented performance was foreseeable and
    provision could have been made for the event’s occurrence.” Rebell v. Trask, 
    632 N.Y.S.2d 624
    , 627 (N.Y. App. Div. 1995) (frustration of purpose) (citations omitted); Kel Kim Corp.,
    70 N.Y.2d at 902 (impossibility). As a corollary, if the parties’ contract provides for the
    occurrence of the alleged frustration or impossibility, then the parties obviously foresaw
    the frustration or impossibility and the doctrines are not available.
    [¶29] In Center for Specialty Care, Inc. v. CSC Acquisition I, LLC, 
    127 N.Y.S.3d 6
    , 9
    (N.Y. App. Div. 2020), the defendants agreed to purchase the plaintiff’s surgical center
    and to lease the premises until closing. The defendants failed to pay the rent under the
    lease but argued they were excused from doing so because the purpose of the lease was
    frustrated as they could not occupy the surgical center without a Certificate of Need (CON)
    9
    from the Health Department, which could not be obtained by the effective date of the lease.
    Id. at 13-14. The court concluded the frustration of purpose doctrine was not available
    because the parties’ agreements “acknowledged and planned for” the fact the defendants
    would not be able to occupy the surgical center on the lease date due to the need for them
    to obtain a CON. Id. at 14. Specifically, the parties’ agreements allowed the defendants
    to start deriving benefits from the surgical center prior to their occupancy of the building.
    Id.
    [¶30] Similarly, in Warner v. Kaplan, 
    892 N.Y.S.2d 311
    , 313 (N.Y. App. Div. 2009), the
    plaintiff agreed to purchase a cooperative apartment from the defendants. The sales
    contract required plaintiff to deposit $230,000 in escrow and the sale to be approved by the
    cooperative’s Board of Directors. 
    Id.
     The plaintiff made the requisite deposit and the
    Board approved the sale. 
    Id.
     The plaintiff died prior to closing. 
    Id.
     Her estate sought
    return of the deposit due to, among other things, frustration of purpose. 
    Id. at 313-15
    . It
    claimed it was justified in not continuing with the purchase of the apartment because the
    plaintiff was purchasing the apartment solely for her own residence and she was no longer
    living. 
    Id. at 314-15
    . The court concluded the frustration of purpose doctrine did not apply
    because the sales contract expressly stated it was binding on the parties’ “heirs, personal
    and legal representatives and successors in interest.” 
    Id. at 313
    . It reasoned: “The
    inclusion of this provision indicates that the parties explicitly contemplated, and provided
    for, the possibility of either party’s death before closing, by specifying that the death would
    not terminate the contract, but that the contract would survive, to be performed by the
    successors or heirs of the deceased party.” 
    Id.
     Because the contract made explicit
    provision for the event of either party’s death, the frustration of purpose doctrine was not
    available. 
    Id. at 315
    . See also, Neumann v. Metro. Med. Grp., P.C., 
    557 N.Y.S.2d 663
    ,
    664 (N.Y. App. Div. 1990) (plaintiffs’ proposed amendments to their complaint were
    properly denied as meritless because their “cause of action seeking a declaration that the
    contract was terminated by frustration of purpose was correctly rejected, as the record
    demonstrates that the alleged ‘frustration’, Falkirk Hospital’s cessation of operations, was
    contemplated by the contract”).
    [¶31] In this case, the HFA II expressly states “failure of performance of contractor” and
    “natural or mechanical supply well failure” will excuse a party’s performance and the
    payment of liquidated damages if they “are outside [the party’s] reasonable control” and
    “could not have been avoided or overcome by [the] exercise of reasonable care and due
    diligence.” Because the parties “explicitly contemplated, and provided for” the possibility
    that BCCK would fail to perform under the construction contract and the supply wells
    would naturally or mechanically fail, the frustration of purpose and impossibility doctrines
    are not available. Warner, 
    892 N.Y.S.2d at 313
    .
    [¶32] Moreover, as the district court noted, the parties set forth the grounds for termination
    of the HFA II in § 2.5, which provides:
    10
    A Party shall be entitled to terminate this Agreement if
    the other Party is in default of a material obligation hereunder
    and has not commenced and does not diligently pursue, a cure
    of such default within 90 days following a reasonable period
    of receipt of Notice from the non-defaulting Party.
    Notwithstanding the foregoing, the Parties shall endeavor in
    good faith to rectify any material default hereof as
    expeditiously as possible upon receipt of Notice from the non-
    defaulting Party.
    [¶33] “The fundamental, neutral precept of contract interpretation is that agreements are
    construed in accord with the parties’ intent. . . . The best evidence of what parties to a
    written agreement intend is what they say in their writing. . . . Thus, a written agreement
    that is complete, clear and unambiguous on its face must be enforced according to the plain
    meaning of its terms.” Greenfield v. Philles Records, Inc., 
    98 N.Y.2d 562
    , 569-70 (N.Y.
    2002) (citations and quotations omitted). “A contract is unambiguous if the language it
    uses has a definite and precise meaning, unattended by danger of misconception in the
    purport of the [agreement] itself, and concerning which there is no reasonable basis for a
    difference of opinion.” 
    Id.
     (citation and quotations omitted). See also, Riverside S.
    Planning Corp. v. CRP/Extell Riverside, L.P., 
    13 N.Y.3d 398
    , 404 (N.Y. 2009) (“Where
    the language chosen by the parties has a definite and precise meaning, there is no
    ambiguity.”) (citation and quotations omitted).
