DocketNumber: No. CV98-0061494S
Citation Numbers: 1999 Conn. Super. Ct. 3547
Judges: SYLVESTER, JUDGE TRIAL REFEREE.
Filed Date: 3/25/1999
Status: Non-Precedential
Modified Date: 7/5/2016
The Commissioner filed an answer and a return of record on May 21, 1998. The plaintiff filed a brief in support of the appeal on July 31, 1998, and the defendant's brief was filed on August 27, 1998. The hearing, scheduled for January 5, 1999, was waived by the parties. The matter was taken on the papers by the court, Sylvester, J.
On May 15, 1997, a formal administrative hearing, at which the plaintiff appeared pro se, was held in Hartford, Connecticut, before the office of the commissioner of consumer protection, hearing officer Thomas Cerasulo presiding. On October 3, 1997, Cerasulo issued a proposed final decision. In this proposed decision, Cerasulo concluded that the plaintiff violated the Home Improvement Act, General Statutes §
Based on this conclusion, the hearing officer proposed that 1) the plaintiff post a bond in the amount of ten thousand dollars in order to obtain and/or renew a home improvement contractor certificate of registration; 2) that the plaintiff immediately cease and desist from engaging in conduct violative of the Home Improvement Act and; 3) that the plaintiff make restitution in the amount of $22,882.59 to Lester Uris Smith and $18,687.05 to Charles Irene Moore. (ROR, #4.) On December 31, 1997, the Commissioner adopted the proposed final decision in full. (ROR, #5.) CT Page 3549
In his appeal dated February 13, 1998, the plaintiff alleges that "[t]he Commissioner of Consumer Protection erred in adopting the Proposed Final Decision of the hearing officer in that false material was presented at the hearing, the appellant was unrepresented at the hearing, the decision was based on erroneous information and the decision is not supported by the evidence." (Plaintiff's Appeal, February 13, 1998.)
"[T]he fundamental test for determining aggrievement encompasses a well-settled twofold determination: first, the party claiming aggrievement must . . . demonstrate a specific personal and legal interest in the subject matter of the decision. . . . Second, the party . . . must . . . establish that this specific personal and legal interest has been specially and injuriously affected by the decision. . . . Aggrievement is established if there is a possibility, as distinguished from a certainty, that some legally protected interest . . . has been adversely affected." (Citations omitted; internal quotation marks omitted.) United Cable Television Services Corp. v. Dept. ofPublic Utility Control,
Here, the plaintiff has been ordered by the defendant to post a bond to secure a license and also been ordered by the defendant to pay restitution to two separate parties. The plaintiff's legally protected interests have been adversely affected and, therefore, the plaintiff is aggrieved.
The record is also silent as to how service was made on the defendant. Since the defendant has neither raised the issue of service at any time, nor acted in a manner inconsistent with actual service or notice,1 the court will assume that the defendant was served. Since the file lacks a sheriff's return, the court will again assume that service was made on the defendant by United States mail as contemplated by General Statutes §
The plaintiff, however, has failed to file an affidavit attesting how service was made as required by General Statutes §
As stated above, the defendant has acted in a manner consistent with service and notice and does not argue that it has not been properly served. The court, therefore, finds that the defendant has not been prejudiced by the plaintiff's failure to include an affidavit of service. The appeal was filed within forty-five days of the decision and is timely in that regards.
An agency's factual determination must be sustained if it is reasonably supported by substantial evidence in the record taken as a whole. Connecticut Resources Recovery Authority v. Planning Zoning Commission,
The commissioners adoption of the proposed final decision included the hearing officer's conclusions of law that the plaintiff violated the Home Improvement Act by failing to complete contracted work and failing to provide contracts in compliance with the law. (ROR, #5.) The plaintiff claims that the substantial evidence in the record was insufficient to support this decision and the defendant's subsequent order that the CT Page 3552 plaintiff pay restitution on both the Smith and the Moore contracts.
Section
In the proposed final decision that was adopted by the commissioner, the hearing officer found that "[t]he contracts fail to comply with the requirements of the Home Improvement Act insofar as said contracts did not contain the mandatory three day right of cancellation, the start and completion date, signature and date by both the [contractor] and consumer." (ROR, #4.) The hearing officer also found that the contract between the plaintiff and his consumers failed to detail the scope of work to be performed by the contractor. (ROR, #4.)
A review of the record indicates that substantial evidence exists to support these findings of fact by the defendant.
The record contains the results of an investigative report conducted by the State of Connecticut department of consumer protection in regard to the plaintiff's contract with the Smiths. In the course of its investigation, the department of consumer protection investigator, Robin Cox, concluded that the contract between the plaintiff and the Smiths violated §
The record reveals similar evidence in regard to the contract between the plaintiff and the Moores. An investigative report conducted by Barbara Syp of the department of consumer protection, for instance, concludes that the plaintiff failed to include starting or ending dates in the contract. (ROR, #3, Ex. 3A). Robin Cox, of the frauds division of consumer protection, testified as to numerous deficiencies in the contract. (ROR, #2, pp. 90-93.) Finally, a review of the contract reveals that the rider attached to the original contract was not signed by all the parties, fails to state a start and completion date, and does not contain a notice of cancellation. (ROR, #3, Ex. 4A.)
