DocketNumber: No. 408-77
Citation Numbers: 230 Ct. Cl. 338, 676 F.2d 634
Judges: Cowen, Davis, Nichols
Filed Date: 4/7/1982
Status: Precedential
Modified Date: 1/13/2023
This case concerns the unsuccessful attempts of the Norfolk Naval Shipyard ("Shipyard”) to dispose of a surplus portal dock crane through a sales contract with plaintiff, Peck Iron and Metal Co., Inc. Eventually, when plaintiff failed to remove the crane from the Shipyard, the contract was terminated and the crane scrapped. Plaintiff sues for breach of contract and the defendant counterclaims for its scrapping costs, liquidated damages, and breach of stipulation of settlement, the first two being claimed in the alternative. In each instance the issue of liability was severed for trial. The defendant
The contract of August 12, 1966, under which plaintiff paid $7,351.73 for the crane required plaintiff to remove it from the Shipyard within 30 days. The plaintiff promptly made ready to do so but was halted by the Shipyard because Drydock No. 4 ("DD 4”), beside which the crane had been stored in the open for many years, was suddenly to be occupied by the Shangri La, a large aircraft carrier putting in for emergency repairs. The Shipyard’s paramount obligation was to provide repair services to vessels of the Atlantic Fleet. Crane removal activities at DD 4 would interfere with simultaneous repairs to the Shangri La, and had thus to be subordinated.
The government thereupon issued a contract modification whereby it accepted responsibility and expense for loading the crane onto plaintiffs barge which was to be floated into the flooded DD 4 and moored alongside the crane location. The logistics were formidable. Heavy prospective costs disproportionate to the consideration involved, and other factors, caused the government to breach the modification. Conferences between the parties failed to result in agreement on moving the crane. The contract limited the government’s liability for breach to returning the purchase money. In February 1967 the government cancelled the contract and refunded plaintiff the $7,351.73 purchase money.
Plaintiff filed suit here for breach of contract. Peck Iron & Metal Co. v. United States, Ct. Cl. No. 335-68. It was settled on the basis of a stipulation of March 5,1970, and judgment was entered for plaintiff in the amount of $10,000 and title to the crane. The settlement stipulation required plaintiff to remove the crane from the Shipyard within 90 days (July 10, 1970) at its own expense and in a manner satisfactory to the Shipyard.
The sale had been handled by Defense Surplus Sales Office ("DSSO”), which neglected to give the Shipyard formal notification of the settlement of the suit until July 6, 1970, four months after the settlement. In the meantime the plaintiff had informally advised the Sales Contracting Officer ("SCO”) at the Shipyard of the settlement. The SCO
When the Shipyard finally received official word of the settlement stipulation on July 6, 1970, the parties conferred. Plaintiff was instructed to submit to the Shipyard for approval a proposal describing how the crane was to be removed.
The only method of removal that was logistically and economically feasible, and which corresponded to the method which the government had planned to employ in 1966 when it had assumed removal responsibility under the modification to the original contract, was to lift the crane, either intact or in disassembled parts, onto a barge to be moored in a flooded DD 4, thence to be towed to plaintiffs adjacent wrecking yard. There is dispute as to the feasibility of other methods, such as moving the crane or its disassembled parts overland via temporary tracks or special wheeled vehicles to other locations in the Shipyard for deposit on a barge at the water’s edge, or even moving the crane to Drydock No. 7 adjacent to DD 4 and thence lifting it onto a barge in Drydock No. 7 for removal by water. However, these alternatives were not practicable. The only practicable and economically justifiable method was to lift the crane or its disassembled parts onto a barge or barges floating alongside a flooded DD 4, and then to tow the loaded barge(s) to the plaintiffs waterside facility nearby the Shipyard. This was the method which both parties regarded at the time to be the most feasible.
On July 31, 1970, plaintiff submitted to the SCO a proposal for removal of the crane furnished by Williams Enterprises, Inc. Williams planned to bring its crane or cranes to the Shipyard from its facility near Washington, D. C., and deposit the subject crane onto plaintiffs barge moored in DD 4 in the manner described in the preceding paragraph, although DD 4 was not expressly mentioned. At defendant’s instance plaintiff furnished the Shipyard a more detailed description of the Williams proposal on
At a conference between the parties on November 18, 1970, an oral agreement was reached on the details of plaintiffs use of DD 4 for removing the crane. During some future exchange of vessels plaintiff would be given the use of DD 4 in a flooded condition for 2 to 3 days (referred to hereafter as a "window”) to deposit the crane on a barge or barges moored alongside. Thirty days ahead of the window date plaintiff would be given a "tentative-tentative” notice of availability so that it could bring necessary equipment to the worksite and dismantle the crane for loading onto the barge(s). A more firm confirmation would be given 2 weeks ahead of the window. Seventy-two hours ahead of the window a fixed commitment to the window date would be given plaintiff, subject only to the possibility of emergency repairs to a vessel that could not have been anticipated. Conditions were imposed by the Shipyard, namely: The cranes brought in for the removal undertaking could not be operated less than 7 feet from the edge of the "bathtub.”
