DocketNumber: No. 526679
Citation Numbers: 1993 Conn. Super. Ct. 6421
Judges: TELLER, J.
Filed Date: 6/30/1993
Status: Non-Precedential
Modified Date: 4/18/2021
The defendants moved to dismiss the action on the ground that Tri-J, as a disappointed bidder, had no standing to bring this action, thus depriving the court of subject matter jurisdiction. C J also moved to dissolve the temporary restraining order and the City moved that the court order the plaintiff to post a bond.1
The court, with the agreement of the parties, began CT Page 6422 to hear evidence simultaneously on the motions to dismiss and to dissolve the temporary injunction, as the issues were intertwined. Later, by agreement, the hearing was expanded to include the defendant's motion for posting of bond. On the final day of hearing, as the defendants had answered the complaint and closed the pleadings, the parties stipulated that all of the evidence may be considered by the court in entering a final judgment on the issue of whether the plaintiff was entitled to a permanent injunction.2
The contracted work is to be performed on a scheduled and emergency basis and generally involves excavation of a street to the depth of the present or proposed city water main and the repair, replacement or installation of new water pipe lines and fittings, as applicable, and back filling and repaving the affected areas.
On or about December 10, 1992, the DPU opened the four bids filed, and the defendant C J, an excavating contractor, appeared to be the lowest bidder, Ledyard General Contractors, Inc. ("Ledyard") was the second lowest bidder, and the plaintiff, who had won bids for such contracts for the past 19 or so years, the third lowest. Thereafter, Tri-J's president, Johnson, the holder of a contractor's P-7 license,3 telephoned the DPU to inquire whether the other bidders possessed a P-7 license.4 The DPU requested this information from the two lowest bidders and the plaintiff, but did not do so from the fourth bidder because its bid was too high in comparison to the other bids.
C J provided a copy of the requested license held by one Martilla together with a statement that it intended to subcontract with Martilla to supervise and install any work to be performed under the contract. Neither of C J's principals nor any of its employees hold a P-7 license nor held one at the time of the bid. The second lowest bidder, Ledyard, provided a copy of a P-7 license in the name of Peter Locarno, but no explanation of the nexus or CT Page 6423 relationship between Ledyard and Locarno.
On or about April 30, 1993, the City and DPU decided to award the contract for Bid #5165 to C J, and this action ensued, and no work has been performed on the contract. The City and DPU have, however, been able to have any required work done by their employees.
"It is a basic principle of law that a plaintiff must have standing for the court to have jurisdiction. Standing is the legal right to set judicial machinery in motion. One cannot rightfully invoke the jurisdiction of the court unless he has, in an individual or representative capacity, some real interest in the cause of action, or a legal or equitable right, title or interest in the subject matter of the controversy. . . . Standing is not a technical rule intended to keep aggrieved parties out of court; nor is it a test of substantive rights. Rather it is a practical concept designed to ensure that courts and parties are not vexed by suits brought to vindicate nonjusticiable interests and that judicial decisions which may affect the rights of others are forged in hot controversy, with each view fairly and vigorously represented. . . . These two objectives are ordinarily held to have been met when a complainant makes a colorable claim of direct injury he has suffered or is likely to suffer in an individual or representative capacity. Such a personal stake in the outcome of the controversy. . . provides the requisite assurance of ``concrete adverseness' and diligent advocacy." (citations and internal quotation marks omitted.)
Unisys Corporation v. Department of Labor,
In Ardmare Construction Co. v. Freedman,
The court further pointed out in Ardmare, supra, that:
"The public interest in preventing the granting of contracts through arbitrary or capricious action can properly be vindicated through a suit brought by one who suffers injury as a result of the illegal activity, but the suit itself is brought in the public interest by one acting essentially as a private attorney general; . . . and that the scope of our holding in Spiniello was to strike the proper balance between fulfilling the purposes of the competitive bidding statutes and preventing frequent litigation that might result in extensive delay in the commencement and completion of government projects to the detriment of the public."
Ardmare, supra, 504-505.
