DocketNumber: ASBCA No. 60014
Judges: Melnick
Filed Date: 11/22/2016
Status: Precedential
Modified Date: 12/5/2016
ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) KBAJ Enterprises, LLC t/d/b/a Home Again )ASBCA No. 60014
) Under Contract No. SPE5EM-14-V-5503 ) APPEARANCE FOR THE APPELLANT: Mr. Joseph Dente General Manager, Member and Corporate Officer APPEARANCES FOR THE GOVERNMENT: Daniel K. Poling, Esq. DLA Chief Trial Attorney John F. Basiak, Jr., Esq. Steven C. Herrera, Esq. J. Maxwell Carrion, Esq. Trial Attorneys DLA Troop Support Philadelphia, PA OPINION BY ADMINISTRATIVE JUDGE MELNICK ON GOVERNMENT'S MOTION TO DISMISS This appeal arises from an alleged deemed denial by the contracting officer (CO) of appellant's claim seeking payment for delivered items under a purchase order (PO). The government moves to dismiss the appeal for lack of jurisdiction, or alternatively, for failure to state a claim upon which relief can be granted. Subsequent to the filing of the government's motion, the Board, sua sponte, directed the parties to brief whether a sum certain claim was submitted to a CO for a decision pursuant to the Contract Disputes Act of 1978 (CDA), 41 U:S.C. §§ 7101-7109. In response, the government contends that no proper claim was submitted to the CO. Because we conclude that a claim was not submitted to a CO, we dismiss the appeal for lack of jurisdiction. FINDINGS OF FACT 1. On 31 July 2014, Defense Logistics Agency Troop Support, Hardware (DLA or government), issued unilateral PO No. SPE5EM-14-V-5503 (PO 5503) to KBAJ Enterprises, LLC t/d/b/a Home Again 1 (KBAJ or appellant) for the delivery of 1 The PO was issued to "KBAJ ENTERPRISES DBA." This appeal was filed by appellant's representative in the name of KBAJ Enterprises LLC. At the Board's direction, the parties clarified that the proper name of appellant in this 500 weather-resistant neoprene rubber strips for a total price of $4,505 (R4, tab 3 at 9-13 2; compl. ~ 4). The PO contemplated delivery of the quantities by 10 November 2014 (R4, tab 3 at 13). 2. Under block 6 of PO 5503, Ms. Sharon Sax is identified as the "Local Admin" (R4, tab 3 at 9). Ms. Sax was not the CO who issued the PO. 3. On 17 September 2014, KBAJ received notice from DLA that 60 of the 500 shipped items were accepted (comp I. ~ 31; gov't mot. at 3, ~ 16). Two days afterward, KBAJ received a partial payment of $540.60 for the accepted items without allegedly receiving any information as to why the other shipped items were not accepted (comp I. `` 32-33; gov't mot. at 3, ~ 17). 4. Between September 2014 and March 2015, KBAJ corresponded with various DLA personnel, including Ms. Sax and her supervisor Mr. Jonathan Hampton, who identified himself as a Branch Chief for the "Industrial Hardware/Post Award-FHCC" division, seeking an explanation as to why DLA withheld payment of $3,964.40, the balance corresponding to the 440 items under PO 5503 that DLA did not formally accept (R4, tab 4; app. supp. R4, tabs 3, 7). 5. In a letter dated 21 April 2015 addressed to Ms. Sax, KBAJ stated in part: RE: CONTRACT NO. SPE5EM-14-V-5503 Dear Sharon: You are listed as the local administrator of the above referenced contract. As you know from our past requests we have been attempting to resolve the alleged issues associated with this award. To date we have been ignored, stonewalled and simply not responded to with regard to our attempts to resolve the alleged problems. Therefore, pursuant to the terms and conditions of said contract we are hereby asking if you would agree to submit this matter to [Alternative Disputes Resolution (ADR)] for resolution. Please let us know your position on or before COB, Friday April 24, 2015. Ifwe do not hear from you appeal is "KBAJ Enterprises, LLC t/d/b/a Home Again" (see Bd. corr. gov't ltr.41 U.S.C. § 7103 (a); CCIE & Co., 14-1 BCA ii 35, 700 at 174,816. The CDA does not define the term "claim"; however, FAR 2.101 defines a claim, in relevant part, as "a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain." A claim is not required to be submitted in any particular form or use any particular wording, but must provide to the CO adequate notice of the basis and amount of the claim and request a final decision. M Maropakis Carpentry, Inc. v. United States,609 F.3d 1323, 1328 (Fed. Cir. 2010). The claim must also be submitted to a CO. To satisfy the submission requirement, a contractor can either submit its claim directly to a CO or "to its primary contact [with the government] with a request for a final decision of the contracting officer and a reasonable expectation that such a request will be honored, and the primary contact in fact timely delivers the claim to the contracting officer." Neal & Co., Inc. v. United States,945 F.2d 385, 388 (Fed. Cir. 1991); see also Gardner Zemke Co.,ASBCA No. 51499, 98-2 BCA ii 29,997. 