DocketNumber: No. 06-3840
Citation Numbers: 496 F.3d 552, 2007 WL 2048925
Judges: Clay, Suhrheinrich, Sutton
Filed Date: 10/19/2007
Status: Precedential
Modified Date: 11/5/2024
SUTTON, J., delivered the opinion of the court, in which SUHRHEINRICH, J., joined. CLAY, J. (pp. 560-63), delivered a separate dissenting opinion.
OPINION
More than three years after signing a consent decree with the United States to pay for the environmental remediation of a contaminated industrial site in Arcanum, Ohio, RSR Corporation filed this lawsuit seeking contribution for the clean-up costs from Commercial Metals Company. Because the district court properly determined that RSR filed this contribution action after the three-year limitations period, see 42 U.S.C. § 9613(g)(3), we affirm.
I.
From 1966 through 1982, Harold Shane reprocessed car, truck and industrial batteries at a facility in Arcanum, Ohio. Shane received the batteries from several suppliers, including RSR and Commercial Metals. Toxic byproducts of the facility’s activities included battery acid and a “lead oxide sludge [ ],” both of which seeped into the ground and eventually threatened local water supplies. JA 256.
In 1983, the EPA placed Shane’s facility on the National Priority List, and the federal agency began cleaning up the site. See Amendment to National Oil and Hazardous Substance Contingency Plan; National Priorities List, 48 Fed.Reg. 40,658, 40,670 (Sept. 8,1983) (codified at 40 C.F.R. pt. 300, app’x B). In 1989, the United States filed a lawsuit against Shane under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) seeking “to recover response costs incurred by the United States” in cleaning up the site. JA 253; see 42 U.S.C. § 9607(a) (“[T]he owner and operator of ... a facility ... shall be liable for ... all costs of removal or remedial action incurred by the United States Government. ...”).
On February 11,1998, the United States filed a proposed consent decree between itself and Shane, which the district court accepted and entered seven months later. On March 23, the district court approved a de minimis consent decree, resolving the liability of many minor polluters at the Arcanum site. And on August 28, the United States filed with the district court a proposed consent decree among itself, RSR, two major contributors and one de minimis contributor, and the court entered the consent decree in April 1999.
Consistent with the April 1999 consent decree, RSR and its co-defendants agreed to reimburse the United States for $201,832 in past response costs, to “finance and perform” the remedial work needed to finish cleaning up the Arcanum site, JA 514, to post a bond for $5,800,000 (the estimated cost of the remaining remedial work), to “undertake ... further response actions to the extent” necessary, JA 529, and to reimburse the United States for up to $150,000 in future response costs. In return, the United States agreed “not to sue or take administrative action” that would impose additional liability on RSR and its co-defendants, JA 578, and the defendants received the right to seek contribution from other potentially responsible parties. Attached to the consent decree was a “final volumetric ranking” of contributors to the contamination at the site, showing RSR as the largest and Commercial Metals as the 62nd largest of the 444 known contributors. JA 665-67. The consent decree also provided that the district court would retain jurisdiction over the parties until the complete remediation of the site.
On July 2, 2001, RSR and its co-defendants finished cleaning up the site at a total cost of $2,631,606.
On January 16, 2003, RSR filed this contribution action against Commercial Metals, and the district court consolidated the action with the Shane litigation. Commercial Metals moved to dismiss the complaint on statute-of-limitations grounds, and the district court granted the motion.
II.
CERCLA “grants the President broad power to command government agencies and private parties to clean up hazardous waste sites.” Key Tronic Corp. v. United States, 511 U.S. 809, 814, 114 S.Ct. 1960, 128 L.Ed.2d 797 (1994). The statute permits the United States to issue enforcement orders “as may be necessary to protect public health and welfare and the environment.” 42 U.S.C. § 9606(a). And it authorizes a number of causes of action designed to obtain the prompt remediation of waste sites and the fair apportionment of remediation costs: reimbursement actions for “[a]ny person who receives and complies with the terms” of an enforcement order, id. § 9606(b)(2)(B); abatement actions to prevent the “actual or threatened release of a hazardous substance,” id. § 9606(a); governmental cost recovery actions that allow the United States, a State or an Indian tribe to recover “all costs of removal or remedial action incurred” from potentially responsible par
Appreciating the risk that never-ending litigation might impede a “swift and effective response to hazardous waste sites,” Anspec Co., Inc. v. Johnson Controls, Inc., 922 F.2d 1240, 1247 (6th Cir.1991), Congress authorized the United States and potentially responsible parties to launch clean-up efforts first, then recover the costs from other responsible parties later — through settlements, consent decrees and, if need be, judgments. See, e.g., 42 U.S.C. § 9622(b)(1) (authorizing settlements to reimburse parties for certain remedial actions); id. § 9622(d) (authorizing consent decrees to enforce cleanup agreements); id. § 9622(h) (authorizing settlements for recovery of “costs incurred by the United States Government” from responsible parties); id. § 9622(g) (authorizing settlements for cost recovery from de minimis responsible parties); see also, e.g., id. § 9606(b)(2)(A) (authorizing those who “compl[y]” with enforcement orders to seek reimbursement from the United States); id. § 9607(a) (authorizing actions to recover costs “incurred” in a cleanup effort).
