DocketNumber: Sac. No. 1956.
Citation Numbers: 127 P. 50, 163 Cal. 782
Judges: Henshaw
Filed Date: 9/24/1912
Status: Precedential
Modified Date: 10/19/2024
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 784 Plaintiff sued defendants for damages in tort for injuries caused to his land. It is charged that the defendants cut a ditch some sixty feet wide and twelve feet deep through the bank of the Sacramento River and through a large levee constructed about one hundred and fifty feet back from the river margin, to permit the passage of a dredger; that after so excavating and cutting the bank, the defendants failed to erect a suitable dam or other fill sufficient to prevent the water of the Sacramento River from flowing through the ditch or canal thus dug and upon plaintiff's land; that by reason of its negligence in this respect the waters of the Sacramento River did flow through this canal upon plaintiff's land, inundating the same, carrying large deposits of sand, destroying fences, removing the soil, and injuring it in the amount sued for. The defendants were Blauth, Goethe, and Silva, trustees of Reclamation District No. 785, Ashley, the surveyor and engineer of the district, and the Bay and River Dredging Company, which cut the canal. The Reclamation District was not made a party to the action, and a nonjoinder was set up by defendants' answer. It was proven at the trial that the defendants Blauth, Goethe, and Silva were acting in their official capacity as trustees of the Reclamation District. A nonsuit was granted as to the Bay River Dredging Company, and as to Ashley, the surveyor and engineer of the district. The jury rendered a verdict in favor of the plaintiff against the defendants Blauth, Goethe, and Silva. From the judgment which followed and from the order denying their motion for a new trial these defendants appeal.
1. The complaint sufficiently states a cause of action. While the complaint alleges that at all times therein mentioned plaintiff was the owner of the property, it is contended that is does not allege that he was the owner and in possession at the time of the commencement of the action, and it is argued that for all that appears to the contrary at the time of *Page 786 the commencement of the action plaintiff may have sold the property, and with it his right to damages for its injury. All, however, the plaintiff is required to show in this regard is his right of action at the time of the commencement of the suit. The answer tendered issue on the question of ownership by denying that plaintiff was at any time or at all the owner or in possession of the property. The ownership thus becoming an issue, evidence was introduced thereon and the case was tried upon the theory of the issue thus joined. This sufficiently cured any defect that it may be conceived existed in the complaint. It is next urged that the complaint does not aver that the cutting of the canal and the failure to erect the dam was done without plaintiff's consent. But we are not advised of any rule of pleading which requires a declaration from plaintiff that an unlawful trespass was committed without his acquiescence. There is no presumption that a plaintiff consents to an unwarranted invasion of his personal rights or rights of property. For the third objection to the sufficiency of the complaint, appellants argue that it is not averred that any work was negligently done and that no facts are alleged from which negligence can be imputed. In this connection it is said that there is no averment that no dam or obstruction to the water of the river was erected, but only that no sufficient dam or other obstruction was erected. It is, of course, not necessary to aver in terms that an act was negligently done to state a cause of action in tort. Says Cooley (2 Elements of Torts, p. 19): "One may become liable in an action as for tort, either: 1. By actually doing to the prejudice of another something he has no legal right to do; 2. By doing something he may rightfully do, but wrongfully or negligently doing it by such means, or at such time, or in such manner, that another is injured; 3. By neglecting to do something which he ought to do, whereby another suffers injury." The allegations of the complaint taken together amount to this: That the defendants cut a canal through the natural bank of the Sacramento River; after cutting the canal they failed to take proper precautions to prevent the waters of the river from flooding plaintiff's land; that the waters of the river did in fact flood plaintiff's land to his injury. The complaint was therefore sufficient to pass a general demurrer. *Page 787
2. Notwithstanding the fact that Blauth, Goethe, and Silva were acting as trustees of the Reclamation District, they were responsible to plaintiff for the injury occasioned to his property by the negligent performance of their duty. The argument of appellants against this proposition is that the Reclamation District entered into a contract with the Dredging Company to do the dredging work; that the part which the defendants took was solely in their official capacity as trustees of the district; if the work was negligently performed the legal responsibility rests upon the district alone. But if a tortious act has been committed by an agent acting under authority of his principal, the fact that the principal thus becomes liable does not of course exonerate the agent from liability. It may be conceded that a liability was cast upon the principal. (Hopkins v. ClemsonCollege,
The case presented against these defendants is precisely that of Brownell v. Fisher,
3. The evidence established the negligence of the defendants in their failure to construct a suitable dam or fill to prevent the entrance into the cut or canal of the river water. The evidence showed that entering from the river the dredger made a cut fifty or sixty feet in width up to the levee, through the levee and along the side of respondent's ranch. Thereafter a small fill or dam was made between the excavation in the levee and the channel of the river. This fill was four feet below the natural bank of the river and but twelve or fourteen feet wide on top. Nothing further was done to obstruct the flow of the river or to protect the lands of the respondent. Thus, while theretofore respondent's lands had been protected by a levee situated from one hundred to one hundred and fifty feet from the natural bank, which levee was twenty to fifty feet on its base and about eight feet above the natural surface of the ground, the condition left by these defendants was a canal fifty or sixty feet wide cut twelve feet below the natural surface and dammed to prevent the intruding waters to a height not even level with the natural surface, but four feet below. It is in evidence that this fill or dam gave way, with the resulting overflow of the respondent's lands while the water in the river was below its natural bank level. There was a sand bar near to the mouth of this canal and the sand from this bar, by reason of the depth of the cut, was *Page 791 drawn through it and deposited in great quantities upon plaintiff's land. Many subordinate questions in the case as to whether the sand was actually deposited through the cut or through breaks in the levee in front of plaintiff's place, which afterward occurred, were all submitted to the jury under conflicting evidence, and their findings are conclusive upon this court.