4 KBAJ's notice of appeal did not attach nor indicate a specific document that serves as its claim in this appeal. Although KBAJ failed to respond to our order, its complaint characterizes its 21 April 2015 letter as a "final demand letter" (finding 5). We presume that KBAJ attempts to appeal from an alleged CO's deemed denial of this letter. On its face, the 21 April letter is specifically addressed to Ms. Sax, who is identified by KBAJ as a local administrator and is also identified as a "Local Admin" under PO 5503 (findings 2, 5). The letter also copied Mr. Hampton who is identified as a "Branch Chief' in prior correspondence (finding ~ 4 ). KBAJ' s notice of appeal to the Board alleges that Ms. Sax and Mr. Hampton are COs, but a review of the record does not substantiate that allegation. Therefore, we are unable to conclude that the 21 April letter was submitted directly to a CO for jurisdictional purposes. We next determine whether KBAJ meets the CDA's submission requirement by sending a proper claim to a primary contact. Pursuant to Neal, the requirement may be met by submitting a claim to the primary contact "with a request for a final decision of the contracting officer and a reasonable expectation that such a request will be honored."945 F.2d at 388. While the 21 April letter does expressly request a decision from Ms. Sax, even if we were to assume she is a primary contact and the letter otherwise meets the requirements of the FAR definition of a claim, the evidence fails to establish that KBAJ intended and reasonably expected a decision from a CO. We can reasonably infer that, based on statements made in KBAJ's 24 April letter to CO Manco, KBAJ was aware that CO Manco was the cognizant CO on matters related to PO 5503 and other POs, going so far as requesting her recusal (finding 8). Even with this knowledge, KBAJ elected to submit its 21 April letter directly to Ms. Sax. See Bruce E. Zoeller,ASBCA No. 55654, 07-1 BCA ~ 33,581 at 166,347 (appellant was aware of the CO's identity under the lease, and submitted a claim seeking "a Chief Accountable Officer's decision" that failed to establish a submission of a claim to a CO under the CDA). Under these circumstances, we conclude that KBAJ intended to resolve its dispute with Ms. Sax, or in other words, someone other than the cognizant CO at the time. See D.L. Braughler Co. v. West,127 F.3d 1476, 1481-82 (Fed. Cir. 1997) (letter styled as a claim with a certification and submitted to the resident engineer, who was an authorized representative of the CO, did not meet submission requirement because letter sought to resolve matter directly with resident engineer). Therefore, KBAJ has failed to prove that it has satisfied the CDA's submission requirement. We lack jurisdiction to entertain this appeal. 3 3 Because we determine that KBAJ' s failure to submit a claim to a CO for a decision deprives us of jurisdiction over this appeal, we need not address alternative grounds for dismissal raised in DLA's motion. 5 CONCLUSION We dismiss the appeal for lack of jurisdiction, without prejudice to the contractor's submission of a claim to a CO. Dated: 22 November 2016 MARK A. MELNICK Administrative Judge Armed Services Board of Contract Appeals I concur ~#= MARK N. STEMPLER Administrative Judge RICHARD SHACKLEFORD Administrative Judge Acting Chairman Vice Chairman Armed Services Board Armed Services Board of Contract Appeals of Contract Appeals I certify that the foregoing is a true copy of the Opinion and Decision of the Armed Services Board of Contract Appeals inASBCA No. 60014, Appeal ofKBAJ Enterprises, LLC t/d/b/a Home Again, rendered in conformance with the Board's Charter. Dated: JEFFREY D. GARDIN Recorder, Armed Services Board of Contract Appeals 6