DocketNumber: No. 01-35922
Citation Numbers: 288 F.3d 1140
Judges: Canby, Kleinfeld, Politz
Filed Date: 4/29/2002
Status: Precedential
Modified Date: 11/5/2024
Tillamook County appeals the denial of its motion for preliminary injunction to prevent intervenor-defendant the City of McMinnville, Oregon, from continuing the enlargement of its existing municipal water supply reservoir along the Nestucca River. The County complains that the finding by the United States Army Corps of Engineers that the proposed expansion would not have a significant environmental impact was arbitrary and capricious, and that the district court abused its discretion in denying the preliminary injunction. Concluding that the Corps conducted an adequate investigation and that the district court did not abuse its discretion, we affirm.
BACKGROUND
The existing reservoir is situated at the headwaters of the Nestucca River, approximately twelve miles from the City, and is an integral component of the municipality’s water supply system. The City seeks to expand the reservoir to avert water shortages caused by an increasing population. The initial water shortage is expected to occur sometime between 2002 and 2020, depending upon rain conditions. The proposed expansion would entail raising the existing dam by 30 feet to increase the storage capacity of the reservoir. It would directly impact 13.26 acres of navigable waters, 12.7 acres of which would be affected by filling the reservoir after construction of the new dam and spillway in 2002. Because the expansion includes the placement of dredge or fill materials into navigable waters of the United States, the Commission was required to obtain a section 404 permit from the Corps.
In seeking to obtain federal and state authorization for the proposed expansion of the reservoir, the Water Commission of the City of McMinnville applied for a dredge or fill permit from the Army Corps of Engineers to fill 2.4 acres of navigable waters under section 404 of the Clean Water Act.
The Corps prepared an initial assessment and, following a period of public comment and a review process, determined that the project would not have a significant impact on the environment. In February 2001, the Corps issued its final environmental assessment and Finding of No Significant Impact, and a section 404 permit to the Commission to place fill material in 2.36 acres of navigable waters.
In June 2001, the County brought the instant action
In September 2001, the district court denied the County’s motion for a preliminary injunction. On October 3, 2001, the County filed the instant appeal and moved for an emergency stay pending appeal which we denied in November 2001.
ANALYSIS
Preliminary Injunction Standard
We review the denial of a motion for preliminary injunction for abuse of discretion.
Probability of Success on the Merits
The County contends that the Corps’ decision not to prepare an EIS based on its conclusion that there would be no significant environmental impact violated the NEPA because of the significant and uncertain impacts of the proposed expansion. The County adds that even if an EIS would not be required under the NEPA the environmental assessment failed to evaluate adequately alternatives and to describe mitigation measures under the proposed action. We are not persuaded.
A. Requirement of an EIS
We review an administrative agency’s decision not to prepare an EIS to assure that the decision was not arbitrary and capricious.
The NEPA is a procedural statute intended to ensure environmentally informed decision-making by federal agencies.
Specific guidance for when a full environmental impact statement must be prepared is provided by regulations promulgated by the Council on Environmental Quality.
B. Adequacy of the Environmental Assessment
The County complains that the environmental assessment prepared by the Corps failed to adequately describe mitigation measures pertaining to sediment and erosion control and dam safety and analyze an adequate range of alternatives. These contentions lack merit. While the Corps was required to develop the proposed mitigation measures “to a reasonable degree,” it was not required to develop a complete mitigation plan detailing the “precise nature ... of the mitigation measures” nor were the measures required to “completely compensate for adverse environmental impacts.”
The Council on Environmental Quality regulations require that an environmental assessment “include brief discussions” of the need for the proposed action, alternatives as required by the NEPA, and “the environmental impacts of the proposed action.”
The judgment of the district court is AFFIRMED.
. 33 U.S.C. § 1344.
. Id.
. 42 U.S.C. § 4332(2)(C).
. The 2.36 acres were comprised of 1.8 acres of open water and .56 acres of wetlands.
.The complaint sought relief under the Administrative Procedure Act, 5 U.S.C. § 706, alleging that the Corps failed to comply adequately with the NEPA and the Clean Water Act in issuing the section 404 permit.
. Walczak v. EPL Prolong, Inc., 198 F.3d 725, 730 (9th Cir.1999).
. Id.
. Los Angeles Mem’l Coliseum Comm’n v. NFL, 634 F.2d 1197, 1201 (9th Cir.1980).
. Alaska v. Native Vill. of Venetie, 856 F.2d 1384, 1388-89 (9th Cir.1988).
. 5 U.S.C. § 706(2)(A).
. Greenpeace Action v. Franklin, 14 F.3d 1324, 1331-32 (9th Cir.1993) (citations omitted).
. Cal. Trout v. Schaefer, 58 F.3d 469, 473 (9th Cir.1995) (citations omitted).
. Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 351, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989).
. 42 U.S.C. § 4332(2)(C).
. Robertson, 490 U.S. at 350, 109 S.Ct. 1835.
. Strycker’s Bay Neighborhood Council, Inc. v. Karlen, 444 U.S. 223, 227, 100 S.Ct 497, 62 L.Ed.2d 433 (1980) (citations omitted).
. 40 C.F.R. § 1500.2 et seq.
. Id. § 1500.2(a)(1).
. 40 C.F.R. § 1508.13; LaFlamme v. FERC, 945 F.2d 1124, 1127 (9th Cir.1991).
. Wetlands Action Network v. U.S. Army Corps of Eng'rs, 222 F.3d 1105, 1121 (9th Cir.2000), cert. denied, - U.S. -, 122 S.Ct. 41, 151 L.Ed.2d 14 (2001).
. Id.
. 40 C.F.R. § 1508.9(b).
. See id. § 230.10(a). "An alternative is practicable if it is available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes.” Id. § 230.10(a)(2).
. Northwest Environmental Defense Center v. Bonneville Power Admin., 117 F.3d 1520, 1538 (9th Cir.1997) (citations omitted).