Judges: Beach, Prentice, Roraback, Thayer, Wheeler
Filed Date: 7/17/1914
Status: Precedential
Modified Date: 10/19/2024
The first ground of the demurrer to the appeal is that it does not appear, nor is it alleged, that the city of Norwalk has, or ever had, any power to build the new bridge. While it is true that the petition is defective in not specifically alleging that the Act of consolidation and incorporation of the city of Norwalk was approved by the electors of the town, it does appear from the appeal that the city of Norwalk was a party to the proceedings before the Commission, and that it is bound by law to construct and maintain the new bridge. The language of § 29 of the Public Utilities Act is that any city aggrieved by an order of the Commission in any matter to which "it was or ought to have been made a party may appeal therefrom to the Superior Court," etc. This ground of demurrer to the appeal is not well taken.
The second ground of demurrer is that the provisions of chapter 207 of the Public Acts of 1911, p. 1486, have no application to the bridge in question. The argument is that the bridge is a new bridge, and that, although the Act requires a street-railway company, under the conditions stated, to pay an equitable part of the expense of constructing a new bridge, it nevertheless omits to give the Commission authority to apportion the cost of a new bridge, but only gives authority to apportion the cost of repairing, strengthening, or reconstructing an old bridge.
This point is too fine for practical use in the construction of the statute. The word "reconstruction," as distinguished from repair and strengthening, means *Page 475
rebuilding. It cannot be limited to an exact reproduction of the original bridge. Some latitude must be allowed for present and prospective changes in highway and waterway traffic, and for the expression of architectural design. Similar objections were made when the former board of railroad commissioners exercised their authority to alter the location of existing highways in eliminating grade-crossings. The claim was then made that they had exceeded their powers by laying out new highways, as distinguished from relocating highways. It was held, in answer to this claim, that while the commissioners had no power to lay out a new highway as an independent matter, they did have power to lay out what was in one sense a new highway, but was in fact a substitute for the old, discontinued, highway. State's Attorney v. Branford,
It is also claimed that the jurisdiction of the Commission is confined by the statute to cases where the parties have disagreed, or at least have had an opportunity to disagree, as to the necessity and character of the proposed reconstruction. But the letter of the statute is satisfied if the parties disagree either as to the necessity or character of the reconstruction, or as to the apportionment of the expense. In this case the parties disagreed, not only as to the apportionment of the expense, but also as to the number of tracks and type of rail to be laid across the bridge, and the double track ordered by the Commission involves a substantial *Page 476 change in the strength and expense of the reconstruction as compared with what would have been sufficient if a single track had been ordered. For these reasons we think that the objections to the jurisdiction of the Public Utilities Commission are not well founded.
The remaining paragraphs of the demurrer question the jurisdiction of the Superior Court, first, on the ground that the whole subject-matter is beyond the constitutional jurisdiction of the court because its determination calls for the exercise of executive as distinguished from judicial functions; and second, on the narrower ground that the reasons of appeal do not present any issues properly cognizable in the Superior Court under the provisions of the Public Utilities Act respecting appeals to that court.
As to the constitutional question, we said in Spencer'sAppeal,
The next question is as to the extent of such appellate jurisdiction, and that depends on the statute. The Public Utilities Act provides as follows: "Sec. 31. PROCEDURE. QUESTIONS REVIEWED. Each appeal shall be brought by a complaint in writing, stating fully the reasons therefor. . . . Said court shall hear such appeal and re-examine the question of the legality of the order, authorization, or decision appealed from, and the propriety and expediency of such order, authorization, or decision, in so far as said court may properly have cognizance of such subject, either by itself or a committee, and shall proceed thereon in the same manner as upon complaints for equitable relief; and the decision of such court, subject, however, to review on appeal to the Supreme Court of Errors on questions of law, shall be final and conclusive upon the parties." *Page 478
This section appears to have been drawn with careful regard to the decisions of this court as to the nature of so-called appeals from administrative tribunals, and as to the limitations on the jurisdiction of our courts in passing on such appeals. It recognizes the fact that such appeals are in the nature of original applications to the Superior Court, by directing them to be proceeded with in the same manner as complaints for equitable relief. Malmo's Appeal,
The order apportioning the expense of this bridge was passed in the exercise of such a quasi-judicial function, and we think that § 31 of the Public Utilities Act properly requires the Superior Court, on an appeal therefrom, to re-examine, not only the legality of the order, but also its expediency and property. The *Page 479 reasons of appeal required by the statute must, of course, fairly present the questions desired to be reviewed; and the remaining question is whether any of the reasons of appeal are sufficient to properly invoke the appellate or correctional jurisdiction of the Superior Court.
Some of the reasons of appeal are open to the objection of treating the Public Utilities Commission as if it was a court engaged in the trial of a civil action. That is not so. Neither the Commission, nor the Superior Court on appeals from its orders, is bound by the technical rules respecting the admissibility or relevancy of evidence. So far as this case is concerned, they sit to receive aid in the formation of a personal judgment as to what is an equitable apportionment of the expense, under all the circumstances. Hopson'sAppeal,
There is error, and the cause is remanded with direction to overrule the demurrers to the reasons of appeal.
In this opinion PRENTICE, C. J., THAYER and RORABACK, Js., concurred.
Malmo's Appeal From County Commissioners ( 1899 )
Scranton v. Department of Motor Vehicles, No. 44545 (Oct. ... ( 1991 )
Lee v. Delponte, Comm'r of Motor Vehicles, No. 29 52 08 (... ( 1990 )
Town of Andover's Appeal From Public Utilities Commission ( 1931 )
Coppola v. New York, New Haven & Hartford Railroad ( 1956 )
State Water Commission v. City of Norwich ( 1954 )
Speck v. Zoning Board of Appeals ( 1980 )
Wilson Point Property Owners Assn. v. Connecticut Light & ... ( 1958 )
Huntington Telephone Co. v. Public Utilities Commission ( 1933 )
Root v. New Britain Gas Light Co. ( 1916 )
City of Norwalk v. Connecticut Co. ( 1915 )
Kram v. Public Utilities Commission ( 1940 )
Modeste v. Public Utilities Commission ( 1922 )
Papa v. Department of Motor Vehicles, No. 44456 (Oct. 16, ... ( 1991 )
Magnan v. Anaconda Industries, Inc. ( 1980 )
Congress Bank & Trust Co. v. Brockett ( 1930 )