DocketNumber: No. CV 98-042 1694
Judges: PITTMAN, JUDGE.
Filed Date: 8/4/1999
Status: Non-Precedential
Modified Date: 4/17/2021
The services of the defendant were retained in 1996 to repair a culvert carrying a stream beneath the surface of the land located at 2425 Dixwell Avenue, Hamden, CT. A restaurant, the Dutchess Restaurant, was in operation on the site. The collapsed culvert ran below the parking area, so that the restaurant remained open but with only limited parking. Bids were invited to repair the culvert and repave the parking lot.
The defendant submitted a written bid for the job on September 30, 1996. On October 7, 1996, a standard American Institute of Architects form contract for the work was entered into with a contract price of $193,400. The contract referred to the obligated parties as the "owner" and the "contractor." There is no dispute that the "contractor" was Neri Corporation, and the contract was signed on behalf of Neri by Kimberly Neri, treasurer, as the authorized agent for Neri.
The "owner" portion of the contract listed the following: the owner's agent Barry I. Steinberg, P. E., the "property owner" Harry Kruger, and the "restaurant owner" Shaun Lavin. The contract is signed "Barry I. Steinberg, P.E., Agent for the Owners." In fact, the restaurant was owned by Dutchess of Dixwell Avenue, Inc., to which no reference was made anywhere in the contract. Shaun Lavin was a 25 % owner of the corporation.
The contract contained an arbitration clause providing that any controversy or claim arising out of or related to the contract was to be settled by arbitration. AIA Contract 6 4.5.1. It also contained a provision obligating the contractor to "maintain the operation of the existing drive-thru between the hours of 11:00 a.m. and 3:00 p. m. each day unless permitted by the Restaurant Owner." CT Page 10682
After the construction was completed, the contractor claimed that additional work had been necessary for which compensation was due. The property owner denied that any further money was owed. The contractor demanded arbitration of Harry Kruger and Shaun Lavin. The demand was filed with the American Arbitration Association ("AAA") on June 9, 1998. On July 9, 1998, Harry Kruger and Shaun Lavin filed an answer with AAA denying the allegations of the claimant. Also included in their papers was a counterclaim on behalf of Duchess of Dixwell Avenue, Inc. Duchess alleged that it was a third party beneficiary of the contract and that it was owed money as a result of the contractor's delay or interference with its business during construction. The contractor opposed the inclusion of the counterclaimant in the arbitration process, and the counterclaimant — the plaintiff here — filed this action to compel the contractor to arbitrate the dispute.
The plaintiff claims that Duchess is a third party beneficiary of the contract and as such is entitled to enforce the contract provisions, including the arbitration clause, against the defendant. The defendant, surprisingly, concedes that this is a correct statement of contract law as it pertains to arbitrations. Rather, the defendant claims that Duchess is not a third party beneficiary of the contract.
As support for the proposition that a third party beneficiary of a contract can enforce an arbitration clause against one of the signatories to the contract, the plaintiff cites Gilden v. SingerManufacturing Co.,
In the 1959 term of the Supreme Court, Justice Murphy authored two other decisions that dealt with the ability of a non-signatory to compel arbitration. The first was Arsenault v.General Electric Company,
Within the same month, the Supreme Court decided McCaffrey v.United Aircraft Corp.,
Gilden, properly read, does not stand for the proposition advanced by the plaintiff.
Subsequent Connecticut case law is hardly more definitive. InWesleyan University v. Rissil Construction Associates, Inc.,
When Rissil later tried to compel arbitration directly with Wesleyan, with whom Rissil had signed no contract, it met with failure. Wesleyan University v. Rissil Construction Associates,Inc.,
Once viewed as violating public policy, see discussion inParanko v. State,
There is accordingly little reason to distinguish between a third party beneficiary's right to enforce an arbitration clause of a contract and a third party beneficiary's right to enforce any other clause of a contract.
Gaudet v. Safeco Insurance Co.,
The most recent scholarly commentary on Connecticut arbitration law agrees, however, that the issue of whether a third party beneficiary can enforce an arbitration clause in a contract against a reluctant signatory is unsettled. Hodgson and Parley, Alternative Dispute Resolution in Connecticut's Courts, § 2.8.4, p. 33 (1998). The trend seems to be to treat the application and enforcement of procedural rights under a contract, relating to remedies and to dispute resolution, in the same way as substantive rights are treated. But in this court's view, that characterization of the state of the law has yet to be CT Page 10685 pronounced in Connecticut. And before a court so holds, the principle deserves a more thorough analysis than it has yet been afforded.
