DocketNumber: No. CV00 033 85 14 S
Citation Numbers: 2002 Conn. Super. Ct. 1054
Judges: WHITE, JUDGE.
Filed Date: 1/25/2002
Status: Non-Precedential
Modified Date: 4/18/2021
The parties' claims were tried to the court on October 2, 2001. After considering all evidence offered at trial as well as the arguments of counsel the court finds against the plaintiff and for the defendant on sole count of the complaint. The court further finds for the defendant and against the plaintiff on the defendant's counterclaim to the extent that the defendant seeks a judgment for payment of three months rent plus a five percent late fee. The court, however, does not award judgment to the defendant for reimbursement of the $3,500.00 broker's fee, attorney's fees or any statutory interest.
Prior to the start of the lease term the plaintiff read the written least and inspected the leased premises while accompanied by her father, her step-mother and Brown. In addition, the plaintiff received the keys to the leased premises and had uninhibited access to it. Although the plaintiff enjoyed possession of the leasehold both before and after July 1, she did not return the signed lease to the defendant until July 12, 1999. One week after returning the written lease to the defendant the plaintiff, who had planned to renovate the premises, became concerned with the condition of the floor and arranged near the end of July to have the premises inspected by a civil engineer named George Jerves. Despite the plaintiffs concern about the floor, she wrote a check on July 27 for the August rent.
Jerves inspected the first floor and its supporting structure in the basement in the last week of July and issued a written report dated August 2, 1999. The plaintiff received a copy of the report as did her attorney, Patrick Crehan. As a result of the inspection Jerves determined that there were structural problems with the premises, that the premises were in violation of the State Building Code and that there was no danger that the first floor would collapse. Jerves found that the building could be brought into compliance with the Code and made safer if certain inexpensive remedial actions were taken. The plaintiffs contractor estimated that it would cost $2,750.00 to make the necessary repairs.
Crehan then wrote a letter dated August 9, 1999 to the defendant about the structural problem and also spoke about it with Jerry Sullivan, the defendant's attorney. Crehan subsequently telephoned the defendant to discuss the problem in the second week of August while the defendant was on vacation in Cape Cod, Massachusetts. At that time, the defendant told Crehan that the defendant would have his own engineer inspect the premises and have his own contractor estimate how much it would cost to remedy the structural problem. During the third week of August, after the defendant returned from vacation, his engineer verified that there was a CT Page 1057 structural defect and his contractor estimated that it would cost $850.00 to repair. At the time that the defendant's engineer inspected the premises neither the defendant nor his engineer had a copy of Jerves' report. In the last week of August the defendant notified Crehan about the engineer's findings, his contractor's repair estimate and indicated his willingness to make the necessary repairs at his own expense. The defendant also offered to arrange a meeting between Crehan and the contractor regarding the estimated repairs. Notwithstanding the defendant's agreement to remedy the structural defect at his own expense, as required by the contract, the plaintiff moved out and failed to pay any rent for September and for subsequent months.
When the plaintiff refused to pay rent for September, October and November the defendant re-rented the premises to another tenant for the months of December, 1999 through April, 2000 when the property was sold. He has the $10,500.00 security deposit paid by the plaintiff to cover the unpaid rent for the period between September and November. The new tenant paid the defendant the same $3,500.00 per month rent for the months of December through April. The defendant, a real estate broker who was familiar with the real estate market in New Canaan where he has worked since 1967, used another broker to find a replacement tenant in lieu of finding one himself. Additional facts will be provided as necessary.
A lease is a contract. Cohn v. Fennelly,
138 Conn. 474 ,476 ,86 A.2d 183 . In construing it, three elementary principles must be kept constantly in mind: (1) The intention of the parties is controlling and must be gathered from the language of the lease in the light of the circumstances surrounding the parties at the execution of the instrument; (2) the language must be given its ordinary meaning unless a technical or special meaning is clearly intended; (3) the lease must be construed as a whole and in such a manner as to give effect to every provision, if reasonably possible. Perkins v. Eagle Lock Co.,118 Conn. 658 ,663 ,174 A. 77 . Ingalls v. Roger Smith Hotels Corporation,143 Conn. 1 ,6 ,118 A.2d 463 (1955); Lonergan v. Connecticut Food Store, Inc.,168 Conn. 122 ,128 ,357 A.2d 910 (1975); Collins v. Sears, Roebuck CT Page 1058 Co.,164 Conn. 369 ,373-74 ,321 A.2d 444 (1973); Perruccio v. Allen,156 Conn. 282 ,285 ,240 A.2d 912 (1968). (Internal quotation marks omitted.)
