DocketNumber: 14872
Judges: Clief
Filed Date: 3/27/1893
Status: Precedential
Modified Date: 10/19/2024
—On November 3, 1890, the respondent-plaintiff (a corporation), as party of the first part, and the appellant-defendant, as party of the second part, executed the following agreement: —
“That the said party of the first part, for and in consideration of the covenants and agreements hereinafter mentioned*3 to be kept and performed by said party of the second part, does covenant and agree unto the chartering and letting to hire of its coal lighter ‘ Wilmington/ her anchor and chain, unto the said party of the second part, for the term of one mouth from the date hereof; said lighter to be exclusively employed during the term of this charter party in transporting rocks from Santa Catalina Island to Wilmington Bay, for use on the government breakwater. The said party of the second part, in consideration of the foregoing and the use of said lighter ‘Wilmington,’ does hereby covenant and agree to and with the said party of the first part to pay for the chartering and use of said lighter ‘Wilmington/ under the aforesaid conditions, at the rate of fifty dollars ($50) per month, payable in advance, and to return the said lighter ‘Wilmington’ to said party of the first part, in the same good condition as when received, ordinary wear and tear not excepted, upon twenty hours’ notice being given by the said party of the first part, and to deliver said lighter alongside the Southern Pacific Company’s wharf at San Pedro; and should said lighter ‘Wilmington’ be lost or damaged to the extent that it cannot be put in the same good condition as when received, the party of the second part, to pay the party of the first part, the sum of three thousand five hundred dollars (|3,500) for said lighter ‘Wilmington.’
‘‘Wilmixg-tox Teakspoetatiok Co., " By its Secretary, W. Gr. Halstead. "Pateick O’Niel.”
The action is based upon the agreement to pay $3,500 in case the lighter should be lost; and it is averred in the complaint that the lighter "Wilmington” was delivered to defendant according to the agreement; “ that on or about the twelfth day of November, 1890, said coal lighter ‘Wilmington/ while in the use and occupation of the defendant, was lost and damaged to the extent that it cannot be put in the same good condition as when received from plaintiff by defendant, said coal lighter ‘Wilmington’ being totally lost and destroyed; that under and by virtue of the terms and • conditions of said agreement the defendant became indebted to the plaintiff in the sum of $3,500, as provided in said agreement, no part of which sum has been paid.
The prayer is for judgment against defendant for the sum of $3,500, “with interest thereon from November 12, 1890 (date of the loss), until paid, with costs of this action.”
The complaint contains no averment as to the value of the lighter, nor as to the “twenty hours’ notice” mentioned in the agreement.
Defendant demurred to the complaint on the general ground that it does not state facts sufficient to constitute a cause of action.
The demurrer was overruled by the court, and defendant answered.
The answer admits the execution of the agreement, and alleges: “That the lighter was not injured, lost, or destroyed by any act, negligence, or default of the defendant, but by aet of God and the elements,” and proceeds to state particularly the manner and causes of the loss during a storm. Further alleges that the value of the lighter at the time it was delivered to defendant, or at any time thereafter, did not exceed $1,800. And further alleges that the defendant, at all times, has been and now is willing “ to pay to the plaintiff the sum of $2,500, which, he avers, is more than the value of said lighter and the damages sustained by plaintiff.”
In this state of the pleadings the plaintiff moved for judgment on the pleadings according to the prayer of the complaint; which motion was granted, the judgment being for $3,717.81, with interest thereon until paid. This includes interest on $3,500 from the date of the loss of the lighter.
The defendant appeals from the judgment and contends:
1. That the answer raised a material issue as to whether the lighter was lost by inevitable accident. 2. That the sum to be paid <($3,500) in case the lighter should be lost or damaged, etc., was not intended to be fixed or liquidated damages, and that such intention does not appear from the agreement properly construed; and 3. That.if the sum of $3,500 was intended as liquidated damages, the agreement, to that extent, is made void by sections 1670 and 1671 of the Civil Code.