The statutory authority of government entities and private parties to bring cost-recovery and contribution actions later, however, does not last forever. “An initial action for recovery of the costs ... for a remedial action,” for example, must be filed “within 6 years after initiation of physical on-site construction of the remedial action,” and subsequent cost recovery actions “may be maintained at any time during the response action, but must be commenced no later than 3 years after” its completion. Id. § 9613(g)(2)(B). A potentially responsible party may bring a contribution action “during or following any civil action” under the statute’s enforcement and cost-recovery provisions, id. § 9613(f)(1); see Cooper Indus., Inc. v. Aviall Servs., Inc., 543 U.S. 157, 161, 125 S.Ct. 577, 160 L.Ed.2d 548 (2004), or after resolving its liability to the United States “in an administrative or judicially approved settlement,” 42 U.S.C. § 9613(f)(3)(B). Such an action for “response costs or damages” must be filed within 3 years of:
(A) the date of judgment in any action ... for recovery of such costs or damages, or
(B) the date of an administrative order under section 9622(g) of this title (relating to de minimis settlements) or 9622(h) of this title (relating to cost recovery settlements) or entry of a judicially approved settlement with respect to such costs or damages.
Id. § 9613(g)(3).
As RSR’s complaint indicates, it filed this action “pursuant to 42 U.S.C. § 9613(f)” — the contribution provision. JA 3. RSR’s right to seek contribution from Commercial Metals and other potentially responsible parties arose from the 1999 consent decree, which required it to pay the United States $201,832 in past response costs, to pay up to $150,000 in future response costs incurred by the United States, and, most critically, to “finance” the costs of the as-yet-unfinished remedial work, JA 514. See 42 U.S.C. § 9613(f)(3)(B) (“A person who has resolved its liability to the United States or a
RSR has never disputed that its complaint amounted to a contribution action, see 42 U.S.C. § 9613(f), as opposed to a cost recovery action, see id. § 9607(a)(4)(B). And § 113(g)(3) of CERCLA requires that an “action for contribution for any response costs or damages” commence within three years of the “entry of a judicially approved settlement with respect to such costs or damages.” Id. § 9613(g)(3). RSR acknowledges that the 1999 consent decree constitutes a “judicially approved settlement” “resolv[ing] [RSR’s] liability to the United States” for the purpose of authorizing a contribution action. See id. § 9613(f)(3)(B). And we see no reason why it does not also constitute a “judicially approved settlement” for the purpose of limiting when that action may be brought — for determining in other words when the right to bring that action accrues for statute-of-limitation purposes. To conclude otherwise would allow a “judicially approved settlement” to authorize a contribution action to recover the “costs” imposed by that settlement without placing any limit on when that action must be brought. Cf. Am. Cyanamid Co. v. Ca-puano, 381 F.3d 6, 13 (1st Cir.2004) (explaining that the reference to “such costs or damages” in § 113(g)(3)(A) “refers to the costs or damages contained in the ‘judgment’ ” “mentioned earlier in the sentence and identifies a particular claim or payment”). Because RSR waited more than three years to bring its contribution action after the April 1999 consent decree, its complaint lies outside of the limitations period and must be dismissed.
RSR resists this interpretation on the ground that CERCLA contains a “general [six-year] statute of limitations” in § 113(g)(2) with “four narrow exceptions” in § 113(g)(3), and that none of the exceptions applies here because RSR entered into only a “cleanup agreement” with the United States. Br. at 9. The statutory text, however, does not set forth a “general statute of limitations” with exceptions but instead sets forth different limitations periods for different causes of action. See 42 U.S.C. § 9613(g)(1) (three-year limitations period on “[a]ctions for natural resource damages”); id. § 9613(g)(2)(A) (three-year limitations period on the “initial action for recovery of the costs” of a removal action); id. § 9613(g)(2)(B) (six-year limitations period on the “initial action for recovery of the costs” of a remedial action); id. § 9613(g)(2) (three-year limitations period on “any subsequent action ... for further response costs”); id. § 9613(g)(3) (three-year limitations period on any “action for contribution”); id. § 9613(g)(4) (three-year limitations period on any “action based on rights subrogated ... by reason of payment of a claim”); id. § 9613(g)(5) (three-year limitations period on indemnification actions).