The record does contain substantial evidence to support the findings of fact of the defendant in concluding that the plaintiff failed to provide contracts in compliance with the Home Improvement Act.
In regards to the plaintiff's contract with the Smiths, the record is somewhat unclear as to the scope of work to be performed by the plaintiff. The Smiths testified that they hired the plaintiff to transform a two family home into a four family home. (ROR, #2, pp. 45, 66.) Apparently, when the Smiths were notified by the plaintiff that this was not possible, the Smiths agreed that the plaintiff would transform the attic into a third floor apartment. (ROR, #2, pp. 45, 66.) The plaintiff, on the other hand, testified that the third floor was not meant to be a separate apartment, but merely an addition to the second floor.3 (ROR #2, pp. 84-85.)
Regardless of the total amount of work that was to be performed, the record indicates that at a certain point during the plaintiff's ongoing work, the City of Stamford issued a "Stop Work Order" as a result of numerous code violations found by the CT Page 3554 Building Inspector to exist at the premises. (ROR, #3, Ex. 8.) When the attempts to have the plaintiff remedy these violations failed, the Smiths terminated the contract of the plaintiff and hired other contractors to remedy the problems contributing to the "Stop Work Order." (ROR, #3, Ex. 11.)
Concerning the Moores' contract with the plaintiff, Charles Moore testified that at a certain point in time, with numerous items in need of completion, the plaintiff stopped coming to the Moore residence altogether. (ROR, #2, pp. 96-98.) When the Moores attempted to contact the plaintiff, the plaintiff never returned his calls. (ROR, #2, p. 96.) As a result, the Moores eventually hired new contractors to complete the remaining work. (ROR, #2, pp. 102-103.)
In his memorandum in support of the appeal, the plaintiff argues that he did not fail to complete either of the projects of his own volition. Rather, the plaintiff argues that a period of hospitalization, lack of final payments, and an order to stop prohibited him from completing any work.
Concerning the Smiths' contract, the plaintiff testified that he was unable to respond to the concerns raised by the Stamford building inspector due to the fact that he was hospitalized for three weeks with back surgery. (ROR, #2, p. 30.) The plaintiff further testified that when he finally did try to straighten the matter out, he discovered that he had already been discharged by the Smiths. (ROR, #2, p. 30.) As to the Moores project, the plaintiff testified that he did not finish because the Moores' failure to pay amounts due made it impossible for the plaintiff to continue carrying the site without further eroding any profit margin. (ROR, #2 pp. 110-11, 127.)
The court does not review the record de novo. Huck v. InlandWetlands Watercourses Agency,
A review of the record reveals that the commissioner could have drawn the conclusion that the plaintiff was responsible for failing to complete both the Smith and the Moore contracts. Pertaining to the Smith contract, the record indicates that on March 28, 1995 a rider signed by the plaintiff and Lester Smith indicated that the project would be completed in its entirety on May 15, 1995. (ROR, #3, Ex. 7; ROR, #2, p. 70.) When the plaintiff was discharged by the Smiths on September 13, 1995, the project still was incomplete and contained numerous building code violations. The record also shows that though the plaintiff may have been hospitalized for a period of time, communications between the Smiths and Stamford building officials and the plaintiff seemed to indicate that the plaintiff was unwilling to finish the project. (ROR #2, pp. 57-58.) The plaintiff failed to respond to most inquiries and seemed unconcerned about the situation on the occasions he did respond. (ROR #2, pp. 57-58; ROR #3, Ex. 10.)
Based on the record before the court, the Commissioner may also have found that the plaintiff failed to complete the Moore contract. By his own admission, the plaintiff indicated that nearly 10% of the Moore project was not completed. (ROR, #2, pp. 118, 122.) The owner Charles Moore testified as to the various items left unfinished. (ROR, #3, Ex. 7A; ROR, #2, pp. 99-101.)
Though the plaintiff indicated that he stopped work on the Moore contract because the Moores failed to timely pay the plaintiff, the record also indicates that the Moores' payments to the plaintiff were contingent upon inspection and approval from Moores' bank, which was to pay funds directly to the plaintiff (ROR, #2, p. 114.) According to Charles Moore, the plaintiff was aware of this arrangement and yet failed to pursue any of the required inspections. (ROR, #2, p. 127.) Furthermore, the record shows that the plaintiff apparently did not notify the Moores of his decision to stop work, but rather simply failed to show up at the job and refused to answer any of the times the Moores attempted to reach the plaintiff. (ROR, #2, pp. 98-99.) The record further shows that after a mediation attempt between the parties, the plaintiff indicated to the Moores that he would be willing to have another contractor complete the work at hand. (ROR, #2, p. 121.)
