DocketNumber: ASBCA No. 63221
Judges: Smith
Filed Date: 6/10/2022
Status: Precedential
Modified Date: 6/27/2022
ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Zahra Rose Construction & Logistics )ASBCA No. 63221
Services Company ) ) Under Contract No. H92237-20-P-3029 ) APPEARANCE FOR THE APPELLANT: Ms. Zahra Noori CEO APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Deputy Chief Trial Attorney Maj Brian Shust, USAF Maj Ashley Ruhe, USAF Trial Attorneys OPINION BY ADMINISTRATIVE JUDGE SMITH ON APPELLANT’S MOTION FOR RECONSIDERATION This appeal was dismissed for lack of jurisdiction in our decision of May 19, 2022. We received appellant’s May 23, 2022, objection to our decision which we will treat as a timely-filed motion for reconsideration under Board Rule 20. No further briefing is required and we deny the motion. Board Rule 20 requires a party to provide “specific[] grounds relied upon to grant the motion” but appellant only makes a vague argument, without any evidence to support it, that appellant’s two projects discussed in our dismissal were run by different project managers (app. mot. at 1). Appellant implies, without actually stating or showing, that one of the project managers may have been impeded more by the Taliban takeover of Afghanistan than the other, justifying equitable tolling of the jurisdictional time limit to submit this appeal. But even if there were two project managers who were affected differently by the Taliban, it does not refute our fact finding, supported by the record, that appellant demonstrated email capability during the 90-day period for submitting its notice of appeal here. Given the low bar for the contents of a notice of appeal (see Board Rule 1(a)), appellant has not shown that it required detailed information from its project manager, or that he or she was prevented from providing such information by the Taliban. There is no factual basis upon which to consider equitable tolling. We also note that appellant’s motion seeks to negotiate the claim with the contracting officer (app. mot. at 1). Our dismissal explicitly provided appellant that opportunity, assuming the government determines there is any merit to appellant’s claim – a decision we do not possess jurisdiction to make. Last, even though appellant asserts that, as a contractor, it has given many years of support to the United States, under the Contract Disputes Act, the time limit for appeal to the Board is within 90 days of receipt of the contracting officer’s final decision (see41 U.S.C. § 7104
(a)), unlike the rules for the Court of Federal Claims, which allow one year. Date: June 10, 2022 Brian S. Smith Administrative Judge Armed Services Board of Contract Appeals I concur I concur RICHARD SHACKLEFORD J. REID PROUTY Administrative Judge Administrative Judge Acting Chairman Vice Chairman Armed Services Board Armed Services Board of Contract Appeals of Contract Appeals I certify that the foregoing is a true copy of the Opinion and Decision of the Armed Services Board of Contract Appeals inASBCA No. 63221
, Appeal of Zahra Rose Construction & Logistics Services Company, rendered in conformance with the Board’s Charter. Dated: June 13, 2022 PAULLA K. GATES-LEWIS Recorder, Armed Services Board of Contract Appeals 2