DocketNumber: No. 543089
Judges: HURLEY, JUDGE TRIAL REFEREE.
Filed Date: 5/17/1999
Status: Non-Precedential
Modified Date: 4/18/2021
Following a non-jury trial before this court, the parties filed post-trial memoranda on February 11, 1999. The court now makes the following findings of fact and conclusions of law.
On May 29, 1996, the parties signed and agreed to Change Order Number MC2, which changed the contract as follows: "Blast ledge in foundation area to obtain foundation depth [$1,600]; Excavator to move blasting mats and remove rock [$1,200]." The contract price was thereby increased from $223,854 to $226,654, and the date of substantial completion was extended from September 14, 1996 to September 18, 1996.
On July 3, 1996, the parties signed and agreed to Change Order Number MILEC-02, which, through various changes and credits, decreased the total contract price by $14,860. Thus, as of July 3, 1996, the total contract price owed by the defendant was $211,794.
The parties further agree that two verbal change orders increased the contract price by $750 for stump removal, and $9,007 for kitchen cabinets. Therefore, after adding these items, the total contract price was at $221,551. The parties also agree that the contract price was further reduced by $1,100 (granite top credit), $600 (two cabinets credit), $4,115 (direct payment to Kitchen Beautiful by defendant), and $1,000 (direct payment to Ray's Sheetmetal by defendant). The contract price was therefore reduced by $6,815, so as to bring the total contract price to CT Page 6070$214,736.
The plaintiff also adds $3,591 as the balance to complete the contract, thus increasing the contract price to $231,481. However, the plaintiff subtracts $800 (light fixture allowance), $100 (tub surround) and $1000 (floor finish) to decrease the contract price to $229,581.
The defendant, on the other hand, claims that he paid an additional $17,324.76 to complete the construction of the house, plus $13,375 for the cost of missing items that the plaintiff allegedly failed to install. The defendant also claims $20,636.99 in attorney's fees, plus $21,703.26 in interest on his construction loan after the contract date of completion, and $25,550.24 as the balance of 15% lost profit from projected sale price of home. Thus, including the $3,744.12 that the defendant claims he overpaid, the defendant claims that the plaintiff owes him a total of $102,334.37. CT Page 6071
"Substantial performance of a building contract . . . is ordinarily a question of fact for the trier to determine . . . It is peculiarly within the province of the trier of fact to judge the credibility of a witness." (Citations omitted; internal quotation marks omitted.) Edens v. Kole Construction Co.,
"Generally, where a time for performance is stated in an agreement, a party's tender of performance within a reasonable CT Page 6072 time thereafter will be considered substantial performance unless the parties intend that time for performance be of theessence. . . . Because delays are typical in transactions involving real property or building contracts, time is ordinarily not of the essence in these contracts. . . . The resolution of whether it is part of the contract involves a question of the intent of the parties, to be determined, as a matter of fact, from the language of the contract, the circumstances attending its negotiation, and the conduct of the parties in relation thereto." (Citations omitted; internal quotation marks omitted; emphasis added.) Miller v. Bourgoin,
The court finds that time was not of the essence in this contract. Therefore, the court must determine whether the plaintiff substantially completed his performance by the contractual ending date of September 18, 1996, or a reasonable time thereafter. After reviewing the exhibits, and hearing testimony, this court concludes that the plaintiff did not substantially complete the contract by September 18, 1996. However, the court must determine whether the defendant's acts or omissions precluded the plaintiff from substantially completing the contract at that date or a reasonable time thereafter.
The plaintiff claims that the defendant's failure to record the subject lot as a distinct and separate lot from the subdivision prevented him from securing a building permit. This omission of the defendant allegedly caused the plaintiff a delay in commencement of construction, and ultimately, preventing him from being able to substantially complete the contract by the specified date.
It is implied "that the contractor shall be permitted to proceed with his construction in accordance with the contract and that he shall be given possession of the premises to enable him to do so." Hartford Electric Applicators of Thermalux. Inc. v.Alden,
Under the contract, the plaintiff was obligated to "secure and pay for the building permit and other permits . . . necessary for proper execution and completion of the Work. . . . General Conditions, § 3.7.1. "If the Contractor [plaintiff] is delayed at any time in progress of the Work by an act or neglect of the Owner [defendant] . . . or other causes beyond the Contractor's control . . . then the Contract Time shall be extended by [written] Change Order for such reasonable time as the Architect may determine." General Conditions, § 8.3.1.
The court finds that the plaintiff properly attempted to secure building permits but was unable to do so for reasons beyond his control. Although the plaintiff should have extended the contract time through a written change order, the court finds that the defendant allowed the plaintiff to extend work beyond the September ending date. In fact, as late as November 25, 1996, the defendant was still permitting the plaintiff to perform without terminating him despite his failure to substantially complete by September 18, 1996.
Accordingly, the court finds that the proper date by "which to measure whether the plaintiff substantially performed would necessarily have to be beyond the September 18, 1996 completion date. The plaintiff's testimony, which was not substantially rebutted, indicates that the house was 99% complete by February, 1997. In light of the defendant's apparent waiver of exact compliance with the original contract-ending date, February, 1997 was a "reasonable time thereafter." Other than floor finishing, touch-up painting and tub tile surround, the court finds that the house was substantially completed by February, 1997.