    [¶34] Section 2.5 is clear and unambiguous. Under its plain language, Denbury may
    terminate the HFA II only if APMTG is in material default and fails to timely cure the
    default. APMTG is not in material default of the HFA II. Moreover, § 2.5 does not include
    “failure of performance of contractor” and “natural or mechanical supply well failure” as
    grounds for termination. Had the parties wished to allow termination of the agreement due
    to these events, they could have included them in § 2.5. They did not and we are not at
    liberty to re-write the HFA II to include them. See Beardslee v. Inflection Energy, LLC,
    
    25 N.Y.3d 150
    , 157 (N.Y. 2015) (“[C]ourts may not by construction add or excise terms,
    nor distort the meaning of those used and thereby make a new contract for the parties under
    the guise of interpreting the writing.”) (citations and quotations omitted); Robitzek
    Investing Co., Inc., 
    40 N.Y.S.2d at 822
     (“If it were the intention of the parties [that the
    lease be cancelled in the event of a regulation of defendant’s business], they could readily
    have provided [so] by employing language to that effect.”).
    [¶35] Denbury wants us to imply the doctrines of frustration of purpose and impossibility
    of performance into the HFA II because without them, it claims, “the HFA II contains no
    mechanism to address a situation where, as here, a party has done all things ‘reasonably
    practicable’ to overcome a valid force majeure event, but cannot do so because the only
    viable options require ‘extraordinary costs’ or ‘more than commercially reasonable
    investments.’” The cases it relies on for the proposition that we can imply terms into a
    11
    contract are inapposite. They involved implied duties, in particular, the implied covenant
    of good faith and fair dealing, not implied defenses to the nonperformance of such duties,
    such as the doctrines of frustration of purpose and impossibility of performance. See, e.g.,
    Wakefield v. N. Telecom, Inc., 
    769 F.2d 109
    , 112 (2d Cir. 1985) (implied covenant of good
    faith and fair dealing prevented employer from terminating plaintiff for the purpose of
    avoiding the payment of commissions which are otherwise owed the plaintiff); Zilg v.
    Prentice-Hall, Inc., 
    717 F.2d 671
    , 679 (2d Cir. 1983) (holding the promise to publish the
    plaintiff’s book implies a good faith effort by the publisher to promote the book);
    Travellers Int’l, A.G. v. Trans World Airlines, Inc., 
    41 F.3d 1570
    , 1575-77 (2d Cir. 1994)
    (concluding district court did not err in finding defendant had breached the implied
    covenant of good faith and fair dealing due to its inadequate promotional efforts).
    Moreover, its argument is contrary to New York law, cited above, which refuses to apply
    these doctrines if the parties could have or, as here, did provide for the occurrence of the
    alleged frustration or impossibility in their contract.
    [¶36] The district court did not err in denying Denbury’s request to terminate the HFA II
    under the doctrines of frustration of purpose and impossibility of performance.
    2. Contractor Failure FM
    [¶37] The district court found the unambiguous terms of the HFA II prevented Denbury
    from claiming its November 15, 2012 Contractor Failure FM was still viable and ongoing
    beyond May 23, 2013, the date the parties executed the HFA II. According to the court,
    “[t]he HFA II represents the parties[’] negotiated and agreed resolution of their dispute
    over the existence, vel non, of a qualifying force majeure event excusing Denbury’s non-
    performance and, among other things, it expressly provides for an agreed-upon new
    commencement date of no later than August 1, 2013, for Denbury to provide helium to
    APMTG.” It also found Denbury had “failed to prove that any purported ongoing force
    majeure event on or after May 23, 2013 (i.e., the effective date of the HFA II) excusing
    non-performance under the HFA II was ‘outside the reasonable control of [Denbury] that
    could not have been avoided or overcome by [Denbury’s] exercise of reasonable care and
    due diligence.’” The court explained:
    Denbury assumed control of completion of the Riley Ridge
    Plant on August 1, 2011, and Denbury became its own
    ‘engineer, designer, and general contractor’ assuming the task
    of bringing the Riley Ridge Plant to ‘mechanical completion’
    when it removed BCCK in January 2012. Denbury was in
    control of scheduling, sub-contracting, engineering, designing,
    and performing the work necessary to perform on its agreement
    with APMTG to supply helium feed gas under the HFA II.
    12
    It further found Denbury had failed to provide any notice, as required by the HFA II, of
    any ongoing or new force majeure event from May 23, 2013, to July 11, 2014, when it
    provided notice of the Well Failure FM. It rejected Denbury’s claim that a string of emails
    concerning the start-up of the Plant between its project manager, Clay Duellman, and an
    APMTG engineer, Michael Carberry, provided the requisite notice.
    [¶38] Denbury argues the district court erred in rejecting its Contractor Failure FM based
    on its finding that Denbury became its own “engineer, designer, and general contractor”
    after it removed BCCK from the project and therefore Denbury was responsible for the
    continuing delays in starting-up the Riley Ridge Plant. It claims that finding ignores the
    unrebutted testimony that (1) Denbury only assumed the responsibility of bringing the
    Plant to mechanical completion because it had to fix the failures of contractor BCCK under
    the turn-key construction contract, and (2) Denbury would not have assumed that
    responsibility but for the failure of performance of contractor BCCK. It points to the
    testimony of Bill Jackson, its construction project management expert, who opined “[t]he
    root cause of Denbury’s failure to timely start the Plant up . . . was a failure by BCCK to
    properly engineer the plant and execute the project.” Denbury further claims that had it
    not fixed BCCK’s failures, it would have violated its obligations under § 17.4 of the HFA
    II, which requires it “to proceed with diligence and do all things reasonably practicable . .