The court declines to adopt the concession of the defendant that were plaintiff found to be a third party beneficiary, arbitration could be compelled. Rather the court accepts the invitation of both sides to determine whether the plaintiff is indeed a third party beneficiary of the contract. The court finds that the plaintiff is not.
The written contract to repair the culvert came about after Carl A. Neri, president of the Neri Corporation, received an inquiry from Barry Steinberg, the engineer who had done the site work. Mr. Neri submitted a bid. He testified that he did a title search before he entered into the written contract to make certain that he was dealing with the record owner of the real property. Mr. Neri testified that he did not know who owned the restaurant and did not care. He knew nothing of the business dealings of the restaurant, and only learned of the corporate status of the establishment after the construction work was substantially complete and the payment dispute arose.
Shaun Lavin, vice-president of Duchess of Dixwell Avenue, Inc., testified that it was of great importance to the restaurant not to have the construction work interfere with the drive-thru lane at midday. He made this fact known to Barry Steinberg. Lavin also testified that the private arrangement between Harry Kruger and Duchess was that each would pay one-half of the cost to rebuild the culvert. Neri had no knowledge that the corporation was contributing to the cost or indeed that such a corporation even existed.
The law in Connecticut, recently reaffirmed in Grigerick v.Sharpe,
In Grigerick, the court found error in the trial court's CT Page 10686 instruction that a third party beneficiary could be one who was aforeseeable beneficiary of the contract, as opposed to one who was an intended beneficiary under a contract. The Court reiterated that the focus in contract law is the intention of both parties as expressed through their voluntary exchange of mutual obligations, thus allowing the parties to control through their negotiations the scope of their, contractual duties and obligations. Id., 318.
Furthermore the facts in Grigerick are not dissimilar from the facts of the instant case and are persuasive of a finding here that Duchess was not an intended beneficiary of the Neri contract. Grigerick was a purchaser of land from the seller Lang. Before Grigerick bought the land, lie offered to pay Lang a higher price if Lang would take the necessary steps to have the land approved as a building lot. Lang hired the defendant Gary Sharpe, an engineer, to perform professional services for Lang. Based on Sharpe's work, the town granted approval of the site as a building lot, and Lang sold the property to Grigerick at the higher price. When Grigerick tried to get a permit for a septic system, however, the permit was refused by the new town sanitarian because the land was found to be unsuitable for a septic system. Grigerick sued Sharpe for breach of contract. Gregerick claimed to be a third party beneficiary of Lang's contract with Sharpe.
Responding to special interrogatories, the jury found that while Grigerick was a foreseeable beneficiary of the contract, he was not an intended beneficiary of the contract, a finding that resulted in the Supreme Court remanding and directing that judgment be entered for the defendant on the breach of contract count.
In that case and this, the facts include a landowner entering into a contract for services for his own benefit, although perhaps also intending to benefit another who has or may acquire an interest in that land. But the party supplying the services had no such intention. The fact that an incidental benefit might be realized by a third party is insufficient to support third party beneficiary status. Rather the parties must have intended that the promisor (Neri) would owe a direct obligation to the third party (Duchess of Dixwell Avenue, Inc.). Knapp v. New HavenRoad Construction Co.,
Absent from the language of the contract and the circumstances attending its making are any indications that Neri Corporation intended to assume a direct obligation to Duchess. Neri was not even aware of the existence of a corporation by that name until this dispute arose. Neri Corporation took steps to make sure that it was signing a contract with at least one individual who possessed adequate security to pay the contract price. There is no evidence that Neri intended any other entity than the landowner to be able to enforce the contract or to benefit from Neri's services.
Arbitration is a creature of contract. Connecticut courts have routinely recognized that, barring an unambiguous finding that the parties agreed to arbitrate, they will not be forced to do so. Scinto v. Sosin,
The plaintiff's application to compel arbitration is denied.
Patty Jenkins Pittman, J.