DocketNumber: No. X06-CV-94-0155982 S
Judges: McWEENY, JUDGE.
Filed Date: 11/15/2002
Status: Non-Precedential
Modified Date: 4/18/2021
Evergreen Woods is owned and operated by Shoreline Life Care, LLC, the successor to Shoreline Care Limited Partnership (Shoreline), the plaintiff in this action. Shoreline complains in the fifth amended complaint that the defendants negligently designed and installed what it perceives is a defective heating, ventilating and air conditioning system (HVAC) at Evergreen Woods
The defendant Weitz Company, Inc. (Weitz) contracted with Shoreline on October 5, 1989, to provide "general contractor services" with respect to Phase I of the project, and subsequently contracted with Shoreline on April 30, 1991, to perform similar services for Phase II of the construction. These contracts represented the agreement between Shoreline and Weitz relating to the construction and installation of Evergreen Wood's HVAC system.
The Phase II agreement contained a clause providing that any controversies or claims arising out of the agreement would be settled by arbitration. The Phase I agreement did not contain any arbitration clause.
Weitz hired a subcontractor, Janazzo Heating Air-Conditioning (Janazzo), to install the HVAC system. Following the commencement of this CT Page 14654 litigation, Weitz sued Janazzo, and Janazzo remains a third-party defendant in the action.
Shoreline hired Technical Planning Associates, Inc. (TPA) as its architect for Phases I and II of the project. TPA is not a party to this litigation. TPA hired the defendant Jansen Rogan Consulting Engineers, P.C. (Jansen Rogan) to provide mechanical and electrical engineering consulting services on the project.
Weitz completed its work in December of 1992 and was paid in full by Shoreline.1 Shoreline subsequently became aware of what it perceived as defects and inadequacies in the HVAC system, and made claims against Weitz. Following court intervention, Weitz and Shoreline arbitrated the Phase II disputes, but not those involving Phase I. In a memorandum of decision dated July 17, 2000, this court granted, on the basis of res judicata, Weitz' motion for summary judgment on all claims arising out of the Phase II contract. Accordingly, as to Weitz, this litigation is limited to Shoreline's complaints with respect to the Phase I contract.
Shoreline's claims against Weitz are contractual in nature, while its complaint against Jansen Rogan is based on allegations of negligence arising from an alleged breach of the standard of care applicable to the design of a life care facility.
At trial, Shoreline introduced a substantial amount of evidence regarding the problems experienced with maintaining adequate heat in the facility and with the air balancing of the system.2 Shoreline established that the HVAC system lacks sufficient capacity to maintain a desirable level of heat throughout the facility. Certain areas within the facility, including the entryways, vestibules and the nursing wing corridor, lacked any heat source upon completion of the construction in suit. Shoreline also established that there was improper installation of the HVAC system in the links between the buildings comprising Evergreen Woods, inasmuch as no insulation was applied in certain areas.
This litigation has continued to this date due to the difficulty in assigning responsibility for these problems. The complaints about the Evergreen Woods' HVAC system center on maintaining an appropriate level of heat in a life care facility in light of, or in spite of, the type of system installed. At the time this litigation commenced, Evergreen Woods was heated by an air to air electric heat pump system. The electric heat pump system is the cheapest heating system to install, but the most expensive heating system to operate.
In its claim for damages, Shoreline seeks all costs of retrofitting CT Page 14655 Evergreen Woods with a gas powered heating system. Shoreline already has renovated the facility by installing two new gas-fired central boiler units to provide heat in the hallways and patient rooms in each of the nursing wings, and seeks to recover all costs incurred. Shoreline also claims damages for the repair of frozen sprinkler pipes in the links between the buildings and in other common areas. Interest, costs and expenses of litigation also are claimed.
David Reis is the principal of Shoreline. Evergreen Woods represents Mr. Reis's first embarkment into the construction of a life care facility. In the years since undertaking the Evergreen Woods project, Mr. Reis has successfully developed a number of other life care communities.
Shoreline failed to prove at trial that it elected to install an electric heat pump system, as opposed to other available HVAC systems, based on any representation by Weitz about the HVAC system installed at Essex Meadows. The evidence instead demonstrated that Mr. Reis preferred an electric rather than gas heat source because of his perception that older residents would be uncomfortable having a gas heat source in their apartments, and because of budgetary concerns about the higher CT Page 14656 installation cost of a gas-powered system. The court finds that Shoreline's decision to install an electric heat source was made independently, and was not decided on the basis of any representations by Weitz.
Shoreline also failed to demonstrate that an electric system was not a viable system for a Connecticut facility. Gary DeFillippo, as Shoreline's expert, testified that a properly installed electric system would perform well in Connecticut. Shoreline's lender retained its own consultant, Levien, Rich Company (Levien-Rich), to evaluate the HVAC system and found it appropriate, although perhaps somewhat undersized. Shoreline's architect, TPA, approved as a reasonable choice the use of electric air to air heat pump units, and Jansen Rogan's engineer recommended such a system.
Accordingly, the court finds that Weitz has no contractual liability with respect to Shoreline's decision to use an electric heat pump system.
The air balancing process as described at trial is accomplished by measuring air flow at a given outlet and comparing it to the design criteria for air flow at that outlet. This process was not designed to prevent the defect that Shoreline is complaining about, being an overall negative pressurization in the system, combined with an inadequate amount of heat.
