DocketNumber: No. 549374
Citation Numbers: 1999 Conn. Super. Ct. 16341
Judges: CORRADINO, JUDGE.
Filed Date: 12/20/1999
Status: Non-Precedential
Modified Date: 7/5/2016
The defendants have filed a motion for summary judgment claiming there was a failure to comply with the requirements of the Home Improvement Act §
The defendants have filed a motion for summary judgment based on the alleged noncompliance with the provision of subsection (7) of §
The defendants argue that because the proposal fails to set forth a starting and completion date as required by §
The plaintiff argues that under the circumstances as existed here, there was compliance with the act. Mr. Caulkins submitted an affidavit claiming that on April 14, 1997, he and the Triebs met to review a proposed contract. He claims the terms of the contract were discussed "including the specific issues of starting and completion dates, as all were aware that these dates were required elements of the contract." The affidavit goes on to say that firm dates would not be given "because full permitting was not yet available and the scope of the project was still unclear due to incomplete architectural plans. . . ." The Caulkins' affidavit goes on to say that "nevertheless," the Triebs wanted the plaintiff to begin work "and as a result, the portions of the contract which related to starting and completion dates were typed in as ``not available' being the only specification of starting and completion dates. The Triebs were aware of and consented to this form of contracting at the time of our meeting and executed the contract as such." The Triebs do not CT Page 16343 contest these just mentioned factual allegations but argue that despite these claims the act was not complied with.
The plaintiff also argues that apart from the strict question of compliance with the act it has presented a question of fact as to whether the defendants have knowingly and voluntarily waived the requirements of the act with respect to including a specific and firm starting and completion date in the contract proposal. Finally, the plaintiff argues that it has raised a question of fact as to whether the defendants have made a bad faith invocation of the protections of the act.
Regarding the waiver issue, the second Trieb affidavit states when he signed the proposal, Mr. Trieb was unaware of the provisions of the act and that he was signing a "home improvement contract."
He states that he did not know the act required a commencement and completion date and that their absence would entitle him to invalidate the contract. He first learned of the act's requirements from his attorney several months after signing the proposal.
The rules applicable to deciding a motion for summary judgment are well known. A court cannot grant such a motion if a genuine material issue of fact must be decided. A party has a constitutional right to a jury trial. On the other hand, if no genuine issue of material fact exists and the dispute between the parties can be decided as a matter of law, it should be so decided to prevent the continuation of litigation that is not meritorious.
The language of the act is mandatory in nature. Certain provisions "shall" be complied with under subsection (a) to §
The plaintiff argues that this case should be distinguished from Rizzo because as noted the date issue was discussed, the parties realized no such dates could be set forth at the time the contract was signed, "the law does not require one to perform the impossible," "not available was the best that could be done under the circumstances." (Page 7 of plaintiff s brief).
But this act posits the notion of an unsophisticated homeowner dealing with an experienced business person engaging in these contracts for a living and well aware of factors such as the time it takes to complete jobs, get permits, receive materials, etc. Given this scenario, the dangers to the consumer presented by absence of firm commencement and completion dates still exist even though their absence and the "reasons" therefore were brought to the homeowner's attention by the contractor and even though after the "conversation" between the homeowner and experienced businessperson the homeowner wants work to start without firm dates.
Taking an overview of the purposes of the act, but still mindful of fairness to the contractor, it makes more sense to say what the legislature made clear. Firm dates must be set forth. If the contractor is still pressed by the homeowner to begin work even though no such firm dates can be indicated through no one's fault, then the solution is easy. Let the contractor secure a written waiver from the homeowner of his or her rights under the act, specifically the right to have a commencement and completion date, cf. Wadia Enterprises, Inc. v. Hirschfeld,
The result of all this is that where the act is not literally complied with, there is a presumption that the contractor cannot bring suit against the homeowner. The contractor can overcome this presumption only if waiver or bad faith is proved and on these matters the contractor has the burden of proof. CT Page 16345
The final way in which the plaintiff contractor seeks to distinguish Rizzo is to say that in that case the plaintiff contractor did not even attempt to begin construction for a year after the contract was made, whereas in this case, a significant amount of the addition had been built and substantial payments had been made to the plaintiff. But equities of that nature will not forestall the strict application that the provisions of the act explicitly require, or, to be more exact, force a strained interpretation of statutory language that is intended to be remedial. Thus, subsection (a)(1) of §
The court concludes that there has not been compliance with the provision of §
As previously noted, the Triebs attempt to rely on this language by an affidavit wherein Mr. Trieb said he did not know that his contract was a home improvement contract, did not know the act required the requisite dates, and did not know of his right to invalidate the contract if the starting and completion dates were not included in the contract proposal. In purely linguistic terms, the defendants appear to have a strong argument. How could they have waived their rights under an act whose existence they were not aware of at the time they signed the contract. The plaintiff does not dispute by affidavit or otherwise that the Triebs were unaware of the act, its provisions, and their rights under the act so summary judgment for the defendants would seem to be in order.
