DocketNumber: No. D-44
Citation Numbers: 79 Ct. Cl. 302, 1934 U.S. Ct. Cl. LEXIS 295, 1934 WL 2016
Judges: Booth, Green, Littleton, Whaley, Williams
Filed Date: 5/7/1934
Status: Precedential
Modified Date: 10/19/2024
delivered the opinion of the court:
The principal items, upon which the claim presented in this suit is based, are (1) the amount of $31,130.28, increased cost of labor due to defendant’s increases in wages paid for labor at the Charleston Navy Yard and increased cost for cement, sand, and stone over the price thereof at the date of the contract and over the price upon which plaintiff based his bid; (2) deduction of $6,000 from the contract price for elimination of waterproofing of basement against surface drainage after this work had- been performed in accordance with the contract; (3) deduction of $6,225 from the contract price as a result of the elimination of the furnishing and installation by plaintiff of freight entrance doors; and (4) deduction of $14,850 from the amount due under the contract as penalty for delay. Other items involving amounts claimed for alleged extra work, etc., will be hereinafter set forth.
Upon the issuance by the Navy Department of the advertisement for bids, accompanied by the specifications for the storehouse at Charleston, plaintiff, Arnold, who had been engaged in the building-construction business for a number of years, visited the site of the building for the purpose of
We are of opinion that plaintiff’s written statement of September 4, 1917, which was incorporated in the contract, became a part of the contract terms and must be given effect. Charles Ward Engineering Works v. United States, 73 C.Cls. 557. That the terms and conditions of such statement formed a part of the contract clearly appears from a consideration of paragraph 191 of Specification no. 2469 and paragraphs first, seventh, and eighth of the contract. In specifying these terms and conditions plaintiff was complying with paragraph 191 of the specifications. The first paragraph of the formal contract provides for construction of the building complete in accordance with the specifications, as contemplated in item 1, paragraph 191 thereof, except as thereinafter modified, and paragraph 8 of the contract modified the specifications by making plaintiff’s statement a part of the contract. This further clearly appears, we think, from the seventh paragraph of the contract which
In these circumstances plaintiff is entitled to recover the increased cost for labor independently of addendum no. 1 to the General Provisions, as to the construction of which by the Bureau we have some doubt, and the increased costs for cement, sand, and stone in excess of the prices upon which the amount stated in the contract was based. These amounts are: Labor, $27,763.71; cement, $1,588.89; sand and stone, $1,777.68. Counsel for defendant contend that if any amounts are allowable on account of these items, only the increased cost to February 8, 1918, the expiration date of the period of one hundred and twenty days for completion of the work, should be allowed because of plaintiff’s failure to complete the work on time. In view of the remission of the penalty deducted by the defendant, hereinafter mentioned, the total increased costs are allowable. The findings show that defendant was responsible for many of the delays.
The next two items involve claims for increased amounts of $735.94 and $780.65 under change orders for additional work in raising the basement floor level and installing additional toilets. Plaintiff submitted estimates of the cost of these changes and they were considered at the time by a board on changes under paragraph 17 of the General Provisions. Findings X and XII. The General Provisions, un
The next item of the claim is for $1,013.83, being the cost of removing two concrete piers. These piers were not poured in accordance with the specification and no recovery can be had for the removal thereof.
Plaintiff next seeks to recover $3,111.21, representing the cost of driving additional piles in certain footings where the piles driven by the subcontractor with a hammer weighing less than 3,000 pounds had been cut off. Whether or not the required number of piles driven for these footings with the 2,370-pound hammer had a bearing capacity equal to that called for by the specification, plaintiff is in no position to recover this extra cost. The amount therefore is disallowed.
The next item relates to plaintiff’s claim for $3,183.50 arising from the deduction of $6,225 from the contract price as a result of a change order eliminating from the contract the furnishing and the installation by plaintiff of freight entrance doors, the facts concerning which are set forth in finding XIII. The record shows that the amount deducted and the manner in which it was arrived at were so grossly erroneous as to imply bad faith, and we have so found. The amount by which the contract price should have been reduced was $3,041.50 plus 10 percent, or $3,345.65. Plaintiff agreed to furnish and install the doors for $3,041.50 and he could and would have furnished and installed them for that amount had they not been omitted. The difference between the amount deducted and the amount deductible is $2,879.35. Plaintiff is entitled to recover the last-mentioned amount, and the same will be included in the judgment.
Before the building was completed the public works officer demanded of plaintiff that he stop the leakage. The plaintiff, while insisting that it was due to tidal pressure and not to surface drainage, attempted to comply with directions of the Government officer, but without success. After expending $1,226.21 for labor and materials for this purpose, plaintiff refused to proceed further; thereupon the Government attempted to prevent the leakage by installing new felt membrane and pitch and laid an additional 3-inch concrete floor. This did not stop the leakage and, so far as the proof shows, it was never stopped. Plaintiff seeks to recover this amount of $1,226.21 so expended. This was an unwarranted expense to which plaintiff was put by the public works officer, but it was extra work not called for by the contract, and since no claim on account thereof was presented by plaintiff in accordance with paragraph 19 of the General Provisions no recovery can be had.
