DocketNumber: 22-1709
Filed Date: 7/19/2023
Status: Precedential
Modified Date: 7/24/2023
In the United States Court of Appeals For the Seventh Circuit ____________________ Nos. 22-1347, 22-1709 & 22-1737 DRIFTLESS AREA LAND CONSERVANCY, et al., Plaintiffs-Appellees, Cross-Appellants, v. RURAL UTILITIES SERVICE, et al., Defendants-Appellants, Cross-Appellees, and AMERICAN TRANSMISSION COMPANY LLC, ITC MIDWEST LLC, and DAIRYLAND POWER COOPERATIVE, Intervening Defendants-Appellants, Cross-Appellees. ____________________ Appeals from the United States District Court for the Western District of Wisconsin. Nos. 21-cv-096-wmc & 21-cv-306-wmc — William M. Conley, Judge. ____________________ ARGUED SEPTEMBER 28, 2022 — DECIDED JULY 19, 2023 ____________________ Before EASTERBROOK, HAMILTON, and BRENNAN, Circuit Judges. 2 Nos. 22-1347, 22-1709 & 22-1737 EASTERBROOK, Circuit Judge. The Cardinal-Hickory Creek Project is a planned electric transmission line that would de- liver wind energy from Iowa to Southern Wisconsin. The util- ity companies responsible for the line asked the Fish and Wildlife Service to allow construction across the Upper Mis- sissippi River National Wildlife and Fish Refuge alongside a road and railroad that already cross the Refuge. In October 2019 the Rural Utilities Service completed an environmental impact statement assessing this transmission line under the National Environmental Policy Act,42 U.S.C. §4332
(2)(C). The Fish and Wildlife Service and the Army Corps of Engineers adopted the statement for their own use in considering the project. In December 2019 the Fish and Wildlife Service determined that permi]ing the line to pass through the Refuge would be “compatible” with its “major purposes” under the Refuge Act. 16 U.S.C. §668dd(d)(1)(A). The agency issued a right-of-way permit in September 2020. Several environmental advocacy groups sued, arguing that the permit violates the Refuge Act and that the environ- mental impact statement is deficient under the National Envi- ronmental Policy Act. While litigation was pending, the utility companies applied for an amended permit slightly altering the route, which still would largely parallel the road. They also asked the Fish and Wildlife Service to consider a land ex- change under 16 U.S.C. §668dd(b)(3) as an alternative to the permit. While reviewing these new requests, the agency dis- covered that it had relied on incorrect easement documents in issuing its original compatibility determination. By a le]er dated August 27, 2021, it revoked the determination and per- mit. This le]er also promised to consider the proposed land Nos. 22-1347, 22-1709 & 22-1737 3 exchange. Almost two years have passed, but the agency has not issued a new decision. Despite the absence of an effective decision, the litigation continued. The district court entered a declaratory judgment that, under the Refuge Act, the agency’s compatibility deter- mination could not support a crossing either by right of way (the rescinded decision) or land transfer (the pending pro- posal). The court also vacated the Rural Utilities Service’s de- cision to adopt the environmental impact statement and re- manded to the agency for further proceedings, although it de- clined to enjoin ongoing construction of the project on private land outside the Refuge.580 F. Supp. 3d 588
(W.D. Wis. 2022). The agencies and utility companies appealed, and the advo- cacy groups cross-appealed from the denial of injunctive re- lief. (There were earlier appeals too, but the issues those deci- sions resolved do not affect the parties’ current disputes. See Driftless Area Land Conservancy v. Huebsch,969 F.3d 742
(7th Cir. 2020); Driftless Area Land Conservancy v. Valcq,16 F.4th 508
(7th Cir. 2021).) We must first ensure that the district court had subject- ma]er jurisdiction. The utility company defendants maintain that the challenge to the revoked permit is moot. A claim is moot “when the issues presented are no longer live or the parties lack a legally cognizable interest in the out- come. [This occurs] only when it is impossible for a court to grant any effectual relief whatever to the prevailing party.” Chafin v. Chafin,568 U.S. 165
