DocketNumber: No. 04-1105
Judges: Ginsburg, Henderson, Sentelle
Filed Date: 5/6/2005
Status: Precedential
Modified Date: 11/5/2024
JUDGMENT
This cause was heard on the record from the Federal Energy Regulatory Commission and on the briefs and arguments by counsel. For the reasons set out in the accompanying memorandum, it is
ORDERED that the petition for review is denied.
Pursuant to D.C. Circuit Rule 36; this disposition will not be published. The Clerk is directed to withhold issuance of the mandate herein until seven days after resolution of any timely petition for rehearing or rehearing en banc. See Fed. R. App. P. 41(b); D.C.Cir. Rule 41.
The Federal Energy Regulatory Commission (FERC or Commission) issued a series of orders granting licenses to S.D. Warren Company (Warren) to operate and maintain five hydroelectric projects on the Presumpseot River in the State of Maine. S.D. Warren Co., Project Nos. 2897-003, 2932-003, 2941-002, 2931-002 and 2942-005, 105 FERC H 61,013, 2003 WL 22279522 (2003) (Multi-Project Order); S.D. Warren Co., Project No. 2931-002, 105 FERC K 61,010, 2003 WL 22279523 (2003); S.D. Warren Co., Project No. 2932-003, 105 FERC 1161,011, 2003 WL 22279524 (2003); S.D. Warren Co., Project No. 2941-002, 105 FERC 1161,012, 2003 WL 22273231 (2003); and, S.D. Warren Co., Project No. 2942-005, 105 FERC 1161,009, 2003 WL 22279525 (2003). Pursuant to the terms of the Federal Power Act (FPA), 16 U.S.C. §§ 792 et seq., the FERC attached conditions to the licenses to protect environmental and recreational interests affected by Warren’s hydroelectric projects. The conditions included fish-way prescriptions filed by the Department of Interior (Interior) under § 18 of the FPA, id. at § 811, that required Warren to install eel ladders at each project dam to facilitate upstream migration by American eel and mandated an eight-hour shutdown of the project turbines for an eight-week period in the fall of each year to protect downstream eel migration. Multi-Project Order, 105 FERC at 61,138, 1ÍH 42-43. Interior also placed conditional obligations on Warren to provide upstream and downstream fish passage facilities at each project dam as fish passage is achieved at the next most downstream dam. Id. at 61,-137-38, H1f 35 — 41. Specifically, if fish passage is achieved at a downstream dam not controlled by Warren over which the FERC lacks jurisdiction, within two years Warren is required, inter alia, to construct denil fish ladders at its most downstream dam. Id. at 61,137, 1136. Construction of fish passage facilities at each of Warren’s upstream dams is conditioned on the attainment of specific fish population triggers at the next downstream dam. Id. The FERC also attached conditions imposed by the State of Maine pursuant to the state water quality certification (WQC) process under § 401 of the Clean Water Act, 33 U.S.C. § 1341(d). Maine’s WQC conditions imposed, inter alia, dissolved oxygen standards and minimum bypass flows (intended to mitigate the dewatering of the Presumpseot River spillways below each project) and required Warren to develop a recreational facility enhancement plan for each project. See Multi-Project Order, 105 FERC at 61, 136, H 25. In addition, pursuant to § 10(a) of the FPA, 16 U.S.C. § 803(a), the Commission imposed conditions designed to ensure that the projects would “be best adapted to a comprehensive plan for ... the adequate protection, mitigation, and enhancement of fish and wildlife (including related spawning grounds and habitat), and for other beneficial public uses, including ... recreation[ ].” Id. at § 803(a)(1). Based on the Final Environmental Impact Statement (FEIS) issued by the Commission staff on June 26, 2002, the FERC required Warren, inter alia, to develop a Shoreline Management Plan (SMP) for its two largest projects with a shoreline buffer zone of 200 feet. Multi-Project Order, 105 FERC at 61,141-42, 111164-66. The FERC also required Warren to monitor and report on recreational use near the project sites every 12 years. Id. at 61,149-50, Article 409. The FERC issued the licenses for a 40-year term. Id. at 61, 144, 1186.
Warren petitioned the Commission for rehearing. On rehearing, the FERC upheld the orders with respect to the license requirements which it had included and denied rehearing as to the § 18 and § 401
Warren challenges the sufficiency of the evidence in the record to support the Commission’s § 10 conditions and Interior’s § 18 prescriptions. Warren also challenges the 40-year license term as arbitrary and capricious. We uphold the Commission’s orders because they are supported by substantial evidence in the record, 16 U.S.C. § 8251(b), and because the Commission “examined the relevant data and provided a reasoned explanation supported by a stated connection between the facts found and the choice made.” North Carolina v. FERC, 112 F.3d 1175, 1189 (D.C.Cir.1997) (internal quotation marks omitted). The conditions imposed by the Commission under § 10 are supported by substantial evidence. The FEIS upon which the Commission relied considered the comments of several entities, including the FWS and National Park Service, as well as the Maine Department of Marine Resources, the Maine Atlantic Salmon Commission, the Maine Department of Inland Fisheries and Wildlife and three individuals. See Multi-Project Order at 61,-135, It 18 & n. 5. The Commission altered the scope of the conditions recommended by the FWS, reducing the 500-foot buffer zone for the SMPs to 200 feet and decreasing the reporting requirement for recreational use studies from every six years to every 12 years, because the FWS had failed to provide sufficient evidence to support its more stringent recommendations. Id. at 61,141-42,111164-66.
With respect to Warren’s challenge to Interior’s fishway prescriptions under § 18, we apply the same arbitrary and capricious standard that governs the actions of the Commission. Wisconsin Rower & Light Co. v. FERC, 363 F.3d 453, 461 (D.C.Cir.2004). Interior’s fishway prescriptions must be “reasonably related” to its goal of fish preservation. Bangor Hydro-Electric, 78 F.3d at 663. The scientific evidence in the record demonstrates significant populations of American eel and a 2000 study of the Presumpscot projects commissioned by Warren documents the extent to which the project dams impaired the ability of the eels to migrate upstream due to difficulty ascending dam faces. Studies of similar projects demonstrated the hazards of downstream migration, specifically, high mortality rates caused by project turbines. Interior’s prescriptions are reasonably calculated to mitigate these harms. The required eel passageways provide for efficient upstream migration at a “relatively low cost,” according to the FEIS. Interior’s requirement that Warren shut down turbine operation for a period of eight hours per day for eight weeks during peak migration is likewise a reasonable prescription. Interior reasonably concluded that current scientific evidence does not permit a rehable estimate of a shorter peak migratory period that would ensure similar protection of the eel with a less stringent shutdown requirement. Interior has directed Warren to conduct a three year study of migratory patterns, the results of which may enable Interior to
The conditions imposed by the FERC require Warren to undertake a “moderate amount of construction and environmental mitigation and enhancement measures.” See Multi-Project Order at 61,144, f 86. The record evidence supports the Commission’s assessment. More extensive construction that might be required under Interior’s conditional fishway prescriptions could, if actually imposed, provide a basis for extending the license term. Until that time, the 40-year license term, instead of the 50-year license Warren had sought for “extensive” construction, cannot be considered arbitrary or capricious.