DocketNumber: No. CV90-0378684
Citation Numbers: 1991 Conn. Super. Ct. 10306, 7 Conn. Super. Ct. 195
Judges: SATTER, STATE TRIAL REFEREE.
Filed Date: 12/19/1991
Status: Non-Precedential
Modified Date: 7/5/2016
Necessarily implicated are an interpretation of key provisions of the Connecticut's mechanic's lien statute, Conn. Gen. Stats.
The court finds the following facts: Plaintiff PDS, at the times relevant herein, was engaged in the business of designing and constructing industrial and commercial buildings. Defendant Double RS was engaged in the business of developing and owning such buildings. Mr. Joseph Russo, a partner of Double RS, contacted Mr. Frank Borawski, president of PDS, in October 1988 for the purpose of having Borawski review certain preliminary plans for the construction of a strip plaza, consisting of retail commercial and office space on Berlin Turnpike land on which Double RS had an option. After PDS reviewed the plans, Russo asked PDS to prepare revised design and engineering drawings and to assist Double RS in obtaining all necessary building permits and approvals. PDS submitted a price of $1,120,000 for the design and construction of the strip plaza which was accepted by Double RS. They agreed PDS could start construction after all building permits were obtained from Newington and Wethersfield. Beginning in November 1988 PDS undertook design and engineering services directed to preparing final building drawings and plans. On March 9, 1989 Double RS took title to the property and the towns of Newington and Wethersfield issued building permits. Immediately thereafter PDS hired subcontractors who did the following work on the building site: established building corners, laid out storm drain lines and catch basins, cut brush, flagged trees for removal, made test borings and soil tests, delivered and spread fill with excavation equipment, and installed a silt fence.
On March 27, 1989 PDS and Double RS memorialized their earlier oral agreement by a written contract on a form of the American Institute of Architects. In that contract PDS was identified as architect and contractor and agreed to construct a retail building and do associated site work for the price of $1,120,000, work to commence on receipt of CT Page 10308 a building permit, which had been already obtained.
At that time Double RS was negotiating with United Bank for a construction mortgage. Attorney Jacek Smigelski, counsel for the bank, contacted Borawski of PDS several days before the closing and asked him to sign a collateral assignment of contract rights. In the bank's file at that time were the building permits and the contract between PDS and Double RS. Smigelski never asked Borawski to sign a lien waiver and none was ever signed by PDS. The mortgage closing took place on April 13, 1989. A mortgage deed in the amount of $1,750,000 by Double RS to United Bank and a collateral assignment of leases and rentals were executed and recorded on that date on the land records of Wethersfield and Newington.
The bank admitted in response to plaintiff's request for admission that it "had knowledge, information or belief that labor had been performed or material had been furnished in connection with the construction of the Project prior to the recording of the Note and the Mortgage."
PDS proceeded with construction of the building and was paid as work progressed. However, commencing in June, 1989 payments we relate and by August 1989 Double RS started to fall behind. From time to time the parties orally agreed to change orders for which PDS billed Double RS. Although the contract required change orders be in writing, there is no dispute the work was done. PDS stopped work in January 1990 because Double RS stopped paying PDS invoices.
PDS filed its mechanic's lien certificate in the town clerk's offices of Wethersfield and Newington on January 31, 1990, claiming to be owed $215,497.15 for work performed and materials furnished "commencing March 27, 1989 and ending January 15, 1990."
Connecticut's mechanic's lien statute,
United Bank, on the other hand, contends: (1) PDS work done before Double RS took title to the property and/or before the contract was signed is not lienable; (2) off-site CT Page 10309 engineering work and the minimal work done by PDS before recording of United Bank's mortgage do not amount to "commencement of services" within the meaning of
This court determines that United Bank cannot prevail in its first four defenses but concludes that United Bank can prevail on its defense that the mechanic's lien law would unconstitutionally deny United Bank due process of law were it applied to give PDS's lien priority over United Bank's mortgage.
