On January 6, 1993, the plaintiff, Milone MacBroom, Inc. (hereinafter "plaintiff"), filed a mechanic's lien on the CT Page 6843 Middletown land records, in the amount of $14,000.00, for engineering services allegedly provided by the plaintiff for the defendants, Bysiewicz Corporation, principal, and Ameritage Corporation, Bysiewicz Corporation's agent, for the preparation of subdivision plans for property known as Long Hills Farms Subdivision, located in Middletown, Connecticut (hereinafter "subject property").
On April 20, 1993, the plaintiff filed the present action to foreclose upon its mechanic's lien.
On April 27, 1993, the defendant, Bysiewicz Corporation (hereinafter "defendant"), filed its motion to discharge or reduce the plaintiff's mechanic's lien, pursuant to General Statutes Sec.
a. The subject property to be foreclosed is not the same property described in the plaintiff's Notice to File Mechanic's Lien and Mechanic's Lien and violated state law[;]
b. [t]he provisions of Connecticut General Statutes [Sec.]
49-34 have not been complied with in that not all of the owners of the property described in the plaintiff's Notice of Intent to File Mechanic's Lien and Mechanic's Lien were notified in a proper manner in accordance with state law[; and]c. [t]he plaintiff did not perform the services it seeks to be reimbursed for.
(Court file, defendant's motion to discharge or reduce mechanic's lien, Item #101.
The defendant's memorandum of law in support was filed May 27, 1993. The plaintiff filed its memorandum of law in opposition to the defendant's motion to discharge or reduce plaintiff's mechanic's lien on June 14, 1993.
On the same date, the defendant's motion to discharge or reduce the plaintiff's mechanic's lien was heard by the court. CT Page 6844
General Statutes Sec.
(a) Upon the hearing held on the application or motion set forth in section
49-35a , the lienor shall first be required to establish that there is probable cause to sustain the validity of his lien. Any person entitled to notice under section49-35a may appear, be heard and prove by clear and convincing evidence that the validity of the lien should not be sustained or the amount of the lien claimed is excessive and should be reduced.(b) Upon consideration of the facts before it, the court or judge may: (1) Deny the application or motion if probable cause to sustain the validity of the lien is established; or (2) order the lien discharged if (A) probable cause to sustain its validity is not established, or (B) by clear and convincing evidence its invalidity is established; or (3) reduce the amount of the lien if the amount is found to be excessive by clear and convincing evidence; or (4) order the lien discharged or reduce the amount of the lien conditioned upon the posting of a bond, with surety, in a sum deemed sufficient by the judge to indemnify the lienor for any damage which may occur by the discharge or the reduction of amount.
A. Whether the different descriptions of the subject property in the plaintiff's mechanic's lien and that alleged in the complaint, in the present foreclosure action, are grounds to discharge the plaintiff's mechanic's lien. CT Page 6845
General Statutes Sec.
However, the Connecticut Supreme Court has carved-out an exception, to this general rule, when the description of the property within the mechanic's lien is overly broad. "[A] mere mistake in including more land than can be made subject to the lien will not void the lien. . . ." (Citations omitted.) Tramonte v. Wilens,
The mechanic's lien legislation is remedial in character and should be construed so as to carry out its fundamental purpose. Pierce, Butler Pierce Mfg. Corporation v. Enders,
118 Conn. 610 ,615 ,174 A. 169 , and cases cited. Courts have been liberal in considering errors in matters of detail but have insisted upon reasonable compliance with specific provisions of the statute. So it has been held that a lien will not be held invalid because of a mistake in stating the date of ceasing to render services; Westland v. Goodman,47 Conn. 83 ,85 ; or the amount of land covered Tramonte v. Wilens,89 Conn. 520 ,524 ,94 A. 978 .
City Lumber Company v. Borsuk,
In the present action, the plaintiff's mechanic's lien describes the subject property, as well as additional property not intended to be the subject of the plaintiff's lien. The property description of the subject property, within the mechanic's lien, although overly broad, satisfies the requirements of General Statutes Sec.
Therefore, even though the plaintiff's mechanic's lien describes more property that is properly the subject of the lien, this presents insufficient grounds to discharge the plaintiff's mechanic's lien.
B. Whether failure to notify any and all property owners, pursuant to General Statutes Sec.
General Statutes Sec.
