DocketNumber: Civ. No. 1134.
Judges: Hall
Filed Date: 2/13/1913
Status: Precedential
Modified Date: 10/19/2024
Plaintiff recovered judgment against defendant upon a bond given by defendant to secure the faithful performance by one Evans of a contract to erect a building for plaintiff. Defendant moved for a new trial, which being denied defendant appealed to this court both from the judgment and the order.
The building contract was in all respects valid, and was duly filed in the recorder's office.
Evans, the contractor, abandoned the contract before completion, and plaintiff completed the building according to the original plans and specifications. By this action he sought to recover the excess in the total cost of the building over the contract price, claimed to be $633.15, and also $250 attorneys' fees paid, and $54.75 costs incurred in defending two suits brought by lien claimants against him and the original contractor.
The court found in favor of plaintiff, and gave judgment for the amount prayed for.
1. As to the finding to the effect that plaintiff was compelled to pay to complete the building any sum in excess of the original contract price, it is claimed by appellant that such finding finds no support in the evidence.
This contention must be sustained. The contract was for the payment of the total sum of $9,291, to be made in designated installments, with a final thirty-five day payment of $2,325. At the time of the abandonment of the contract by Evans, plaintiff had, in strict accordance with the contract paid thereon $5,705, which left a balance for the completion of the building in the sum of $3,586.
The owner expended in economically completing the building in strict accord with the plans and specifications the sum of $1,795.15, and no more, which left in his hands the sum of $1,790.85, which is the full amount that he was legally bound to pay to lien claimants. (Hoffman-Marks Co. v. Spires,
The payments due and made under the contract prior to the abandonment, amounting to $5,705, the amount expended by the owner in completing the building $1,795.15, and the sum of $1,790.85, make up the total of $9,291, which was the contract price.
An owner who has fully complied upon his part with the terms of a valid building contract cannot be compelled to pay anything in excess of such contract price. (Hoffman-Marks Co.
v. Spires,
In the case at bar plaintiff, probably supposing that he was obliged to turn over to the lien claimants the entire amount of the final thirty-five day payment, voluntarily paid the amount thereof and one hundred dollars retained from a prior installment, into court for such claimants. It is only by crediting him as against the surety with the full amount of such payment that the finding of the court can be sustained. The surety cannot be charged with any voluntary payment that plaintiff may have made in excess of what he was legally liable for.
Neither can he recover as against the surety the attorneys' fees and costs incurred by him in defending against the claims of the lien claimants. This was so decided by this court inAlcatraz etc. Assoc. v. United States Fidelity etc. Co.,
Some other points are discussed in the briefs; but as the views above expressed appear to us to be determinative of the entire case upon its merits, we do not think it necessary to discuss the other points urged for a reversal.
The judgment and order appealed from are reversed.
Lennon, P. J., and Murphey, J., pro tem., concurred.