, 172 (2013) (cleaned up). But a case does not inevitably become moot when a party chooses to stop the challenged conduct. Cessation implies mootness only when it is “absolutely clear” that the “allegedly wrongful behavior could not reasonably be expected to recur.” Friends 4 Nos. 22-1347, 22-1709 & 22-1737 of the Earth, Inc. v. Laidlaw Environmental Services (TOC), Inc.,528 U.S. 167
, 190 (2000). We presume that an agency acts in good faith when it al- ters its course of action. Ozinga v. Price,855 F.3d 730
, 734 (7th Cir. 2017). This does not end our inquiry, however. An agency’s decision to change course does not moot a lawsuit when the change is “not implemented by statute or regulation and could be changed again.” Sefick v. Gardner,164 F.3d 370
, 372 (7th Cir. 1998). That is the case here. Although the Fish and Wildlife Service has revoked the original compatibility determination, it has not promised never to issue a new per- mit for the crossing. Tellingly, the agency itself does not argue that the litigation has become moot. The district court therefore had jurisdiction to review both the revoked right-of-way permit and the proposed land ex- change under the Refuge Act. But jurisdiction alone does not allow a court to reach the merits. Final agency action also is essential to judicial review. See5 U.S.C. §704
(part of the Ad- ministrative Procedure Act or APA). “[T]wo conditions … generally must be satisfied for agency action to be ‘final’ under the APA.” Army Corps of En- gineers v. Hawkes Co.,578 U.S. 590
, 597 (2016). The challenged action must represent the “consummation” of an agency’s de- cisionmaking process and must determine “rights or obliga- tions”.Ibid.
(citing BenneP v. Spear,520 U.S. 154
, 177–78 (1997)). In other words, §704 asks whether a “terminal event” has occurred. Salinas v. Railroad Retirement Board,141 S. Ct. 691
, 697 (2021). In Hawkes the Supreme Court found that the Army Corps of Engineers’ determination that waters on the plaintiffs’ Nos. 22-1347, 22-1709 & 22-1737 5 property were subject to the Clean Water Act was a final agency action. This determination was the end of the agency’s decisionmaking process: it was issued “after extensive fact- finding” and was to remain valid for five years. 578 U.S. at 597–98. It was also “definitive”: plaintiffs were denied a safe harbor from liability under the Clean Water Act, even though the determination did not itself impose monetary liability. Id. at 598–600. By contrast, the Fish and Wildlife Service’s current stance regarding the proposed transmission line does not meet the Court’s criteria of finality. The compatibility determination is not a final action. Even before it was rescinded, the determi- nation was just a prerequisite to a permit rather than the end of the agency’s process. And although the right-of-way permit may have “consummated” the agency’s decisionmaking pro- cess while it stood, the agency has revoked it. A revoked per- mit lacks legal consequence. It neither allows nor forbids the challenged crossing. Ma]ers are back where they were before the permit issued: under consideration at the agency. Once an agency has made a final decision, a reviewing court evaluates whether that decision is supported by sub- stantial evidence.5 U.S.C. §706
(2)(E). In Hawkes the agency’s decision was issued after “extensive factfinding”, which gave the Court a record to review. That’s impossible here: now that the Fish and Wildlife Service has rescinded the compatibility determination and permit, the court lacks an administrative record. To determine whether a permit allowing the transmis- sion line to cross the Refuge would be “compatible” with the Refuge’s “major purposes”, 16 U.S.C. §668dd(d)(1)(A), a court needs to evaluate the agency’s factual findings about compat- ibility, as well as any findings about the “major purposes” of 6 Nos. 22-1347, 22-1709 & 22-1737 this particular Refuge; until the agency has made its record and articulated findings based on that record, a judicial deci- sion is premature. The potential land transfer likewise is not ready for judi- cial review. The Fish and Wildlife Service agreed to consider a proposal but has not reached a decision. Agreeing to review a proposal cannot be the “consummation” of the agency’s de- cisionmaking process, as the decision is still to come. Again, the Fish and Wildlife Service has not produced a record of any factfinding in support of a transfer. How can a court review a decision that has not been made based on a record that has not yet been produced? Sometimes courts review decisions that an agency has reached but has yet to enforce. See AbboP Laboratories v. Gard- ner,387 U.S. 136