The notice shall be served upon the owner or original contractor, if such owner or original contractor resides in the same town in which the building is being erected, raised, removed or repaired or the lot is being improved, or the plot of land is being improved or subdivided, by any indifferent person, sheriff or other proper officer, by leaving with such owner or original contractor or at his usual place of abode a true and attested copy thereof. If the owner or original contractor does not reside in such town, but has a known agent therein, the notice may be so served upon the agent, otherwise it may be served by any indifferent person, sheriff or other proper officer, by mailing a true and attested copy of the notice by registered or certified mail to the owner or original contractor at the place where he resides. If such copy is returned unclaimed, notice to such owner or original contractor shall be given by publication in accordance with the provisions of section
1-2 . When there are two or more owners, or two or more original contractors, the notice shall be so served on each owner and on each original CT Page 6847 contractor. The notice, with the return of the person who served it endorsed thereon, shall be returned to the original maker of the notice within said period of ninety days.
In the present action, the plaintiff does not contest that certain property owners of land described in the mechanic's lien were not provided notice, pursuant to General Statutes Sec.
The plaintiff's argument is based on the same reasoning derived from the previously referred to decisions dealing with an overly broad property description within a mechanic's lien. See Tramonte, supra; also Borsuk, supra. Neither Tramonte nor the Borsuk decision dealt with the issue of a lienholder's failure to provide statutory notice.
Although a scrivener's error in the property description is not necessarily fatal to the lien, lack of adequate notice to any and all property owners, on the other hand, is an insurmountable defect. See Roundhouse Construction Corporation v. Telesco Masons Supplies Co.,
It is fundamental that property cannot be taken without procedural due process as guaranteed by the fourteenth amendment to the constitution of the United States and article
first , Sec,10 , of the constitution of Connecticut. For more than a century, the central meaning of procedural due process has been clear. "Parties whose right are to be affected are entitled to be heard; and in order that they may enjoy that right CT Page 6848 they must first be notified." Baldwin v. Hale,68 U.S. 223 ,233 ,17 L.Ed. 531 ; Windsor v. McVeigh,93 U.S. 274 ,23 L.Ed. 914 ; Hovey v. Elliott,167 U.S. 409 ,17 S.Ct. 841 ,42 L.Ed. 215 ; Grannis v. Ordean,234 U.S. 385 ,34 S.Ct. 779 ,58 L.Ed. 1363 . It is equally fundamental that the right to notice and an opportunity to be heard "must be granted at a meaningful time and in a meaningful manner." Armstrong v. Manzo,380 U.S. 545 ,552 ,85 S.Ct. 1187 ,14 L.Ed.2d 62 . The United States Supreme Court has reiterated that these fundamental requirements apply to the deprivation of "any significant property interest." Boddie v. Connecticut,401 U.S. 371 ,379 ,91 S.Ct. 780 ,28 L.Ed.2d 113 .
Roundhouse Construction Corporation v. Telesco Masons Supplies Co.,
In the present action, the defendant's property interest are affected by the recording of the plaintiff's mechanic's lien. As a result of the plaintiff's mechanics lien, the property owners have suffered a loss or a taking in that the plaintiff's mechanic's lien severely restricts the opportunity for and possibly of alienation. The plaintiff's failure to comply with the notice requirements, under General Statutes Sec.
Therefore, the court grants the defendant's motion to discharge the plaintiff's mechanic's lien because the plaintiff failed to comply with the mandatory notice requirements, pursuant to General Statutes Sec.
It is so ordered.
HIGGINS, J.
Windsor v. McVeigh , 23 L. Ed. 914 ( 1876 )
Tramonte v. Wilens , 89 Conn. 520 ( 1915 )
Grannis v. Ordean , 34 S. Ct. 779 ( 1914 )
Roundhouse Construction Corporation v. Telesco Masons ... , 168 Conn. 371 ( 1975 )
Pierce, Butler & Pierce Manufacturing Corp. v. Enders , 118 Conn. 610 ( 1934 )
Armstrong v. Manzo , 85 S. Ct. 1187 ( 1965 )
Hovey v. Elliott , 17 S. Ct. 841 ( 1897 )
City Lumber Co. of Bridgeport, Inc. v. Borsuk , 131 Conn. 640 ( 1945 )