1. The issue of the lienability of PDS work done before defendant Double RS acquired title on March 9, 1989 and before the contract was signed between PDS and defendant Double RS on March 27, 1989
United Bank contends work done by plaintiff PDS before Double RS acquired title to the subject property on March 9, 1979 is not lienable. In Bridgeport People's Savings Bank v. Palaia,
However, in this case the critical fact is plaintiff PDS furnished materials and performed labor after Double RS took title to the property on March 9, 1989 and before defendant United Bank recorded its mortgage on the property on April 13, 1989. Those acts are sufficient to establish the precedence of PDS' mechanic's lien, under
Moreover, the services and materials provided by PDS were paid for as its work progressed, at least up to August 1989. Thus, the court can infer that PDS invoices CT Page 10310 prior to March 9, 1989 are not a part of the debt PDS is now claiming to be due and owing.
United Bank also contends work done by PDS before March 27, 1989, when the contract between PDS and Double RS was signed, is not lienable. Section
2. The issue of commencement of services
Section
The facts found by this court are that PDS began preparing revised architectural plans and engineering drawings as early as November 1988 and continued until October 2, 1989, the date on the final revision of the plans used for the building.
There is a sharp conflict among the states on whether or not preliminary plans and drawings of architects and engineers, before visible work is done on the site, constitute commencement of services within the meaning of a state's mechanic's lien statute. Cases holding that such non-visible work does not amount to commencement of services, so as to trigger relating back the priority of a mechanic's lien to the date work first started, are: Williams and Works, Inc. v. Springfield Corp.,
Cases holding that architects ``and engineers' preliminary plans and drawings do constitute commencement of work within the meaning of a state's mechanic's lien law CT Page 10311 are: Bankers Trust Co. v. El Paso Pre-Cast Co.,
The disparity in the holding of these two groups of cases can in large part be explained by differences in the wording of state mechanic's lien statutes.
The only Supreme Court case in Connecticut is Marchetti v. Sleeper,
Since in this case, PDS' architectural and engineering services were used in the construction of the building on the land subject to the mechanic's lien, the court concludes that under Connecticut law its lien fixed at least on March 9, 1989 when Double RS took title to the property, which was well prior to the date of United Bank's mortgage. This conclusion, however, is not critical to this court's decision because the court finds PDS did physical work on the site before United Bank's mortgage was recorded.
United Bank also contends the minimal work done by PDS on the project before April 13, 1989 did not amount to commencement of services and furnishing of materials rendered in the construction of the building, within the meaning of
The facts are that between March 9 and April 13, 1979 PDS hired subcontractors who did the following work on the building site: established building corners, laid out storm drain lines and catch basins, cut brush, flagged trees for removal, made test borings and soil tests, delivered and spread fill with excavation equipment, and installed a CT Page 10312 silt fence.
Only two old Connecticut cases deal with the meaning of commencement of services under the mechanic's lien law: Middletown Savings Bank v. Fellowes,
The cases of other states conflict as to what constitutes commencement of construction for purposes of determining the accrual of mechanics' liens. See 1 A.L.R.3rd 822 (1965). The courts are not bound by any strict rules but have examined all the circumstances to satisfy themselves that it is apparent from the work done that the construction of the building is underway. Id. at 825. Thus, in Diversified Mortgage Investors v. Gepada, Inc.,
Both of these cases and other well-reasoned opinions recognize that "commencement of services" is a term of art keyed to notice being given to persons coming on the property that the work already done sufficiently indicates that construction is going forward. Woolridge Constr. Co. v. First Nat'l. Bank, supra at 19; Diversified Mortgage Investors v. Gepada, supra at 685.
In this case this court concludes the physical work done by PDS on the site prior to April 13, 1989 was sufficient to give adequate notice to United Bank that the construction of a building was underway. Consequently PDS' mechanic's lien antedates United Bank's mortgage.
3. The issue of equitable estoppel
United Bank asserts PDS should be equitably estopped from asserting the priority of its mechanic's lien over the CT Page 10313 bank mortgage because of its failure to disclose the work it had done prior to the mortgage closing. The facts are as follows: Attorney Jacek Smigelski, counsel for United Bank, called Frank Borawski, president of PDS several days before the closing, saying he needed from PDS a collateral assignment of its contract with Double RS and a list of subcontractors. He did not specifically ask whether any work had been done up to then. Borawski replied he would sign the collateral assignment, get Smigelski a list of the subs, and added that no bills would be presented at the closing. This conversation was repeated on the day of the closing. Smigelski had at that time in the bank mortgage file the Newington and Wethersfield building permits and a copy of the contract between PDS and Double RS which provided work would start when building permits were issued. Smigelski never asked Borawski to sign a lien waiver and Borawski never indicated he would not sign one.
