DocketNumber: No. 80-1782
Citation Numbers: 660 F.2d 1309
Judges: Arnold, Ross
Filed Date: 10/7/1981
Status: Precedential
Modified Date: 11/4/2024
The National Labor Relations Board petitions this Court for enforcement of its order of June 12, 1980, ordering Metal Container Corporation to cease and desist from refusing to bargain collectively with the International Brotherhood of Electrical Workers, Local No. 1 (IBEW), as the exclusive bargaining representative of the production-support electricians at its Arnold, Missouri plant. The company’s refusal to bargain is based on its contention that a separate unit of maintenance electricians at this facility is inappropriate and that the only appropriate unit is a “wall-to-wall” production-and-maintenance unit. We enforce the Board’s order.
I.
Metal Container Corporation’s facility at Arnold, Missouri, manufactures two-piece aluminum beer cans for its parent company, the Anheuser-Busch Corporation. The Arnold facility is a high-speed, totally automated plant with three computer-controlled production lines, each of which has the capacity of making 800 cans a minute. The plant operates 24 hours a day, seven days a week. This is a new plant with no prior bargaining history.
The IBEW represents approximately 800 maintenance electricians in the St. Louis, Missouri, area. Three electrician bargaining units represented by the IBEW are at three-piece can plants, and the fourth is at the two-piece American Can plant where a separate bargaining unit was established by agreement of the parties. The union maintains an apprenticeship program.
The production-support electricians at the Arnold facility spend approximately 80% of their time doing preventive maintenance on the production line. The maintenance is scheduled by the electrical supervisor days or even weeks in advance and is done in accordance with a written check list. There was conflicting testimony as to the degree of skill required to perform this job. The electrical engineer described the work as repetitive and routine. Members of the proposed unit testified that it required a high degree of skill and knowledge of the electrical field. While performing preventive maintenance, the electricians work alone, although they may talk with the production workers in attempting to determine how a machine is operating and whether there is any malfunction or trouble. There was testimony that 50% of this preventive maintenance work is non-electrical or requires a combination of skills involving mechanical, pneumatic, hydraulic, and electrical systems. The other 20% of the electricians’ time is spent in the separate electrical shop making repairs, on the production line troubleshooting, or making repairs in other parts of the plant.
The company does not require journeyman status or licensing of applicants. Company officials testified that they looked for basic electrical skills plus experience in other areas such as mechanical, hydraulic, and pneumatic systems. Experience in another high-speed manufacturing process is also considered valuable. The plant’s electrical engineer who participated in the interviewing process testified that applicants were questioned about their electrical knowledge, and that the four electricians hired were “highly skilled.”
The electricians are supervised both from within and from outside their craft. Their preventive-maintenance schedules are prepared by the electrical supervisor, and he and the electrical engineer are in the plant
Both the physical layout and the personnel structure of the plant are designed to foster an integrated work environment in which all employees, both production and maintenance, work together to maintain the uninterrupted operation of the production line. The company has a program for cross-training employees in aspects of production outside their regular assignments. The cross-training has a limited effect on the electricians’ craft status. Employees in other classifications have not been trained to do major electrical work; and the production-support electricians, after initial training, will work on the production line only in emergencies. On days known as “maintenance day” one of the three lines is closed down for complete inspection and maintenance. On those days, the electricians will work with other employees in teams. Only electricians perform major electrical repair work.
All conditions of employment and fringe benefits are uniform for hourly employees throughout the plant. All use the same entrance and punch the same timeclock. Production-support electricians have the top pay scale for hourly employees, and have a separate wage scale and progression rate.
After a hearing, the Regional Director issued his decision and direction of election in which he found that the electrician unit petitioned for by the IBEW was an appropriate unit, and that it would be separately certified if the maintenance electricians voted for the IBEW in the required election.
II.
Although the company makes numerous arguments challenging the Board’s characterization of the evidence and alleged failure to weigh competing factors, we think that this case hinges on one basic question: Whether the highly integrated nature of the company’s operation has destroyed the community of interest necessary to support the designation of a separate craft unit.