Shoreline also relies on testimony from its air balancing expert, Richard Wing, that the HVAC system had substantial leakage which was due to improper installation. However, the sample data on which Mr. Wing relied at trial does not calculate the system loss or properly attribute any loss to difficulties in the installation of the system. Shoreline CT Page 14657 also failed to establish that any pressurization problems existed in the Phase I south neighborhood residential apartments air balanced by its subcontractor, Janazzo.
Weitz' deviation from its obligation to use an independent certified balancer was waived by Shoreline through its architect, Brian Ameche.Wadia Enterprises, Inc. v. Hirschfeld, supra,
The Phase II contract, however, did not contain identical general conditions, requiring "actual knowledge" by the general contractor. The Phase II arbitration award (Plaintiff's Exhibit 612) also does not contain a finding that Weitz had actual knowledge of design deficiencies. A review of the arbitrators' findings, specifically, finding number three, clearly relies on a standard of what "should have been known" to constitute chargeable actual knowledge. That is not the standard in the contract before this court and is not binding in this proceeding.
Moreover, the lender's independent engineer, Levien-Rich, reported CT Page 14658 design deficiencies as early as February 9, 1990, by letter advising Mr. Reis that the HVAC system was, perhaps, undersized. The architect and project design engineer, Jansen Rogan, re-certified the system and proceeded with the project without any change in the HVAC system. It is difficult to imagine that a different result would have followed a complaint by Weitz regarding the same problem. As noted above, the basic design decision concerning electric air to air heat pump versus a gas-fired system was made by the owner taking into consideration client concerns and budgetary constraints. Shoreline has not met its burden of proving that Weitz had actual knowledge that the system was in any way inadequate.
At trial, Shoreline did not point to any term in the contract calling for value engineering by the general contractor, nor was any other writing made evidence that the HVAC system would be engineered by Weitz, in the absence of an evaluation by Shoreline's architect or engineer. Mr. Reis testified that "at the end of the day all the value engineering . . . we really went into the job below budget." The court finds that Weitz performed a value analysis satisfactory to the owner, and it had no contractual obligation beyond that to independently redesign the HVAC system. Accordingly, Shoreline has not proven breach of any contractual duty by Weitz with respect to value engineering. CT Page 14659
Shoreline concedes that it has not specifically broken down damages claimed between Phases I and II; instead, it seeks a proportional breakdown of damages. The problem with that approach is apparent when one considers that the major construction deficiency is the absence of insulation. Failure to insulate primarily occurred in the links. Two of the three links in question are part of the Phase II contract, which with respect to Weitz is not part of this litigation.
The court finds that as to Weitz, Shoreline has failed to prove its damages arising from construction deficiencies with respect to Phase I of the project. Accordingly, the fifth amended complaint against Weitz is hereby dismissed. Inasmuch as Janazzo is in the case only in response to Weitz' third party complaint, the third party complaint also is dismissed.
Shoreline proved at trial that the HVAC system designed by Jansen Rogan fails to provide heat in the nursing wing hallways and sufficient heat in the nursing wing patient rooms; provides inadequate heat in the pool area locker rooms and the hallways leading to the pool; fails to heat the main entrance vestibule to the community building; and fails to provide heat sources in the elevator equipment rooms.
Jansen Rogan argues that Shoreline failed to provide an expert opinion from a licensed professional engineer regarding the standard of care owed by the engineer to Shoreline. The court finds that Gary DeFillippo, as Shoreline's expert, though not a licensed engineer, is an experienced mechanical contractor whose testimony was sufficient to establish the obligation of the mechanical engineer, and the failure of Jansen Rogan to comply with that duty. CT Page 14661
As a result of Jansen Rogan's negligence, Shoreline incurred the following expenses, which are reasonably included in its damages:
(1) payments to Enterprise Builders for the installation of gas-fired central boiler units to provide heat in the hallways, in-patient rooms and in each of the nursing wings — $84,789.60;
(2) installation of radiant heating panels in locker rooms and hallways leading to the pool — $6,639;
(3) installation of a heated air curtain system in the main entrance vestibule in the community building — $10,931.38; and
(4) addition of heat in each elevator equipment room — $1,494.
The remaining problems that Shoreline demonstrated with respect to the under-sizing of the heating system do not require Shoreline's demanded remedy, which would be a substantial upgrade utilizing a gas powered heating system. Jansen Rogan's expert witness, Michael Salamone, proved that the system could be enhanced to meet all code requirements with respect to heating. According to Mr. Salamone, introducing coils to existing ductwork and replacing existing units with units of slightly larger capacity where needed could be accomplished for a total estimated cost of $125,000.
Accordingly, the court awards damages to Shoreline and against Jansen Rogan as follows:
(1) Gas-fired central boiler units $84,789.60
(2) Radiant heating panels in pool area 6,639.00
(3) Heating elevator equipment rooms 1,494.00
(4) installation of a heated air curtain system in the main entrance vestibule in the community building 10,931.38
(5) Cost to have system meet code heating requirements 125,000.00 ___________
Total Damages: $228,853.98 CT Page 14662
All other demands by Shoreline are denied.
So ordered this 15th day of November, 2002.
___________________, J. ROBERT F. McWEENY