To appreciate the necessity for such close and indefinite timing, it should be noted that DD 4 was one of the busiest drydocks at the Shipyard. While routine maintenance for ships of the Fleet were scheduled long in advance, DD 4 had to be kept available for repairs to vessels in emergencies that could not be foreseen. In advance of the arrival of a vessel for drydocking DD 4 would have to be pumped dry and large blocks of varied size and configuration would be placed in the bathtub part of the drydock to fit the external shape of the incoming vessel. Water valves would then be opened to flood the drydock and thereby release the caisson which served as a seal at its otherwise open seaward end.
It was with these circumstances in mind that the Shipyard was to squeeze a window between scheduled vessel repairs for the plaintiff to use DD 4 in a flooded condition for removal of the crane. The chief reason for uncertainty until the last minute that the window date assigned would actually materialize was that the period for use of DD 4 for scheduled repairs of a vessel might be underestimated, since the full extent of needed repairs would often be unknown until the vessel could be inspected in the dry. Also, even if the repaired vessel departed on schedule there was always a realistic chance that another vessel would have to be accommodated for emergency repairs. Thus the only fairly safe date to select for a window for plaintiff to use DD 4 for crane removal had to be sandwiched in between vessels scheduled for routine maintenance. This narrowed the selection of an available window considerably, and even then subjected the date selected to unavoidable uncertainty.
From the plaintiffs standpoint there was a good deal of unrelievable risk involved in accepting an assigned window for use of a flooded DD 4. It estimated that it would take about 14 or 15 working days and involve a cost of $16,000 to $20,000 to marshal sufficient lifting equipment at the worksite, including the disassembly of auxiliary lifting cranes for transport from a distant location, their travel to the DD 4 worksite, and their reassembly there to use in disassembling the subject crane and lifting its component parts onto a barge. Once the necessary equipment was at
If during dismantlement of the crane circumstances caused cancellation of the assigned window the plaintiff would be forced to make a difficult and costly choice. It could either complete the dismantlement of the subject crane on the coping alongside DD 4, and then decide whether to retain the hired equipment at the worksite waiting for the next available window to be assigned, or it could cause the contractor to remove his equipment and then return it later to complete the loading part of the operation whenever the next window was assigned. Either way there were large potential costs involved to the plaintiff, so for this reason the timing of the window by the Shipyard, and adherence to it, would be of critical importance. The Shipyard would have permitted plaintiff to leave the dismantled components of the crane at the worksite if plaintiffs operations were interrupted because of official use of DD 4, but as explained this did not solve the cost problem if there was a hitch in plans.
The terms of the oral agreement of November 18, 1970, have been described earlier. The defendant agreed to draft a contract modification accordingly. A draft of a proposed modification was furnished plaintiff on December 31, 1970, for comment and concurrence. The draft is not in evidence and it cannot be determined whether it fully corresponded to the oral agreement. There is some dispute as to this, but it is reasonable to conclude from all the facts that any departures from the oral agreement were not significant and were susceptible to resolution. Plaintiff did not submit its comments on the proposed modification until February
In the meantime a series of windows were proffered to plaintiff by the defendant. The first one was for December 3, 4, and 5, 1970, which was offered at the conference on November 18,1970. The Shipyard commander considered it to be "unreasonably tight”, since it gave very little time for plaintiff to get ready. Plaintiff said it would consult its moving contractor, which it did, and informed defendant that the proffered window of December 3-5 could not be met. Plaintiff was entirely justified in its refusal. The offer of a 3-day rather than a 2-day window corroborates plaintiffs version of the nature of the oral agreement of November 18, 1970, rather than the defendant’s which apparently tried to narrow the window to 2 days in drafting a written modification purporting to reflect the oral agreement.
When plaintiff declined the December 3-5 window on November 20, 1970, it was offered on a "tentative-tentative” basis a window on or about January 16, 1971, which due to lack of available equipment plaintiff declined and requested another date. It was then offered a window for about February 23 which it said it would work toward. Because of the inclement weather working in the winter months was less attractive to plaintiff than the balance of the year. Due to Shipyard requirements the February 23 window was cancelled. On January 25 plaintiff was informed that the next tentative window would be March 14-16. On March 5 an emergency use of DD 4 caused the defendant to cancel the window of March 14-16. In any event about the same time plaintiff advised defendant that it could not meet the March date.