Review of the Board’s unit certification is limited to a determination of whether the decision is arbitrary, capricious, an abuse of discretion, or lacking in substantial evidentiary support. NLRB v. Target Stores, Inc., 547 F.2d 421, 423 (8th Cir. 1977). To set aside a Board certified unit, the employer must show that the designated unit is not appropriate. It is not enough to show that another kind of unit would have been more appropriate. NLRB v. J.C. Penney Co., supra, 559 F.2d at 375. A reviewing court may not “displace the Board’s choice between two fairly conflicting views, even though the court would justifiably have made a different choice had the matters been before it de novo." Hy-Vee Food Stores, Inc. v. NLRB, 426 F.2d 763, 764 (8th Cir.), cert. denied, 400 U.S. 879, 91 S.Ct. 120, 27 L.Ed.2d 116 (1970), quoting Universal Camera Corp. v. NLRB, 340 U.S. 474, 488, 71 S.Ct. 456, 464, 95 L.Ed. 456 (1951).
The Regional Director weighed the relevant factors as follows (citations omitted):
In view of the record as a whole, including the fact that there is no history of bargaining in a plant-wide unit including the production support electricians at the Employer’s Arnold, Missouri, Facility, although there is a plant-wide unit history of bargaining at the Employer’s two other facilities and at 71 2-piece can plants in the United States, and a separate maintenance electrician craft unit history of bargaining in 4 can plants in the St. Louis Metropolitan Area, one of which is a 2-piece can plant, the fact that the IBEW has a specialized experience representing maintenance electricians, the fact that the production support electricians are highly skilled electricians, exercise substantial independent judgment in the performance of their work, and are the only classification which performs major electrical repair work, and the fact that production support electricians are primarily supervised within their own craft lines, and despite the integrated nature of the Employer’s operation, the fact that production support electricians will routinely perform work not traditionally categorized as electrical, the production support electricians’ contact with other employees, the similarity of their benefits and working conditions with those enjoyed by other employees, the Employer’s policy of
After reviewing the evidence presented to the Regional Director, we are convinced that the production-support electricians at the company’s Arnold plant have retained sufficient characteristics of a separate craft unit to justify the Board’s certification under our limited scope of review. There is no rigid rule that a high-speed industrial environment automatically destroys a separate community of interest among craft workers. The Board addressed this contention in Atlantic Richfield:
Where . . . there is no history of bargaining on a more comprehensive basis, neither the integrated nature of a production process nor the fact that skilled employees must coordinate their operations with other employees in achieving maintenance goals is, in itself, sufficient to preclude the formation of a craft unit.
Atlantic Richfield Co., supra, 231 N.L.R.B. at 32. Integration of a manufacturing process is one factor to be considered in unit determinations.
But it is not in and of itself sufficient to preclude the formation of a separate craft bargaining unit, unless it results in such a fusion of functions, skills, and .working conditions between those in the asserted craft group and others outside it as to obliterate any meaningful lines of separate craft identity.
E.I. DuPont de Nemours and Co., 162 N.L. R.B. 413, 419 (1966). We think the Board has permissibly found that the Arnold plant’s mode of operation has not so fused “functions, skills, and working conditions” as to preclude a separate craft unit. We rely particularly on the fact that the electricians are the only plant employees who make major electrical repairs and have primary responsibility for the electrical maintenance of the entire plant. Plant officials testified that at the first sign of trouble on the line the electrician is the first person called, because he has the greatest skill in diagnosing production malfunctions. There is ample evidence that the electricians exercise independent judgment in determining when, where, and in what order repairs will be made. The electricians’ supervisors seemed to take pride in the sophisticated combination of skills required to keep the electrical components of the computer-controlled production line running smoothly. The fact that the electricians do most of their electrical work in the production area does not prevent them from being a “distinct and homogeneous group of skilled journeymen craftsmen.” While the electricians are required to have knowledge of mechanical, pneumatic, and hydraulic components, they use these skills within the context of their primary function at the plant — electrical maintenance. The requirement that they have other skills in addition to electrical knowledge does not diminish the fact that the core requirement for the job was extensive training and/or experience as electricians.
Metal Container cites three cases as governing Board precedent. Joseph Schlitz Brewing Co., Container Division, 192 NLRB 553 (1971); Kaiser Aluminum & Chemical Corp., 177 NLRB 682 (1969); Joseph Schlitz Brewing Co., 16-RC-4263 (1966) (unreported decision). In each of these cases the Board denied separate craft units in plants using the two-piece process. Metal Container contends that the Board’s decision in the present case is an arbitrary departure from these precedents. When the Board departs from prior precedent without explanation, its decisions have been held arbitrary as a matter of law. NLRB v. Meyer Label Co., 597 F.2d 18 (2d Cir. 1979).