    . to overcome and/or remedy the [force majeure].” It also maintains the district court erred
    in deciding it had failed to provide proper notice of a force majeure event after the
    execution of the HFA II.
    [¶39] At the outset, we note the limited scope of Denbury’s arguments. It does not
    challenge the district court’s conclusion that the HFA II resolved the parties’ dispute as to
    whether or not Denbury’s November 12, 2012 Contractor Failure FM constituted a valid
    force majeure event under the HFA I or the court’s conclusion that Denbury’s alleged
    November 12, 2012 Contractor Failure FM did not continue after May 23, 2013, the date
    the HFA II was executed. Moreover, the Riley Ridge Plant began producing on December
    30, 2013. While Denbury alleged in the district court the Contractor Failure FM had
    continued into August of 2014,4 Denbury makes no such claim on appeal. Therefore, the
    limited question before us is whether the district court erred in finding Denbury failed to
    prove a valid force majeure event between May 23, 2013, and December 30, 2013. We
    see no error.
    [¶40] Section 17.1 of the HFA II defines “Force Majeure,” in relevant part, as “any event
    outside the reasonable control of a Party that could not have been avoided or overcome by
    that Party’s exercise of reasonable care and due diligence and shall include without
    4
    Dan Cole, Denbury’s Vice President of Commercial Development and Governmental Relations, testified
    the Contractor Failure FM continued after the MOU and HFA II. He also indicated in an August 14, 2014,
    letter to APMTG that the Contractor Failure FM “has actually continued and continues to this time.”
    However, in Denbury’s July 11, 2014 Well Failure FM notice, Mr. Cole expressly stated the Contractor
    Failure FM “continued until December 30, 2013, when the Plant commenced operations . . . .”
    13
    limitation the following . . . delay(s) or failure of performance of contractor(s) (of any tier)
    or vendor(s).” “Force majeure clauses are to be interpreted in accord with their purpose,
    which is to limit damages in a case where the reasonable expectation of the parties and the
    performance of the contract have been frustrated by circumstances beyond the control of
    the parties. . . . [W]hen the parties have themselves defined the contours of force majeure
    in their agreement, those contours dictate the application, effect, and scope of force
    majeure.” Constellation Energy Servs. of New York, Inc. v. New Water St. Corp., 
    46 N.Y.S.3d 25
    , 27 (N.Y. App. Div. 2017) (citations and quotations omitted).
    [¶41] The phrase “failure of performance of contractor” contemplates the failure of
    performance of a third-party contractor, not one of the parties. It would make little sense
    for a party’s failure of performance to be contained in a force majeure provision, which is
    intended to excuse a party’s non-performance. Properly construed, the district court
    correctly found there was no “failure of performance of contractor” between May 23, 2013,
    and December 30, 2013, because there was no third-party contractor. Denbury had
    removed BCCK from the project approximately 18 months earlier. See Kel Kim Corp.,
    524 N.Y.2d at 386 (“[C]ontractual force majeure clauses [are] clauses excusing
    nonperformance due to circumstances beyond the control of the parties . . . . Ordinarily,
    only if the force majeure clause specifically includes the event that actually prevents a
    party’s performance will that party be excused.”) (emphasis added).
    [¶42] Moreover, § 17.1 requires any “failure of performance of contractor” to be (1)
    outside the party’s reasonable control, and (2) incapable of being avoided or overcome by
    that party’s exercise of reasonable care and due diligence. Any failure to complete the
    Riley Ridge Plant between May 23, 2013, and December 30, 2013, was not outside
    Denbury’s “reasonable control,” because at that time Denbury, not BCCK, was in charge
    of bringing the Plant to mechanical completion. The fact Denbury had to correct BCCK’s
    failures in order to do so is immaterial. As of May 23, 2013, Denbury knew of BCCK’s
    failures and was in the process of correcting them. Yet, it executed the HFA II, in which
    it expressly agreed to begin delivering helium to APMTG by August 1, 2013. Additionally,
    as the district court found, by executing the HFA II, Denbury terminated its ability to
    continue to rely on its November 12, 2012 Contractor Failure FM to excuse any delay in
    the start-up of the Plant. Again, Denbury has not appealed that finding. Executing the
    HFA II was completely within Denbury’s “reasonable control.”
    [¶43] The district court also correctly found Denbury failed to provide notice of a new
    force majeure event between May 23, 2013, and December 30, 2013. Section 17.3 of the
    HFA II requires the party “whose performance under the Agreement is affected by Force
    Majeure [to] promptly notify the other Party of the occurrence, and the effect and likely
    duration of the Force Majeure event, and . . . keep the other Party informed of any changes
    to those circumstances.” Section 19.1 allows notices to be transmitted by post, facsimile,
    email or personally, but § 19.3 requires them to be addressed to APMTG’s General
    Manager in Allentown, Pennsylvania, with a copy provided to Matheson in New Jersey.