Plaintiff then inquired of the defendant when the caisson would be removed from DD 4 for repairs and maintenance. Caissons were scheduled for routine maintenance every 4 or 5 years. During the 3 or 4 weeks while a caisson is absent from its drydock for maintenance the drydock is perforce in a flooded condition and rarely in use. At the conference of November 18, 1970, plaintiff had been told that the caisson
On April 2, 1971, the SCO notified plaintiff that the next tentative date for a window would be about June 15 (a 3-day window) subject to being made relatively firm by June 1 and made firm 72 hours prior to the window. Plaintiff was instructed to inform the SCO by April 30 whether the arrangement was acceptable. Plaintiff was also told that it would be required to remove the crane from the Shipyard within 90 working days from April 2 — or August 10,1971— and that if it was not removed by June 15 by water via DD 4, then thereafter it would have to be removed in some other way entailing overland movement via rail or roadway. In such case state permits would be required and the plaintiff would have to submit detailed plans to the Shipyard for approval.
On April 16 plaintiff responded to the SCO’s letter of April 2 but made no reference to whether the proffered June 15 window was acceptable. Instead it accused defendant of refusing to implement the settlement stipulation of March 5, 1970, and asked when DD 4 would be available to it "for an indicated 90-day availability period.” Neither the original contract nor the settlement stipulation of March 5, 1970, gave plaintiff any express right to use DD 4 or any other Shipyard facilities for removal of the crane, although it was tacitly assumed that DD 4 would be used. The requirement of the settlement stipulation and of the SCO’s letter of April 2, 1971, that plaintiff remove the crane within 90 days was not tantamount to giving plaintiff use of
Even though plaintiff had failed to notify the SCO by the April 30 deadline as to whether the June 15 window was acceptable, on May 27 the SCO advised plaintiff that it would still be permitted to use DD 4 for 72 hours about June 15, and requested a response from plaintiff by June 2, failing which it would be assumed that plaintiff intended to remove the crane without utilizing DD 4, in which case plaintiff would have to submit plans to the Shipyard for approval.
The plaintiffs reply of June 1 to the SCO still failed to reveal whether it intended to use the assigned DD 4 window of June 15 and alleged that defendant had given no firm date for use of the drydock. On June 4 the SCO further extended to June 7 the deadline for plaintiff to inform whether it intended to use the June 15 window proffered it, and plaintiff was warned that it would be held to respond in damages for default. Plaintiffs response of June 10 reiterated that it had received no specific time to use DD 4 and asked for a firm date for its availability, requesting also that the SCO issue findings of fact. On June 16 the SCO issued such findings, advised plaintiff of its appeal rights, and repeated that plaintiff had until August 10, 1971, to
Plaintiff wrote the SCO on July 28 that it intended to start removing the crane by August 2. The SCO reminded it that it could no longer use DD 4 for crane removal and would have to submit to the Shipyard for approval its plans to remove the crane in any other fashion. When plaintiff was denied access to DD 4 on August 2 to commence removal activities it complained, and the SCO reminded it again that removal plans would require Shipyard approval.
Because the crane had not been removed by the August 10, 1971, deadline, on the following day the SCO declared plaintiff to be in default and warned that, unless the default was cured by August 26 as the contract provided, plaintiff would lose title and would be liable for storage charges. The default not having been cured by August 26 the next day legal custody of the crane was turned over to DSSO by NSC, which returned the crane to the Shipyard for disposal as scrap.
In the meantime on August 20, 1971, plaintiff filed its complaint with the Armed Services Board of Contract Appeals ("ASBCA” or "Board”) appealing from the adverse decision of the SCO of June 16. It contended that it had been denied reasonable access to use DD 4 and demanded that the Shipyard be required to give it 90 days’ use of DD 4 in a flooded condition. While the case was pending before the Board the crane was scrapped by the Shipyard starting September 14, 1971, at a cost to defendant of $14,747. On November 4, 1971, the Board dismissed the appeal because it sounded in breach of contract over which the Board had no jurisdiction, since there was no remedy provided under the contract. Nor did the Board have jurisdiction to reinstate the contract, the plaintiffs right to the crane having been lost by terms of the contract when it failed to remove the crane within the 15-day cure period issued by the SCO.