A bid, even the lowest responsible one, submitted in response to an invitation for bids is only an offer which, until accepted by the City, does not give rise to a contract between the parties. John J. Brennan Construction Corporation, Inc. v. Shelton,
Our Supreme Court has also declared that: "[m]unicipal competitive bidding laws are enacted to guard against such evils as favoritism, fraud or corruption in the award of contracts, to secure the best product at the lowest price, and to benefit the taxpayers, not the bidders." CT Page 6426 Ardmare, supra, 504.
The evidence here indicates that Tri-J had first obtained a contract similar to Bid #5165 in 1969. Prior contracts awarded to Tri-J were for one year with options for two years, which Tri-J always extended. From 1969, up until December 10, 1992, Tri-J was always awarded the water main contract, with one exception.
The provision in the invitation for bid documents upon which the plaintiff heavily relies upon states: "In keeping with the Rules and Regulations of the State Board of Plumbing and Piping Examiners a P-7 contractor license is a definite requirement for all bidders." The City and DPU consistently appeared to interpret the bidding documents to require an "in house" P-7 license, however, there was no evidence that any lowest bidder in prior years did not have an "in house" license or that such a bidder was rejected or declared ineligible. There was also no evidence that any interested persons without "in house" P-7 licenses were discouraged from bidding by City or DPU officials. Tri-J's principal, Johnson, testified that he studied for and obtained a P-7 license to enable his company to be a "responsible bidder."
This prior interpretation by the DPU and the City is borne out by their failure to immediately award the contract in this case to the lowest bidder, C J, which did not have such a license.
In fact, the officials responsible for the intended award to C J were not certain of their ability to do so, in the light of their own bidding regulations, and referred the matter to the City attorney. Only after receiving counsel's advice did they decide about five months after the bid opening to award the bid to C J.
In Ardmare, supra, 506, in a case where the lowest bidder was rejected for stamping its president's signature on the bid form instead of one personally signed, the court held the lowest bidder to be without standing, and said: "Noticeably absent in this case are elements traditionally thought to undermine the competitive bidding process. The commissioner did not apply the requirement inconsistently or in a discriminatory fashion. Nor was there any proof that CT Page 6427 the Commissioner was acting in bad faith. In short, the Commissioner made a good faith interpretation of the competitive bidding statute requirements and applied it in a consistent fashion." (emphasis added).
In this case, the plaintiff points to no fraud or corruption, nor is it able to. Also, the officials involved acted in good faith, and showed no favoritism. Although the court notes that the plaintiff was not the second lowest bidder, but the third lowest bidder, there was no evidence that the P-7 license proffered by Ledyard was "in house." Therefore, if the plaintiff's interpretation of the bidding documents is correct, the plaintiff would then advance to the position of "lowest responsible bidder." On the other hand, if Ledyard's license was in fact "in house," then by the terms of the bidding documents plaintiff would "be considered a backup contractor, if the successful bidder is too busy or. . . not available." Plaintiff's Exhibit B, page 8. However, under the circumstances of this case, where there appeared to be a long standing custom of appearing to require an "in house" P-7 license, reinforced by the above-quoted language in the bid document that "a P-7 license is a definite requirement for all bidders," the court concludes that this abrupt change in determination of bidder eligibility conferred the requisite standing upon the plaintiff as a ``private attorney general' to raise the issue of whether "the very object and integrity of the competitive bidding process is defeated by the conduct of the officials." Ardmare, supra, 504-505.
B. The plaintiff also claimed that it had standing as a taxpayer. Paragraph. 15 of its amendment to the complaint alleges that it is harmed as both an unsuccessful bidder and as a taxpayer, however, the allegations of harm relate solely to its status as an unsuccessful bidder. However, in paragraph 16 of its amendment to the complaint, it alleges that it will suffer increased taxes in that bids of potential bidders without P-7 licenses were not received which could have been lower than that of C J, thereby resulting in increased taxes to Norwich taxpayers. A taxpayer must show, in order to have standing, that he has suffered a pecuniary or other direct loss in that capacity. Cassidy v. Waterbury,
As C J aptly point out in its brief, a plaintiff CT Page 6428 who relies on taxpayer status for standing must "prove that the transaction involved will probably result, directly or indirectly, in an increase in his taxes as would, in some other fashion, cause irreparable injury. American-Republic, Inc. v. Waterbury,
Although the plaintiff showed that it was a taxpayer, and further showed that the City may contribute funds for capital expenditures to its DPU, the plaintiff failed to show any harm to itself as a taxpayer in the event C J's bid was allowed to stand.