    14
    [¶44] The email exchange between Mr. Duellman and Mr. Carberry does not satisfy either
    § 17.3 or § 19.3. On May 28, 2013, Mr. Carberry emailed Mr. Duellman requesting a
    status update and stated: “I’m hearing that you are now looking at something in early
    August. Any confirmation o[r] further information will be appreciated.” The next day, a
    mere six days after Denbury had executed the HFA II and agreed to begin delivering helium
    to APMTG by August 1, Mr. Carberry responded,
    We experienced delays in material deliveries and we now have
    all materials. Workforce was increased to recover schedule but
    we are now addressing productivity concerns with the
    mechanical contractor. Startup will not occur in July and the
    outlook appears to be late August based on current
    productivity.    Safety revisions are approximately 50%
    complete. Denbury has hired Carl Robertson (PM) and placed
    [him] at the plant site until startup. I am focusing on
    operational readiness items.
    This email exchange does not mention § 17, force majeure, a failure of performance of
    contractor, or otherwise indicate Denbury was declaring a force majeure. It was not sent
    to APMTG’s General Manager, nor was a copy sent to Matheson. The failure of this email
    exchange to constitute proper notice is readily apparent when it is compared to Denbury’s
    November 12, 2012 and July 11, 2014 written notices of the Contractor Failure FM and
    Well Failure FM. Denbury knew how to provide proper notice of force majeure; it did not
    provide any such notice between May 23, 2013, and December 30, 2013.
    [¶45] Denbury argues that under New York law, a lack of notice does not prevent a party
    from invoking a force majeure clause unless the contract clearly indicates notice is a
    condition precedent to a party’s reliance on the force majeure provision. We agree with
    this statement of New York law. See Oppenheimer & Co., Inc. v. Oppenheim, Appel, Dixon
    & Co., 
    636 N.Y.S.2d 734
    , 737 (N.Y. 1995) (“A condition precedent is an act or event, other
    than a lapse of time, which, unless the condition is excused, must occur before a duty to
    perform a promise in the agreement arises.”) (quotations and citations omitted); Kidder
    Peabody & Co., Inc. v. Unigestion Intern’l, Ltd., 
    903 F. Supp. 479
    , 501 (S.D.N.Y. 1995)
    (“[A] contractual duty is not to be construed as a condition precedent unless the language
    of the contract clearly imposes such a condition.”). Denbury then claims nothing in the
    HFA II indicates notice is a condition precedent to reliance on the force majeure provision.
    We agree the HFA II does not expressly make notice a condition precedent to a party
    invoking the force majeure provision. Rather, it simply requires the party claiming force
    majeure “[to] promptly Notify the other Party of the occurrence, and the effect and likely
    duration of the Force Majeure event, and . . . keep the other Party informed of any changes
    to those circumstances.” See Toyomenka Pac. Petroleum, Inc. v. Hess Oil Virgin Islands
    Corp., 
    771 F. Supp. 63
    , 67 (S.D.N.Y. 1991) (“Although Clause QQQ requires the party
    15
    claiming force majeure to give written notice within forty-eight hours, whether such notice
    is a condition precedent to invoking force majeure is determined by the intention of the
    parties as expressed in the contract . . . . Clause QQQ does not expressly make a force
    majeure defense conditional upon giving notice within forty-eight hours.”). Nevertheless,
    as Denbury acknowledges, it still had a duty under the HFA II to provide notice of a force
    majeure. See Kidder Peabody & Co., 
    903 F. Supp. at 501
     (although notice was not a
    condition precedent, it remained a contractual duty); Toyomenka Pac. Petroleum, Inc., 
    771 F. Supp. at 68
     (although notice was not a condition precedent to a force majeure defense,
    it was still a duty to be performed under the contract). Denbury failed to provide any notice
    of a force majeure between May 23, 2013, and December 30, 2013.
    [¶46] Denbury maintains it did not materially breach its duty to provide notice because
    APMTG did not suffer any prejudice due to the lack of notice. It claims APMTG “was
    well-aware of the underlying facts and ongoing problems that delayed start-up of the [Riley
    Ridge] Plant,” and it did not identify any different actions it would have taken had it
    received notice. The cases Denbury relies upon for this proposition, however, are
    inapposite. They either did not apply New York law or involve untimely notice, not a
    failure to provide any notice. See Toyomenka Pac. Petroleum, Inc., 
    771 F. Supp. at 68
    (untimely notice); Vinegar Hill Zinc Co. v. United States, 
    149 Ct. Cl. 494
    , 499-500, 
    276 F.2d 13
    , 16 (Ct. Cl. 1960) (federal law). Moreover, the evidence Denbury relies on for the
    proposition that APMTG was “well aware” of the underlying problems delaying the start-
    up of the Plant primarily consists of correspondence between Denbury and APMTG
    outside the relevant time period, i.e., prior to the HFA II or after the wells failed in 2014.
    The only communication occurring between May 23, 2013 and December 30, 2013, was
    the email exchange noted above, which indicated the Plant would start-up in late August,
    and an email exchange between Denbury and one of APMTG’s representatives between
    September 11, 2013, and October 3, 2013, in which Denbury informed APMTG it could
    not provide a tour of the Riley Ridge Plant due to a “flurry of activity as we make the big
    push to complete, test, and get [the Plant] online.” Neither of these email exchanges,
    however, indicated Denbury was relying on a force majeure, in particular, a failure of
    performance of a contractor, to excuse its failure to start-up the Plant on August 1.