Equally unavailing is RSR’s contention, seconded by the dissent, that the underlying agreement between RSR and the United States is not a “judicially approved settlement” under § 113(g)(3)(B). Here is the key language of the statute in context:
No action for contribution for any responses costs or damages may be commenced more than 3 years after—
*557 (A) the date of judgment in any action under this chapter for recovery of such costs or damages, or
(B) the date of [1] an administrative order under section [122(g) of CERCLA] (relating to de minimis settlements) or [2] [an administrative order under section 122(h)] (relating to cost recovery settlements) or [3] entry of a judicially approved settlement with respect to such costs or damages.
Id. § 9613(g)(3). As RSR and the dissent see it, the “with respect to such costs or damages” language in subparagraph B refers only to costs or damages arising from § 122(g) or (h) administrative orders.
That is not, however, the natural way to read the provision. The point of this section of the statute, as the introductory clause indicates, is to establish a time bar for contribution actions for “any response costs or damages.” Subparagraph (A) says that the three-year time bar applies to “such costs or damages” arising from “judgment[s],” while subparagraph (B) says that it applies to “such costs or damages” arising from (1) “de minimis settlements” reflected in an administrative order under § 122(g), (2) “cost recovery settlements” reflected in an administrative order under § 122(h) and (3) “judicially approved settlement[s].” In other words, just as the phrase “such costs or damages” in subparagraph (A) limits the time bar on judgment-authorized contribution actions to those “costs or damages contained in the ‘judgment’ mentioned,” Am. Cyanamid, 381 F.3d at 13, so the same phrase in subparagraph (B) limits the time bar on settlement-authorized contribution actions to those “costs incurred in the settlement,” id. at 15.
A contrary reading would work considerable damage to the statute, as it would mean that there is no time bar on contribution actions arising from “judicially approved settlements” of recovery actions initiated by private parties, individual States or Indian Tribes. Here is why. While §§ 122(g) and (h) authorize the United States to settle cost-recovery actions administratively, the United States is not the only entity entitled to bring a cost-recovery action. Individual States, Indian tribes and private parties who incur cleanup costs may also seek “cost recovery (as distinct from contribution)” under § 107(a). See 42 U.S.C. § 9607(a); Atl. Research Corp., 127 S.Ct. at 2338. If, as RSR reads the statute, the provision relating to “judicially approved settlement^]” refers only to settlements under § 122(g) or (h), then the contribution-action clock would never start as to settlements arising from actions initiated by these other parties. Rather than focus on who settled the cost-recovery action, in short, the statute asks us to focus on what was settled. Cf United States v. Navistar Int’l Transp. Corp., 152 F.3d 702, 712 n. 17 (7th Cir. 1998) (rejecting reading of another CERC-LA limitations provision that “would lead to the awkward result that actions brought by private parties to recover response costs would be subject to a different statute of limitations trigger when no government agency is involved in the clean-up”).
To suggest that the 1999 consent decree covered only compensation for past response costs, as RSR suggests, also would be inaccurate. RSR was the largest polluter at the Arcanum site, and its expected liability was $2,335,407.96 based on RSR’s contribution of almost 10,000 tons of hazardous materials (at' the rate per pound established for de minimis contributors). The quid pro quo for seeking less reimbursement from RSR was RSR’s agreement along with its co-defendants to assume liability for — to “finance and perform” — the as-yet-unfinished remedial work at the Arcanum site, JA 514, to post
RSR insists that it could not have resolved its liability to the United States in the consent decree before the completion of the remedial action. Reply Br. at 1. But RSR’s promise of future performance was the very consideration it gave in exchange for the United States’ covenant not to seek further damages. RSR and its co-defendants in other words resolved their liability to the United States by agreeing to assume all liability (vis-a-vis the United States) for future remedial actions. And even if the covenant regarding future response costs did not take effect until the remedial action was complete, the statute of limitations for contribution actions runs from the “entry” of the settlement, 42 U.S.C. § 9613(g)(3)(B), not from the date that each provision of that settlement takes effect.
