DocketNumber: No. CV 99 0172425
Judges: LEWIS, JUDGE.
Filed Date: 10/23/2001
Status: Non-Precedential
Modified Date: 4/17/2021
The revised complaint against Atlas, which is dated July 16, 1999, is in two counts. In the first count, the plaintiff alleges that it performed services and supplied material in accordance with its written contract with Atlas dated April 16, 1998, but that it withdrew from further work on the project on October 16, 1998, because the defendant had refused to make timely payments for its work and materials as called for in the contract. The plaintiff also alleges that it is owed a balance of $284,492.47 on the contract. In the second count, the plaintiff alleges that it is owed that same amount under the theory of unjust enrichment. The third and fourth counts are directed against the owner, State Street, and the surety, Liberty Mutual, respectively, and claim that these defendants have failed to pay the plaintiff what it is owed.
The defendant Atlas denied the material allegations of the complaint and filed several special defenses. In the first special defense, this defendant alleges that the work performed by the plaintiff was defective and incomplete. In the second special defense, it is claimed that the plaintiff wrongfully abandoned the project. In the third special defense, the defendant alleges that the plaintiff cannot recover under the theory of unjust enrichment because it had an express written contract with the defendant.
The defendant Atlas also filed a counterclaim alleging that the plaintiff breached the contract in a number of ways, including failing to furnish necessary materials and manpower, interfering with the timely performance of work by other subcontractors, abandoning the job, and failing to properly supervise the project, all of which obliged the defendant to expend money to hire other subcontractors to finish the project and to correct the plaintiff's faulty workmanship.
The defendant State Street denied the material allegations of the complaint and filed a special defense claiming it was not liable to the plaintiff to the extent it had paid its general contractor, Atlas. The bonding company, Liberty Mutual, denied that it owed any money to the plaintiff and filed special defenses. In the first such defense, Liberty Mutual claims that the work performed by the plaintiff was done in an CT Page 14529 unworkmanlike and incomplete fashion. In the second special defense, this defendant claims that the plaintiff wrongfully abandoned the project.
The case was referred to Attorney Bernadette Coomaraswamy, an attorney trial referee, in accordance with General Statutes §
The attorney trial referee concluded that: (1) the plaintiff sustained damages because the defendant Atlas had breached the subcontract in question by not paying the plaintiff the amounts due it in a timely fashion; and (2) Atlas did not prove its counterclaim because the plaintiff's work was not defective and the plaintiff did not wrongfully abandon the project. The referee recommended that judgment enter in favor of the plaintiff for $284,390, plus prejudgment interest from October 16, 1998, the date when payment was due the plaintiff.1
The attorney trial referee filed an amended report on April 20, 2001, in response to requests by both the plaintiff and State Street, in which she acknowledged that it was State Street that was holding $72,000 in escrow, not Liberty Mutual, as originally stated. Thus, State Street's liability is limited to $72,000, and the defendants Atlas and Liberty Mutual are responsible for $212,390 of the recommended award to the plaintiff of $284,390.
The attorney trial referee filed an additional report dated May 17, 2001, in response to a request by Atlas for "findings," purportedly as authorized by Practice Book §
The defendant Atlas filed objections2 dated April 11, 2000, to the attorney trial referee's report. The defendant claims that the attorney trial referee erred in that: (1) Atlas was not awarded a credit of $40,427.81 for payments made to the plaintiff's subcontractors; (2) the referee misinterpreted the contract and the prior course of dealings regarding when payment was due the plaintiff; (3) the referee failed to find that the plaintiff wrongfully abandoned the project and thus breached its contract with Atlas; (4) the plaintiff waived its right to receive monthly payments because it accepted late payments; (5) the sum of $29,465 was awarded to the plaintiff which represents a "double recovery;"3 (6) any delays or problems involving vents, fan coils or shower units were caused by the owner, State Street, and not by Atlas; (7) Atlas incurred additional expenses of approximately $800,000 more than the plaintiff's claim in order to complete the project after the plaintiff stopped work; (8) the referee should not have recommended prejudgment interest because there was no bad faith or wrongful conduct on the part of Atlas; and (9) Atlas was entitled to damages based on its counterclaim.
Practice Book §
The case of Killion v. Davis,
Other principles governing attorney trial referee reports provide that: "A reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court . . . or the Superior Court reviewing the findings of . . . attorney trial referees." (Citations omitted.) Wilcox Trucking, Inc. v. MansourBuilders, Inc.,
The first issue is whether there is support in the record for the referee's findings of fact that were challenged by the defendant. The objections involve two distinct claims by the defendant: first, did the defendant make timely payments to the plaintiff and, second, was the plaintiff justified in leaving the project when it did.
A review of the transcript indicates that there is sufficient support in the record for the referee's key findings that the defendant did not pay the plaintiff when it was obliged to do so under the contract and, thus, the plaintiff was justified in leaving the job.4
It is quite evident that the referee chose to believe the testimony offered by the plaintiff and not that of the defendant regarding timeliness of payment and the caliber of the work. "The finder of fact is in a better position to determine the credibility of witnesses and the weight to be accorded their testimony." Beizer v. Goepfert,
Based upon a review of the report regarding the counterclaim by the defendant, the court finds that the attorney trial referee's conclusions and recommendations are supported by the subordinate facts that she found. The ultimate conclusion that the defendant is not entitled to recover any money from the plaintiff on its counterclaim follows logically and legally from the findings by the attorney trial referee that the defendant had breached the contract by not paying its subcontractor, the plaintiff, the money that was due. The attorney trial referee did not recommend compensation for lost profits, but by recommending a recovery of $284,390, she did attempt to put the plaintiff in the same position that it would have been in had the defendant not breached the contract. L.F. Pace Sons, Inc. v. Travelers IndemnityCo.,
The referee did not recommend paying the plaintiff for the balance due on the contract, approximately $840,000, or $84,000, claimed by the plaintiff as a loss of profits of 10%. Rather the referee recommended payment of just what was owed the plaintiff when it left the job site, plus the retainage, and reimbursement for the cast iron pipe left for the defendant Atlas.
The referee also recommended interest as authorized by General Statutes §
Thus, no material error in the report has been found, and there is no other sufficient reason for rendering the report unacceptable. See Practice Book §
Costs are to be taxed in favor of the plaintiff by the clerk of this court in accordance with General Statutes §
So Ordered.
Dated at Stamford, Connecticut, this 23rd day of October, 2001.
William B. Lewis, Judge