    [¶47] Further, the record supports a conclusion that APMTG was prejudiced by Denbury’s
    failure to provide notice. Robert Lein, APMTG’s general manager, testified that while
    APMTG was aware Denbury was not delivering helium, it did not know the failure was
    due to a force majeure event. Without such notice, Air Products and Matheson could not
    inform their customers not to expect helium deliveries due to their helium supplier being
    in force majeure, which in turn affected their “credibility and interactions with their
    customers.”5
    5
    Although they formed APMTG in order to obtain helium from the Riley Ridge Plant, Air Products and
    Matheson remained competitors in the industrial gas market.
    16
    [¶48] The district court correctly decided Denbury had failed to prove its nonperformance
    between May 23, 2013, and December 30, 2013, was excused by a force majeure event.
    3. Well Failure FM
    [¶49] The district court found Denbury had “proven that between July 11, 2014, [the date
    it provided notice of the Well Failure FM], and mid-August of 2014, Denbury’s selected
    end-date of the force majeure event (i.e., approximately 36 days), its non-performance
    under the HFA II was excused by a qualifying force majeure event which was then ‘outside
    the reasonable control [of Denbury] that could not have been avoided or overcome by
    [Denbury’s] exercise of reasonable care and due diligence.’” However, it found Denbury
    had failed to show the Well Failure FM “extended beyond mid-August of 2014.” The
    district court explained:
    Denbury failed . . . to prove that, “as soon as practicable
    after the commencement of the Force Majeure, [Denbury]
    proceed[ed] with due diligence and [did] all things reasonably
    practicable at its own cost to overcome and/or remedy the
    situation, and to recommence performance of its obligations”
    or that [to do so it would have been] “required to incur any
    extraordinary costs or make more than commercially
    reasonable investments.” (HFA II, § 17.4). Denbury failed to
    prove that any event(s) excusing non-performance under the
    HFA II after mid-August of 2014 were “outside the reasonable
    control of [Denbury] that could not have been avoided or
    overcome by [Denbury’s] exercise of reasonable care and due
    diligence.” Examples, but not a complete itemization of
    decisions and/or actions that Denbury has failed to prove were
    “outside the reasonable control of Denbury” or that “could not
    have been . . . overcome by Denbury’s exercise of reasonable
    care and due diligence” excusing its non-performance under
    the HFA II, were (and are): failure to use the 20-14 well as a
    supply well; failure to attempt to or to actually implement
    remedy/remedies for the sulfur deposition issues in the supply
    wells; failure to actually use the Big Horn formation as an
    alternative source of gas for the Riley Ridge Plant; and failure
    to use the 16-31 and 16-24 wells to supply gas to the Riley
    Ridge Plant from the Madison formation or from the Big Horn
    formation.
    [¶50] Denbury argues the district court correctly found the Well Failure FM was a
    qualifying event of force majeure under § 17 of the HFA II. It claims, however, the court
    erred in finding the Well Failure FM ended in mid-August of 2014. Denbury claims mid-
    17
    August was “plainly nothing more than a good faith estimate, not a binding determination.”
    It also claims the unrebutted evidence shows the Well Failure FM was far from over on
    August 15, 2014. Rather, Denbury had lost another CT string in the 10-14 and its expert
    had advised it not to attempt any further CT operations due to the harsh downhole
    environment. As a result, it could no longer rely on the primary method it had planned to
    use to address downhole sulfur deposition and had to begin the “long, costly, and difficult
    process of evaluating countless potential alternatives.”
    [¶51] The evidence supports the district court’s finding that Denbury chose mid-August
    as the end date of the Well Failure FM. Denbury’s July 11, 2014 letter declaring the Well
    Failure FM was clear. It stated: “Denbury is claiming a new Force Majeure starting on
    June 15 continuing until about mid-August, at which time the Plant is expected to be back
    on but at a potentially reduced rate.”6 (Emphasis added). While the exact date in mid-
    August was an estimate, Denbury clearly informed APMTG it was declaring a force
    majeure only until mid-August. Denbury never informed APMTG the circumstances had
    changed or provided APMTG a new force majeure end date.
    [¶52] Denbury claims it extended the Well Failure FM in a letter dated August 14, 2014,
    in which it stated the Riley Ridge Plant “has never had more than thirty-five days of
    sustained helium production performance, and the [helium] at that time was limited to the
    volume produced from only one supply well . . . .” It explained: “Denbury has been
    diligent in its attempts to solve the downhole problems that have been encountered since
    start-up. Nevertheless, while efforts continue to be made to find a permanent solution for
    the downhole well problems, none has yet been found.” Read as a whole, however, the
    purpose of the August 14, 2014, letter was not to extend the Well Failure FM, but rather to
    invoke the HFA II’s dispute resolution procedures to resolve the parties’ disagreement over
    the validity of the Well Failure FM. Additionally, the letter speaks to Denbury’s failure to
    find a permanent solution to the downhole problems, not Denbury’s inability to implement
    shorter-term solutions to resolve the Well Failure FM.
