DocketNumber: No. 01-2917
Citation Numbers: 45 F. App'x 183
Judges: Fuentes
Filed Date: 6/14/2002
Status: Precedential
Modified Date: 11/5/2024
OPINION OF THE COURT
This claim arises from two contracts (the “Agreements”) dated October 10, 1989, between Pitcairn Enterprises (“Pitcairn”), a Pennsylvania car dealership, and Universal Computer Consulting and Universal Computer Maintenance (“Universal”), two Texas-based manufacturers and installers of inventory software for car dealers. The terms of the Agreements were extended by addendum in March 1991.
The Agreements allowed Pitcairn to defer a portion of its monthly payment to Universal for the first two years of the Agreements, after which Pitcairn agreed to repay the deferred amounts, plus interest, over the following sixty months. Each Agreement contained, at Section 17, a segment entitled “Dispute Resolution,” that provided that all “claims, disputes, controversies and other matters,” between the parties and based on the Agreement, “shall be settled by arbitration.” Sections 17A-G of the Agreement outline the procedure to be followed in the event that one of the parties decides to file an arbitration claim.
On June 6, 2000, Universal commenced an arbitration proceeding with the American Arbitration Association (the “AAA”) and notified Pitcairn, as required by the Agreement. On June 29th, Pitcairn filed objections to the arbitrator’s jurisdiction with the AAA, claiming that Universal had waived their right to arbitration. See, Agreements § 17E (stating that “[sjhould the party demanding the arbitration fail to name an arbitrator within ten days of the demand, his right to arbitration shall lapse.”).
On November 1, 2000, Pitcairn filed its initial complaint in the District Court, requesting that the Court enjoin the arbitration proceedings based, once again, on Universal’s alleged waiver and the arbitration panel’s resulting lack of jurisdiction. On January 3, 2001 Pitcairn filed a motion for a Temporary Restraining Order (TRO) to stay arbitration proceedings pending the resolution of its preliminary injunction motion. On January 4, 2001, the District
On June 20, 2001, the District Court issued its Memorandum Opinion and Order. Pitcairn Enterprises, Inc. v. Universal Computer Consulting, Inc., 2001 WL 695048 (E.D.Pa.2001). In its Opinion, the Court first determined that a valid and enforceable arbitration agreement existed. Id. at *2. Next, the Court relied on the “expansive, all-encompassing language” used by the parties in crafting the arbitration provision to decide that the dispute at issue “plainly fell within the substantive scope of [the arbitration] provision.” Id. Finally, the Court determined that the waiver provision of Section 17E was “inconsisten[t]” with the rest of the Section’s provisions, and that the arbitration panel “must have the initial opportunity to address the apparent ambiguity within the arbitration clause.” Id. Consequently, the Court denied Pitcairn’s motion for summary judgment, granted Universal’s motion for summary judgment, and dismissed as moot Pitcairn’s motion for a temporary restraining order. Id. at *3
Pitcairn now appeals the District Court’s Order. The narrow issue for this Court’s adjudication is whether the District Court or the Arbitration Panel was the proper forum to decide whether the waiver clause in the Agreement was an unambiguous bar to an arbitration proceeding. See Paine Webber, Inc. v. Hoffman, 984 F.2d 1372 (3d Cir.1993) (instructing that “whether or not [a party is] bound to arbitrate, as well as what issues it must arbitrate, is a matter to be determined by the Court” but warning that “a court is not to rule on the potential merits of the underlying claims, no matter how frivolous the claims may appear to the court”). We find the District Court’s analysis of this issue to be both accurate and persuasive and we therefore affirm substantially for the reasons stated by the District Court.
Pitcairn raises an alternative argument on appeal, namely that, since certain provisions of the Agreements can be construed as usurious under Texas law, the entire Agreement is unenforceable and therefore not subject to arbitration. We disagree and conclude that the issue was properly before the arbitration panel. Under applicable Texas law, usury is not a defense to the enforceability of the underlying contract. See Steves Sash & Door Co., Inc. v. Ceco Corp., 751 S.W.2d 473, 476 (Tex.1988). Rather, the usurious interest is forfeited, a penalty is imposed upon the usurer, and that amount is then set-off against any principal owed plus any interest below the relevant usurious rate. See TX CIV. ST. Art. 5069-1.06 (1991). The arbitration panel found for Pitcairn on its usury claim, and meticulously calculated its set-off under the relevant Texas statutory and case law. Therefore, Pitcairn’s usury claim is without merit.
Pitcairn’s appeal is rejected on one final ground. On December 7, 2001, nearly six months after the District Court’s final Order in this case, Universal commenced an action in the U.S. District Court for the Southern District of Texas to confirm the arbitration award.
. Because we write solely for the benefit of the parties, we recount the facts and the procedural history of the case only as they are relevant to the following discussion.
. Universal has acknowledged that it did not propose its first arbitrator until July 5, 2000, twenty-nine days after its demand for arbitration was filed.
. We have noted that Sections 9-11 the FAA "authorize [a] district court to confirm, vacate, or modify [an arbitrator's] award under a narrow scope of judicial review”. See John Hancock Mut. Life Ins. Co. v. Olick, 151 F.3d 132 (3d Cir.1998)
. 9 U.S.C. § 12 states, in relevant part, that “Notice of a motion to vacate, modify, or correct an award must be served upon the adverse party or his attorney within three months after the award is filed or delivered.”