The language of the contract establishes the intent of the parties to require the defendant "to make any changes at its own expense upon receipt of notice of non-compliance . . . from the [plaintiff] . . . of [structural] defects. . . ." When the defendant received notice of the structural defect in the middle of August 1999 he verified its existence and arranged for a contractor to estimate the repair cost. The defendant fully intended to fulfill his obligation under the contract and was prepared to do so within two weeks of receiving notice from Crehan. The plaintiff argues that the defendant had an obligation to act immediately to cure the structural defect when Crehan called him in Cape Cod, and that by the end of August it was too late for the defendant to carry out his obligation under the lease. The plaintiff further argues that this delay, coupled with the defendant's failure to directly notify the plaintiff of his efforts to take remedial action, constitutes a breach of contract by the defendant. The court disagrees.
The contract states that the defendant was required to remedy the structural problem "upon receipt of notice" from the plaintiff It does not indicate that time is of the essence, nor does it state an outside time limit for performance. The contract language must be interpreted in light of reason and the surrounding circumstances. When a contract does not indicate that time is of the essence, then a failure to perform immediately does not necessarily constitute a breach. See Kakalik v.Bernardo,
The plaintiff by her own testimony admitted that she failed to pay rent for the months of September, October and November of 1999. Had she paid, the defendant would have received from her a total of $10,500.00. At the time of her failure to pay she had no legally justifiable basis for refusing to perform her contractual obligation and she has failed to offer one. As has already been indicated, the defendant acted reasonably in regard to his obligation to fix the structural problem. Even if, however, his actions were not reasonable the plaintiff still had an obligation to pay rent. The covenants of a lease are independent and the defendant's alleged failure to perform did not excuse the plaintiff from her obligation to pay rent. The Supreme Court said in In re Edgewood ParkJunior College, Inc.,
In addition to the three months rent at $3,500.00 per month, the defendant is entitled to recover late fees in the amount of $525.00. The parties' agreement allows the defendant to collect a five percent late fee for each rental payment that is more than ten days overdue. The rent installments due for September, October and November of 1999 are far more than ten days late and the defendant, therefore, may recover the late charges due under the terms of the contract.
The defendant is not, however, entitled to recover the $3,500.00 broker's fee he allegedly paid. The credible evidence shows that the defendant failed to mitigate this claimed element of damages. He was a real estate broker in New Canaan since 1967 and was familiar with the local real estate market. He did not need to employ the services of another broker to find a new tenant because he could have and reasonably should have found a tenant himself Under the circumstances the court does not find it credible that the defendant used another broker to do what he CT Page 1060 could have easily done himself In addition the defendant is not entitled to recover attorney's fees because he has provided no statutory, case law or other justification for receiving such fees.
Finally, the court refuses to award the defendant the statutory interest he seeks pursuant to General Statutes §
White, J.
In Re the Dissolution of the Edgewood Park Junior College, ... , 123 Conn. 74 ( 1937 )
Collins v. Sears, Roebuck & Co. , 164 Conn. 369 ( 1973 )
Central New Haven Development Corporation v. La Crepe, Inc. , 177 Conn. 212 ( 1979 )
Perkins v. Eagle Lock Co. , 118 Conn. 658 ( 1934 )
Sagamore Corporation v. Willcutt , 120 Conn. 315 ( 1935 )
Lonergan v. Connecticut Food Store, Inc. , 168 Conn. 122 ( 1975 )
Cohn v. Fennelly , 138 Conn. 474 ( 1952 )
Perruccio v. Allen , 156 Conn. 282 ( 1968 )
Ingalls v. Roger Smith Hotels Corporation , 143 Conn. 1 ( 1955 )