(1967); Hawkes, 578 U.S. at 597–600. But pre- enforcement review does not imply the propriety of pre-deci- sion review. San Francisco Herring Association v. Department of the Interior,946 F.3d 564
(9th Cir. 2019), does not hold other- wise, despite plaintiffs’ protestations—there, too, the agency had made a final decision, though review occurred before it had been enforced. The Fish and Wildlife Service has not issued a final deci- sion that could harm plaintiffs. The agency has not permi]ed a land transfer and perhaps never will. Approval of the trans- mission line would require further proceedings: a new com- patibility determination and permit, evaluating the amended permit application, deciding to abandon the permit in favor of a land exchange, or abandoning the crossing. The district court gave two reasons for declaring unlawful actions that the agency may or may not ever take. First, Nos. 22-1347, 22-1709 & 22-1737 7 relying on its erroneous conclusion that the permit consti- tuted a final decision even after its revocation, the court held that a land exchange was “very likely” subject to the same standard as the permit and so could not replace the construc- tion permit. 580 F. Supp. 3d at 599. Second, it found that “hardship to the parties” weighed in favor of review. The judge expressed concern that delayed review would leave the project “nearly completed” everywhere except the Refuge, creating a sunk cost so large that a reviewing court would have “li]le choice but to approve” the crossing. Id. at 599–600. Neither of these rationales justifies ignoring §704’s finality requirement. We do not share the district court’s certainty that the statutory requirements for a land exchange and right-of- way permit are identical. The Refuge Act uses different words to describe the standard the different potential actions must meet. An inquiry into whether a land exchange is “suitable” under 16 U.S.C. §668dd(b)(3) may differ from the compatibil- ity analysis for a right-of-way permit under 16 U.S.C. §668ee(1), if only because a land exchange entails an increase in the Refuge’s extent, which must be offset against a loss else- where. The Fish and Wildlife Service recently opined that land exchanges do not require compatibility determinations but that their “conservation benefits” must “outweigh identi- fiable harm” and “further the Refuge System’s mission and the individual refuge purposes.” Department of the Interior, Office of the Solicitor, M-37078 (May 31, 2023). In other words, the agency must determine a swap’s net effects. But without knowing what land the agency agrees to acquire and cede, it is impossible for a reviewing court to evaluate whether the agency’s decision about net benefits is supported by substan- tial evidence. 8 Nos. 22-1347, 22-1709 & 22-1737 In finding that the standards of review for a land exchange and right-of-way permit are identical, the district court relied on a single decision: Friends of Alaska National Wildlife Refuges v. Bernhardt,463 F. Supp. 3d 1011
(D. Alaska 2020). That deci- sion was reversed by a panel of the Ninth Circuit. Friends of Alaska National Wildlife Refuges v. Haaland,29 F.4th 432
, 443–44 (9th Cir. 2022). The panel decision was vacated pending en banc review.54 F.4th 608
(9th Cir. 2022). The agency has since withdrawn from the exchange, the appeal has been dis- missed, and the district court’s decision has been vacated.2023 U.S. App. LEXIS 14927
(9th Cir. June 15, 2023). We do not express any opinion on the merits of the question other than to say that the Ninth Circuit did what our district court should have done: it terminated the litigation once the agency re- scinded its decision. Any “hardship to the parties” from delayed review cannot override §704’s finality requirement. In AbboP Laboratories the Court permi]ed pre-enforcement review where the plaintiffs faced hardship in the form of a choice between complying with the final agency action or incurring civil or criminal pen- alties.387 U.S. at
