DocketNumber: No. CV02-0172753S
Citation Numbers: 2002 Conn. Super. Ct. 11674, 33 Conn. L. Rptr. 85
Judges: HOLZBERG, JUDGE.
Filed Date: 9/13/2002
Status: Non-Precedential
Modified Date: 7/5/2016
Plaintiff hired Blastech, Inc. to perform blasting work pursuant to a building permit issued to the plaintiff for the construction of a two family residence, including the installation of a foundation. The terms of the excavation and foundation permit require that the work be completed within six (6) months of the issuance of the March 5, 2002 permit. Because the site is comprised of rock and ledge, Blastech applied for, and received in March, 2002, a 30 day blasting permit from the defendant Fire Marshal. The permit was reissued for successive thirty day periods in April and May. In June, however, the Fire Marshal refused to issue another permit, citing complaints by neighbors that the blasting caused damage to foundations in their condominium project.
On August 6, 2002, the plaintiff filed this application for a mandatory temporary injunction, claiming that state statutes and regulations deprive the defendant Building Inspector discretion to deny a blasting permit except in accordance with standards enumerated in the statute and regulations. Specifically, the plaintiff relies on General Statutes §
Relying on these provisions, the plaintiff argues that the Fire Marshal must issue a blasting permit if: (1) the applicant provides a license issued by the State Fire Marshal and if the Fire Marshal is satisfied as to (2) the identity of the applicant and (3) as to what use will be made of the explosives. Because there is no dispute that the applicant in fact produced a license issued by the State Fire Marshal and because there is no dispute that defendant Fire Marshal is satisfied both as to the identity of the applicant and as to what use will be made of the explosives, the plaintiff argues that the defendant is obligated to issue the blasting permit without further inquiry or investigation.
The defendant contends that while the literal criteria of the regulation may be satisfied, he has inherent authority to deny the permit when, as here, he is presented with complaints by neighbors that raise concerns of public safety that require additional review and investigation. Evidence presented at the hearing indicates that at an unspecified time in June, after denial of the blasting permit, the defendant commenced an investigation into the complaints of nearby residents of a condominium complex who complained of cracks to their floors and foundation walls.
The investigation, which is still not completed, consisted of taking written statements from the neighbors, conducting inspections of the complainants' residences and taking photographs of the claimed damage. The defendant Fire Marshal has also sought the assistance of the State Fire Marshal, but because of other pending investigations the State Marshal has been unable to actively participate in the local investigation. The defendant is unable to specify when the investigation will be concluded or what other additional information must be collected. For its part, the plaintiff presented testimony indicating that its insurer has investigated each and every complaint submitted by the neighbors. Based on that investigation, conducted by a firm specializing in investigating blasting related damage, the insurer was advised that the cracks in foundations and walls cited by the neighbors are not of recent origin, and are not likely to have been the result of plaintiff's blasting given the distance of the neighbors from the blasting cite, and the force of the blasts themselves. CT Page 11676
The law governing plaintiff's application for a mandatory injunction-which the parties concur is an application for a writ of mandamus-is well established. The authority to issue a writ of mandamus is granted to the Superior Court under C.G.S. Section
As previously noted, the principal legal issue in this dispute is whether the defendant Fire Marshal retains discretion to deny an application for a blasting permit despite the language of the statute and implementing regulations, §
It is not necessary to resolve the precise issue raised by the parties because it is clear that even assuming the Fire Marshal retains discretion to deny a permit for reasons other than those specified in the statute and regulations, the Marshal's discretion is subject to reasonable limitations with respect to the nature and duration of the investigation it seeks to conduct. In this case the testimony demonstrates that the defendant's investigation has been ongoing for CT Page 11677 almost three months and has not moved beyond the stage of initial interviews of the complainants and visual inspections of some, but not all of the properties in question. In the face of the State Marshal's unavailability, the defendant has not made any attempt to obtain the assistance of any other experts, either public or private. It is both unknown and unknowable when, if at all, the investigation will be completed.
By contrast, the plaintiff has presented evidence indicating that its insurer undertook and completed a prompt investigation into the claims of damages by neighboring residents. That investigation discloses that the blasting activity is a substantial distance from the neighbor's condominium, that the force of the blast dissipates almost immediately and that the cracks in the basement floors and outer foundation are not of recent origin.
Assuming, without deciding, that the Fire Marshal has reasonable discretion to investigate complaints of an ultra hazardous activity, the Fire Marshal has failed to complete the investigation in a timely manner. To date, over three months have elapsed since the commencement of the investigation into the neighbors' complaints. The maximum duration of a permit is six months, such that the investigation has consumed 50% of the maximum duration of the permit. The investigation has not produced any reliable findings that would warrant the conclusion that the blasting by Blastech has caused any damage to the neighbors' property. Indeed, the evidence presented at the hearing strongly favors the conclusion that the any damage in the condominium basements and foundation walls is unrelated to any blasting activity at the plaintiff's site.
Under the circumstances of this case, the failure of the defendant to timely conclude its investigation implicates the plaintiff's constitutional due process rights to the use of his property. The court is mindful that the particular site in question is the source of ongoing disputes between and amongst the neighbors and the plaintiff, and that the nature of the excavation creates noise and dust that may be disruptive to the neighbors. Nevertheless, the law clearly allows the plaintiff to obtain a blasting permit, even in the face of such incidental disturbance. The fact that both state statute and regulation authorize the issuance of a blasting license and permit under the conditions set forth in those provisions is a recognition of the fact that the legislature has struck the balance between protecting public safety and avoiding unacceptable levels of nuisance, on the one hand, and allowing a property owner to develop his property, on the other.
Therefore, the defendant is ordered to issue the blasting permit to the CT Page 11678 plaintiff. Any blasting conducted pursuant to the permit shall be done in the presence and under the supervision of the local and/or state Fire Marshals. The blasting shall be monitored to insure that it does not exceed the level of force permitted by regulations and/or the terms of the permit. Should any blast exceed the permitted levels, as measured by the Fire Marshal and/or Blastech, the Marshal shall immediately order the cessation of such blasting, and such blasting shall not be permitted to resume until further order of the court.
SO ORDERED.
Robert L. Holzberg, J.
LARS Realty, LLC. Judicial District of Waterbury
v. At Waterbury
Mallamaci, Carmen August 9, 2002
The parties are to appear at 11:30a.m. on August 16, 2002 at which time the Defendant is to provide testimony under oath concerning the results of his investigation of the Plaintiff's blasting activities. Specifically, the Defendant is to indicate whether his investigation has determined whether the Plaintiff's blasting has damaged surrounding properties and the specific factual basis for such findings, if any. The defendant is also to specify whether continued blasting will jeopardize the health or safety of abutting neighbors, and the specific factual basis of such conclusion, if at all.
BY THE COURT (Holzberg, J)
/s/___________________ TALC
Notice sent via facsimile On August 9, 2002 by JF CT Page 11679
[EDITORS' NOTE: This page is blank.] CT Page 11680