The issues governing the case in chief, essentially factual in nature, are whether the Shipyard provided plaintiff sufficient opportunity to remove the surplus crane and, if so, whether plaintiff defaulted by failing to remove it.
The January 16 window was proffered to plaintiff on November 20, 1970, long in advance of the target date, but plaintiff declined it due to lack of available equipment. The details of this reason are not presented in the record and, it being the plaintiffs burden, the plaintiff can properly be charged with responsibility for its failure in accepting the date. It is known that plaintiff preferred not to perform the removal operations during inclement winter months, but that reason without more would not suffice as an acceptable excuse.
The next — and last — opportunity for crane removal was the window of June 15, 1971, which was offered to plaintiff on April 2, 1971, far longer notice than the 30-day notice required by the parties’ oral agreement of November 1970. The offer of the June 15 window specified, consistent with the November 1970 agreement, that the date would be made more firm by June 1, 1971, and would be made firm 72 hours ahead of the target date. Despite the fact that plaintiff was directed to notify the Shipyard by April 30 as to whether the June 15 window was acceptable, the plaintiffs letter of April 16 made no response to the offer and instead demanded to know when DD 4 would be made available to it "for an indicated 90-day availability period.” We have remarked earlier that this demand was a misreading of the settlement stipulation of Márch 5, 1970, which specified the 90-day period only as the time within which the crane was to -be removed, and was not intended to
Plaintiff also made a nonresponsive reply of June 1 to defendant’s letter of May 27 holding the June 15 offer open provided plaintiff accepted by June 2. Defendant again extended the acceptance deadline to as late as June 7, with still no responsive reaction from plaintiff other than a repeated demand that a firm date be made for the availability of DD 4.
The major reason plaintiff gives for failing to use the June 15 window which had been offered it is that the letter containing that offer added that if the June 15 date "is not acceptable to you,” the crane would thereafter have to be removed without use of DD 4. That limitation, plaintiff avers, was arbitrary and unlawful. We can assume that this is so (see the discussion infra) but nevertheless that improper "ultimatum” did not excuse plaintiff from using the June 15 window, if it reasonably could. There is no evidence that Peck Iron and Metal could not utilize that period, if it had wanted to do so, and the existence of an improper limitation on future activities could not, and did not, preclude Peck from making use of the June period. If plaintiff feared that it would be bound by the improper condition even if the June window had to be cancelled by the Government at the last minute, the correct response would have been to accept the June 15 window but disavow the limitation on later activities which Peck reasonably considered to be erroneous. There was nothing to prevent that course, but plaintiff did not take it, or indicate in any way that the June 15 period was acceptable to it, but that it did not consider itself tied by the additional restriction if removal could not be effected in June (through no fault of Peck’s). We must conclude, therefore, that plaintiff did not fulfill its obligation when it failed and refused to remove the crane in June, as it could and should have.
We come then to defendant’s counterclaims. Defendant now concedes that any recovery by it is limited to liquidated damages of $1,470.35.
CONCLUSION OF LAW
Upon the findings and opinion the court concludes as a matter of law that plaintiff is not entitled to recover and, therefore, the petition is dismissed. Defendant’s counterclaims are also dismissed.
The court’s opinion is based on that of former Trial Judge Bernhardt, with modifications and a partially different result.
The court adopts the trial judge’s findings of fact, with some changes as indicated in the order entered this day, but they are not reproduced with this opinion. Any findings contained in the opinion that are not also embodied in the formal findings shall likewise be considered part of the court’s findings.
"Bathtub” is vernacular for the recessed core of the drydock in which vessels are temporarily lodged while undergoing repairs.
Plaintiff, pointing out that the April 2d letter also said: "If the June date is acceptable to you, please let us know not later than 30 June 1971 so that the necessary paper work can be effectedinsists that the emphasized portion of the sentence meant that Peck would have to agree to a written version of the oral agreement — to the terms of which it objected — before it could use the June 15 window. We have no adequate reason for thinking that the simple words "so that the necessary paper work can be effected” (which would seem to relate to government paper work necessary to the use of DD 4) carried that special meaning — especially since plaintiff never
We have considered plaintiffs other arguments why it did not breach the agreement, but find them either unpersuasive or irrelevant.
The Disputes Clause of the reinstated contract specifically provided that the maximum sum recoverable by the Government for plaintiffs failure to remove the crane was the "formula amount,” i.e. liquidated damages (20% of the purchase price of the item).
We do not consider that the record sufficiently supports a finding that plaintiff could not have removed the crane after June 15th, even if DD 4 had been offered to it. Conversely, the record does not sustain the opposite finding that plaintiff would in fact have done so. Both parties have failed in their burdens of proof.