Metal Container also calls our attention to a recent Board decision denying a séparate electricians’ craft unit in another highly integrated manufacturing industry. Procter & Gamble Paper Products Co., 251 N.L.R.B. 77 (1980). Several factors distinguish the Procter and Gamble decision. There the Board found that 50% of the electrical work in the plant was performed by over 200 other technicians who had some electrical skills. While the Procter and Gamble electricians were the most highly skilled electricians in the plant and spent 100% of their time doing electrical work, they worked in teams with other maintenance and production workers and did not function as a separate group. There was also movement in and out of the unit, with production workers moving into the electrician jobs. Here, in contrast, all four electricians were hired as electricians, they are responsible for all the major electrical repair work, they do not work in teams except on “maintenance day,” and there has been no movement into or out of the class. On the whole, this case is closer, on its facts, to other craft unit certification cases in which the Board has certified a separate craft unit. Lianco Container Corp., 177 N.L.R.B. 907 (1969) (only electricians in the unit perform electrical work; no apprenticeship but electrician experience required); Atlantic Richfield Co., 231 N.L. R.B. 31 (1977) (unit employees hired as skilled employees, no transfers out of unit, most electrical work done by unit employees); Anheuser-Busch, Inc., 170 N.L.R.B. 46 (1968) (experience and license required; highly integrated production line does not obliterate separate craft identity).
In summary, we hold that there is substantial evidence in the record as a whole to
Accordingly, we enforce the Board’s order.
. Four other unions petitioned for plant-wide production-and-maintenance units. The United Steelworkers of America and the International Brotherhood of Teamsters, Chauffeurs, Ware-housemen, and Helpers intervened in the representation proceeding in support of the company’s contention that only a wall-to-wall unit was appropriate. They are not parties to this enforcement proceeding.
. The two-piece process produces a seamless can with an integral bottom and an aluminum top. The older three-piece-can process produces a can with a separate bottom which is assembled by the customer.
. Before the hearing officer the parties stipulated that the separate electricians' unit at the new American Can plant in St. Louis was formed by agreement of the parties without Board sanction or approval.
. The electricians are responsible for maintenance and repair of all electrical equipment in the plant, not just the production line. When there is a malfunction on the line, the computer signals the area where the problem is occurring. It is then up to the electrician to diagnose the problem. Defective parts are quickly removed to prevent shutting down the line. Repairs are then made either in the shop or, if necessary, the part is returned to the manufacturer for repair.
. The electricians had the choice of voting for separate representation, or for representation in the production-and-maintenance unit, or for no union.
. A true craft has been defined as a unit consisting of “a distinct and homogeneous group of skilled journeymen craftsmen, working as such, together with their apprentices and/or helpers. To be ‘a journeyman craftsman,’ an individual must have a kind and degree of skill
. 29 U.S.C. § 159(b), in part, provides: “The Board shall decide in each case whether, in order to assure the employees the fullest freedom in exercising the rights guaranteed by this subchapter, the unit appropriate for the purposes of collective bargaining shall be the employer unit, craft unit, plant, or subdivision thereof....”
. When a union seeks to carve out a unit of craft workers from a previously established collective-bargaining unit, the Board is guided by Mallinckrodt Chemical Works, 162 N.L.R.B. 387, 397 (1966). While not controlling in a non-severance situation, the Mallinckrodt test has been applied by the Board in determining whether an appropriate craft unit should initially be established. Anheuser-Busch, Inc., 170 N.L.R.B. 46 (1968).
. All four electricians hired at the time of the hearing had extensive training and experience which will not be recounted here. The lack of a formal apprenticeship or training program does not bar a craft determination when extensive experience is required. No other class of employees is required to have electrical knowledge.
. Only one paragraph of the 1966 Schlitz decision is devoted to the petition for a separate electricians’, unit. There is insufficient information from which to make a detailed comparison with the present case.
. In response to our post-argument order of June 16, 1981, the Board has filed an analysis of the 73 two-piece can manufacturing plants known to have bargaining units. Relevant information was unavailable for 36 of the plants. In 26 plants a wall-to-wall unit was stipulated to by the parties and approved by the Board. Several units were established by Board decisions in which separate craft status was not an issue. In five cases the Board denied separate craft status. Three of these cases involved lithographers, one was a request for a separate maintenance unit, and the other was the 1966 Schlitz case discussed above. The three lithographer cases and the maintenance case are of limited relevance to the issue of the appropriateness of a separate electricians’ unit. In another Schlitz case, No. 12-RC-1126 (1961) (unreported decision), the Board found a separate unit of electricians appropriate and capable of severance from a maintenance unit.