Judges: Walker
Filed Date: 4/23/1913
Status: Precedential
Modified Date: 11/2/2024
Count 3 of the complaint in this case is in the form prescribed by the Code for a complaint on a dependent covenant or agreement. — Code, § 5382, form 9. This is enough to say in support of the conclusion that that count was not subject to the demurrer interposed to it.
Counts 1 and 2 followed the same form, except that, instead of the general averment of the code form of a compliance by the plaintiff with all the provisions of the contract on its part, each contained a specific averment that the plaintiff built the boilers as agreed upon, and was ready and willing to deliver and set the same as provided in the contract, which was followed in the first count by averments to the effect that the defendant wrongfully prevented the plaintiff from completing his
The second and third counts of the complaint were founded upon an instrument in writing, which was set out. The defendant’s plea 1, which was duly sworn to, contained all the averments found in the code form for a plea of non est factum. — Code, § 5383, form 33. It seems that the further averments found in that plea in denial of the execution of the instrument sued on by the individual who made oath to the plea in behalf of the defendant corporation could not have had the effect of casting on the plaintiff the burden of proving anything more than the execution of the instrument sued on by the defendant or by some one authorized to bind it (C'ode, § 3967), and that this feature of the plea, which alone distinguished it from the Code form for a plea of non est factum, did not render it subject to a demurrer which did not suggest as an objection to the plea the presence in it of the superfluous averments. However that may be, it is quite apparent that the subsequently filed pleas 3 and 4, each of which was substah-
Pleas E, F, H, I, and J each sought to put in issue averments contained in the complaint. The defendant
There was evidence tending to prove that the defendant’s refusal to accept the boilers made by the plaintiff was justifiable on the ground that they were materially defective in construction. Whether or not under evidence which was admitted without objection the jury might have found that the defendant had waived compliance by the plaintiff with the provision of the contract as to the time for completing and delivering the boilers, though the fact of such a waiver was not within the issues presented by the pleadings, yet the plaintiff would not have been entitled to recover the value of the boilers made by it if the defendant’s refusal to accept them in the condition in which they were proposed to be delivered was because of material defects in their construction which the plaintiff wrongfully refused to remedy, and not because the work had not been done within the time specified in the contract. The jury might well have inferred from the instruction embodied in written charge 1 which was given at the instance of the plaintiff that he was entitled to recover the value of the boliers in an incomplete condition “if the defendant notified the plaintiff some time after he had commenced the construction of the boilers that it would not accept them,” even though it was found from the evidence that the giving of such notice was in consequence of a refusal by the plaintiff to remedy material faults of construction which were disclosed by the’test of the boilers which was made with a view of their delivery to the defendant. It is plain that the defendant should not be required to pay for incomplete boilers which the
Reversed and remanded.