DocketNumber: No. X03-CV-01-0508999-S
Citation Numbers: 2002 Conn. Super. Ct. 1185
Judges: AURIGEMMA, JUDGE.
Filed Date: 1/29/2002
Status: Non-Precedential
Modified Date: 4/17/2021
Allegations of the Complaint
On December 18, 1995, FLB and Town of Manchester ("Manchester") entered into a Standard Form of Agreement Between Owner and Architect, AIA Document B 141 ("the Contract") to provide certain architectural services for the alterations and additions to the Manchester Town Hall ("the Project"). USA is not a party to the Contract. The plaintiff has incorporated the Contract into the Complaint and, therefore, the court can consider the terms of the Contract in ruling on the present Motion.
Article 2.6.4 of the Contract provides, in relevant part:
The Architect shall be a representative of and advise and consult with the Owner (1) during construction until final payment to the Contractor is due . . . [t]he Architect shall have authority to act on behalf of the Owner only to the extent provided in this Agreement unless otherwise modified by written instrument.
Article 2.6.11 of the Contract imposed the following obligation on FLB:
The Architect shall have the authority to reject Work which does not conform to the Contract Documents . . . [h]owever, neither this authority of the Architect nor a decision made in good faith either to exercise or not to exercise such authority shall give rise to a duty or a responsibility of the_Architect to the Contractors Subcontractors, material and equipment suppliers, their agents or employees or other persons performing portions of the Work.
Article 9.5 of the Contract between FLB and Manchester contained an anti-assignment clause. This clause reads, in relevant part:
CT Page 1187 Neither Owner nor Architect shall assign this Agreement without the written consent of the other.
Article 9.7 of the contract between FLB and Manchester specifically prohibited the creation of a beneficiary relationship in favor of a third party:
Nothing contained in this Agreement shall create a contractual relationship with, or cause of action in favor of, a third party against either the Owner or Architect.
Subsequent to the execution of the Contract between FLB and Manchester, on or about September 18, 1996, Manchester hired USA to build the project in accordance with FLB's designs. Revised Complaint, ¶ 6. On December 15, 2000, all rights held by Manchester under its contract with FLB were assigned to USA. Revised Complaint, ¶ 25.
The First Count of the Revised Complaint includes the following allegations:
8. On or about April 23, 1998, USA substantially completed the work under the Contract and Manchester accepted the Contract work from USA, issuing a temporary certificate of occupancy.
9. As further evidence that the Project was substantially complete, Manchester actually occupied and began to use Town Hall during April and May 1998.
10. Despite the fact that the Project was substantially complete, and despite the. fact that Manchester was enjoying the use and occupancy of Town Hall, Manchester terminated USA's contract on June 1, 1998, claiming that USA was in breach of the Contract.
11. Manchester's termination of the Contract was effectuated, in whole or in part, by the acts and omissions of FLB, as described below in Paragraph 13.
12. Under the Contract, USA could not be terminated for default unless and until FLB certified, in writing, that USA was in material breach of the CT Page 1188 Contract, and the grounds thus existed to terminate the Contract for cause unless USA cured its material breach within the cure period set forth in the Contract.
13. Although no grounds existed to justify such certification by FLB (a fact known to FLB), and although FLB also knew that USA had already substantially completed its obligations under the Contract, it nonetheless wrongfully produced such certification upon demand by the Town. FLB was aware of the contractual realtionship between USA and Manchester, but still intentionally interfered with that relationship by:
a. wrongfully producing the certification upon demand from the Town;
b. certifying that grounds existed to terminate the Contract for default by USA without any independent investigation;
c. by misrepresenting the status and progress of USA's work leading the Town to terminate USA.
In the Revised Complaint, USA asserts five counts against FLB. The First Count alleges intentional. interference with a beneficial or contractual relationship. The Second Count alleges negligence. The Third Count alleges that USA was as a third party beneficiary of the original contract between Manchester and FLB. The Fourth and Fifth counts allege breach of contract and negligence, respectively, as an assignee of Manchester.
FLB has moved to strike all of the counts of the Revised Complaint on the grounds that they fail to state a cause of action.