152–53. The agency’s actions here have not put plaintiffs to a choice. Whatever hardship they face comes not from the agency’s promise to consider a land exchange but from the utility companies’ decision to build on their own land. The cost of construction is one the utility companies have opted to incur and bear the risk of, not one imposed by the agency. In the absence of any final agency action under §704, the district court erred in reviewing the merits of the proposed land exchange. Plaintiffs’ request for relief against the Rural Utilities Ser- vice under the National Environmental Policy Act likewise is Nos. 22-1347, 22-1709 & 22-1737 9 premature. Dairyland Power Cooperative, a utility company with a nine percent ownership interest in the project, has told the Service that, after the transmission line is complete, it may seek a federal loan that will replace some or all of the line’s current private financing. Dairyland has yet to make any pro- posal to the Service, so financing is even farther from finality than is the land swap. We grant that the Environmental Impact Statement for the transmission line is “final” in the sense that multiple agen- cies have adopted it. But an EIS differs from a decision to ap- prove any given action. NEPA requires an agency to include a statement as part of its “recommendation or report” for “major Federal actions significantly affecting the quality of the human environment”.42 U.S.C. §4332
(2)(C). It is the deci- sion incorporating the statement into a recommendation or report that is a reviewable agency action. Citizens for Appropri- ate Rural Roads v. Foxx,815 F.3d 1068
, 1079 (7th Cir. 2016). Yet the Rural Utilities Service has yet to issue a recommendation or report on any proposal, because Dairyland has not made one. When the agency adopted the environmental impact statement, that did not “consummat[e]” its decisionmaking process, Hawkes, 578 U.S. at 597, but took just one preliminary step toward an eventual decision. And the agency’s conclu- sion that the statement complies with the National Environ- mental Policy Act lacks legal consequences—any entitlements will flow from the ultimate funding decision. To which we add that it is not possible to evaluate the environmental con- sequences of any decision, such as the extension of federal credit, before knowing what that decision would entail. Environmental impact statements are required only for “major” federal actions “significantly affecting the quality of 10 Nos. 22-1347, 22-1709 & 22-1737 the human environment”.42 U.S.C. §4332
(2)(C). It is not ob- vious that funding part of a project that will be completed with or without federal assistance is a major federal action. The transmission line that plaintiffs object to will be in opera- tion before Dairyland even requests funding. If the agency de- cides that federal loans will replace some private financing, that decision may or may not “significantly” affect the envi- ronment. That leaves only plaintiffs’ cross-appeal of the district court’s refusal to issue a permanent injunction against con- struction of the transmission line on non-federal land. The court entered a preliminary injunction barring activities sub- ject to the Army Corps’ authorization under the Clean Water Act,2021 U.S. Dist. LEXIS 210178
(W.D. Wis. Nov. 1, 2021), and plaintiffs argue that it abused its discretion by failing to make that injunction permanent. But the activities plaintiffs seek to enjoin here are not subject to federal authorization; they are privately funded and take place on land outside of federal control. Thus, the preliminary injunction cannot provide a ba- sis to enjoin the entire project. The district court did not abuse its discretion by declining to enter a permanent injunction. We affirm its denial. In all other respects, we vacate the judgment of the district court and remand for the dismissal of this litigation. The decision that we have vacated will not have any authoritative or prec- edential effect in any future suit, once any of the federal agen- cies makes a new decision.
Citizens for Appropriate Rural v. Anthony Foxx , 815 F.3d 1068 ( 2016 )
Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )
Timothy Ozinga v. Thomas E. Price , 855 F.3d 730 ( 2017 )
John Sefick v. Richard Gardner , 164 F.3d 370 ( 1998 )
Friends of the Earth, Inc. v. Laidlaw Environmental ... , 120 S. Ct. 693 ( 2000 )
Abbott Laboratories v. Gardner , 87 S. Ct. 1507 ( 1967 )