DocketNumber: No. CV-90-0375968S
Citation Numbers: 1993 Conn. Super. Ct. 4155, 8 Conn. Super. Ct. 538
Judges: AURIGEMMA, J.
Filed Date: 4/28/1993
Status: Non-Precedential
Modified Date: 7/5/2016
The lien at issue in this case was filed on October 5, 1989 against lot 14 only, claiming the sum of $83,391.65 CT Page 4156 for services rendered and materials furnished in the "improvement of any lot and in the site development and subdivision of the plot of land." On the same date Butch filed two other virtually identical mechanic's liens on 13 lots in the Pheasant Farms Subdivision, and the other on 4 lots in that subdivision. Each lien claimed the same $83,391.65 due for the same work, commenced and completed on the same date for the same project.
Butch claimed at trial that the mechanic's liens covering 17 lots in the subdivision had been extinguished by the foreclosure of the first mortgage on those lots. He claims that the entire $83,391.65 for work which was done on or for the benefit of all 18 lots constitute a lien on lot 14 and seeks to foreclose that lien.
The defendants claim that the lien is barred by the provisions of
Section
Sec.
49-33 . Mechanic's lien. Precedence. Rights of subcontractors. (a) If any person has a claim for more than ten dollars for materials furnished or services rendered in the improvement of any lot or in the site development or subdivision of any plot of land, and the claim by virtue of an agreement with or by consent of the owner of the land upon which the building is being erected or has been erected or has been moved, or by consent of the owner of the lot being improved or by consent of the owner of the plot of land being CT Page 4157 improved or subdivided, or of some person having authority from or rightfully acting for the owner in procuring the labor materials, the building, with the land on which it stands or the lot or in the event that the materials were furnished or services were rendered in the site development or subdivision of any plot of land, then the plot of land, is subject to the payment of the claim.
Prior to 1974, Section
In 1974 Public Act No. 74-310 expanded the scope of Section
In Pomarico, the defendant had performed grading, paving and other work necessary to complete a roadway, and water and sewer lines for a subdivision. The defendant filed a blanket lien upon thirteen lots within the subdivision. Some of the lots had already been built upon and sold by the plaintiff. The Court held that the defendant was entitled to lien all the subdivision lots without identifying the specific work done for each lot because the work was of value to all lots in the subdivision and the lien "falls within the site development purview of General Statutes
The 1974 amendment to
The Connecticut Supreme Court has interpreted
In Ginsberg a defendant lienor supplied materials for two houses on one lot. He filed a mechanic's lien against the entire property for the amount due on both buildings. The court found that the buildings were separate and distinct pieces of property and held that the lien was invalid because it failed to accurately reflect the amount of materials furnished to each separate property.
The plaintiff in this case was entitled to file a blanket lien against the entire subdivision without stating an allocation of services or materials. The court in Pomarico upheld such a lien under the site development purview of
The statute clearly differentiates between improvements to a "lot" and site development of a "plot" of land. There is a presumption of purpose behind every sentence, clause or phrase, and no word in a statute is to be treated as superfluous. Beloff v. Progressive Casualty Ins. Co.,
Under the language of
The mechanic's lien is a creature of statute. therefore, a lienor must comply with statutory requirements in order to perfect his claim. H S Torrington Associates v. Lutz Engineering Co.,
It is clear from the evidence presented at trial that much of the work performed or materials supplied by the plaintiff did not constitute improvements to lot 14. The plaintiff did not attempt to allocate any amounts specifically to lot 14. Absent proof of services rendered or materials furnished which constituted improvements to lot 14, the court cannot enforce the lien against that lot.
The defendants' other arguments against the validity of the lien lack merit. The defendants claim that the amounts they paid to the original owner of lot 14 constitute "good faith" payments which exceed the amount of the lien and which invalidate the lien. Under the language of
The lien is not invalidated by the plaintiff's failure to give the first mortgagee, Northeast Savings, notice of intent to claim a mechanic's lien or to serve a copy of the CT Page 4160 mechanic's lien certificate on Northeast Savings. Legal title in a mortgagee does not make the mortgagee an owner within the scope of the mechanic's lien statute. PDS Engineering
Construction, Inc. v. Double RS a/k/a Double RS Partnership, et al,
The mechanic's lien is valid only with respect to services rendered and materials furnished on the property on which the lien is claimed, lot 14. The court will give the plaintiff an opportunity to prove those amounts at a subsequent hearing at a time mutually agreeable to the court and the parties.
By the Court
Aurigemma, J.