DocketNumber: No. CV 95 57916 S
Citation Numbers: 1996 Conn. Super. Ct. 5256-MMMMMM
Judges: KLACZAK, J.
Filed Date: 8/9/1996
Status: Non-Precedential
Modified Date: 4/18/2021
In this case, Ultimate seeks damages for losses incurred as a result of Merrimack's breach of contract in failing to provide a bridge expansion joint conforming to contract specifications and which was, therefore, unusable.
Ultimate seeks compensation for loss of profit and for costs incurred in attempting to install the defective joint. It also claims the defendant is unjustly enriched by refusing to return a deposit made by the plaintiff.
The Court finds the issues for the defendant for the following reasons:
1. Deposit: The plaintiff did not introduce evidence as to the amount of deposit, if any, applicable to the bridge contract involved in this case. This claim has not been proved. CT Page 5256-NNNNNN
2. Loss of Profit: The plaintiff carries the burden of proving with a reasonable degree of certainty the profit it claims to have lost.
There was testimony that Ultimate's bid to the State of Connecticut for this particular joint was $28050, that Merrimack had contracted to provide the part for $15806 and that it would have cost an estimated $2000 to install it for a lost profit of $10244.
The substitute joint was installed for approximately $1500 with a nominal profit of approximately $100 to Ultimate. This claim has not been proven with sufficient reasonable reliability. Ultimate claims it spent almost $6000 in an effort to install the original defective joint. It seems move likely than not that it would cost substantially more than $2000 to install even if it did meet specifications. Besides, the decision to replace the defective joint without giving Merrimack the opportunity to correct was a judgment call made by Ultimate. While it was reasonable under all the circumstances, when that decision was made Ultimate knew it was giving up any profit on that aspect of the bridge job and opted to do so in order to be sure of finishing the job with out further unanticipated delay.
In Vine v. Orchard Hills, Inc.,
3. Back Charges: The Court concludes that Ultimate did not do all it could have reasonably done to minimize the costs of trying to install the bridge joint. It could have immediately contacted Merrimack, but rather, spent several days trying to make the joint fit, in meetings with engineers, in devising alternate proposals to either repair to replace the joint. These efforts, while done in good faith, did not mitigate the damages incurred CT Page 5256-OOOOOO by Merrimack. The Court is also mindful of the equitable considerations referred to herein.
Accordingly, judgment shall enter for the defendant.
Klaczak, J.