    [¶53] In any event, the district court also found Denbury had “failed to prove that the
    qualifying force majeure event deemed to have commenced on July 11, 2014, extended
    beyond mid-August of 2014.” Specifically, it found Denbury had failed to prove any event
    after mid-August was “outside the reasonable control of [Denbury] that could not have
    been avoided or overcome by [Denbury’s] exercise of reasonable care and due diligence”
    as required by § 17.1 of the HFA II. Denbury maintains the district court was precluded
    from making this finding. It argues by finding the Well Failure FM was a valid force
    majeure event between July 11, 2014, and mid-August of 2014, the district court
    necessarily found the sulfur deposition was “outside [Denbury’s] reasonable control” and
    6
    Although Denbury claimed in its July 11, 2014 notice that the Well Failure FM began on June 15, 2014,
    the district court decided Denbury’s notice was not “prompt” under §§ 7.2 and 17.3 of the HFA II and, as
    a result, deemed the Well Failure FM to have commenced on July 11, 2014. Denbury does not dispute this
    decision on appeal.
    18
    “could not have been avoided or overcome by the exercise of reasonable care and due
    diligence.” And, it claims we cannot review this finding because APMTG chose not to
    appeal it. Denbury argues once the district court made this finding under § 17.1, it was
    required to analyze under § 17.4 whether Denbury “proceeded with diligence and did all
    things reasonably practicable” to overcome the Well Failure FM, subject to the
    “extraordinary costs” and “more than commercially reasonable investments” limitations.
    Denbury is mistaken for two reasons.
    [¶54] First, its argument assumes the district court found sulfur deposition to be the force
    majeure event occurring between July 11, 2014, and mid-August 2014. The district court,
    however, did not specifically identify the force majeure event. The evidence shows the
    force majeure event was not supply well failure due to sulfur deposition but rather
    “mechanical supply well failure.” In its July 11, 2014 Well Failure FM notice, Denbury
    informed APMTG the 10-14 and 17-34 had stopped producing due to sulfur deposition.
    However, the events Denbury described were the need to perform a CT operation on the
    10-14 and to retrieve equipment from the 17-34. It was these events which were expected
    to be completed by mid-August of 2014, the date Denbury stated the force majeure would
    end. Dan Cole, Denbury’s Vice-President of Commercial Development and Governmental
    Relations and the author of the July 11, 2014 notice confirmed it was these events, not
    sulfur deposition, which formed the basis for Denbury’s Well Failure FM. He testified
    Denbury sent the July 11, 2014 force majeure notice because “after the issues with the well
    flow started in April or May and we were working to try to get the gas flow back, we had
    some issues with equipment lost in the hole . . . and the snubbing unit trying to recover the
    junk in the hole that the decision was made that we probably should be sending those force
    majeure due to mechanical well failure.” (Emphasis added).
    [¶55] Second, even if the district court found sulfur deposition to be the force majeure
    event between July 11, 2014, and mid-August 2014, this finding means only that sulfur
    deposition during that time period was outside Denbury’s reasonable control and incapable
    of being avoided or overcome by the exercise of reasonable care and due diligence. It did
    not preclude the district court from finding that after mid-August, sulfur deposition was
    not a valid force majeure event because it was within Denbury’s reasonable control and
    could have been avoided or overcome by the exercise of reasonable care and due diligence.
    [¶56] Under § 17.1 of the HFA II, “natural or mechanical supply well failure” constitutes
    force majeure only if it (1) is outside the reasonable control of the party, and (2) could not
    have been avoided or overcome by the exercise of reasonable care and due diligence.
    In evaluating whether the ‘reasonable control’ element
    of [a] force majeure clause[] has been met, courts consider two
    related notions:
    19
    “First, a party may not affirmatively cause the
    event that prevents his performance. The
    rationale behind this requirement is obvious. If a
    contractor were able to escape his
    responsibilities merely by causing an excusing
    event to occur, he would have no effective
    obligation to perform.
    The second aspect of reasonable control is more
    subtle. Some courts will not allow a party to rely
    on an excusing event if he could have taken
    reasonable steps to prevent it. The rationale
    behind this requirement is that the force majeure
    did not actually prevent performance if a party
    could reasonably have prevented the event from
    occurring. The party has prevented performance
    and, again, breached his good faith obligation to
    perform by failing to exercise reasonable
    diligence.”
    In re Old Carco LLC, 
    452 B.R. 100
    , 120-21 (Bankr. S.D.N.Y. 2011) (emphasis added)
    (quoting Nissho–Iwai Co. v. Occidental Crude Sales, Inc., 
    729 F.2d 1530
    , 1540 (5th Cir.
    1984)).
    [¶57] The district court’s finding that sulfur deposition after mid-August of 2014 was
    within Denbury’s reasonable control and could have been avoided or overcome by the
    exercise of reasonable care and due diligence is not clearly erroneous and is supported by
    the evidence. Prior to starting up the Riley Ridge Plant, Denbury knew sulfur deposition
    was likely because Madison gas contains hydrogen sulfide and Exxon experiences sulfur
    deposition at its nearby plant, which processes the same gas. Indeed, the Plant’s wells were
    purposefully equipped with larger and more expensive tubing than normal in order to
    increase the flow rates and thereby move any sulfur deposition to the surface, where it is
    easier to remediate.
    [¶58] Denbury also knew the wells had damage (“skin”) prior to starting up the Plant.