First, there is no showing that the City funds the day-to-day operations of its DPU. The evidence, as required by Chapter XII, Section 6 of the City's charter, is to the contrary. That provision provides for a budget to be prepared by the DPU and that not less than ten percent (10%) of the DPU's gross revenues in the preceding year be turned over to the City. Hence, the plaintiff has shown no direct or indirect correlation between the costs and expense of the water main contract and its effect on the City's tax revenues.
Second, there was no proof by the plaintiff that there was any degree of probability that there were any potential bidders without "in house" P-7 licenses who would have entered lower bids than C J, or that if the project were re-bid, of any probability of lower bids.
Accordingly, the plaintiff has not shown that it has standing as a taxpayer.
The plaintiff relies heavily on the paragraph in the Request for Quotation which states: CT Page 6429
"NOTE: In keeping with the Rules and Regulations of the State Board of Plumbing and Piping Examiners, a P-7 contractor license is a definite requirement for all bidders." Exhibit 3, page 5. As previously noted, General Statutes
It is also elementary that the bidding documents must be read as a whole when attempting to interpret them. Included in the bidding documents furnished to each potential bidder are the specifications and general conditions. Plaintiff's Exhibit B. In the general conditions are the following pertinent provisions:
Para. 5. If subcontractors are employed same [insurance] limits as named above shall apply and the certificate of insurance must be filed with the department.
Para. 6. The contractor shall indemnify and save harmless the city against any and all damages. . . arising out of [these] operations. . . including operations of subcontractors and acts or omissions of employees or agents or contractor or his subcontractors.
Para. 15. Sub-Contracts.
The contractor agrees to obtain the agreement of every sub-contractor to be bound to terms and conditions materially and substantially comparable to those contained herein unless otherwise authorized and approved by the [DPU].
Para. 16. Assignment.
. . . The contractor [shall not] subcontract any substantial portion of this contract without [DPU's] written consent.
Para. 19. Contractor shall. . . cause all his sub-contractors to furnish, maintain and use all necessary safety devices and safe practices in prosecution of the CT Page 6430 work. . . . [c]ontractor shall defend, indemnify and save harmless the city. . . from any injury or damage. . . caused by an act, omission or neglect of the. . . subcontractor. . . from claims of defect in violation of
Para. 43. Payment to sub-contractor.
The [DPU] assumes no obligation to pay or see to the payment of any sum to the sub-contractor.
Additionally, the documents provide that prevailing wage rates must be paid by contractors and subcontractors except as exempted by Public Act 79-325.
Also, the request for Quotation, Plaintiff's Exhibit B, page 7, provides: "The Department will consider the pipe laying contractor as the prime contractor in the event that a subcontractor may be employed for temporary and/or permanent resurfacing or any other subcontractor work, and to eliminate conflict of responsibility, the Department will hold the pipe laying contractor responsible. . ." (emphasis added)
Nowhere do the bidding documents say that a bidder must be controlled or owned by a P-7 licensee, or have such a licensee on its payroll as an employee. Nor do the documents prohibit the use of a sub-contractor holding such a license. Nor do they prohibit a joint venture or partnership involving a P-7 licensee. Nor does the plaintiff point to, or can the court discern any rational basis for a distinction between a bidder having an "in house" license or having one available by subcontract, joint venture, or other means. Rather, a plain reading of the bidding documents as a whole, compels the conclusion that they only require that a P-7 licensee perform the work which the statute and regulations require to be done by a licensee.
In the present case, as in Ardmare, supra, C J was not given any special advantage over the plaintiff or other bidders in submitting its bid; nor, was it privy to any secret or undisclosed information.
"All that is required of officials is that they observe good faith and accord all bidders just consideration, CT Page 6431 thus avoiding favoritism and corruption. An honest exercise of discretion will generally not be disturbed." Joseph Rugo, Inc. v. Henson,
Here, the City and DPU officials involved in the bidding process, with the assistance of City counsel, fairly and reasonably interpreted their bidding documents in an effort "to secure the best product at the lowest price, and to benefit the [rate payers], not the bidders." They acted in good faith, and in the exercise of the discretion imposed upon them to protect the public interest.