The last item claimed is the amount of $4,725.24, balance admittedly due under the contract as set forth in the final voucher issued by the Bureau, but which plaintiff refused to accept as a full and final settlement of all claims under the contract. To this amount plaintiff contends there should be added $118.80, being 10 percent profit on extra reinforcing steel required by the Government and furnished by plaintiff. In this voucher the Bureau allowed plaintiff the extra cost of extra steel and also a profit on a portion thereof, but no profit was allowed on $108 of this extra cost which appears to have been due to a mistake. The correct am'ount allowable on this item of the claim is $10.80.
Finding XVIII shows a difference of $15 in favor of plaintiff, to which he is entitled under the contract, and the same is hereby allowed.
The total amount of the items of the claims which the court finds allowable is $59,610.67. Judgment in favor of plaintiff will accordingly be entered. It is so ordered'.
ON DEFENDANT’S MOTION FOR NEW TRIAL
delivered the opinion of the court:
Counsel for defendant submits a motion for a new trial requesting numerous amendments of the findings of fact.
The errors of law assigned in the motion involve merely a refusal of the court to construe the contract as originally contended by the defendant, and the propositions made are fully answered and discussed in the original opinion. No useful purpose would bé served by a detailed discussion of the argument made in the motion for a new trial inasmuch as the propositions advanced have heretofore been fully and carefully considered by the court.
Only a word need be said with reference to (1) waterproofing the basement floor of the building in question; (2) deductions made by defendant and disallowed by the court in connection with the elimination from plaintiff’s contract of the installation by him of freight entrance doors; and (3) responsibility for delays.
The information on which the defendant seeks a new trial with reference to these items is not newly discovered evidence under the well-established rule governing such matters. The information offered as newly discovered evidence was at all times in possession of the defendant and by due diligence could have been discovered and submitted on the trial. Moreover, it is merely cumulative and some of it is not relevant nor material to a decision on the question with respect to which it is proposed to be offered. Most of the newly discovered evidence has been tendered with the motion for a new trial and has been examined by the court. If it were legally in evidence it would not change the conclusion reached by the court on the items to which it relates. It has long been the established rule of this court that motions for a new trial on the ground of newly discovered evidence will not be granted where due diligence on the part of the
The alleged newly discovered evidence with reference to the waterproofing of the basement floor of the building consists of tide tables at Fort Sumter, Charleston, S.C., and the Atlantic Coast tide tables and weather maps. The question of the effect of the tide on seepage of water through the basement floor of the building after it had been constructed in accordance with the contract and specifications was considered on the original trial and much evidence was taken with respect thereto. Defendant introduced the tide tables at Charleston, S.C. We found as a fact that the leakage was caused by tide pressure. A reconsideration of the evidence of record on this point, together with the new evidence which the defendant proposes to offer, fully supports this conclusion. Counsel for defendant confuses tide water with tide pressure. It was not necessary that the water be salty, as defendant argues, to be the result of tide pressure. It was ground water forced up by tide pressure of additional tide water. The evidence shows that the water standing in the open excavation prior to the laying of the basement floor and prior to the time the floor was raised, in order to take it out of tide pressure, rose and fell with the tide. The tide tables now offered by defendant cover only a portion of the period involved, and even these tide tables show that the tide rose higher than the elevation of the basement floor as finally raised on at least four occasions for a period of from two to three days at a time.
The alleged newly discovered evidence relating to the elimination of the freight entrance doors from the contract by the defendant has no bearing upon the question presented, as pointed out by defendant’s counsel during the original trial when plaintiff questioned the Government witness with reference to what the defendant paid for the installation of such doors after they had been eliminated from the contract.
. The remaining alleged newly discovered evidence presents a novel method of proving responsibility for delay. We have been unable to find any decision where the court has been called upon to predicate a decision upon such an hypothesis of unrelated facts. Under this assignment of “ newly discovered evidence ” defendant wishes to offer certain contracts that plaintiff had with the defendant in each of which it is claimed he was charged with liquidated damages. It is not contended that such deductions ever received judicial approval, even if, by the greatest stretch of the rules of evidence, such collateral matters could be inquired into for the purpose of determining whether the liquidated damages charged by the Bureau in the case at bar, involving a different contract performed under different conditions and circumstances and at a different location, were proper. The general rule is that the law will not consider evidence that a person has done a certain act at a particular time as probative of a contention that he has done a similar act at another time, and this case does not come within any exception thereto. If the deductions of penalties for delay made under other contracts, concerning which defendant now proposes to inquire into in the case at bar, were based on the same causes that brought about the deduction here, it would seem that plaintiff should have availed himself of his legal remedy at the time.