The two essential elements of equitable estoppel are "that one party must do or say something which is intended or calculated to induce another to believe in the existence of certain facts and to act in that belief, and that the other party, influenced thereby, must change his position or do some act to his inquiry which he otherwise would not have done." Bozzi v. Bozzi,
The court finds Attorney Smigelski failed to ask Borawski the right questions: whether or not work had been done on the site and if so, was it going to be the basis of a mechanic's lien? More significantly, United Bank admitted, by its response to request for admissions, that it had a belief that labor had been done prior to the recording of its mortgage, so even if Borawski lacked candor in his conversation with Smigelski, United Bank did not rely on his answers.
Another ingredient of equitable estoppel is that the person claiming estopped "must show that he has exercised due diligence to know the truth and that he not only did not know the true state of things but also lacked any reasonably available means of acquiring knowledge." State v. American News Co.,
Here, United Bank had in the file the building permits dated March 9, 1989 and contract between PDS and Double RS providing that work was to start when the permits were issued. It also had the opportunity to send a representative to the site to see the work then underway, which should have alerted CT Page 10314 it to make further inquiry of Double RS. On balance, this court finds United Bank did not exercise due diligence to discover the true situation. Thus, the defense of equitable estoppel is without merit.
4. The issue of the amount of the lien
PDS produced evidence at the trial that it was owed $215,497 for work done on the contract plus interest, per the contract, of $38,375, making the total $253,872 as of January 24, 1991.
United Bank challenges the amount on two grounds: (1) since the building was not completed, a deduction should be made for the cost of completion, and (2) much of the balance claimed to be due is based on work done on change orders which were not approved in writing by the owners, as required by the contract.
Connecticut law is that a contractor suing for the contract price, when he has not completed the building, should have deducted the cost of having the work comply with the contract. Daly Sons v. New Haven Motel Co.,
At trial PDS' appraiser testified it would cost $235,000 to complete the building. However, he did not base that estimate on an actual review of plans and specifications. The court finds it unreliable. Better evidence is the credit of $58,941 given by PDS to Double RS for certain unfinished items under the plans and specifications. This credit does make the proper allowance for the uncompleted work.
While the contract between PDS and Double RS required that changes in the work "shall be authorized by written Change Orders signed by the Owner," the evidence is clear that a representative of PDS orally approved the change orders and the work was in fact done. Our law is that even when a written contract provides "that it may not be changed except in writing, a parol agreement modifying its terms will be given effect." Blakeslee v. Water Commissioners,
Thus, the court concludes the work done by PDS on the oral change orders can be included in the amount due PDS on its mechanic's lien, which the court finds to be $253,872 as of January 24, 1991.
5. The constitutional issue CT Page 10315
Having resolved all the issues relating to the validity of the mechanic's lien in favor of PDS, this court must, finally, turn to the constitutional defense raised by United Bank.
This court starts its inquiry of the constitutionality of the statute with Roundhouse Construction Corporation v. Telesco Masons Supplies Co.,
The General Assembly immediately acted to correct some of the constitutional infirmities of the statute.
In June 1991 the United States Supreme Court decided Connecticut v. Doehr, 501 U.S. —
a. The property interest affected
There is a sharp conflict in courts throughout the country as to the adverse consequences to the property owner of the filing of a mechanic's lien on the land records. In the leading case of Spielman-Fond, Inc. v. Hanson's, Inc.
Spielman-Fond was summarily affirmed by the United States Supreme Court at
The Connecticut Supreme Court in Roundhouse. supra, found a significant deprivation from the fact "the recording of a mechanic's lien, while it does not prevent alienation of the property, does, as a practical matter, severely restrict the opportunity for and possibility of its alienation." To the same effect is Barry Properties, Inc. v. Fiola Bros. Roofing Co.,
In Doehr, at footnote 4 (
However, this court is not concerned with the impact of the filing of the mechanic's lien on the interest of the property owner, Double RS, but on the interest of the mortgagee United Bank. There is no question United Bank has an interest in the property subject to the mechanic's lien equal to its mortgage on that property in the original amount of $1,750,000. At trial the property was appraised for $1,150,000, so the bank's mortgage, with accrued interest and costs of foreclosure, substantially exceeds the value of the property. There is no question if the mechanic's lien of plaintiff PDS in the amount of $215,497.15, plus interest, costs and attorney's fees, is found in this proceedings to have priority over United Bank's mortgage, United Bank will be adversely affected precisely by that amount.