Also, there was no evidence that any interested persons or potential bidders without an "in house" P-7 license were told by bidding officials in the past that they were not eligible to bid. Nor was there any evidence that in past years any lowest bidder was declared ineligible for lack of such a license. Nor is there any evidence that such interested persons or potential bidders were deterred from bidding on this contract over the past twenty years. Hence, as there was no opportunity until now for bidding officials to make the determination that bidders not possessing "in house" P-7 licenses were eligible to bid, the present determination that C J was eligible and could subcontract P-7 work cannot be termed inconsistent.
This is not the situation dealt with in Blakeslee Arpaia Chapman, Inc. v. City of New Haven, et al, Civil No. N-83-497 D. Conn., (October 27, 1983) (Burns, J.), upon which the plaintiff strongly relies. There, the second lowest bidder was found to have standing because the lowest bidder failed to submit with its bid required certifications that it would utilize in the work minimum percentages of women and minority business enterprises. Nor is this the situation in Spiniello, supra, where favoritism was found when the bidding officials allowed a single bidder to combine two separate bids to achieve a lower total bid, when the other bidders were not given the opportunity to do so. Nor is this the situation dealt with in Community Associates, Inc. v. City of New Haven,
The scenario here, rather, is somewhat closer akin to that in Premier Roofing v. Dept. of Public Works, CV91-702631, J.D. Hartford-New Britain at Hartford, (April 10, 1992) (Aronson, J.), where the DPW awarded the contract to the lowest bidder. The second lowest bidder sought injunctive relief on the ground that the work to be done exceeded the "threshold limits' described in General Statutes
Accordingly, the plaintiff's claim that the defendants City and DPU misinterpreted their own regulations or acted inconsistently and arbitrarily in deciding to award the contract to an unqualified bidder and defeated the very object and integrity of the bidding process fails.
The plaintiff has simply failed to sustain its burden of proving that any ambiguities in the bidding documents "chilled" the pool of likely bidders, and defeated the very object and integrity of the bidding process. Hence, this claim fails.
For the reasons previously stated, the court enters the following orders:
The temporary restraining order is dissolved; the applications for temporary and permanent injunctions are denied; and judgment shall enter for the defendants. In light of the foregoing, the court does not reach the issue of whether the plaintiff must post a bond.
At the conclusion of oral argument on June 15, 1993, the parties reserved the right to file briefs on or before June 18, 1993. The plaintiff filed an application for a stay pursuant to General Statutes
Applications for a stay of execution brought pursuant to Practice Book 4047 are ordinarily addressed to the sound discretion of the court. See In re Bromell G.,
Granting a temporary injunction also lies within the sound discretion of the court. See Covenant Radio Corp. v. Ten Eighty Corp.,
In determining whether to grant or deny the application for a stay, under either Practice Book 4047 or General Statutes
The court cannot find that plaintiff's application for a stay was made only for delay and not in good faith. However, the court does find, after considering all of the factors previously discussed, that the plaintiff has not shown a clear legal right to relief, and that the continuation of the temporary injunction would unduly restrict and hamper the ability of the City and its DPU to provide necessary services to its citizens, including emergency work, and unduly interfere with their governmental operations, and also adversely affect C J so that great and irreparable injury will be done if the ex parte order were allowed to continue.
Therefore, the application for stay pursuant to General Statutes
Teller, J.
Wood v. Town of Wilton , 156 Conn. 304 ( 1968 )
John J. Brennan Construction Corporation, Inc. v. Shelton , 187 Conn. 695 ( 1982 )
Covenant Radio Corporation v. Ten Eighty Corporation , 35 Conn. Super. Ct. 1 ( 1977 )
Joseph Rugo, Inc. v. Henson , 148 Conn. 430 ( 1961 )
H. O. Canfield Co. v. United Construction Workers , 134 Conn. 623 ( 1948 )
American-Republican, Inc. v. City of Waterbury , 183 Conn. 523 ( 1981 )
Spiniello Construction Co. v. Town of Manchester , 189 Conn. 539 ( 1983 )