DocketNumber: No. CV 91-0055194
Judges: PICKETT, J.
Filed Date: 1/30/1991
Status: Non-Precedential
Modified Date: 7/5/2016
The Petitioner Iroquois Gas Transmission System, Inc. of CT Page 120 Connecticut ("Iroquois, Inc.") is a Delaware corporation wholly owned by Iroquois, which acts as Iroquois' agent, specifically with respect to acquisition of the Connecticut portion of the right-of-way. Iroquois, Inc. is a co-holder of the FERC certificate along with Iroquois for this purpose.
This petition is brought pursuant to C.G.S. Section
The line is scheduled to be completed by January 1, 1992. To meet this completion date, construction must be underway in Connecticut by June 1, 1991. Delay of the start of construction beyond June 1st would mean that gas to be transported by Iroquois would not be available for the 1991-92 heating season in Connecticut. Connecticut's natural gas companies would be forced to increase their reliance on uneconomic substitutes, to the extent such substitutions are available, greatly increasing their ratepayer's costs; and might even be required to curtail deliveries to their customers. Moreover, any such delay could significantly increase the cost of building the pipeline, and therefore the ultimate cost of transporting the gas.
To begin construction by June 1, 1991, Iroquois must be able to complete its surveys and acquire the right to commence construction now. In this case, the landowner has refused to grant Iroquois even the access necessary to complete the environmental and centerline surveys, which Iroquois must complete before it can refine the location of its right-of-way and complete its construction planning. It is clear that access cannot await a determination of damages in these cases. Moreover, there will not be sufficient time for Iroquois to complete the proceedings for acquiring title by eminent domain to these and other properties which must be condemned, and for a court to determine the damages due, before construction must commence.
The Petitioner accordingly has invoked two state statutes CT Page 121 which provide two independent bases for the immediate relief it seeks — C.G.S. Sec.
The immediate entry right is available both to allow a condemnor access to a property for the purpose of completing surveys necessary to specifically identify the location of a right-of-way to be taken, Northeastern Gas Transmission Co. v. Benedict,
The Connecticut portion of the Iroquois pipeline will be 24 inches in diameter, and made of one-half inch thick steel. Except for valves, sales meter stations, and some other appurtenant facilities, all of the pipeline facilities will be buried underground. The permanent right-of-way through Connecticut will generally be fifty feet wide. Iroquois will also required temporary construction rights for an additional twenty-five to fifty feet of right-of-way. Construction would involve nine sequential operations: clearing and grading of the right-of-way; trenching; stringing; pipe installation; backfilling; clean up and temporary erosion controls; hydrostatic testing; commissioning activities; and final clean-up and restoration. The full width of the construction right-of-way is necessary to accommodate these activities and to minimize or eliminate off right-of-way damages.
Pipelines can be constructed economically only if work crews can move along the length of a complete right-of-way, to perform their various operations in a smooth, continuous sequence. If the crews cannot move continuously along the right-of-way, but must CT Page 122 skip sections of it, and then return, the company pays a substantial penalty in time and expense.
Implicit in the issuance of FERC's Certification of Public Convenience and Necessity is a finding of public need for a supply of natural gas which the plaintiff is in a position to make available, and the economic feasibility of the project approved. Algonquin Gas Transmission Co. v. Coleman,
Further, the need of Iroquois and its shippers to avoid costs from delay and interruption of construction continuity would alone require a grant of immediate entry. Immediate entry will be granted to enable a pipeline company to avoid cost increases associated with delay and to meet contract commitments for the delivery of gas by a stipulated date. Algonquin Gas Transmission Co. v. Coleman,
Sections
[u]nder Federal Law, such companies are granted a right of condemnation, but the exercise of that right so far as the determination of damages is concerned, is confined to the Federal courts where jurisdiction is limited to condemnation involving damages of $3,000.00 or more. As the average damages for a right-of-way over a single piece of property would be less than $3,000.00, it is necessary to make possible the CT Page 123 construction of natural gas pipelines in Connecticut that the State courts be made available.
Accordingly, the legislature granted the right of eminent domain to "any corporation. . ." which holds a certificate of public convenience and necessity issued pursuant to the Federal Natural Gas Act. C.G.S. Section
Although the Connecticut act was clearly intended (according to its Statement of Purpose) to apply to any "natural gas company" which held a certificate under the Natural Gas Act and the federal act defines both a "natural gas company" and a "corporation" to include partnerships [
The same reasons which justify the grant of an order of immediate entry support the issuance of an order pursuant to Section 4046 of the Practice Book, terminating the automatic stay which would otherwise come into effect upon the taking of an appeal because the due administration of justice so requires.
In Northeastern Gas Transmission Co. v. Benedict,
When a motion to terminate a stay of execution is filed before judgment, it may be ruled upon when judgment is entered, thereby avoiding the stay which would otherwise be in effect until the time within which an appeal could be taken had expired. CT Page 124 Practice Book Section 4046. Accordingly, the court has provided in its order granting immediate entry that the petitioner's motion to terminate stay of execution is also granted.
For the reasons stated the application for immediate entry is granted, conditioned upon the petitioner's deposit with the court' of the sum of $92,000.00 which deposit will be applied according to said statutes; it is further ordered that the due administration of justice requires that the execution of this order not be stayed by appeal.
PICKETT, J.