DocketNumber: File No. 05
Citation Numbers: 342 A.2d 910, 32 Conn. Super. Ct. 529
Judges: PER CURIAM.
Filed Date: 4/30/1975
Status: Precedential
Modified Date: 4/14/2017
This action was brought in two counts, the first claiming a balance due and owing on a written contract together with certain extras performed by the plaintiff during the course of the execution of the contract, and the second claiming damages for the reasonable value of the benefit of labor and materials furnished by the plaintiff to the defendants. In addition, the defendants filed a counterclaim claiming damages for failure to perform substantially in accordance with the contract and for unworkmanlike and unsatisfactory work. *Page 530
The report and finding of the referee disclose that on August 10, 1965, the plaintiff and the defendants entered into a written contract wherein the plaintiff agreed to construct a dwelling house on land of the defendants for the sum of $19,200 as the basic construction price plus additional payments for extras performed by the plaintiff less an allowance for credits due the defendants. Installment payments totaling $16,650 were made on the basic contract price, leaving a balance due of $2550. Extras in the amount of $1156.57 were performed by the plaintiff, and it was agreed that credits due the defendants amounted to $1120. Certain defects in the work were corrected by the plaintiff, and the defendants took possession of the premises during November, 1965. The finding reveals that the plaintiff substantially performed all the terms and conditions of the construction contract and substantially and satisfactorily performed all the extras claimed by it.
The court then concluded that there is due and Owing to the plaintiff from the defendants the sum of $2586.57 together with interest from August 11, 1968, and also concluded that no damages were due the defendants on the counterclaim.
In their assignment of errors, the defendants have made a wholesale and confusing attack on the court's findings and conclusions, claiming error on the face of the record as well as error in the conduct of the trial. Such a procedure is unwarranted and needlessly requires a great deal of time to be utilized in a fruitless task of reviewing the transcript of evidence. Attacks such as those rarely produce any beneficial results. "This court strongly disfavors such an unwieldy method of presenting an appeal." Pawlinski v. Allstate Ins. Co.,
The court's conclusions which are attacked are to be tested by the finding. Brockett v. Jensen,
On the complaint, the court found that there was substantial performance, and on the counterclaim the court found that there was no defective or unworkmanlike work. Those findings of fact support the conclusions of the court.
We shall discuss one final claim of the defendants, namely, that judgment based on an implied contract cannot be entered where an express contract exists. That rule, alluded to in such cases as Corriveau v. Jenkins Bros.,
The defendants seek a credit of $1120 under the terms of the provision which they now cite to prevent payment to the plaintiff for extras. It is immaterial whether the award for extras to the plaintiff is based on the provisions of the original contract or a subsequent implied contract. Casey v. McFarlane Bros. Co.,
There is no error.
BARBER, SPEZIALE and SPONZO, Js., participated in this decision.
Freda v. Smith , 142 Conn. 126 ( 1955 )
Von Langendorff v. Riordan , 147 Conn. 524 ( 1960 )
M. J. Daly & Sons, Inc. v. New Haven Hotel Co. , 91 Conn. 280 ( 1917 )
Johnston Jewels, Ltd. v. Leonard , 156 Conn. 75 ( 1968 )
Casey v. McFarlane Bros. Co. , 83 Conn. 442 ( 1910 )
McCaffrey v. Groton & Stonington Street Railway Co. , 85 Conn. 584 ( 1912 )
Corriveau v. Jenkins Bros. , 144 Conn. 383 ( 1957 )
Shelton Yacht & Cabana Club, Inc. v. Suto , 150 Conn. 251 ( 1963 )
Brockett v. Jensen , 154 Conn. 328 ( 1966 )
Tartaro v. La Conte , 157 Conn. 583 ( 1969 )