The question is whether the filing of the mechanic's lien, in and of itself, deprives United Bank of any property interest. The filing does not have the affect on United Bank it can have on a property owner: reduce the chances of a second mortgage, taint credit rating, place an existing mortgage in technical default. It does, however, have one consequence: the lien, by claiming priority over United Bank's CT Page 10318 mortgage, casts a cloud on the status of the mortgage as a first lien and reduces the prospect of United Bank selling its mortgage. The court can take judicial notice of the commercial practice of banks assigning mortgages among themselves or selling mortgages in a secondary market to adjust portfolios and to meet liquidity demands. In Roundhouse our Supreme Court held that a restriction on "the opportunity for and the possibility of [property] alienation" amounts to a significant taking. Roundhouse, supra p. 384. Thus, this court finds the impact of recording the mechanic's lien on United Bank is significant and it must be weighed against the other Doehr factors in determining the issue of denial of due process here presented.
b. The risk of erroneous deprivation of property
As indicated above, in Roundhouse our Supreme Court held the procedures for filing a mechanic's lien under the 1974 law were constitutionally inadequate to sustain the validity of the lien.
The 1975 legislature let stand the procedures that: (1) the claimant can file the lien ex parte without authorization or control by a judicial officer, (2) the sworn certificate is required to contain only conclusory statements as to when the work commenced and the amount claimed to be justly due, without any substantive, underlying facts. But it amended the law to require that the lienor notify the owner of the real property when recording the lien (
No direct challenge has since been made to the constitutionality of the statute as amended. (But see General Electric Supply Co. v. SNETCO,
The question here is whether United Bank, as a mortgagee, has the rights of an "owner" within the meaning of
This legalistic concept of legal and equitable title is applied only as between mortgagor and mortgagee. Thus, in Barclay Bank of New York v. Ivler, supra, the court held that after the law day had passed, the mortgagor's equity of redemption was extinguished and title vested absolutely in the mortgagee.
But the legal title in the mortgagee does not make the mortgagee an owner in any other context. In State v. Stonybrook, Inc.,
The legislative history of the 1975 amendment to the mechanic's lien law is silent on the meaning of "owner" as used in
Thus, this court concludes United Bank is not an owner of the subject property within the meaning of
The consequence is that United Bank was not entitled to notice of the filing of plaintiff's mechanic's lien pursuant to
In General Electric Supply Co. v. SNETCO,
Roundhouse is, in fact, directly on point as it applies to United Bank in this case. In Roundhouse the court held that when the owner of property subject to a mechanic's lien did not have a right to a timely hearing, before or after the recording of the lien, to require the lienor to justify the lien, there was an unconstitutional deprivation of due process under the state and United States constitutions. Here United Bank does not have that right.
PDS points to language in Doehr to the effect that when a debtor-creditor relationship exists and the debt can be established by documentary proof, there is less constitutional necessity for a hearing.
Thus, this court is obligated to follow the holding of Roundhouse, and hold that the statute cannot constitutionally operate to give PDS' lien priority over United Bank's mortgage, unless the heightened property interest PDS has as a mechanic's lienor tips the constitutional scale in its favor.
c. The interest of the mechanic's lienor
The interest of the mechanic's lienor in the property is based on the services rendered and materials furnished in the construction of the building on the property. The contractor is vulnerable to subsequent encumbrances from the time he commences his work. Strong public policy justifies affording him the protection of a lien on the property, the value of which he enhances. Cook v. Carlson,
There is a sharp distinction between the property interest of plaintiff PDS here and the plaintiff in Doehr. The Doehr plaintiff had no existing interest in the defendant's CT Page 10321 real estate when he sought the attachment. His interest in the property was to ensure the availability of an asset to pay his judgment if he prevailed in the action. PDS, on the other hand, by constructing the building, added directly to the value of the property.