RSR also suggests that Commercial Metals waived this time-bar defense. But Commercial Metals raised the issue through its motion to dismiss on statute-of-limitations grounds, and the consolidation of this case with the Shane litigation (contrary to RSR’s suggestion) did not moot the motion. If there is any waiver on this score, it is one of RSR’s doing: It never raised the issue below. See J.C. Wyckoff & Assocs., Inc. v. Standard Fire Ins. Co., 936 F.2d 1474,1488 (6th Cir.1991).
The dissent also contends that our interpretation fails to respect congressional intent (as evidenced by the legislative history of the Superfund Amendments and Reauthorization Act of 1986, Pub.L. No. 99-499, 100 Stat. 1613) because Congress did “not evince any intent ... to codify a uniform three-year statute of limitations for all contribution actions.” Dissent at 563. But the legislative history suggests that is just what the National Legislature had in mind, see H.R.Rep. No. 253, pt. I, at 79 (1985) (“This section establishes a three-year statute of limitations for the filing of an action for contribution for response costs or damages.”), and indeed that history does not distinguish among types of judicially approved settlements when discussing that limitations period, see id. (“The statute of limitations [for contribution actions] begins to run at the date of judgment for recovery of response costs or damages or the date of entry of a judicially approved settlement with respect to such costs or damages.”). The face of the amendments, more importantly, reveals a design to codify one limitations period for contribution actions and another period for cost-recovery actions — one subsection authorizes contribution actions, (entitled “(f) Contribution”); another places a limitations period on contribution actions, see 42 U.S.C. § 9613(g)(3) (entitled “(g) Period in which action may be brought” and “(3) Contribution”); whereas a third imposes a limitations period on cost-recovery actions, see id. § 9613(g)(2) (entitled “Actions for recovery of costs”).
Nor does this interpretation conflict with decisions of the First and Tenth Circuits. See Dissent at 561-62. In American Cyanamid Co. v. Capuano, 381 F.3d 6 (1st Cir.2004), the plaintiff filed a contribution action for groundwater-cleanup costs during negotiations with the United States over the recovery of those costs. Pointing to § 113(g)(3)(A), the defendant claimed that a 1988 judgment against the plaintiff for soil-cleanup costs triggered the limitations period for any contribution action that the plaintiff might bring regarding the site. In rejecting this argument, the First Circuit held that “such costs or damages” in § 113(g)(3)(A) referred only to “the costs or damages contained in the ‘judgment’ mentioned” in that subpara-graph, not to “any response costs or damages that could arise in the future.” 381 F.3d at 13. Our holding follows that approach, because we likewise construe “such costs or damages” in § 113(g)(3)(B) to refer only to those “costs or damages” imposed by the judicially approved settlement. See Am. Cyanamid, 381 F.3d at 15 (CERCLA “allows a settling PRP to seek contribution within three years of that settlement for costs incurred in the settlement.”). Those “costs” here included the costs incurred under RSR’s obligation to “finance and perform” the as-yet-unfinished remedial work at the Arcanum site. JA 514.
The plaintiff in Sun Co., Inc. v. Browning-Ferris, Inc., 124 F.3d 1187 (10th Cir. 1997), sought recovery under § 107(a) and § 113(f) for costs it incurred remediating a brownfield site. The Tenth Circuit held that — because the government had never filed a “civil action” against the plaintiff but only issued a unilateral administrative order — the plaintiffs action was an “initial action for recovery of ... costs” and thus was covered by the six-year statute of limitations for cost-recovery actions: § 113(g)(2). See Sun Co., 124 F.3d at 1192 (internal quotation marks omitted). Indeed, Sun Co. agreed with our resolution of the only question before us: “If the PRP incurred its cleanup costs pursuant to a civil action under §§ 106 or 107, it will have three years from the date of judgment or settlement in which to bring its contribution claim.” Id. at 1193.
The dissent also rejects our reading of the text on the ground that it is “simply not practical .,. because future cleanup costs cannot be accurately estimated or determined” in time to bring a contribution action. Dissent at 562. But there is little question that Congress intended to impose a limitations period on actions under CERCLA, see 42 U.S.C. § 9613(g) (“Period in which action may be brought”), and intended a limitations period to apply even before a site was fully cleaned up, see id. § 9613(g)(2)(B) (initial action to recover remedial costs must commence “within 6 years after initiation of physical on-site construction”).
To the extent the dissent means to raise a fairness concern, this is not the case to raise it. RSR knew that the cleanup of the Arcanum site was expected to cost up to $5,800,000 when it signed the 1999 consent decree, and the effort turned out to be far cheaper than expected, costing only $2,631,606. If anything, RSR’s expected
III.
For these reasons, we affirm.