DocketNumber: File No. CV 8-698-8645
Citation Numbers: 6 Conn. Cir. Ct. 507, 276 A.2d 912, 1970 Conn. Cir. LEXIS 139
Judges: Kinmonth
Filed Date: 10/2/1970
Status: Precedential
Modified Date: 11/3/2024
The plaintiffs bring their action on a bond given in substitution for a mechanic’s lien.
The plaintiffs’ first assignment of error is addressed to the court’s failure to strike certain findings as found without evidence. This claim is without merit, since the challenged paragraphs of the finding either are directly supported by the evidence or are based on inferences reasonably drawn from the evidence. Schurgast v. Schumann, 156 Conn. 471, 475.
The plaintiffs’ second assignment of error seeks to have added to the finding a number of paragraphs of the draft finding on the ground that the facts stated in them were admitted or undisputed. To secure an addition on this ground it is necessary for an appellant to point to some part of the transcript, the pleadings, or an exhibit properly before us which discloses that the appellee admitted that the fact in question was true or that its truth was conceded to be undisputed. That a fact was testified to and was not directly contradicted by another witness is wholly insufficient. The trier is the judge of the credibility of witnesses. Martin v. Kavanewsky, 157 Conn. 514, 515. The plaintiffs have not established any failure on the part of the trial court to
The plaintiffs finally assign error in the conclusions of the trial court. The court’s conclusions are to he tested by the finding and must stand unless they are legally or logically inconsistent with the facts found or unless they involve the application of some erroneous rule of law material to the case. Mayock v. Martin, 157 Conn. 56, 62. We do not retry facts or determine the credibility of witnesses. French v. Oberreuter, 157 Conn. 181, 184.
The following facts were found: The defendant is a land development corporation engaged in constructing commercial buildings on land it owns. On March 11, 1968, the defendant contracted with Connecticut Structures, Inc., to furnish, fabricate and erect structural steel, steel joists and a steel roof deck on a building, to be 120 by 180 feet, for the price of $27,000. This building was to be located approximately 700 feet to the rear of a building occupied by the defendant and used to conduct its own business. Connecticut Structures, Inc., subcontracted the work of erecting structural steel, steel joists and a roof deck to the plaintiffs for the sum of $3803, as evidenced by a purchase order dated July 16, 1968. The plaintiffs commenced work on the building on July 12, 1968, and had their thirty-five-ton crane on the job with workmen on July 12 and 13, on which days they proceeded to erect the structural steel and joists, and the steel deck was landed in big bundles on top of the steel joists. The roof of the structure was bare. On July 19, 22, 24, 25 and 27, the plaintiffs straightened the building and steel joists, put in x-braces, put down the steel roof deck and welded it to the steel joists, completing the job on July 27, 1968. On
From these facts the court concluded that the payment of July 17, 1968, was made in good faith and that it was a defense in toto to the plaintiffs’ right to a lien.
The plaintiffs contend that the trial court erred in finding that the defendant in good faith paid the full contract price before it had any knowledge or information that the plaintiffs were furnishing services for its building. The plaintiffs insist that this conclusion is not justified by the evidence which is before us, and we are asked to correct the finding so that it will express an opposite conclusion. As stated above, the plaintiffs are not entitled to any changes in the finding. An examination of the record discloses that the evidence was conflicting and that the weight of it tended to sustain the defendant’s contention that the payment made to the contractor was made in good faith. The proof relied on by the plaintiffs to show that the payment made by the defendant to the contractor was not made in good faith was that the defendant had a general knowledge that the crane did not belong to the contractor and that therefore someone else must be
The finding of the court is in substance that the defendant did not, until after the payment had been made, have knowledge by name of any person who had rendered services. The burden of proof is on the plaintiffs, who claim that payment was not made in good faith, to bring home to the defendant the fact of knowledge at the time of the payment, and on these findings the plaintiffs have failed to sustain that burden of proof. See Hubbell, Hall & Randall Co. v. Pentecost, 89 Conn. 262, 268.
The statute is explicit: only payments made to the contractor by the owner in good faith before receiving notice of the lien shall be allowed. What constitutes a payment in good faith the statute leaves for judicial determination. It particularizes as to
The plaintiffs in their argument and brief suggest that they are at least entitled to the 2 percent discount given to the defendant. This claim is without merit. It is a common practice to give cash discounts, and furthermore the plaintiffs have failed to show that they knew the terms of the contract and relied on it.
We find nothing in the appeal which requires us to disturb the findings and conclusions of the trial court.
There is no error.
In this opinion Casale and Lextost, Js., concurred.
This action was brought against Coleman B. Levy as trustee in bankruptcy of Connecticut Structures, Inc.; the Connecticut Valley Corporation, the owner; and the Travelers Indemnity Company. Upon the appeal we are only concerned with the defendant Connecticut Valley Corporation.
“Sec. 49-36. liens limited; apportionment; payments to original contractor. . . . [I]n determining the amount to which any lien or liens shall attach upon any land or building, the owner of such land or building shall be allowed whatever payments he has made, in good faith, to the original contractor or contractors, before receiving notice of such lien or liens. No payments made in advance of the time stipulated in the original contract shall be considered as made in good faith, unless notice of intention to make such payment has been given in writing to each person known to have furnished materials or rendered services at least five days before such payment is made.”