Though the court acknowledges that the record is not entirely CT Page 3556 clear as to the precise nature of the work to be completed by the plaintiff, there is cumulative evidence in the record to suggest that the plaintiff failed to complete general contract work. Based on this cumulative evidence, there is substantial evidence in the record to support the commissioners conclusion that the plaintiff violated the Home Improvement Act by failing to complete the contracts of both the Smiths and the Moores.
As previously discussed there is substantial evidence in the record to support the commissioner's findings that the plaintiff failed to provide contracts in compliance with the provisions of the Home Improvement Act and failed to complete the contracted work. Thus, the commissioner may have found that these violations of the Home Improvement Act caused the home owners losses and damages.
The proper measure of damages for failing to complete a construction project is the cost of completion or correction by a third party. Brookfield v. Greenridge, Inc.,
However, "[i]t is axiomatic, that the sum of damages awarded as compensation in a breach of contract action should place the injured party in the same position as he would have been in had the contract been performed. . . . The injured party, however, is entitled to retain nothing in excess of that sum which compensates him for the loss of his bargain." (Citations omitted; internal quotation marks omitted.) Argentinis v. Gould,
Keeping these principles in mind, the court will now review the awards of restitution to both the Smiths and the Moores to see if they are substantiated by substantial evidence of the record.
Under the Moores' contract, the commissioner found that the plaintiff owed restitution to the Moores in the amount of $18,607.05. For the following reasons, the court finds that this amount of restitution is not substantiated by the record.
The commissioner derived the sum of $18,687.05 as the cost of completion pursuant to proof of payment to two new contractors in the amount of $1,500 and $17,187.05. (ROR, #4.) However, the attorney for the Moores testified that the invoices for the completion amounted to $20,030 (ROR, #2, p. 120). The invoices contained in the record for this contract work, however, indicates that the amount of construction to be completed was actually $19,495. (ROR, #3, Ex. 8A, 9A, 10A, 11A.) Regardless of the figure, none of the amounts listed above include a credit for the amount still owed by the Moores to the plaintiff at the time the plaintiff stopped working on the Moore project. According to the homeowner's own exhibit, such an amount was at least $7,500. (See ROR, #3, Ex. 13A (listing credit of $7,500 and seeking damages of $14,330)).
The amount of restitution ordered to the Smiths was $22,882.59. The commissioner found that this was the amount required to complete the contracted work and to make mandatory repairs as required by the Stamford building inspector. In the case of the Smiths, the commissioner apparently did credit the damages required to complete the contract with the amount of money, $2,817.41, still owed the plaintiff by the Smiths.4 (ROR, #4.) CT Page 3558
The application of general damage principles to the Smith contract reveals some further complications. For example, though the estimate from Jefferson Plumbing was for $8,000, the Smiths testified at the formal hearing that they did not pay this amount to Jefferson "because we're friends." (ROR, #2, p. 74.) In fact, the record seems to indicate that Jefferson was paid substantially less. (See ROR, #3, Ex. 22.)5 Moreover, according to the estimate submitted by Bowden Home Improvements, the cost of completing a portion of the work in need of finish would be $17,300. (ROR, #3, Ex. 12.) The testimony of the Smiths during the formal hearing, however, reveals that not only was the work called for in this estimate never done, but, in fact, would not be able to be completed because of a decision by the building inspector prohibiting the completion of an individual apartment on the third floor.
Because of the difficulties in transcribing the formal hearing, the court can only guess as to the reason the work, included in Bowen's estimate; (ROR, #2, p. 79); was stopped by the decision of the building inspector.6 However, based on previous testimony concerning the zoning of the Smiths' home for two families as opposed to three, the plaintiff's argument that the original building plan did not include a kitchen, and apparent emphasis place on the kitchen in Bowen's estimate; (ROR, #3, Ex. 12, (highlighting the kitchen plan for the third floor)); it appears that the Smiths were prohibited by zoning regulations from adding an independent unit, with a kitchen, on the third floor.
Regardless, the proposed findings of fact adopted by the commissioner do not specifically conclude to whether the contract between the plaintiff and the Smiths called for the installment of a kitchen on the third floor. In the present case, the amount of restitution ordered by the commissioner included estimates for work that, apparently because of zoning regulations, will never be — or never could be — completed. As a result of such a bizarre situation, it is necessary that the commissioner determine whether the contract actually called for the construction of a third apartment, or merely an addition as claimed by the plaintiff.
The court, accordingly, finds that the record as a whole does not support the commissioner's order of restitution in the sum of $18,687.05 to the Moores and $22,882.59 to the Smiths. In the former case, the invoices do not agree with the amount found by CT Page 3559 the commissioner and the award of restitution, whatever it is found to be, does not reflect sums of money saved by the Moores as a result of the plaintiff's failure to complete the contract. In the latter case, there appears to be a contradiction in the record as to the amount of estimates offered by the Smiths and the actual amount of money spent on the completion of the project started by the plaintiff.
The record does not contain substantial evidence to substantiate the amount of restitution decreed by the commissioner.
As a result, the court, pursuant to §§
Sylvester, J. Judge Trial Referee