4. The Bay River Dredging Company was not an independent contractor and the court was correct in instructing the jury to this effect. In cases where the nature of the contract between the parties establishing their relationship is in dispute, and the evidence thereon conflicting, the question of employee or independent contractor may properly be left to the jury under appropriate instructions from the court. But where the evidence is not conflicting and the contract between the parties is without dispute, the question of dependent or independent contractual relationship is one of law for the court. (Green v.Soule,
5. Defendants' argument that the damages were caused by an extraordinary flood, an act of God, to prevent the consequences of which the exercise of ordinary care would not avail, is not supported by the evidence. The evidence establishes that while there was a high flood, indeed it may be said an exceptional flood, the dam in the canal went out before the river was even bank full, and that it was by reason of the inadequacy and insufficiency of this dam that sand in injurious quantities was drawn through the cut and cast upon plaintiff's land.
6. To prove damages, evidence of the difference in the market value of the land before and after the injuries complained of was admitted. No objection was made to this evidence, but after the witnesses had left the stand and the case was closed, defendants moved to strike out all the testimony. The motion was properly denied. (People v. Samario,
7. The court instructed the jury fully and even elaborately, and the instructions were quite as favorable to the defendants upon all points as the law and the evidence warranted. Hedged about by the limitations which the court was careful to point out, to the effect that the jury could only award damages for the detriment or injury to the land which they found was caused by the negligent act of defendants, and that if other causes contributed to the injury, defendants were not responsible, it was not error to instruct the jury that the difference in the market value of the land before and after the damage was the measure of defendants' liability. If, as appellants contend, there was no permanent injury to the land, or if the land could have been cleared of its sand and cured of its other injuries, and if respondent could have been reimbursed for all his losses for an amount much less than the damages awarded, it would have been permissible for appellants, in mitigation of the damages claimed by plaintiff, so to have established by evidence. They did not undertake to *Page 793 do so, or at least did not do so to the satisfaction of the jury, and appellants are therefore in no position here to complain.
8. The court erred in allowing interest upon the jury's award from the date of the injury. The damages were unliquidated until assessed by the jury, and only after judgment upon such assessment did legal interest run. (Brady v. Wilcoxson,
The judgment is therefore modified by striking out the allowance of interest. In all other respects the judgment and order appealed from are affirmed. Respondent will recover costs upon this appeal.
Melvin, J., and Lorigan, J., concurred.
Hearing in Bank denied.
Rowley v. City of Cedar Rapids , 203 Iowa 1245 ( 1927 )
Montanick Ex Rel. Montanick v. McMillin , 225 Iowa 442 ( 1938 )
Shirkey v. Keokuk County , 225 Iowa 1159 ( 1937 )
Bayuk v. Edson , 236 Cal. App. 2d 309 ( 1965 )
Falasco v. Hulen , 6 Cal. App. 2d 224 ( 1935 )
Greenwell v. A. v. Wills & Sons , 210 Mo. App. 651 ( 1922 )
Alphonzo E. Bell Corp. v. Listle , 74 Cal. App. 2d 638 ( 1946 )
Marin Municipal Water District v. Peninsula Paving Co. , 34 Cal. App. 2d 647 ( 1939 )
Durante v. City of Oakland , 19 Cal. App. 2d 543 ( 1937 )
Marr v. Postal Union Life Insurance Co. , 40 Cal. App. 2d 673 ( 1940 )
Alonso v. Hills , 95 Cal. App. 2d 778 ( 1950 )
Motzer v. Paoli , 110 Cal. App. 2d 141 ( 1952 )
Archer v. City of Los Angeles , 19 Cal. 2d 19 ( 1941 )
Herzog v. Grosso , 41 Cal. 2d 219 ( 1953 )
Rilovich v. Raymond , 20 Cal. App. 2d 630 ( 1937 )
Kell v. Jansen , 53 Cal. App. 2d 498 ( 1942 )
Langley v. Deshazer , 78 Idaho 376 ( 1956 )
Heimann v. City of Los Angeles , 30 Cal. 2d 746 ( 1947 )
State v. Stanley , 506 P.2d 1284 ( 1973 )