"The general rule to be applied in construction cases is that the failure to make progress payments is a breach of contract so substantial as to render the contract nugatory. . . . The failure CT Page 6074 to make installment payments when due goes to the essence of a contract. . . . A failure to make any payments for work in progress goes to the root of the bargain of the parties and defeats the object of the parties in making the agreement." (Citations omitted.) Silliman Co. v. S. Ippolito Sons,
The court also finds that the defendant made repeated representations to the plaintiff during the month of December that he intended on paying the November 25, 1996 application for payment. The court finds that the defendant's failure or refusal to make this installment payment constitutes a material and substantial breach of the contract.
"Under termination clauses, the owner may be given the right to terminate the contractor ``for cause' or ``for default.'" R. Cushman, supra, § 3.27, p. 123-25. "Many contracts have procedures that require more than simple notice. These procedures will be enforced." R. Cushman, supra, § 8.9, p. 271 n. 77, citingMulti-Service Contractors, Inc. v. Town of Vernon,
"[W]hen a particular form of notice, or length of time, is stipulated to in the contract, exact compliance is necessary, and giving the prescribed notice is an essential prerequisite to termination of the contract." 1 S. Stein, supra, § 4.13 [1] [c]. The termination must be in good faith. 1 S. Stein, supra, § 4.13 [2], citing Dinnis v. Roberts,
Under the contract in the present case, Article 8 allows the plaintiff or defendant to terminate or suspend the contract pursuant to Article 14 of the General Conditions. Article 14 provides in pertinent part: "[T]he Owner, upon certification by the Architect that sufficient cause exists to justify such action, may without prejudice to any other rights or remedies of the Owner and after giving the Contractor and the Contractor's surety, if any, seven days' written notice, terminate employment of the Contractor. . . ." (Emphasis added.) General Conditions, § 14.2.2; see also General Conditions, § 2.4.1 (requiring seven-day written notice).
The court finds that, on two occasions, the defendant terminated the plaintiff without providing the required seven days written notice. The court disagrees with the defendant's argument that the "numerous meetings" and written "punch lists" were adequate to give the plaintiff notice of the defendant's CT Page 6076 intention to terminate. Accordingly, the two acts of wrongful termination constitute material and substantial breaches of the contract.
Quantum meruit is an "equitable remedy of restitution by which a plaintiff may recover the benefit conferred on a defendant in situations where no express contract has been entered into by the parties." Burns v. Koellmer,
"Unjust enrichment applies wherever justice requires compensation to be given for property or services rendered under a contract, and no remedy is available by an action on the contract. . . . A right of recovery under the doctrine of unjust enrichment is essentially equitable, its basis being that in a given situation it is contrary to equity and good conscience for one to retain a benefit which has come to him at the expense of another. . . . [I]t becomes necessary in any case where the benefit of the doctrine is claimed, to examine the circumstances and the conduct of the parties and apply the standard." (Citations omitted; internal quotation marks omitted.) HartfordWhalers Hockey v. Uniroyal Goodrich Tire,
"Plaintiffs seeking recovery for unjust enrichment must prove (1) that the defendants were benefitted [benefited], (2) that the defendants unjustly did not pay the plaintiffs for the benefits, and (3) that the failure of payment was to the plaintiffs' detriment." (Internal quotation marks omitted.) Barbara Weisman, Trustee v.Kaspar,
The court finds that the following items were not part of the original contract, but were subsequently performed or installed by the plaintiff: septic system; Jacuzzi; septic fill; excavator blasting; and site fill. The court does not find credible the defendant's assertion that he did not authorize the additions set forth above. The court also finds that these additions were not anticipated by the parties at the time of contracting and not provided for in the original contract. In addition, the court finds that the plaintiff performed or installed the additional items with the expectation of getting paid for his services, and that, as a result, the defendant's land has been improved and its value increased. Accordingly, the defendant unjustly did not pay the plaintiff for the foregoing beneficial services and provisions to his land.
"It is well settled that in determining whether [an act or] practice violates CUTPA we have adopted the criteria set out in the cigarette rule by the federal trade commission for determining whether [an act or] practice is unfair: (1) [W]hether the practice, without necessarily having been previously considered unlawful, offends public policy as it has been CT Page 6078 established by statutes, the common law, or otherwise — whether, in other words, it is within at least the penumbra of some common law, statutory, or other established concept of unfairness; (2) whether it is immoral, unethical, oppressive, or unscrupulous; (3) whether it causes substantial injury to consumers. . . . All three criteria do not need to be satisfied to support a finding of unfairness. A practice may be unfair because of the degree to which it meets one of the criteria or because to a lesser extent it meets all three. . . . Thus a violation of CUTPA may be established by showing either an actual deceptive practice . . . or a practice amounting to a violation of public policy." (Citations omitted; internal quotation marks omitted.) SaturnConstruction Co. v. Premier Roofing Co.,
"A majority of Superior Court cases support the claim that a simple breach of contract, even if intentional, does not amount to a violation of CUTPA; a claimant must show substantial aggravating circumstances to recover under the Act. . . . A simple contract breach is not sufficient to establish a violation of CUTPA." (Citations omitted; internal quotation marks omitted.)Holeva v. M Z Associates, Superior Court, judicial district of New Haven, Docket No. 098403 (November 18, 1998, Levin, J.). "This does not mean that recovering under CUTPA for a breach of contract is impossible . . . the same facts that establish a breach of contract claim may be sufficient to establish a CUTPA violation." (Citations omitted; internal quotation marks omitted.) Slitz v. Pyramid Custom Home Corp. , Superior Court, judicial district of Danbury, Docket No. 323247 (April 4, 1997, Stodolink, J.) (finding allegations of several misrepresentations during course of parties' dealings sufficient to state CUTPA and breach of contract claims).
