DocketNumber: No. CV00-033 96 70 S
Citation Numbers: 2001 Conn. Super. Ct. 3497
Judges: ADAMS, JUDGE. CT Page 3498
Filed Date: 3/15/2001
Status: Non-Precedential
Modified Date: 4/17/2021
Notice of the Commission's action was published on June 6, 2000. Acorn filed and served its appeal of the Commission's action on June 14, 2000 in a timely fashion.
In March, 2000, Acorn applied to the Brookfield Planning Commission for approval of a revised development project on the Elbow Hill plot (ROR "Findings," ¶ 10). At a wetlands commission meeting on May 8, 2000, the Commission raised several concerns about the revised project mainly involving new wetlands designation and sewage discharge. As a result of these concerns, the Commission voted to require Acorn to submit a new application for a permit for the revised project. The Commission action noted that the existing permit remained valid and in effect. (ROR Item CT Page 3499 4.)
On or about May 25, 2000, Acorn commenced regulated activities on the Elbow Hill plot. According to the Brookfield land use officer who testified at the subsequent hearing, Clare Anne Walsh, Acorn cleared land for a distance of 150 feet on either side or a stream, and more than 100 feet from the stream. (ROR Item 20, Transcript ("Tr.") pp. 3-4.) Perhaps as much as 30,000 square feet were cleared. (Tr. p. 9.) Acorn concedes that cutting and clearing took place within a regulated area. (See Tr. pp. 8,
On May 26, 2000, the Commission issued a cease and desist order to Acorn directing it to:
cease and desist activity on [the Elbow Hill plot] including but not limited to: excavation, tree removal and vegetative cutting within or near any wetlands or watercourses on the premises or surrounding properties; or any activities associated with [Permit 89-38].
The order further stated that a hearing would be held on June 1, 2000 at which Acorn could show cause why Permit 89-38 should not be revoked. (ROR Item 16.)
The order set forth several reasons for its issuance. First, it stated that Acorn had not complied with five conditions set forth in the original permit. Second, the Commission had not issued any permit for regulated activity with regard to the "new project." Third, there was no planning or zoning approval for the project which was the subject of Permit 89-38, and therefore the permit could be not utilized. (Id.)
At the hearing on June 1, 2000, the Commission heard testimony from the land use officer, Weiner, Acorn's president, and reviewed various exhibits. A draft of findings of facts was reviewed, amended slightly and approved. The Commission decided to uphold the cease and desist order issued on May 25, 2000. (ROR Item 22.)
It is axiomatic that proceedings before an administrative agency, such as the case here, must be fair, and the agency must be impartial and unbiased. Proceedings, in the rather flamboyant language of our Supreme Court, "must be conducted so as not to violate the fundamental rules of natural justice." Connecticut Fund for the Environment, Inc. v.Stamford,
The Findings in its original form consisted of six typewritten double spaced pages containing nineteen separate paragraphs and a seventh page with a conclusion that the cease and desist order "was properly issued and should be upheld." The majority of the paragraphs are unexceptional CT Page 3501 and recited the past history of the Elbow Hill plot, delineating for instance each of six extensions of the permit. Other findings, however, go to the heart of the controversy, and while some of them may be undisputed, the Findings were clearly drafted, as its conclusion suggests, to support upholding the cease and desist order. When the Findings were first unveiled at the June 1, 2000 hearing, counsel for Acorn immediately and forcefully objected to them on prejudgment grounds. (Tr. p. 20.)
The Commission chairman made it clear that the document was a "draft" (id.) and read the draft findings into the record at the meeting (id.
The question whether the Commission predetermined the outcome of the hearing before the hearing was held is a question of fact. Pecora v.Zoning Commission,
The Commission does not rely solely on that argument but offers another contention to show that Acorn's activities were not allowed by the permit. The Commission points out that on May 8, 2000 it had decided that Acorn would have to submit a new application for permission to do regulated activities on the Elbow Hill plot. (ROR Item 4.) The new permit application was required because of inter alia possible changes in the wetlands areas in the ensuing ten years since the issuance of Permit 89-38 and the changes proposed by Acorn in its new Summerset project. Nevertheless, the Commission noted the existing permit was still valid, and that is what is at issue here.
The Commission's Findings concluded that Acorn had not satisfied the preconditions set by Permit 89-38 before it started its clearing activities (ROR Findings, ¶ 16). Specifically, the permit required: (1) a preconstruction meeting before each phase of the project between a representative of the Commission, Acorn, the Commission's consultant and a soil erosion and sediment control officer; (2) the appointment of an enviromnental monitor paid by Acorn and approved by the Commission; (3) no trees were to be removed before the preconstruction meeting; and (4) the posting of a $60,000 bond (ROR Item 3). To some extent, Acorn concedes these failures, but minimizes their importance. On June 1, 2000, counsel for Acorn wrote the Commission saying no preconstruction meeting had been set up or a bond posted because the tree cutting was not CT Page 3503 "construction." The letter continued that Acorn wanted a preconstruction meeting and suggested June 5 as the date at which time the bond would be posted. An environmental monitor was also named. (ROR Item 17, Exhibit H.)
The problem with Acorn's position is that the permit required those steps prior to any regulated activity being undertaken. While one might argue about the importance of the timing of those conditions and also argue (as Acorn has) that the Commission made it difficult to comply with some of the conditions, the Commission was correct in finding that the conditions were not complied with.
The Commission also found that Acorn's activities were in violation of General Statutes §
No person shall conduct any regulated activity within an inland wetland or watercourse which requires zoning or subdivision approval without first having obtained a valid certificate of zoning or subdivision approval, special permit, special exception or variance or other documentation establishing that the proposal complies with the zoning or subdivision requirements adopted by the municipality. . . .
(ROR Findings ¶ 18.) The Commission points out that Acorn has never received planning and zoning approval for his Summerset project, either the 1990 version or the 2000 version. Indeed, the latest application is still pending (ROR Item 5). There is no question that regulated activities were undertaken by Acorn (see page 3 of this decision). Acorn contends that the clearing work was in connection with building a driveway for which, it asserts, no planning and zoning permission is needed. A review of the site plan (ROR Item 18, Exhibit A) indicates that the purported "driveway" is in fact 26 feet wide and designed to carry two lanes of opposing traffic which at the very least is an accessway needing approval.
Acorn also points out that the Brookfield Planning Zoning Commission had requested clearing at the site. This is confirmed by the minutes of the Planning and Zoning Commission meeting of May 20, 2000 (ROR Item 4) and by the testimony of Richard Miller, chair of the Planning Commission (Tr. p. 19, ROR Item 19). However, it appears that the clearing requested by planning and zoning was considerably less than what was actually undertaken and completed. (ROR Item 5; Tr. p. 19.)
The court finds that there is substantial evidence in the record to support the Commission's determination to uphold the cease and desist CT Page 3504 order. Clearly, Acorn was performing regulated activities without having the requisite planning and zoning permit in violation of General Statutes §
For the foregoing reasons, the appeal is dismissed.
Adams, J.