If I am not mistaken in this view of the nature of the case, the issue as to the cause of the loss is wholly immaterial. The possibility of a loss was foreseen and provided for in the agreement, whereby the defendant unqualifiedly obligated himself to pay in the event of a loss from any cause and the only qualification or limitation of this obligation by the law is that it would not bind the defendant in case the loss had been caused by the culpable negligence or other wrongful act of the plaintiff, of which there is no pretense,
2. Is the agreement susceptible of the construction that the parties intended the $3,500 as a penalty within which the actual damages for the loss or injury might be assessed, and not as fixed liquidated damages? If such is a proper construction of the agreement, the plaintiff should have alleged and proved the actual damage; and the answer of the defendant that the value of the lighter did not exceed $1,800 would have been material as a partial defense to the action.
The only circumstance that can be said to indicate that the parties intended the sum of $3,500 as penalty and not as liquidated damages, is that the same sum is required to be paid in case the lighter should “be damaged to the extent that it cannot be put in the same good condition as when received,” as in case tlie lighter should “be lost”; though the damage in the former case might be less than in the latter. The rule in cases of this kind, deduced from the cases cited by Mr. Sedgwick, is stated by him, at section 413, as follows: —
“A sum fixed as security for the performance of a contract containing a number of stipulations of widely different impor- • tance, breaches of some of which are capable of accurate valuation, for any of which the stipulated sum is an excessive compensation, is a penalty.”
But upon examination of the cases referred to, it will be seen that this rule has often been applied where it was admitted that the parties intended stipulated damages, and not a penalty, so that the application of the rule does not always. depend upon the intention of the parties. Yet,'where it is otherwise doubtful whether penalty, or stipulated damages was intended, the circumstances that the sum agreed upon greatly exceeds the actual damage; for a breach of any one of the several stipulations tends, in a greater or less degree, according to the disparity between the stipulated sum and the actual damage, to prove that such sum was intended as a penalty and not as stipulated damages. In this case it is not clear what extent of damage to the lighter was meant by the language used, viz., “damaged to the extent that it cannot be put in the same good condition as when received”; and, therefore, the difference between the actual damage meant, and the stipulated compensation therefor, cannot be determined. It seems to me that the damaged condition of the lighter, intended to be expressed or
3. Having determined that the stipulation for the payment of §3,500 is a “contract by which the amount of damage to be paid,” or “compensation to be made” for the loss of, or injury to the property bailed, was determined in anticipation of such damage, in the sense of section 16.70 of the Civil Code, it only remains to be considered whether or not, “ from the nature of the case, it would be impracticable or extremely difficult to fix the actual damage,” in the sense of section 1671 of the same code. These sections are at follows: —
“Sec. 1670. Every contract by which the amount of damage to be paid or other compensation to be made for a breach of an obligation is determined in anticipation thereof is to that extent void, except as expressly provided in the next section.
“Sec. 1671. The parties to a contract may agree therein upon an amount which shall be presumed to be the amount of damage sustained by a breach thereof, when, from the nature of the case, it would be impracticable or extremely difficult to fix the actual damage.”
Section 1671 has been construed by this court in several cases.
In Eva v. McMahon, 77 Cal. 467, it was held that it is not impracticable nor extremely difficult to fix the actual damage sustained by the breach of a contract to deliver the possession of land; and if no actual damage is sustained none can be recovered, though a stated amount was stipulated for in the contract.
In Patent Brick Co. v. Moore, 75 Cal. 205, it was held that a stipulation in a building contract, by which the contractor agreed to pay the owner a certain sum as liquidated damages for each day’s delay in finishing the building after the time appointed in the contract, was within the rule of section 1670, and not within the exception stated in section 1671, andjtherefore void.
In Pacific Factor Co. v. Adler, 90 Cal. 110, there was a contract between plaintiff and defendant, whereby the defendant agreed to deliver to plaintiff, on demand between certain dates, 187,500 grain bags, to be sold by plaintiff on commission of one per cent, and not to sell said bags to any other person than plaint
I think “the nature of the case” at bar cannot be distinguished from that of the cases above cited; and that the plaintiff is entitled to recover only his actual damages proximately resulting from the loss of its lighter, which should have been alleged, and if denied, proved, since the contract fixing the damages at $3,500 is void.
I therefore conclude that the judgment should be reversed and the cause remanded for a new trial, with leave to the parties to amend their pleadings if so advised.
Temple, C., and Haynes, C., concurred.
/
For the reasons given in the foregoing opinion the judgment is reversed and the cause remanded for a new trial, with leave to the parties to amend their pleadings if so advised.
Gaboutte, J., Pateeson, J., Habeison, J;