    Christina Harvick, a Denbury engineer and a member of Denbury’s “sulfur team,” testified
    the 10-14 and 17-34 were perforated in 2011 but were not brought online until December
    2013. She stated that allowing a well to sit between perforation and the flowing of gas can
    create skin, which in turn can decrease the pressure and temperature and cause sulfur
    deposition. Patrick Colin Smith, Denbury’s expert in production chemistry and sampling
    analysis, and Scott Stinson, a petroleum engineer who worked for Cimarex and continued
    on with Denbury until August 2012, confirmed this phenomenon. Moreover, Denbury
    knew temperature played a key role in sulfur deposition and starting the Plant in warmer
    20
    weather would reduce the chances for sulfur deposition. Yet, Denbury chose to start the
    Plant on December 30, 2013.
    [¶59] Denbury started up the Plant with only two supply wells, even though Mr. Stinson
    testified three to four supply wells were needed to allow for flexibility. If one well
    experienced plugging or skin, it could be taken offline for an acid wash or re-perforation
    (adding holes to the tubing to allow more gas to flow into the wellbore), while Denbury
    could continue to produce gas from the other two to three wells. Denbury also failed to
    use the 20-14 as an injection well. Mr. Stinson testified Cimarex obtained permission from
    the Wyoming Oil and Gas Conservation Commission to use the 20-14 as an injection well.
    According to Mr. Stinson, it was imperative to reinject the gas back into the Madison
    Formation in order to prevent drainage, as drainage lowers the pressure in the reservoir and
    thereby increases the chances of sulfur deposition occurring. Mr. Smith confirmed there
    is a greater chance of sulfur deposition with a depleted reservoir.
    [¶60] Prior to starting up the wells, Denbury was also aware of industry operations which
    can minimize or mitigate the effects of any damage in the wells, including sulfur
    deposition. Those operations included acid washes and re-perforating the wells. Ms.
    Harvick testified an acid wash cleans out the perforations, allowing more gas to flow into
    the wellbore and increasing temperature and pressure, which in turn decreases the
    opportunity for sulfur to deposit in the wellbore. Ray Lewis, Denbury’s senior production
    engineer and “well guy,” testified Exxon uses acid washes at its nearby plant, and Mr.
    Stinson testified he had anticipated an acid wash would be performed on the supply wells
    prior to the Plant starting. Similarly, Ms. Harvick and Mr. Lewis stated, and Mr. Smith
    confirmed, re-perforating wells increases flow rates, temperatures and pressures, thereby
    decreasing the chance for sulfur deposition. Denbury did not perform either operation prior
    to starting up the Riley Ridge Plant.
    [¶61] Once the Plant started-up, the supply wells were choked off by sulfur deposition in
    the wellbore. While Denbury believed any sulfur deposition in the wellbore could be
    treated with CT operations and chemical solvents, the chemical solvent failed to restore the
    17-34 to full production and the CT operations resulted in equipment left in the wells.
    Nevertheless, David Hamilton, Denbury’s well engineer, opined the 10-14 and 17-34 could
    still produce even with the equipment in their wellbores. Moreover, the very same
    operations Denbury could have performed to reduce the risk of sulfur deposition prior to
    starting up the Plant could have been performed in August 2014 to restore flow in the 10-
    14 and 17-34. Mr. Stinson testified acid washes are considered routine well maintenance,
    and he anticipated they would need to be routinely performed at Riley Ridge. In fact,
    Cimarex and Denbury had a permit to inject the used acid from an acid wash into the 20-
    14. Ms. Haverick testified Denbury had to flow the wells to determine the extent of damage
    before performing an acid wash. She stated the sulfur team had discussed performing an
    acid wash on the 10-14 and 17-34, but had not recommended it to Denbury’s Board of
    Directors as a potential remedy. She also testified the sulfur team had considered re-
    21
    perforating the wells but had yet to recommend it because they “would start out with the
    acid [wash] first” because “that’s a cheaper option.” Denbury never performed an acid
    wash or re-perforated the 10-14 and 17-34.
    [¶62] Denbury also could have begun using the 20-14, 16-24 and 16-31 as supply wells
    in mid-August. Henry (J.R.) Roman, Denbury’s project manager and “plant guy,” and
    David Hamilton, a Denbury engineer, testified the 20-14 was drilled to the Madison
    Formation but was never perforated or used as a supply well. Ms. Haverick testified the
    20-14 was never brought online but Denbury plans to perforate it at Layer 25, clean it out,
    and begin producing it. While she testified Denbury is “prepared to move forward [with
    using the 20-14 as a supply well] when needed,” Denbury has not done so. The 16-24 and
    16-31 wells are drilled to the Big Horn Formation. However, Mr. Lewis testified they
    could be capped off above the Big Horn and perforated into the Madison Formation.
    Denbury chose not to use the 16-31 and 16-24 as supply wells.
    [¶63] Denbury claims it proceeded with diligence and did all things reasonably practicable
    at its own cost to overcome and/or remedy the situation, and to recommence performance
    of its obligations under § 17.4. The problem for Denbury is that § 17.4 is triggered only if
    there is a valid force majeure event under § 17.1. See Vol. 15, Ex. 6, p. 19, § 17.4 (“Any
    party whose performance under this Agreement is affected by Force Majeure shall, as soon
    as practicable after the commencement of the Force Majeure, proceed with diligence and
    do all things reasonably practicable at its own cost to overcome and/or remedy the situation,
    and to recommence performance of its obligations, provided that . . . neither Party shall be
    required to incur any extraordinary costs or make more than commercially reasonable
    investments.”). As we have already discussed, the district court found, and the evidence
    shows, sulfur deposition did not constitute a valid force majeure event after mid-August
    2014. In any event, the district court also found Denbury had failed to prove that “as soon
    as practicable after the commencement of the Force Majeure, [Denbury] proceed[ed] with
    diligence and [did] all things reasonably practicable at its own cost to overcome and/or
    remedy the situation, and to recommence performance of its obligations” or that it must
    have been “required to incur any extraordinary costs or make more than commercially
    reasonable investments.”