However, an unrefuted statement in the contractor's affidavit causes this court, at least, some concern. In paragraph 5 of the Caulkins' affidavit, it refers to the point at which the contract was signed and says: "At the time of this meeting, the terms of the proposed contract were discussed, including specific issues CT Page 16347 of starting and completion dates, as all were aware that these dates were required elements of the contract." Why doesn't this present a genuine issue of material fact? In other words, given this statement, its most favorable inference, as the court must, does not this statement allege that the Triebs were made aware that without the dates there would be no enforceable contract, but being aware of that as the affidavit goes on to say they nevertheless told the contractor to proceed with the work which it did to their alleged benefit? Should waiver not be found because the magic words, "Home Improvement Act," were not mentioned? In other words, if these people were told, in effect, that they had rights the act provided them, but were not told the source of those rights, is not the ameliorative purpose of the act satisfied? If knowing their right they still chose to have the contractor go on with its work why wouldn't that be a waiver?
A position contrary to this would almost be tantamount to saying there should be no waiver permitted under such an ameliorative act?
On the other hand, the court is reluctant to make a ruling in this case based on the waiver argument. Given the ameliorative purposes of the act, waiver under the circumstances alleged here would have to be strictly proved. It must be shown that the defendants were explicitly told that contract formation required the necessary dates and that they chose to have the work proceed. Perhaps it could even be argued that given the act's requirements of a written contract (§
The court, however, upheld the trial court's rejection of the three bad faith claims made. The contract was defective because it did not contain a cancellation provision (see §
The second bad faith argument was equally unavailing. No bad faith could be found where the homeowners initially enforced the contract and then subsequently asserted the contract's invalidity as a defense. The court noted that the plaintiff contractor did not allege the homeowners knew of the violation earlier or purposely had it drafted in violation of the act to leave an escape hatch against the contract's enforcement. The homeowners' affidavits claiming they did not know of the act prior to suit was not challenged so it could hardly be claimed that assertion of the invalidity of the contract was made in bad faith. Finally, the court rejected the notion that since bad faith was a question of fact, rejection of the defense could not occur by way of summary judgment,
In Dinnis v. Roberts,
The contract was defective in that it contained no cancellation provision or starting or completion date in violation of subsections (a)(6) and (c)(7) of the act. The court noted that the homeowners claimed they had no knowledge of the provisions of the act prior to consulting an attorney (and presumably before any work was done). The Dinnis court, relying on the facts before it, did not feel obliged to decide whether the bad faith exception is limited to instances of bad faith relating to the formation of, or inducement to enter into a home improvement contract. The court specifically declined to extend the bad faith exception beyond these perimeters,
What concerns the court here is what concerned it in the waiver argument. The court must give the contractor's affidavit its best reading and there it is claimed that these homeowners were told about starting and completion dates and all contracting parties "were aware that these dates were required elements of the contract." Paragraph. 5 of Caulkins' affidavit. A possible inference of this statement is that although the homeowners were not aware of the act at the time of contract formation, and there is nothing to rebut their affidavit to that effect, they were made aware of the fact that a valid contract could not otherwise be entered into without the necessary information concerning starting and completion dates. The court at this time will not rule as a matter of law that under such circumstances a bad faith argument cannot be raised by the contractor. In other words, we have a homeowner who seeks to rebut the bad faith argument where a contractor had done substantial work, by claiming the contract to do the work violated the act and was void ab initio and the homeowner did not know of the act and its provisions.
But despite lack of knowledge of the act, the homeowner is alleged to have been made aware of the fact that the contract might not be valid for the very same reasons that would have voided it under the act and just did not know these reasons also CT Page 16350 violated the act. To permit the homeowner to rebut the bad faith argument under these circumstances, because the act itself was not known to the homeowner, would be little more than a homage to formalism having little to do with consumer protection. In any event, without a full exploration of the relevant conversation at the time of contract formation, the court will not grant the defendant's motion for summary judgment.
Corradino, J.