The Doehr court recognized the significance of this distinction. In footnote 4, after stating that its summary affirmance of Spielman-Fond (which upheld the constitutionality of the Arizona mechanic's lien law) was not entitled to full precedential value, it went on: "The facts of Spielman-Fond presented an alternative basis for affirmance in any event. Unlike the case before us, the mechanic's lien statute in Spielman-Fond required the creditor to have a preexisting interest in the property at issue. As we explain below, a heightened plaintiff interest in certain circumstances can provide a ground for upholding procedures which are otherwise suspect."
The concurring opinion of Justices Renquist and Blackmun picked up on that theme. It notes that workers who contribute their labor and material men who furnish materials to improve the property, cannot reclaim either their labor nor materials once it has become a part of the realty, and the mechanic's lien is the only remedy they have against property owners. The concurring opinion adds, "To require any sort of contested court hearing or bond before the notice of the lien takes effect would largely defeat the purpose of these statutes."
These comments of the Justices of the United States Supreme Court imply that there may be no necessity for a hearing before filing a mechanic's lien. This court need not decide that issue because here PDS has no right to a timely hearing even after the mechanic's lien filing. And in Roundhouse our Supreme Court found a denial of due process when there was not a right to a prompt hearing either before or after the recording of the lien.
Moreover, our Supreme Court in Roundhouse took into account the remedial intent of the mechanic's lien law (
Thus, this court concludes that the mechanic's lien law, to the extent that it were to operate to give priority of PDS' lien over United Bank's mortgage would violate the due process clause of the
A judgment of strict foreclosure may enter in favor of PDS; its debt is fixed at $253,872, plus interest accruing from January 24, 1991 to date. PPS is awarded attorney's fees in the amount of $20,000 and an appraisal fee of $4800. The law day is set as February 24, 1992 for Double RS, the owner of the equity of redemption, and subsequent dates for subsequent encumbrancers in inverse order of their priority. The order of priorities of encumbrances on the property is as follows:
1. United Bank and Trust Co., a/k/a Fleet Bank
2. PDS Engineering and Construction, Inc.
3. Eastern Sewer Pipe Corporation, d/b/a EPPCO
4. G R Valley, Inc.
5. Ronald Guimond, d/b/a Guimond Wallpaper and Paint.
ROBERT SATTER STATE TRIAL REFEREE
Korsunsky Krank Erickson Architects, Inc. v. Walsh , 1985 Minn. LEXIS 1096 ( 1985 )
Connecticut v. Doehr , 111 S. Ct. 2105 ( 1991 )
Barry Properties v. Fick Bros. Roofing Co. , 277 Md. 15 ( 1976 )
Brian Construction & Development Co. v. Brighenti , 176 Conn. 162 ( 1978 )
Bruni v. Behnke , 144 Conn. 181 ( 1956 )
Hillhouse v. Duca , 101 Conn. 92 ( 1924 )
Bankers Trust Co. v. El Paso Pre-Cast Co. , 192 Colo. 468 ( 1977 )
Aladdin Heating Corp. v. Trustees of Central States , 93 Nev. 257 ( 1977 )
Tripp v. Vaughn , 72 Utah Adv. Rep. 54 ( 1987 )
George A. Z. Johnson, Jr., Inc. v. Barnhill , 279 S.C. 242 ( 1983 )
Williams & Works, Inc. v. Springfield Corp. , 408 Mich. 732 ( 1980 )
State v. American News Co. , 152 Conn. 101 ( 1964 )
General Electric Supply Co. v. Southern New England ... , 185 Conn. 583 ( 1981 )
Mathews v. Eldridge , 96 S. Ct. 893 ( 1976 )
Roundhouse Construction Corporation v. Telesco Masons ... , 168 Conn. 371 ( 1975 )
State v. Stonybrook, Inc. , 149 Conn. 492 ( 1962 )
Bridgeport People's Savings Bank v. Palaia , 115 Conn. 357 ( 1932 )
Marchetti v. Sleeper , 100 Conn. 339 ( 1924 )
McKelvey v. Creevey , 72 Conn. 464 ( 1900 )
Blakeslee v. Board of Water Commissioners , 121 Conn. 163 ( 1936 )