    [¶64] Denbury claims this finding is clearly erroneous. Mr. Smith opined Denbury had
    “left no stone unturned” in attempting to remediate the downhole sulfur deposition.
    Denbury maintains APMTG did not present any expert testimony to rebut this opinion and
    it is supported by the evidence. The evidence shows Denbury (1) evaluated downhole
    electrical heat and heat by circulation; (2) investigated and studied physical solvent batch
    treatments; (3) researched a dozen different chemicals for treatment of sulfur deposition,
    including the chemical used by Exxon, and analyzed their effects on the Plant’s equipment;
    (4) became a member of Alberta Sulfur Research, Ltd. (ASRL) and conducted tours in
    Canada and bi-weekly calls with ASRL experts for the purpose of evaluating remediation
    options; (5) engaged in a multi-year survey and analysis of all publicly available
    22
    information from Exxon for information as to how it remediates its sulfur deposition; and
    (6) investigated the possibility of using gas from the Big Horn Formation, which contains
    helium but has a lower sulfur content than gas from the Madison Formation. Based on
    these efforts, Denbury presented the chemical batch treatment and using the Big Horn
    Formation to its Board. The Board approved beginning front-end engineering design for
    both options at a total cost of $1.1 million. Denbury ultimately decided against both
    options because the total estimated cost for the chemical batch option was determined to
    be $60 million in up-front costs (including $31 million to retrofit the Plant in order to
    protect it against the chemicals that would be used), plus $8 million per year in costs for
    the chemicals, and the total estimated cost for the Big Horn option was $160 million. Both
    investments would have equated to a negative present value of $40-$100 million and
    constituted extraordinary costs and exceeded commercially reasonable investments.
    APMTG did not claim otherwise.
    [¶65] We need not decide whether the chemical batch treatment and Big Horn options
    constitute extraordinary costs and would require Denbury to invest more than is
    commercially reasonable. Denbury had other low cost options to re-start the 10-14 and 17-
    34. Mr. Stinson testified an acid wash costs between $300,000 and $1 million and re-
    perforating costs a few hundred thousand dollars. Ms. Haverick and Mr. Lewis confirmed
    these options are inexpensive, and Denbury presented no evidence indicating the
    implementation of these options would require them to incur extraordinary costs and more
    than commercially reasonable investments. See Beardslee, 
    904 F. Supp. 2d at 220
    , aff’d,
    
    798 F.3d 90
     (2d Cir. 2015) (the party invoking a force majeure provision bears the burden
    of establishing it has been met) (citing Phillips Puerto Rico Core, Inc., 
    782 F.2d at 319
    ).
    [¶66] Denbury also could have begun using the 20-14, 16-24 and 16-31 as supply wells.
    Although the 16-24 and 16-31 are drilled to the Big Horn Formation, Denbury presented
    no evidence that plugging them off above the Big Horn and perforating them into the
    Madison Formation would require it to incur extraordinary costs or to make more than
    commercially reasonable investments. Denbury alleges it considered using these other
    wells but decided against it because, without a viable option to address sulfur deposition,
    it would risk losing another $40 million well. Consequently, Mr. Lewis did not recommend
    trying to flow Madison gas through these other wells until Denbury identified a chemical
    that could remove sulfur deposition from the wellbores and studied how the Riley Ridge
    Plant would need to be modified in order to accept that chemical. It claims the evidence
    showed Denbury would have had to spend $60 million to implement this option, which
    would have resulted in a negative present value to Denbury of between $40-100 million.
    [¶67] Denbury’s claim it could lose these wells to sulfur deposition ignores the actions
    available prior to flowing them which would reduce the chances of sulfur deposition in the
    wellbores. Denbury could perform an acid wash to remove any damage to these wells. It
    could perforate them just prior to flowing them, rather than allowing them to sit for two
    23
    years and sustain damage. It could start them up in the summer. And it could use one of
    the wells as an injection well, thereby preventing depletion of the reservoir.
    [¶68] In sum, as the district court aptly stated, “other than to study/investigate options,
    Denbury has not attempted to, nor actually implemented any remedy/remedies for the
    sulfur deposition issues in the [10-14 and 17-34],” and Denbury has “chosen” not to use
    the 20-14, 16-24, and 16-31 as supply wells. These failures and choices do not constitute
    force majeure under the HFA II. The district court correctly decided Denbury had failed
    to prove its nonperformance after mid-August of 2014 was excused by a force majeure
    event.
    CONCLUSION
    [¶69] The district court did not err in finding Denbury had failed to prove its non-
    performance of the HFA II was excused by a valid force majeure event, other than for a
    period of 36 days. It also did not err in denying Denbury’s request to terminate the HFA
    II under the doctrines of frustration of purpose and impossibility of performance. We
    affirm.
    24
    

Document Info

Docket Number: S-19-0172

Filed Date: 12/4/2020

Precedential Status: Precedential

Modified Date: 7/23/2024