Discussion of Law and Ruling
The function of a motion to strike is to test the legal sufficiency of a pleading. Practice Book §
The court should view the facts in a broad fashion, not strictly limited to the allegations, but also including the facts necessarily implied by and fairly provable under them. Dennison v. Klotz,
CT Page 1189
FLB has moved to strike the First Count on the grounds that as an agent of Manchester, FLB cannot be sued by USA for tortious interference with contractual relations. The essential elements of a claim for tortious interference with contractual relations are: 1) the existence of a contractual or beneficial relationship; 2) that the defendant, knowing of that relationship, intentionally sought to interfere with it, and; 3) as a result of such interference the plaintiff suffered actual loss. "A cause of action for tortious interference with a business expectancy requires proof ``that the defendant was guilty of fraud, misrepresentation, intimidation or molestation; Busker v. UnitedIlluminating Co.,
"[A]n agent acting legitimately within the scope of his authority cannot be held liable for interfering with or inducing his principal to breach a contract between his principal and a third party, because to hold him liable would be, in effect, to hold the corporation liable in tort for breaching its own contract, Boyce v. American Liberty Insurance Co.,
204 F. Sup. 317 ,318 (D. Conn. 1962); see also Kecko Piping Co. v. Monroe,172 Conn. 197 ,202 ,374 A.2d 179 (1977); Shaw v. Merrick,60 App.Div.2d 830 ,401 N.Y.S.2d 508 ,509 (1st Dept. 1978), [the agent] could be held liable for such interference or inducement if he did not act legitimately within his scope of duty but used the corporate power improperly for personal gain" Bowman v. Grolsche Bierbrouwerij B.V.,474 F. Sup. 725 ,733 (D. Conn. 1979).
Wellington Systems, Inc. v. Redding Group, Inc.,
While an agent such as FLB normally cannot be deemed to have interfered with the contract of its principal, it can be liable for intentional interference with the contract if it acted in bad faith, maliciously, wantonly or beyond the scope of its authority. Multi-Service v. Town ofCT Page 1190Vernon,
The Second Count of the Revised Complaint alleges a cause of action for negligence. The necessary elements of a negligence action are: duty;
breach of that duty; causation; and, damages. RK Constructors, Inc. v.Fusco Corp.,
FLB cannot owe a duty to USA without breaching its agency agreement with Manchester. "An agent employed [by] another, cannot [act] for himself, whether he be actually or constructively an agent. He is, in such case, a trustee for his employer." Church v. Sterling,
Negligence cannot be predicated upon the failure to perform an act which the actor was under no duty or obligation to perform. Behlman v.Universal Travel,
The Third Count of the Revised Complaint alleges USA is a third party beneficiary of the contract between FLB and Manchester. In Knapp v. NewHaven Road Construction Co.,
In Grigerik v. Sharpe,
In the Fourth and Fifth Counts of the Revised Complaint USA alleges, "all rights held by Manchester pursuant to damages in connection with its contract with FLB were assigned to USA." The defendant has moved to strike these Counts on the grounds that the rights of Manchester could not have been assigned because the Contract between FLB and Manchester contains an anti-assignment clause which prohibits assignment without the written consent of the other party to the Contract.
In the recent case of Rumbin v. Utica Mutual Ins.,
By the court,
____________________ Aurigemma, J.
Skene v. Carayanis , 103 Conn. 708 ( 1926 )
Jones v. O'CONNELL , 189 Conn. 648 ( 1983 )
Knapp v. New Haven Road Construction Co. , 150 Conn. 321 ( 1963 )
Busker v. United Illuminating Co. , 156 Conn. 456 ( 1968 )
Zimmerman v. Garvey , 81 Conn. 570 ( 1909 )
Kecko Piping Co. v. Town of Monroe , 172 Conn. 197 ( 1977 )
Fidelity & Casualty Co. v. Constitution National Bank , 167 Conn. 478 ( 1975 )
Shore v. Town of Stonington , 187 Conn. 147 ( 1982 )
Goldman v. Feinberg , 130 Conn. 671 ( 1944 )