In the present case, the court does not find that the defendant's conduct amounted to an intentional and calculated pattern of attempting to avoid his obligations under the contract. The evidence does not disclose that there were any fraudulent or unethical practices by the defendant so as to rise to the level of a CUTPA violation. Accordingly, the court finds that the plaintiff cannot recover under this count.
The defendant alleges that the plaintiff breached the contract by failing to: (i) make additions to, or deductions from, the contract in writing; (ii) construct the home in compliance with the plans and specifications; (iii) complete work in a timely manner; (iv) perform in a workmanlike manner; and (v) obtain written assent from defendant before supplying and charging for additional items. The defendant also claims that he was forced to pay for repairs to correct and complete the plaintiff's defective work. In addition to claiming that the plaintiff made material misrepresentations and negligently failed to comply with the plans and specifications, the defendant also alleges violations of implied warranties as set forth in the New Home Warranties Act, General Statutes §
Because of the defendant's material breaches in: (1) failing to make a progress payment; and (2) terminating the plaintiff in contravention of the contractually-required seven-day written notice, the defendant is precluded from seeking recovery under the contract. Notwithstanding the defendant's inability to recover under the contract, the court finds that the plaintiff's failure to obtain written change orders in some instances did not amount to a substantial or material breach of the contract. In addition, the court has already found that the plaintiff substantially completed the contract in substantial compliance with the plans and specifications. Accordingly, notwithstanding that the defendant cannot recover under the contract, the court finds that the plaintiff was not in material breach. CT Page 6080
"In every sale of an improvement by a vendor to a purchaser . . . warranties are implied that the improvement is: (1) Free from faulty materials; (2) constructed according to sound engineering standards; (3) constructed in a workmanlike manner, and (4) fit for habitation. . . ." General Statutes §
However, a "purchaser" is defined specifically as the "original buyer . . . of any improved real estate." See "General Statutes §
Because it is undisputed that the defendant owned the land on which the plaintiff contracted to build the house, as a matter of law, the defendant cannot recover under this count.
The plaintiff submitted evidence that he was only able to file a mechanic's lien against the entire subdivision because of the way in which the lot was recorded. This court does not find such an act by the plaintiff to constitute an unfair or deceptive act as defined in CUTPA. In addition, the court did not find any evidence revealing the plaintiff's misrepresentation as to his ability or competence to complete the contract. Accordingly, the court denies the defendant recovery under this count.
The court finds that the plaintiff did not exhibit bad faith, dishonest purposes or sinister motives in his course of performing the contract. To the contrary, the court finds that the plaintiff attempted to preserve friendly and communicative relations with the defendant. Accordingly, the court denies the defendant recovery under this count.
"The determination of whether or not interest is to be recognized as a proper element of damage, is one to be made in view of the demands of justice rather than through the application of any arbitrary rule. . . . The real question in each case is whether the detention of the money is or is not wrongful under the circumstances. . . . Basically, the question is whether the interests of justice require the allowance of interest as damages for the loss of use of money. . . . [This is] primarily an equitable determination and a matter lying within the discretion of the trial court." (Citations omitted; internal quotation marks omitted.) Bertozzi v. McCarthy, supra,
After the change orders and undisputed modifications, the CT Page 6083 total amount owed by the defendant would have been $214,736. See Part II B. The plaintiff also agrees to subtract $800 for light fixture allowance, $100 for tub surround, and $1000 for floor finish, to bring the total amount owed to $212,836. Adding in the additional items, see Part II C, the total amount owed increases by $3,854 for septic system, $1,200 for Jacuzzi, $1,700 for septic fill, $1,400 excavator blasting, and $5,000 site fill, for a total of $13,154. Thus, the total amount owed by the defendant would have been $225,990. In addition, the plaintiff adds in $3,591 as the balance to complete the contract, increasing the total amount owed to $229,581. See Part II C.
It is undisputed that the defendant has paid $218,480.12. Therefore, the court finds that the defendant owes $11,100.88. In addition, the contractual interest at 1.5% for thirteen months equals $2,164.67. The plaintiff incurred reasonable attorney's fees and costs in the amount of $8,209.40. Accordingly, judgment shall enter in favor of the plaintiff for the total amount of $21,474.95.
So Ordered.
D. Michael Hurley Judge Trial Referee